L9-Impulse Voltages and Testing

Embed Size (px)

Citation preview

  • 8/12/2019 L9-Impulse Voltages and Testing

    1/72

    1

    Insulation Coordination

    the selection of insulationstrength

  • 8/12/2019 L9-Impulse Voltages and Testing

    2/72

    2

    Kiski Valley

    Substation - 1938

  • 8/12/2019 L9-Impulse Voltages and Testing

    3/72

    3

    Luxor substation 1933.before lightning arresters

  • 8/12/2019 L9-Impulse Voltages and Testing

    4/72

    4

    Insulation

    Self restoring insulation recovers after aflashover external such as air switches,insulators, external surfaces of bushings(defined at standard atmosphericconditions)Non-self restoring insulation does not

    recover after a flashover enclosed oil, paper, gas, air systems such as transformersand circuit breakers

  • 8/12/2019 L9-Impulse Voltages and Testing

    5/72

    5

    Standardshttp://www.techstreet.com/info/astm.

    Voltages: ANSI C84.1- 1995 System VoltagesVoltages: IEEE 1312 1987 AC Electrical Systems and EquipmentOperating Voltages above 230kvBILs: ANSI 92 defines BILs for the equipment manufacturers to useIEEE std 4 1995 Standard Techniques for High Voltage TestingCircuit Breakers: ANSI C-37.06 1997Transformers: ANSI C57.12 1993 Liquid Immersed Distribution,Power and Regulating Power TransformersSwitches: IEEE C37.34 Standard Test Code for High VoltageSwitchesInsulators: ANSI C29.8 & C29.9 Cap and Pin Type & Post TypeInsulatorsArresters: IEEE C62.11 Metal Oxide surge arresters for AC PowerCircuits Arresters: IEEE C62.22 Guide for application of Metal Oxide surgearresters for Alternating Current Systems

  • 8/12/2019 L9-Impulse Voltages and Testing

    6/72

    6

    Impulse Voltages and Equipment

    Requirements

    Over-voltages

    Transient WaveshapesEquipment testing

  • 8/12/2019 L9-Impulse Voltages and Testing

    7/72

  • 8/12/2019 L9-Impulse Voltages and Testing

    8/72

    8

    Transient Waveforms

    Lightning - 1.2 x 50 u-second

    Front of WaveChopped WavesSwitching - 250 x 2500 u-second

    60 hertz waves

  • 8/12/2019 L9-Impulse Voltages and Testing

    9/72

    9

    Peak or RMS

    60hz voltages are expressed in rms ph-phDuty cycle and MCOV are in rms phase-groundLightning, chopped wave and switching surges are

    expressed in peak volts phase to ground:

    Peak = 2 rms ph-ph 3

    Peak = 2 145kv = 118.4kv3

  • 8/12/2019 L9-Impulse Voltages and Testing

    10/72

    10

    Lightning ImpulsesVery fast rise can cause line insulation to fail

    backflashes - rise in the 500-2000KV per u-secondrange and 10-20 u-sec tail (cfo of line - positive polaritywaves)

    Direct strokes to phase wires (cfo due to negative

    polarity waves) slightly slower rise and longer tail than backflashBIL: Basic Impulse Level is the electrical strength ofinsulation to the crest value of the standard lightningimpulse (for dry conditions)

    BIL = CFO 1.28 x o f (10% probability of flashover)

    Test wave doesnt reflect actual lightning but its easilyreproduced in test labLig htning can be positive or negative compared to the

    earth most strokes are negative. The insulation withstandcan be different for each type

  • 8/12/2019 L9-Impulse Voltages and Testing

    11/72

    11

    Lightning Impulse1.2 x 50 u-seconds

    BIL = 1.0

    .5

    t2

    Virtual tail = 50 micro-seconds

    IEEE std 4-1995 Standard Techniques for High Voltage Testing

    Virtual front = 1.2 micro-seconds

    .9

    .3 A

    B

    t1

    Virtual Zero

    v

    t

    Tolerances:Front: +/- 30%Tail: +/- 20%

  • 8/12/2019 L9-Impulse Voltages and Testing

    12/72

    12

    Impulse Generators:

    Impulse generators are stacks of capacitors and resistorsInitially the capacitors are connected in parallel and charged upThen the capacitors are re-connected in seriesThen they are discharged to provide the high voltage impulse waveResistors are used to shape the front and tail of the wave

