Lampiran Formulir-Formulir Pekerjaan Supervisi

Embed Size (px)

Citation preview

  • 8/17/2019 Lampiran Formulir-Formulir Pekerjaan Supervisi

    1/39

      FORMULIR - FORMULIR 

    Hal - 1 

    FORM 1

    SUMMARY OF DISBURSEMENT SCHEDULE OF CIVIL WORKS

  • 8/17/2019 Lampiran Formulir-Formulir Pekerjaan Supervisi

    2/39

      FORMULIR - FORMULIR 

    Hal - 2 

    SUMMARY OF DISBURSEMENT SCHEDULE OF CONSULTING SERVICES

  • 8/17/2019 Lampiran Formulir-Formulir Pekerjaan Supervisi

    3/39

      FORMULIR - FORMULIR 

    Hal - 3 

    CONTRACT PACKAGE CONTRACT TIME PROGRESS

    NO. OF DATE OFCONTRACT SUM

    (Incl. VAT)

    CONST.

    PERIOD

    (DAYS)

    ELAPSED

    TO DATE

    TO

    PREVIOUSTO DATE

    a. Original a. Original a. Original a. Original

    Contract Contract b. Contract b. CCO

      Change Order 

    b. Adenda b. Adenda c. Total date c. Total

    1 2 3 4 5 6 7 8 9 10 11 12 13 14

    NTP : Notice to Proceed Notice for Column 11

    C.O.W : Commencement of Works A : Environmental Problem E : Capital Delay Prepared by Consultant

    B : Equi pment Delay F : Management P roblem

    C : Lab ou r/ Ma n P ow er G : Co nt ra ct Doc um en t P ro bl em

    D : Material Delay H : Utilities

    R : Rainfall

    (…………………………)

    Team Leader 

    NO.

    LENGTH

    KM

    CAUSE

    OF

    DELAY

    PROJECT SUMMARY

    DISBURSEMENT

    TO DATE

    CERTIFIED CUMULATIVE

    PAYMENT TO DATE

    (Incl. Advance Payment)

    REMARKS

    CONTRACT PACKAGE CONTRACTOR

    NAMA PROYEKPEMILIK PEKERJAANPAKETKONTRAKTOR

    KONSULTAN SUPERVISI

    :

    ::

    ::

