Project Evaluation Project Evaluation Project of Jamuna Multi-Purpose Bridge Submitted to Rabia Shakir

Jamuna Bridge

Embed Size (px)

Citation preview

Page 1: Jamuna Bridge

Project EvaluationProject Evaluation

Project of Jamuna Multi-Purpose Bridge

Submitted to Rabia Shakir

Submitted by Uzair Tabani(MFE after PGD Semester I)

About:

Page 2: Jamuna Bridge

Bangabandhu Bridge, also called the Jamuna Multi-purpose Bridge is a bridge

opened in Bangladesh in June 1998. It connects Bhuapur on the Jamuna River's

east bank to Sirajganj on its west bank.

It is the eleventh longest bridge in the world and the second longest in South

Asia (after Mahatma Gandhi Setu). It was constructed over the Jamuna River,

mightiest of the three major rivers of Bangladesh, and fifth largest in the world in

terms of volumetric discharge.

The bridge established a strategic link between the eastern and western parts of

Bangladesh. It generates multifarious benefits for the people and especially,

promotes inter-regional trade in the country.

Apart from quick movement of goods and passenger traffic by road and rail, it

facilitated transmission of electricity and natural gas, and integration of

telecommunication links.

The bridge is located on the Asian Highway and the Trans-Asian Railway which,

when fully developed, will provide uninterrupted international road and railway links

from South-east Asia to North-west Europe.

History of Construction

Page 3: Jamuna Bridge

Jamuna Multi-purpose Bridge showing 8 rows of bolts for 4 rails

The river Jamuna (Brahmaputra), along with the lower stretch of

the Padma (Ganges) divides Bangladesh into nearly two equal halves. Until now all

road and rail communication between the two parts of the country has had to rely on

time-consuming ferry services that were often disrupted because

of navigability problems. The need for a bridge over the Jamuna River was felt,

especially by the people living in northwestern Bangladesh, for a long time. This

perceived need did not go unnoticed by the policy makers. The people and

successive governments always longed to bridge the mighty Jamuna and thereby

integrate the communication systems of the region.

Popular leader Maulana Abdul Hamid Khan Bhashani first raised the demand for

construction of the Jamuna Bridge at a political level in 1949. In the 1954 provincial

elections of East Pakistan, the 21-point manifesto of the united front contained a

demand for the bridge. On January 6, 1964, Mohammad Saifur Rahman, a member

Page 4: Jamuna Bridge

from Rangpur in the Provincial Assembly inquired about government's intentions with

regard to the construction of a bridge over the Jamuna. On July 11, 1966, Shamsul

Haque, another member from Rangpur in the same Assembly, moved a resolution

for the construction of the bridge and the house adopted it unanimously.

Accordingly, a preliminary feasibility study was carried out in 1969 by Freeman Fox

and Partners of UK. They recommended a rail-cum-road bridge near Sirajganj with

an estimated cost of $175 million. The estimates were preliminary and a more

detailed study was recommended. On the other hand, in his address to the nation

over radio and television on the eve of general election in Pakistan in 1970,

the Awami League leader Sheikh Mujibur Rahman mentioned the construction of

Jamuna Bridge as an election pledge of his party. But all efforts were interrupted due

to political unrest and liberation war.

After Bangladesh attained independence in 1971, the new government publicly

stated its intention in 1972 to construct a bridge over theJamuna and budgetary

provisions were kept for the purpose in the 1972-73 budget. On being invited by the

Bangladesh government, theJapan International Cooperation Agency (JICA) funded

a feasibility study through Nippon Koei Co. Ltd. in 1973 on the construction of a

road-cum-rail bridge over the Jamuna.

The JICA study, completed in 1976, concluded that the Jamuna project would cost

$683 million with an economic rate of return (ERR) of only 2.6%. Considering that

the project was not technically and economically viable, the government abandoned

it. The government revived it in 1982 and commissioned a new study to determine

the feasibility of transferring natural gas to western parts of the country across the

Jamuna. The study concluded that an independent gas connector was not

economically viable. However, the consultants made an assessment of the

engineering feasibility and cost of a combined road-cum-gas transmission bridge,

which introduced the concept of a multipurpose. It was estimated that a 12-km long

bridge with three road lanes would cost $420 million. Upon consideration of the

report, the cabinet made a decision to take immediate steps in pursuit of the project.