    +

    -

    +-

    Charging circuit

    Discharging circuit

  • 8/12/2019 L9-Impulse Voltages and Testing

    13/72

  • 8/12/2019 L9-Impulse Voltages and Testing

    14/72

    14

    Chopped Wave Impulse1.2 x 3 u-seconds

    BIL = 1.0

    IEEE std 4-1995 Standard Techniques for High Voltage Testing

    v

    t

    1.1 - 1.29 x BIL

    t

  • 8/12/2019 L9-Impulse Voltages and Testing

    15/72

    15

    Switching Impulses

    BSL: Basic Switching Level is the electricalstrength of insulation to the crest value of thestandard switching impulse (wet conditions)

    BSL = CFO 1.28 x o f (10% probability offlashover)

    Switching impulses are longer duration both onthe front and the tail (hundreds of u-seconds)Low line surge impedance (> 138kv overheadlines, also cable circuits)Re-closing into trapped charge on line

  • 8/12/2019 L9-Impulse Voltages and Testing

    16/72

    16

    SwitchingSurges:

    Z 0= L/C

    Voltage doubles when closing in on anopen line = 2 P.U. at open line terminal

    Assume that High Speed Re-closing traps a negative 1 P.U. charge on the line.Then when the breaker re-closes the maximum voltage at the open end can

    approach a maximum of 3.5 - 4.0 P.U. for multiple reflections depending ondamping (R):

    Trapped charge = -1.0 P.U.

    3.5 P.U.

  • 8/12/2019 L9-Impulse Voltages and Testing

    17/72

    17

    50% CriticalFlashover VoltageCFO

    Strike Distance

    SwitchingSurges: Insulation strength ofair gaps:

    At operating voltages above 230kv switching transients becomethe constraint that drives system design

    Breakers & switches are only tested for switching surge at345kv and above. Transformers 115kv & above.

  • 8/12/2019 L9-Impulse Voltages and Testing

    18/72

    18

    Switching Impulse250 x 2500 u-seconds

    1.0

    .5

    t2 = 2500 u-secIEEE std 4-1995 Standard Techniques for High Voltage Testing

    v

    tt1 = 250 u-sec

    Tolerances:Front: +/- 20%Tail: +/- 60%

  • 8/12/2019 L9-Impulse Voltages and Testing

    19/72

    19

    Power Frequency (60hz)

    Maximum 60Hz OperatingVoltage

    Nominal + 5%500kv system is nominal + 10%

  • 8/12/2019 L9-Impulse Voltages and Testing

    20/72

    20

    System Voltages ANSI C84.1 - 1995

  • 8/12/2019 L9-Impulse Voltages and Testing

    21/72

    21

    System Voltages ANSI C84.1 - 1995

  • 8/12/2019 L9-Impulse Voltages and Testing

    22/72

    22

    Power Frequency (60hz)Overvoltages

    Rise on unfaulted phases for a line-ground fault(X/R and co-efficient of grounding)Loss of ground (backfeed)

    Ferro-resonance line or cable capacitance withtransformer inductanceLoad rejection

    Ferranti effect long unloaded transmission linesTransformer inrush

  • 8/12/2019 L9-Impulse Voltages and Testing

    23/72

    23

    Coefficient of Grounding

  • 8/12/2019 L9-Impulse Voltages and Testing

    24/72

    24

  • 8/12/2019 L9-Impulse Voltages and Testing

    25/72

    25

    Potential Rise on the Line

    Voltage

    Breaker open

    ..

  • 8/12/2019 L9-Impulse Voltages and Testing

    26/72

    26

  • 8/12/2019 L9-Impulse Voltages and Testing

    27/72

    27

    Equipment Insulation

    Bus InsulatorsAir SwitchesCircuit BreakersTransformersBushings

    Equipment External Clearances

  • 8/12/2019 L9-Impulse Voltages and Testing

    28/72

  • 8/12/2019 L9-Impulse Voltages and Testing

    29/72

    29IEEE 1313.1 1996

    Equipment BILs (Class one equipment) :

  • 8/12/2019 L9-Impulse Voltages and Testing

    30/72

    30

    Equipment BILs/BSLs for EHV (Class two) :

