  • PROBLEM STATEMENT

    This glass fabrication facility was performing well below their potential capacity, resulting in a net operating loss rather than producing a profit. In order to rectify the situation, significant improvements were needed to increase productivity and throughput while decreasing operational costs, downtime, overtime, cycle time, waste, and inventory.

    PROJECT GOAL

    The goal was to optimize the manufacturer’s current processes by increasing the current daily production rate of 4,000 sq. ft. per shift to 7,500 sq. ft. per shift with no additional staff. With this increase, the plant would become profitable.

    BUSINESS CASE

    With strong market growth in nearby territories, there was significant opportunity to increase sales and market share and improve productivity to become profitable.

    PROJECT OVERVIEW

    The Juran Manufacturing Team worked closely with the manufacturer to devel- op a phased and incremental project schedule. Worker behavior was observed, process steps were mapped, and WIP was timed. It was discovered that there were areas throughout the plant that had become “catch-alls” for inventory, unused materials, and items with no specific ownership. There were tools all over the workplace with no specific places for them.

    5S (plus 6S-Safety) was implemented throughout the plant to create a clean and orderly workspace where everything that was needed could be found easily and was readily available in the right quantities and at the appropriate times.

    By conducting a value-added vs. non-value added analysis, the team identified areas where relatively small changes could result in dramatic improvements in a short time. One such area was the Frame Assembly area. Through a simple re-layout of this area, excess handling and product movement was dramatically reduced. A standard work process was developed and implemented.

    Juran worked with the Manufacturing Team to develop a data collection plan for per shift process control. Supervisors had to track the production every hour for a rolled up number per shift of the planned vs. actual square footage produced. Re-cuts and re-work were also monitored for process improvement opportunities.

    LEAN VALUE STREAM ANALYSIS AND MANAGEMENT

    A CUSTOMER SUCCESS STORY

    INDUSTRY

    Manufacturing

    COMPANY

    Glass Manufacturer

    RESULTS

    At project conception, the company was experiencing a $780,000 operating loss. Upon project completion, the company achieved a $750,000 operating income. The projected year-to-year improvement is $1.5 million in operating income.

    TOOLS USED

    Lean – Value Stream Analysis & Management:

    ▪ 6S ▪ Manufacturing Process

    Analysis - Current State ▪ Eliminate/minimize

    non-value added activity

    ▪ Metrics – what is measured, what should be measured, how to measure

    ▪ Milestone chart ▪ Kanbans ▪ Supermarkets ▪ Action item list with

    accountability ▪ Standard Work

    Documents ▪ Spaghetti Diagrams ▪ Manufacturing Process –

    Future State ▪ Production Control

    Boards – Visual Manufacturing

    ▪ Customer Pull Scheduling and Level Loading

    ▪ Continuous team coaching

    TIMELINE

    Four months

    © 2017 Juran, All Rights Reserved. juran.com

  • ▪ Auto-cut: Improved inventory layout and access Scheduled adherence Analysis of inventory and elimination of unused inventory Prioritization process for re-cuts

    ▪ Tempering: Improved oven capacity utilization Increased productivity at unloading of ovens

    ▪ Insulating: Optimized pick-up of glass Eliminated unnecessary non-value added motion

    RESULTS

    Through systematic and incremental improvements, the team reached their goal of increasing the square footage from the current state of 4,000 sq. ft. per shift to the future state of 7,500 sq. ft. per shift with no additional headcount.

    FOR MORE INFORMATION

    For more information on how we can help your organization attain sustainable results, please contact us at 800.338.7726, or visit us on the web at www.juran.com.

    LEAN VALUE STREAM ANALYSIS AND MANAGEMENT

    A CUSTOMER SUCCESS STORY

    INDUSTRY

    Manufacturing

    COMPANY

    Glass Manufacturer

    RESULTS

    At project conception, the company was experiencing a $780,000 operating loss. Upon project completion, the company achieved a $750,000 operating income. The projected year-to-year improvement is $1.5 million in operating income.

    TOOLS USED

    Lean – Value Stream Analysis & Management:

    ▪ 6S ▪ Manufacturing Process

    Analysis - Current State ▪ Eliminate/minimize

    non-value added activity

    ▪ Metrics – what is measured, what should be measured, how to measure

    ▪ Milestone chart ▪ Kanbans ▪ Supermarkets ▪ Action item list with

    accountability ▪ Standard Work

    Documents ▪ Spaghetti Diagrams ▪ Manufacturing Process –

    Future State ▪ Production Control

    Boards – Visual Manufacturing

    ▪ Customer Pull Scheduling and Level Loading

    ▪ Continuous team coaching

    TIMELINE

    Four months