Page 5: Jamuna Bridge

The Jamuna Multipurpose Bridge Authority (JMBA) was set up by an ordinance

promulgated by the then President Hussain Muhammad Ershad on July 3, 1985 to

implement the project. For mobilisation of domestic resources, another ordinance

was promulgated by which a Jamuna Bridge surcharge and levy were introduced. A

total of Tk 5.08 billion was mobilised in the process till its abolition.

In 1986, phase-I feasibility study for the bridge was carried out when the site

between Sirajganj and Bhuapur (Tangail) was found to be the best. Between 1987

and 1989, the phase-II feasibility study was carried out when a road-cum-rail-cum-

power bridge was found both economically and technically viable.

Funding arrangements for the bridge were finally made

with IDA, ADB and JBIC (formerly known as OECF) of Japan by the government of

Bangladesh in 1992. Tenders were invited through international bidding for

construction contracts in 1993. Contracts for the bridge, river training work and two

approach roads were awarded in March 1994. The foundation stone of the bridge

was laid on April 10, 1994. Physical implementation of the project commenced on

October 15, 1994, and all the components except gas transmission line were

completed by June 1998. The bridge was opened for traffic on June 23, 1998.

Jamuna Multipurpose Bridge was constructed at a cost of $62 million. The cost was

shared by IDA, ADB, OECF of Japan, and the government of Bangladesh. Of the

total, IDA, ADB and OECF supplied 22% each, and the remaining 34% was borne by

Bangladesh.

The main bridge is 4.8 km long with 47 main spans of approximately 100

meters and two end spans of approximately 65 meters. Connected to the

bridge are east and west approach viaducts each with 12 spans of 10 meter

length and transition spans of 8 meters. The total width of the bridge deck is

18.5 meters.

Page 6: Jamuna Bridge

The crossing was designed to carry a dual two-lane carriageway, a dual

gauge (broad and meter) railway, a high voltage (230 kV) electrical

interconnector, telecommunication cables and a 750 mm diameter high

pressure natural gas pipeline. The carriageways are 6.315 meters wide

separated by a 0.57 meter width central barrier; the rail track is along the north

side of the deck. On the main bridge, electrical interconnector pylons are

positioned on brackets cantilevered from the north side of the deck.

Telecommunication ducts run through the box girder deck and the gas

pipeline is under the south cantilever of the box section. The bridge has been

built by Hyundai Engineering and Construction (Korea) as a 'design and build'

contract. TY Lin Assoc. of San Francisco carried out the design as a sub-

contractor for Hyundai. The approach roads were constructed by Samwhan

Corporation (Korea).

Considering the fact that the width of the main channel does not exceed

3.5 km, and after making allowances for floods, a bridge length of 5 km was

considered adequate. In October 1995, one year after the start of physical work

of the bridge, a bridge length of 4.8 km, instead of a flood-width of the river at

14 km, was finalized. This narrowing was essential to keep the overall project

cost within economic viability. It has, however, required considerable river

training work to keep the river under the bridge.

SPECIFICATIONS

To withstand predicted scourge and possible earthquakes, the bridge is supported

on 80-85 meter long and 2.5 meter and 3.15 meter diameter steel piles, which were

driven by powerful (240-ton) hydraulic hammer. The superstructure of the bridge is

pre-cast segments erected by the balanced cantilever method. Basic features of the

Page 7: Jamuna Bridge

bridge are length (main part) 4.8 km; width 18.5 meter; spans 49; deck segments

1263; piles 121; piers 50; road lanes 4; railway tracks 1 dual gauge.

Sub-structure

The bridge is supported on tubular steel piles, approximately 80 meters in length,

driven into the river. Sand was removed from within the piles by airlifting and

replaced with concrete. Out of the 50 piers, 21 piers are supported on groups of

three piles (each of 2.5 m diameter) and 29 piers on groups of two piles (each of

3.15 diameters). The driving of 121 piles started on October 15, 1995 and was

completed in July 1996.

The pier stems are founded on concrete pile caps, whose shells were precast and in

filled with in-situ reinforced concrete. The reinforced concrete pier stems support pier

heads which contain bearings and seismic devices. These allow movement of the

deck under normal loading conditions but lock in the event of an earthquake to limit

overall seismic loads through the structure and minimize damage.

Superstructure

The main bridge deck is a multi-span precast prestressed

concrete segmental structure, constructed by the balanced cantilever method.

Each cantilever has 12 segments (each 4 m long), joined to a pier head unit (2 m

long) at each pier and by an in-situ stitch at mid span. The deck is

internally prestressed and of single box section. The depth of the box varies between

6.5 meters at the piers to 3.25 meters at mid-span. An expansion is provided every 7

spans by means of a hinge segment at approximately quarter span. The segments

were precast and erected using a two-span erection gantry.