  • 8/12/2019 L9-Impulse Voltages and Testing

    31/72

    31

    Equipment Insulation60 hz testing:

    60 hz tests wet tests are done on insulators, airswitches and cijrcuit breakers to understandresponse during rain (IEEE std 4 1995)

    and dew conditions (ANSI C-29.1 1988 section4.6)

  • 8/12/2019 L9-Impulse Voltages and Testing

    32/72

    32

    Equipment Insulation

    Bus Insulators

    Air SwitchesCircuit BreakersTransformers

    Bushings

  • 8/12/2019 L9-Impulse Voltages and Testing

    33/72

    33

    Bus Supports & AirSwitches ANSI C37.32

    Withstand (10%)

  • 8/12/2019 L9-Impulse Voltages and Testing

    34/72

    34

    Standard AtmosphericConditions

    Ambient temperature = 20 deg CAir Pressure = 760mm mercury (1 atmosphere)Absolute humidity = 11 gms water/Mtr 3 air

    The test voltages are adjusted as needed whenconditions vary from the standard

  • 8/12/2019 L9-Impulse Voltages and Testing

    35/72

    35

    Equipment Insulation

    Bus Insulators

    Air SwitchesCircuit BreakersTransformers

    Bushings

  • 8/12/2019 L9-Impulse Voltages and Testing

    36/72

    36

    Bus Supports &Air SwitchesANSI C37.32

  • 8/12/2019 L9-Impulse Voltages and Testing

    37/72

    37

    EHV Switches:

    Air SwitchesANSI C37.32

  • 8/12/2019 L9-Impulse Voltages and Testing

    38/72

    38

  • 8/12/2019 L9-Impulse Voltages and Testing

    39/72

    39

    Air Switch Coordination

    - Gap flashover- Gap withstand

    - Insulator flashover- Insulator withstand

    Make the gap withstand 10%higher than the insulator flashover!

  • 8/12/2019 L9-Impulse Voltages and Testing

    40/72

    40

    Bus Supports &Air SwitchesANSI C37.32

  • 8/12/2019 L9-Impulse Voltages and Testing

    41/72

    41

    Passing the 3+9 test:

    Air Switches

    APs switch specification MS 1100 -10 requires transmission switches towithstand 15 impulses without flashover for the gap withstand and alsoflashover for 15 impulses to establish the insulator flashover value.

  • 8/12/2019 L9-Impulse Voltages and Testing

    42/72

  • 8/12/2019 L9-Impulse Voltages and Testing

    43/72

    43

    Equipment Insulation

    Bus Insulators

    Air SwitchesCircuit BreakersTransformers

    Bushings

  • 8/12/2019 L9-Impulse Voltages and Testing

    44/72

    44

    ABB 550 PM

  • 8/12/2019 L9-Impulse Voltages and Testing

    45/72

    45

    Circuit Breaker CoordinationBreaker closed

    Weakest point is typicallythe throat shield to ground

  • 8/12/2019 L9-Impulse Voltages and Testing

    46/72

    46

    ABB 550 PM

  • 8/12/2019 L9-Impulse Voltages and Testing

    47/72

    47

    ABB 550 PM Failure Doubs DL-55, July 8, 2000 Tube Flashover

  • 8/12/2019 L9-Impulse Voltages and Testing

    48/72

    48

    Circuit Breaker CoordinationBreaker openSwitching surge values are higher for the

    gap than for phase to ground

  • 8/12/2019 L9-Impulse Voltages and Testing

    49/72

    Ci i k

  • 8/12/2019 L9-Impulse Voltages and Testing

    50/72

    50

    Circuit Breaker500kv PM Design Tests

    One minute dry withstand 60hz 860kvTen second wet withstand 60hz 775kvFull wave impulse (BIL) 1800kvChop wave impulse 2 u-sec to chop 2320kvChop wave impulse 3 u-sec to chop 2070kvSwitching impulse terminal to gnd 1175kv(breaker open)Switching impulse terminal to gnd 1175kv(breaker closed)Switching impulse terminal to terminal 1300kv(breaker open)

  • 8/12/2019 L9-Impulse Voltages and Testing

    51/72

    51

    Breaker Applications

    Closing resistors are used to reduce theswitching surge created at the far end ofa transmission line when it is energized

    Once breaker is closed the resistor is removedfrom the circuit.