  • 8/17/2019 Lampiran Formulir-Formulir Pekerjaan Supervisi

    4/39

      FORMULIR - FORMULIR 

  • 8/17/2019 Lampiran Formulir-Formulir Pekerjaan Supervisi

    5/39

      FORMULIR - FORMULIR 

  • 8/17/2019 Lampiran Formulir-Formulir Pekerjaan Supervisi

    6/39

      FORMULIR - FORMULIR 

  • 8/17/2019 Lampiran Formulir-Formulir Pekerjaan Supervisi

    7/39

      FORMULIR - FORMULIR 

  • 8/17/2019 Lampiran Formulir-Formulir Pekerjaan Supervisi

    8/39

      FORMULIR - FORMULIR 

  • 8/17/2019 Lampiran Formulir-Formulir Pekerjaan Supervisi

    9/39

      FORMULIR - FORMULIR 

  • 8/17/2019 Lampiran Formulir-Formulir Pekerjaan Supervisi

    10/39

      FORMULIR - FORMULIR 

  • 8/17/2019 Lampiran Formulir-Formulir Pekerjaan Supervisi

    11/39

      FORMULIR - FORMULIR 

  • 8/17/2019 Lampiran Formulir-Formulir Pekerjaan Supervisi

    12/39

      FORMULIR - FORMULIR 

  • 8/17/2019 Lampiran Formulir-Formulir Pekerjaan Supervisi

    13/39

      FORMULIR - FORMULIR 

  • 8/17/2019 Lampiran Formulir-Formulir Pekerjaan Supervisi

    14/39

      FORMULIR - FORMULIR 

  • 8/17/2019 Lampiran Formulir-Formulir Pekerjaan Supervisi

    15/39

      FORMULIR - FORMULIR 

  • 8/17/2019 Lampiran Formulir-Formulir Pekerjaan Supervisi

    16/39

      FORMULIR - FORMULIR 

  • 8/17/2019 Lampiran Formulir-Formulir Pekerjaan Supervisi

    17/39

      FORMULIR - FORMULIR 

    Hal - 17 

  • 8/17/2019 Lampiran Formulir-Formulir Pekerjaan Supervisi

    18/39

      FORMULIR - FORMULIR 

    Hal - 18 

  • 8/17/2019 Lampiran Formulir-Formulir Pekerjaan Supervisi

    19/39

      FORMULIR - FORMULIR 

  • 8/17/2019 Lampiran Formulir-Formulir Pekerjaan Supervisi

    20/39

      FORMULIR - FORMULIR 

  • 8/17/2019 Lampiran Formulir-Formulir Pekerjaan Supervisi

    21/39

      FORMULIR - FORMULIR 

  • 8/17/2019 Lampiran Formulir-Formulir Pekerjaan Supervisi

    22/39

      FORMULIR - FORMULIR 

  • 8/17/2019 Lampiran Formulir-Formulir Pekerjaan Supervisi

    23/39

      FORMULIR - FORMULIR 

  • 8/17/2019 Lampiran Formulir-Formulir Pekerjaan Supervisi

    24/39

      FORMULIR - FORMULIR 

  • 8/17/2019 Lampiran Formulir-Formulir Pekerjaan Supervisi

    25/39

      FORMULIR - FORMULIR 

    Hal - 25 

  • 8/17/2019 Lampiran Formulir-Formulir Pekerjaan Supervisi

    26/39

      FORMULIR - FORMULIR 

  • 8/17/2019 Lampiran Formulir-Formulir Pekerjaan Supervisi

    27/39

      FORMULIR - FORMULIR 

    1 LOKASI :

    2 PEKERJAAN : Lean concreat / Footing / Pier / Abutment / Pierhead Beton K :

    Diaphragma Beton K :

    Plat Lantai Beton K :

    Dinding Beton K :

    Pile Cap Beton K :

    3 REFERENSI Request No : Shop Drawing No :

    Metode Pelaksanaan No : Gambar For Cons. No :

    4 MATERIAL UTAMA Supplier :

    5 FINISH PERMUKAAN Volume : M3  K :

    Fairface Concrete Exposed Conventional Lain-lain

    PEMERIKSAAN CATATAN KONTRAKTOR # 1 CATATAN FIELD TEAM # 2 CATATAN FIELD TEAM

    - Bahan

    - Perancah

    - Dimensi

    - Elevasi & Posisi As

    - Form Oil

    - Vertikalitas

    - Sambungan

    LAPORAN PEMERIKSAAN PEKERJAAN STRUKTUR BETON

       T   I   N   G

    NAMA PROYEKPEMILIK PEKERJAANPAKETKONTRAKTORKONSULTAN SUPERVISIKONSULTAN MANEJEMEN KONSTRUKSI

    ::::::

  • 8/17/2019 Lampiran Formulir-Formulir Pekerjaan Supervisi

    28/39

      FORMULIR - FORMULIR 

    - Kebersihan

    - Bond Agent

    - Utiliti

    - Tenaga Kerja

    - Vibrator 

    - Concrete Pump

    - Penerangan

    Tgl Tgl Tgl

    Jam Jam Jam

     

    Baik / Diterima / Disetujui X Tidak Baik / Ditolak 0   Belum Terpasang

    Tanda Tangan Kontraktor Tanda Tangan Inspector Tanda Tangan Chief Inspector  

    Supervisor : ……………………….. PT. ………………………………. PT. ……………………………….