EVALUATION OF DESIGN AND IMPLEMENTATION

A. Relevance of Design and Formulation

Page 8: Jamuna Bridge

The Project was designed in conformity with ADB’s operational strategy to reduce

poverty in Bangladesh by

(i) Accelerating economic growth through, among other things, improved

physical infrastructure;

(ii) Helping the poor improve their living conditions; and

(iii) Improving and protecting the environment.

The Project aimed at supporting growth by removing major bottlenecks in the railway

infrastructure caused by the need for ferrying traffic across the Jamuna River and for

trans-shipment between differently gauged tracks. The Project provided an

opportunity for seamless, economical, and environment-friendly rail operations

between the northwestern and eastern regions of the country. It also opened up

prospects for using rail for transporting long-haul bulk cargo and intercity passenger

traffic, for which it is ideally suited. The Project was therefore fully consistent with

ADB’s country strategy and program.

Under the Government’s Fifth Five-Year Plan (1997–2002), the main objective for

the transport sector was to develop a balanced and integrated transport network,

bearing in mind the target of achieving an average gross domestic product growth

rate of 7.0% per year and the projected growth of 7.5% per year in the transport

sector. The sector strategy was formulated in light of the increasing volume of

domestic traffic as well as future traffic from the Asian Highway and the Trans-Asian

Railway. For the rail subsector, the need to link the eastern and western zone

networks was identified by the Government, which was consistent with the planned

achievement of deficit-free operations by Bangladesh Railway as envisaged in the

Railway Recovery Program. The Project was therefore highly relevant to the

Government’s sector strategy.

The project design took into consideration lessons learned from previous ADB-

financed project, and current ADB practices. The lessons indicated the need to

Page 9: Jamuna Bridge

(i) address institutional weaknesses;

(ii) strengthen project management to reduce the risk of delays and to

support timely implementation;

(iii) improve selection and prequalification criteria for contractors to

ensure adequate quality and better performance;

(iv) limit administrative complexity, inefficiency, and delays by careful

selection of medium to large procurement packages; and

(v) Submit regular monthly progress reports during project

implementation, including key operational and financial indicators.

Deviations in the Project design from that planned at appraisal included the use of

prestressed concrete sleepers instead of wooden sleepers as in the original

engineering design. The construction supervision consultant (CSC) determined that

significant benefits in terms of improved track geometry would accrue if such

sleepers were used. The CSC noted that the financial benefit resulting from the

longer life of concrete sleepers would substantially offset the cost increase. ADB

accepted the proposal subject to the Government financing the additional cost. In a

second deviation, the track design for contract 2 bypassed the station in Ishurdi to

avoid operational bottlenecks. As a result, the length of dual-gauge track was

reduced from 250km to 245 km. These changes did not affect the time schedules,

expected benefits, or any other measures of efficiency.

Institutional reform and restructuring of Bangladesh Railway and establishment of

Project Management Unit (PMU) supported by the CSCs were covenanted in the

Loan Agreement. Prequalification criteria for contractors were properly formulated,

leading to the selection of experienced and capable contractors. Contract packages

were kept large except where the co financing arrangement did not permit this. ADB

and Bangladesh Railway carried out regular project monitoring through the CSCs’

progress reports and ADB’s project review missions. The CSCs’ interventions were

timely and adequate when difficulties arose during project implementation.

Page 10: Jamuna Bridge

B. Project Outputs

The project outputs envisaged during appraisal were

(i) the construction of 99 km of dual-gauge railway line from Joydebpur to

Jamtoil to connect Bangladesh Railways’ eastern and western networks,

including 5 km of track on Jamuna Bridge;

(ii) the conversion of 245 km of existing broad-gauge track to dual-gauge

track from Jamtoil to Parbatipur in northwest Bangladesh to connect to the

meter-gauge network there;

(iii) the provision of signaling equipment for component i;

(iv) the provision of telecommunications equipment for component

(v) the provision of rails for components i and ii;

(vi) the retrenchment of 3,500 staff through a staff separation scheme that

provided for compensation, retraining, and skills development for

retrenched staff.

All project outputs except component vi, were fully achieved, albeit with cost and

time overruns. The special staff separation scheme was postponed following a

request from Bangladesh Railway based on higher than expected natural attrition

and a forthcoming manpower analysis to be carried out under the ongoing ADB-

assisted study on Organizational Reform of Bangladesh Railway, Phase III7 to avoid

the loss of essential skilled personnel.