    Not designed to handle continuous load currentor fault current.

    AP uses closing resistors on EHV breakers Typical value: 400-450 ohms.

  • 8/12/2019 L9-Impulse Voltages and Testing

    52/72

    52

    Closing resistors :

    Z 0= L/C Rc

    Rc

    Z 0 V 0 Z 0

    (Rc + Z 0 ) V 0 = V S

    bypass

    V S

  • 8/12/2019 L9-Impulse Voltages and Testing

    53/72

  • 8/12/2019 L9-Impulse Voltages and Testing

    54/72

  • 8/12/2019 L9-Impulse Voltages and Testing

    55/72

    55

    Transformer TestLevels

  • 8/12/2019 L9-Impulse Voltages and Testing

    56/72

    56

    Transformers:138-12kv delta-wye

    lowvolage

    wintding

    Gas Space - N 2

    highvoltagewinding

    HV & LV BILs determinethe amount of line end

    insulation ofthe windings

    Turn-Turn failure at line end

  • 8/12/2019 L9-Impulse Voltages and Testing

    57/72

    57

    Turn Turn failure at line end

    138kv disk winding 30/40/50mva

  • 8/12/2019 L9-Impulse Voltages and Testing

    58/72

    58

    Transformer

    lowvolagewintding

    Gas Space - N 2

    highvoltagewinding

    HV BIL determinesthe distance betweenthe high-low windingsand H-L insulation

  • 8/12/2019 L9-Impulse Voltages and Testing

    59/72

    59

    Transformer

    lowvolagewintding

    Gas Space - N 2

    highvoltagewinding

    Induced test determinesthe high-ground

    insulation

  • 8/12/2019 L9-Impulse Voltages and Testing

    60/72

    60

    Transformer

    lowvolagewintding

    Gas Space - N 2

    highvoltagewinding

    LV BIL and thru-faultmechanical forcesstress low-groundinsulation

  • 8/12/2019 L9-Impulse Voltages and Testing

    61/72

    61

  • 8/12/2019 L9-Impulse Voltages and Testing

    62/72

    62

  • 8/12/2019 L9-Impulse Voltages and Testing

    63/72

    63

    Equipment Insulation

    Bus Insulators

    Air SwitchesCircuit BreakersTransformers

    Bushings

    Bushings

  • 8/12/2019 L9-Impulse Voltages and Testing

    64/72

    64

    Bushings

    Condenser type

    bushings are built to

    grade the voltage

    from line to ground

    evenly.

    creep andcontamination

    SF6 weathersheds

    500 kV Bushing Type O

  • 8/12/2019 L9-Impulse Voltages and Testing

    65/72

    65

    g yp

    500 kV Bushing Type O

  • 8/12/2019 L9-Impulse Voltages and Testing

    66/72

    66

    g yp

  • 8/12/2019 L9-Impulse Voltages and Testing

    67/72

  • 8/12/2019 L9-Impulse Voltages and Testing

    68/72

    68

    External Equipment Clearances:

    Need to compare external equipment withstands with bussupport and air switch clearancesCompare phase-to-ground and phase-to-phase equipmentdimensions with the bus design

    Equipment manufacturers will set phase-phase and phase-ground dimensions to pass equipment test standards butthese are not coordinated with bus dimensionsTypically the clearances between live parts on theequipment are too small! Flashovers will occur at theequipment before the bus.Need to specify equipment clearances that willcoordinate with bus clearances

  • 8/12/2019 L9-Impulse Voltages and Testing

    69/72

    69

    Transformer Clearances: 138-12kvxfmr

    PhaseTo phase

    PhaseTo ground

    138kv 49 in. 49 in.

    12kv 6.5 in. 6.5 in.

  • 8/12/2019 L9-Impulse Voltages and Testing

    70/72

    70

    AP TransformerDesign Clearances:

  • 8/12/2019 L9-Impulse Voltages and Testing

    71/72

  • 8/12/2019 L9-Impulse Voltages and Testing

    72/72

    Transformer Terminated Lines

    Initial Switching surge

    ..Breaker openWhen you close this breaker

    a switching transient is createdthat doubles at the other end of

    the line because the transformeris open on the low side

    Reflected wave

    Close linebreaker first

    Then close thexfmr air switch