LIGO Laboratory 1 LIGO-G030289-00-M Adv. LIGO Facilities Modifications (FAC) Plans, Schedule, Costs, Team Plan, Schedule Costs Team

LIGO-G030289-00-M LIGO Laboratory1 Adv. LIGO Facilities Modifications (FAC) Plans, Schedule, Costs, Team Plan, Schedule Costs Team

  • View
    218

  • Download
    0

Embed Size (px)

Citation preview

Page 1: LIGO-G030289-00-M LIGO Laboratory1 Adv. LIGO Facilities Modifications (FAC) Plans, Schedule, Costs, Team Plan, Schedule Costs Team

LIGO Laboratory 1LIGO-G030289-00-M

Adv. LIGO Facilities Modifications (FAC)Plans, Schedule, Costs, Team

Plan, Schedule Costs Team

Page 2: LIGO-G030289-00-M LIGO Laboratory1 Adv. LIGO Facilities Modifications (FAC) Plans, Schedule, Costs, Team Plan, Schedule Costs Team

LIGO Laboratory 2LIGO-G030289-00-M

Adv. LIGO Program Management (FAC)Scope

Conversion of the 2km vacuum system to 4 km» Move the mid-station BSC chamber to the end station connected to the

existing BSC chamber with a spool piece» Install a vacuum spool piece (pipe) in the mid-station where the BSC

chamber previously resided Portable Clean Rooms

» Build more HAM and BSC units to support more parallel installation activity and to support SEI and SUS clean assembly; for each observatory:

– 2 BSC-size clean rooms for high bay assembly area for SEI and SUS– 2 BSC-size clean rooms in the corner LVEA and 1 per end-station VEA for

SEI/SUS integration for “cartridge” installation into chambers– 1 additional HAM-size clean room for parallel installation of input and output optics– And 2 additional BSC-size clean rooms for LHO to eliminate need for clean rooms

to pass from one IFO to the other and to support parallel installation preparation

Input/Output Mode Cleaner Tube Replacement & Bake-out» Larger diameter vacuum tubes are needed for the input & output sections» Tubes must be vacuum baked (perhaps stand-alone)

Page 3: LIGO-G030289-00-M LIGO Laboratory1 Adv. LIGO Facilities Modifications (FAC) Plans, Schedule, Costs, Team Plan, Schedule Costs Team

LIGO Laboratory 3LIGO-G030289-00-M

Larger Diameter Mode (MC) Cleaner Tubes

Larger diameter tube

Larger diameter tube

Possibly largerdiameter tube

Page 4: LIGO-G030289-00-M LIGO Laboratory1 Adv. LIGO Facilities Modifications (FAC) Plans, Schedule, Costs, Team Plan, Schedule Costs Team

LIGO Laboratory 4LIGO-G030289-00-M

Adv. LIGO Program Management (FAC)Schedule

Procurement/contracting for the FAC equipment is not schedule critical (lots of float)

Installation of the IO vacuum tubes occurs during installation activities

Page 5: LIGO-G030289-00-M LIGO Laboratory1 Adv. LIGO Facilities Modifications (FAC) Plans, Schedule, Costs, Team Plan, Schedule Costs Team

LIGO Laboratory 5LIGO-G030289-00-M

FAC Costs

All costs are in base year dollars (un-escalated) Total cost = $4,182K including 22% contingency Proposed construction cost = $4,182K – 1.7 x $198K direct

labor incl. indirect = $3,845K Direct labor costs are borne by LIGO operations funds

Page 6: LIGO-G030289-00-M LIGO Laboratory1 Adv. LIGO Facilities Modifications (FAC) Plans, Schedule, Costs, Team Plan, Schedule Costs Team

LIGO Laboratory 6LIGO-G030289-00-M

FAC Costs: 2km to 4km Conversion

2km to 4km conversion estimate based on initial LIGO experience Planned as a subcontract ($370K) with Lab oversight/management

Page 7: LIGO-G030289-00-M LIGO Laboratory1 Adv. LIGO Facilities Modifications (FAC) Plans, Schedule, Costs, Team Plan, Schedule Costs Team

LIGO Laboratory 7LIGO-G030289-00-M

FAC Costs: Clean rooms

Costs based on initial LIGO actual costs for clean rooms, escalated to base year dollars

Includes estimate for in-house labor to place and oversee the clean room fabrication contract

$1,032K IFO1 + $747K IFO2 = $1,779K total

Page 8: LIGO-G030289-00-M LIGO Laboratory1 Adv. LIGO Facilities Modifications (FAC) Plans, Schedule, Costs, Team Plan, Schedule Costs Team

LIGO Laboratory 8LIGO-G030289-00-M

FAC Costs: I/O Tubes

$651K IFO1 + $585K IFO2 + $585K IFO3 = $1,821K total

Page 9: LIGO-G030289-00-M LIGO Laboratory1 Adv. LIGO Facilities Modifications (FAC) Plans, Schedule, Costs, Team Plan, Schedule Costs Team

LIGO Laboratory 9LIGO-G030289-00-M

Adv. LIGO Program Management (PM)Team

Cognizant Engineers:» John Worden

– Directed the initial LIGO Vacuum equipment effort– LHO Vacuum Equipment Lead Engineer

» Alan Sibley– Directed the initial LIGO Beam Tube bake-out effort at LLO– LLO Vacuum Equipment Lead Engineer