       P   E   R   S   I   A   P   A   N

       P   E   N   G

       E   C   O   R   A   N

    LAPORAN PEMERIKSAAN PEKERJAAN STRUKTUR BETON

    NAMA PROYEKPEMILIK PEKERJAANPAKETKONTRAKTORKONSULTAN SUPERVISIKONSULTAN MANEJEMEN KONSTRUKSI

    ::::::

  • 8/17/2019 Lampiran Formulir-Formulir Pekerjaan Supervisi

    29/39

      FORMULIR - FORMULIR 

    Hal - 29 

  • 8/17/2019 Lampiran Formulir-Formulir Pekerjaan Supervisi

    30/39

      FORMULIR - FORMULIR 

  • 8/17/2019 Lampiran Formulir-Formulir Pekerjaan Supervisi

    31/39

      FORMULIR - FORMULIR 

  • 8/17/2019 Lampiran Formulir-Formulir Pekerjaan Supervisi

    32/39

      FORMULIR - FORMULIR 

  • 8/17/2019 Lampiran Formulir-Formulir Pekerjaan Supervisi

    33/39

      FORMULIR - FORMULIR 

  • 8/17/2019 Lampiran Formulir-Formulir Pekerjaan Supervisi

    34/39

      FORMULIR - FORMULIR 

    PENGUJIAN KEPADATAN LAPIS SUBGRADE

    RINGKASAN HASIL PENGUJIAN KEPADATAN SUMBER BORROW MAT SPESIFIKASI 4X

    LAPIS SUBGRADE …………………………….  AASHTO T99-97

    (AASHTO T233-96) - MDD : ………kN/m3

    - OMC : ………%

    LOKASI PENGUJIAN HASIL PENGUJIAN KESIMPULAN

    DRY DENSITY MOIST CONT PERSEN DENSITY

    kN/m3 % %KA ACCEPTED NOT ACCEPTED

    TANGGALSEKSI STA KI

    NAMA PROYEKPEMILIK PEKERJAANPAKETKONTRAKTORKONSULTAN SUPERVISIKONSULTAN MANEJEMEN KONSTRUKSI

    ::::::

  • 8/17/2019 Lampiran Formulir-Formulir Pekerjaan Supervisi

    35/39

      FORMULIR - FORMULIR 

    LEMBAR PENGESAHAN

    PENGUJIAN TARIK (STRAIN TEST)

    DAN

    PENGUJIAN LENTUR (BENDING TEST)

    BESI BETON BJTD - 40

    URAIAN NAMA / JABATAN TANDA TANGAN

    DIAJUKANKONTRAKTOR

    NAMA PROYEKPEMILIK PEKERJAANPAKETKONTRAKTORKONSULTAN SUPERVISIKONSULTAN MANEJEMEN KONSTRUKSI

    ::::::

  • 8/17/2019 Lampiran Formulir-Formulir Pekerjaan Supervisi

    36/39

      FORMULIR - FORMULIR 

    LAPORAN HARIANTanggal : ………………………………….

    Tanggal : ……………………… Catatan Cuaca :

    No. Jenis Pekerjaan Volume Satuan Keterangan

    No. Jenis Peralatan Volume Satuan Keterangan

    No. Jenis Material Volume Satuan Keterangan

    NAMA PROYEKPEMILIK PEKERJAANPAKETKONTRAKTORKONSULTAN SUPERVISIKONSULTAN MANEJEMEN KONSTRUKSI

    ::::::

  • 8/17/2019 Lampiran Formulir-Formulir Pekerjaan Supervisi

    37/39

      FORMULIR - FORMULIR 

    Hal - 37 

  • 8/17/2019 Lampiran Formulir-Formulir Pekerjaan Supervisi

    38/39

  • 8/17/2019 Lampiran Formulir-Formulir Pekerjaan Supervisi

    39/39

      FORMULIR - FORMULIR 

    Hal - 39 

    VOLUM E HARGA TOTAL

    NO. KONTRAK SATUAN HARGA

    ITEM (Rp.) (Rp.) VOLUME % PAY ITEM % PRESTASI VOLUME % PAY ITEM % PRESTASI VOLUME % PAY ITEM % PRESTASI

    1 3 4 5 6 7 8 9 10 11 12 13 14 15 16

    1 UMUM1,19 Pemeliharaan dan Perlindungan Lalu Lintas

    1. 20( 1) Labor at or ium

    1.20(2) Mobilisasi ( yang tidak tercakup pada 1.20 ( 1 )