C. Project Costs

At appraisal, the cost of the Project was estimated at $269 million equivalent. This

comprised a foreign exchange component of $93.5 million (34.8%) and a local

currency component of $175.5 million equivalent (65.2%). The Project experienced a

cost overrun; and the final cost at the time of completion was $365 million equivalent.

The total increase in project costs was $96 million equivalent (35.7%) over the

original appraisal estimate. The foreign exchange component increased by 128.8%

Page 11: Jamuna Bridge

to $213.91 million, whereas the local currency component was $151.09 million

equivalent (14% less than the appraisal estimate).

The cost overrun was attributed to

(i) higher than estimated bid prices (awarded at a price $22 million higher

than anticipated),

(ii) underestimation during the feasibility study of the extent of works needed

to convert the western zone broad-gauge tracks to dual gauge tracks

(iii) additional requirements for ballast and rail associated because of the poor

condition of existing track materials,

(iv) additional input of consulting services because of an extension of the

project implementation period,

(v) changes necessitated by the use prestressed concrete sleepers instead of

wooden sleepers,

(vi) start-up delays in implementing both contracts, and

(vii) Increased duties and taxes associated with both contracts, and the

settlement of contractors’ eligible claims.

The Project was financed by ADB for Special Drawing Rights (SDR) 80.67 million

($110.0 million equivalent) with co financing from a number of donors. Of the total

project cost of $365 million on completion, ADB provided a loan of $105.9 million

from its Special Funds resources (29% of the project cost). Co financing partners

included the Organization of Petroleum Exporting Countries (OPEC) Fund for civil

works and track construction ($14.91million), the Government of France for the

signaling subcomponent ($7 million), and the Government of Spain for the

telecommunications subcomponent ($6.96 million).

Commercial financing by the Export Development Corporation (EDC) of Canada for

$7.0 million (tied loan) was written off because of the unavailability of an eligible

manufacturer in Canada for procuring “employer-supplied rails” for the Project.

Counterpart funding by the Borrower, the Government of Bangladesh, was $230.19

Page 12: Jamuna Bridge

million. ADB administered the OPEC component, while the respective governments

administered the French and Spanish loans, which were used to finance nominated

subcontracts. The loan was declared effective on 6 March 1998. The original

Loan closing date was 31 December 2001, which was extended to 18 December

2003.

ECONOMIC IMPACTS

Increased connectivity and enhanced economic opportunities

Reduce travel time (8 to 4 Hr)

Reduce freight Cost ( $6.61 to $4.7 )

0.97M person became economically stable

Page 13: Jamuna Bridge

Transport cost reduced

Easy and reliable means of transport for natural gas, electricity,

telecommunication

High rate of revenue collection (recovery time 30YRs)

Annual toll revenue amounts to US$24 million for FY 2006- -07

Page 14: Jamuna Bridge

IRR of the project 14.5%

Open up for more funding to other projects

Protection of environment

Safe journey

Poverty reduction

It generates multifarious benefits promotes inter promotes inter- -regional

trade in the country

SOCIAL BENEFITS OF THE PROJECT

(1) 30 million people 30 million people connected together connecting western part with the developed eastern part

Page 15: Jamuna Bridge

(2) Safe journey: Replaced the traditional ferries, manually operated boat etc. which were time consuming and risky

(3) Poverty reduction: One of the biggest targets and greatest achievements

CONCLUSION

Page 16: Jamuna Bridge

The Jamuna Bridge Project aims to achieve the strategic objective of connecting the

east and west parts of the country separated by the Jamuna River, thus stimulating

the economic growth by facilitating inter-regional, cross-river transport of

passengers, freight and transmission of electricity more economically and efficiently.

The project will also facilitate the transmission of natural gas and

telecommunications between the east and west in a cost-effective manner, as well

as a meter gauge railway connection.

The project consists of:

(a) construction of a bridge about 4.8 km long, with a design life of 100 years;

(b) construction of two end viaducts to connect the bridge to the approach roads;

(c) construction of two guide bunds, of about 2.2 km each and a flood protection bund on the east bank to regulate the river at the chosen site;

(d) construction of east and west approach roads;

(e) measures to mitigate the project's effects on the environment, including resettlement, compensation of project affected persons, fisheries and wild life, and environmental monitoring; and

(f) technical assistance and training.

It is one of the greatest targets and achievements of Bangladesh.

Page 17: Jamuna Bridge

Transport cost reduced