32
Key Milestones 30 Key Milestones Begin Dates Public Outreach and Technical Coordination Ongoing Begin NEPA Environmental Assessment January 2016 Begin Transit/TDM Study April 2016 Public Information Meetings April 11 and 13, 2016 Public Hearing October 24 and 26, 2016 Regional Long-Range Plan Decision November 2016 Final NEPA Decision December 2016 Final Transit/TDM Study December 2016 Final Financial Agreement January 2017 Begin Construction (95 Express) Summer 2017 Project Completion (95 Express) Summer 2019

Key Milestones Begin Dates - ASHE Potomacpotomac.ashe.pro/uploads/3/4/6/0/34606154/ashe_vdot-_10-12-16_00.… · Key Milestones Begin Dates ... Final Transit/TDM Study December 2016

  • Upload
    ngocong

  • View
    219

  • Download
    0

Embed Size (px)

Citation preview

Key Milestones

30

Key Milestones Begin Dates

Public Outreach and Technical Coordination Ongoing

Begin NEPA – Environmental Assessment January 2016

Begin Transit/TDM Study April 2016

Public Information Meetings April 11 and 13, 2016

Public Hearing October 24 and 26, 2016

Regional Long-Range Plan Decision November 2016

Final NEPA Decision December 2016

Final Transit/TDM Study December 2016

Final Financial Agreement January 2017

Begin Construction (95 Express) Summer 2017

Project Completion (95 Express) Summer 2019

Transform 66 Outside the Beltway

Project Scope

• 2 express lanes in each direction from

I-495 (Capital Beltway) to Gainesville

(University Boulevard)

• 3 general purpose lanes in each

direction

• New transit service and park-and-ride

lots

• Safety and operational improvements

at key interchanges

31

Alternative

Technical Concepts (ATCs)

32

Innovative ATCs sought from Proposers to:

• Reduce cost while preserving quality

• Improve mobility and safety

• Reduce construction impact

• Encourage early completion

• Provide advantage to proposer and value to the owner

• No limit on number of ATCs proposed by each proposer

• Process encouraged by FHWA

Alternative

Technical Concepts (ATCs) Process

Fast-track review process of 21 days for each ATC

• Submittal timeline: ATCs submitted from March 1 through July 15, 2016

• Third-party review: Groups including federal agencies, localities and transit

agencies asked to review ATCs that impact their facilities

• Strict document control: Reviewers required to have pre-approved user ID

and password to access documents.

• Confidential process: Reviewers signed confidentiality agreement and are

prohibited from discussing ATC’s with non-participants.

• After review process, proposer notified if ATC is acceptable, not acceptable,

or acceptable with conditions

33

Thank you

34

35

36

37

38

39

40

41

42

43

44

45

PROJECT DEVELOPMENT

Nicholas J. Roper, P.E. District Project Development Engineer October 12, 2016

Agenda

• New Developments

• Smart Scale

• State of Good Repair

• Atlantic Gateway

• Projects Under Development

• Upcoming Procurements

• Local Assistance

• Tracking Development for Smart Scale and

State of Good Repair

47

48

$3.3 B Total Cost

all Projects

$-

$200

$400

$600

HPP and DGP Funds

HPP DPG

Avg Benefit/ SMART SCALE

Cost 10.7

10 11

19

21

23 19

22

20

18

Number of Projects By District

Bristol

Culpeper

Fredericksburg

Hampton Roads

Lynchburg

Northern VA

Richmond

Salem

Staunton

163

Total

0

500

1000

1500

BR CU FR HR LY NO RI SA ST

SmartScale $ vs Other $

Other Cost SmartScale Cost

SMART SCALE: Round 1

SMART SCALE: Round 2

• Expect about half the funding that was available in Round 1 ($1.7B

to $850M)

• Increase in the number of applications and total value compared to

Round 1

• Funding becomes available beginning in FY22 and FY23, efforts will

be made to advance some funding

• Significant changes to scoring/process include:

• Safety (5%) – all crashes instead of only fatal crashes

• IJRs must be completed for every interchange on limited access highways

• After this round, process will occur every other year – next

opportunity will be 2018 for FY2024 and FY2025 funding

49

Round 1 46 Applications $2.1B Value

Round 2 62 Applications +35% $3.28B Value +56%

50

51

For Northern Virginia

• $38.5M for Structurally Deficient Bridges

6 Projects

• $23.2M for deficient pavement

Rte 50 FY17-18, FY19-22 TBD

• $61.7M total in SYIP FY17-22

• Using state force or on-call consultants

to prepare designs/contract documents

Project

Components • $1.4 Billion

• 100% Committed Funding

o 40% Private

o 44% Federal/State

o 16% USDOT Grants

Advertisement Summary for

Projects in Development

53

Administration

Calendar Year for

Advertisement Projects

Construction

Estimate

Total

Project

Estimate

VDOT

24% Projects

70% Value

Oct-Dec 2016 6 $11.2M $11.5M

Nov 2016 I-66 Widening ITB 1 $108M $125M

2017 8 $10M $15.7M

2018- 31 $713M $1.05B

Total 46 $842M $1.2B

Non VDOT

76% Projects

30% Value

2016 26 $19M $22.7M

2017 62 $139M $191M

2018- 59 $177M $305M

Total 147 $335M $518M

Grand Total 193 $1.17B $1.7B

Most VDOT projects

are in later years

21

12

31

23

56

4

14

4

11

15

1 1

0

10

20

30

40

50

60

AC CM I S B/P Other

LAP

VDOT

$212

$18

$185

$40 $63

$2

$880

$134 $136

$48

$8 $1 $0

$100

$200

$300

$400

$500

$600

$700

$800

$900

$1,000

AC CM I S B/P Other

Millio

ns

LAP

VDOT

Type of Improvements

54 CM – Congestion Mitigation, AC – Added Capacity, I – Infrastructure, S- Safety

B/P – Bike/Ped, Other – Landscaping, etc.

Total Number Estimate Amount

$44.7M a/o July 15

Now includes Smart

Scale & NVTA-

funded projects

37 a/o

Dec 15

More Local Assistance projects in all categories

Current Procurements

• I-81 Bridge over New River at Exit 105

• ITS Services for Eastern Region Operations

• Statewide MS4 Services

• Statewide Survey, Photogrammetry and SUE Services

• Fredericksburg Bridge Safety Inspection Services

• Hampton Roads Inspection of Support Structures

• Statewide SUE Services

• NOVA Permit and Street Acceptance Services

• NOVA Inspection of Support Structures

• Construction Division Support Services

• ITS/Operations Design Services

55

Upcoming Procurements

• Western Perimeter Road Design Services – Salem

District/Montgomery County

• Anticipated RFP Advertisement – October 2016

• Project Specific

• I-64/I-264 Witchduck Interchange CEI Services

• Anticipated RFP Advertisement – October 2016

• Project Specific

• Hampton Roads District Wide CEI Services

• Anticipated RFP Advertisement – October 2016

• Term Contract – Single Award

• Culpeper District Wide CEI Services

• Anticipated RFP Advertisement – December 2016

• Term Contract – Multiple Award 56

Upcoming Procurements

• Statewide NEPA/Traffic Studies

• Anticipated RFP Advertisement – December 2016

• Term Contract – Multiple Award

• I-64 Southside & High Rise Bridge – CEI and Design Review

Services

• Anticipated RFP Advertisement – January 2017

• Project Specific

• Salem District Wide CEI Services

• Anticipated RFP Advertisement – January 2017

• Term Contract – Single Award

• Staunton District Wide CEI Services

• Anticipated RFP Advertisement – February 2017

• Term Contract – Single Award 57

Local Assistance New Events & Trends

• Updated FHWA/VDOT Stewardship & Oversight Agreement delegates greater responsibility to VDOT for the oversight on most federally-funded LAPs

• Areas of increased FHWA emphasis include fiscal management, work orders, “Buy America”, environmental compliance and civil rights

• SMART SCALE has placed greater responsibility on the localities for accuracy with regards to project scope, estimates and schedule

• Design-Build is more frequently considered as a delivery option

• Where consultants can help

– Plan Quality

– Project Scoping

– LAP Process LAP MAP training Oct 31!

Chief Engineer’s Briefing to VTCA

Consultant Forum

59

Meeting expectations in Delivering the New Program:

• Tracking of Smart Scale projects.

• Early start/early finish for both activities and advertisement.

• More concurrent rather than sequential.

• Teamwork: Good communication regarding project

development, timeframe, and budget.

• Quality of Plans: Provide the best quality plans to minimize

surprises at advertisement and during construction.

Example of Smart Scale Project

Tracking Tool

60

• Interim tool to be used by NOVA while statewide tool is in development

• Will include all locally administered projects as well as VDOT administered

• Likely to include State of Good Repair projects

Chief Engineer

• Tracking of Smart Scale projects.

• Early start/early finish for both activities and advertisement.

61

Nicholas J. Roper, P.E.

Email: [email protected]

Office: (703)259-1953

Cell: (703)586-3436