    1,26 Pekerjaan dan penanganan aliran air yang sudah ada

    2 P EM BER SI HA N T EM PAT KERJA

    2 ,0 1 P embe rs ih an Te mp at Ke rj a

    3 PEMBONGKARAN

    4 PEKERJAAN TANAH

    4.03(2) Gal ian Biasa un tuk Dibuang

    4 .0 5(1) B or row Mat er ia l

    4,09 Urugan Material Berbutir ( Granular Backfill)

    4 ,12 Pasangan Ba tu Kosong ( B lind ing Stone )

    5 GALIAN STRUKTUR

    5.01(1) Penggalian struktur sampai kedalaman 2m

    5.01(2) Penggalian struktur sampai kedalaman lebih 2m tapi tidak lebih dari 4m

    5.01(3) Penggalian struktur sampai kedalaman lebioh dari 4m

    5.01(4) Tambahan Biaya Galian pada tempat yang mengandung air tanah

    6 DRAINASE

    6.05(2) Pipa Gorong - Gorong Beton bertulang Dia.40 cm Tipe A

    6 .05(3)a Saluran t ipe DS - 8

    6 .05(3)b Saluran t ipe DS - 8A

    6.06(4) Bak Kontrol Beton dan Penutup Tipe DC - 1

    6.07(4) Saluran Pasangan Batu Mortar Tipe DS - 7

    6.08(1) Pipa Drainase Dia.15 cm dengan perlengkapan sambungan dan penyangga

    6.08(2) Pipa Drainase Dia.20 cm dgn perlengkapan samb.dan penyang.

    6 .08(4) Deck Dra in beserta assosorisnya Tipe 1

    6 .07(2) Box Cul lve rt ( 120 x 120 cm )

    7 SUBGRADE

    8 L AP IS AN PO NDAS I AGREG AT ( SUB. BASE )

    9 PERKERASAN

    9.10(4) Persiapan Aspal Concrete Course dan Tack coat

    10 STRUKTUR BETON

    10.03(1 ) PCI Girder,Ben tang 16 m

    10.03(6 ) PCI Girder ,Bentang 30 m

    10.03(7 ) PCI Girder ,Bentang 35 m

    10.03(8 ) PCI Girder, Bentang 40 m

    10.03(9) Plat Pracetak ( concrete plate )

    10.03(12) Precast Planter Concrete Box

    10.05(5) Penyediaan Tiang Pancang Beton Bulat Pretensioned,Dia. 60 cm

    10.05(6) Pemancangan TP. Bulat Pretensined, Dia.60 cm

    10.05(7) Penyediaan dan Pemanc. TP beton Pretensioned. Pile Test Dia.60 cm

    10.05(8)a Pemotongan dan Beton Pengisi TP Beton Pretensioned Dia.60 cm

    10.05(8)b

    10.05(9) Tambahan biaya utk 10.05(2) dan 10.05(6) daerah ada air 

    10.05(10) PDA Test TP beton bulat Pretensioned

    10.05(11) Test Pembebanan statis ( Loading Test ) TP Pretensioned

    10.05(12) Pengeboran Awal untuk Tiang Pancang

    1 0, 08 P embo ra n P erco ba an

    Disetujui Diperiksa Diajujan,

    KONSULTAN MANAJEMEN KONSTRUKSI KONSULTAN SUPERVISI KONTRAKTOR

    ………………………………………………

    ( ……………………………………………..) ( ……………………………………………..) ( ……………………………………………..)

    RESIDENT ENGINEER GENERAL SUPERINTENDANT

    2

    U R A I A N SAT

    LAPORAN KEMAJUAN MINGGUAN

    BOBOT (%) S/D MINGGU LALU MINGGU INI

    KEMAJUAN (PROGRES)

    S/D MINGGU INI

    NAMA PROYEKPEMILIK PEKERJAANPAKETKONTRAKTORKONSULTAN SUPERVISIKONSULTAN MANEJEMEN KONSTRUKSI

    ::::::