LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1

LS1 Day: The Injectors

  • Upload
    tawana

  • View
    49

  • Download
    2

Embed Size (px)

DESCRIPTION

LS1 Day: The Injectors. S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Days: The Injectors. Key Dates What will run in 2013? Reminder: What will not be done What will (should?) be done How are we organised ? A few more outstanding questions - PowerPoint PPT Presentation

Citation preview

Page 1: LS1 Day: The Injectors

1

LS1 Day: The Injectors

S. Baird EN/MEF

Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop….

LS1 Day: The Injectors

Page 2: LS1 Day: The Injectors

LS1 Day: The Injectors 2

LS1 Days: The Injectors

• Key Dates• What will run in 2013?• Reminder: What will not be done• What will (should?) be done• How are we organised?• A few more outstanding questions• AD, EAST Area & NORTH Area• Conclusions

Page 3: LS1 Day: The Injectors

LS1 Day: The Injectors 3

Key dates at the start of LS1 PSBDescription Date

Beam stop (end of Isolde Physics run) 3rd December 2012

PSB radiation cool-down period 4th to 14th December 2012

PSB magnet HV tests 12th to 20th December 2012

PSB ready for general access 21st December 2012

Page 4: LS1 Day: The Injectors

LS1 Day: The Injectors 4

Key dates at the start of LS1 PSDescription Date

Beam stop (end of FT Physics run) 26th November 2012

PS radiation cool-down period 27th November to 9th December 2012

POPS & MPS tests 27th November to 12th December

PS Magnet tests 10th December to 20th December

PS ready for general access 21st December 2012

Page 5: LS1 Day: The Injectors

LS1 Day: The Injectors 5

Key dates at the start of LS1 SPSDescription Date

End of FT Physics 26th November 2012

SPS radiation cool-down period 26th November to 9th December 2012

RP survey and patrol 5th December to 7th December 2012

Magnets tests and inspections. 10th December 2012 to 18th January 2013*

General access 21st January 2013*

• All services must remain on until the 18th January 2013! (ATLAS water?)

• Only works that do not require access and do not affect the operational mode of the SPS will be scheduled before the 21st January 2013!

Page 6: LS1 Day: The Injectors

LS1 Day: The Injectors 6

Key dates at the end of LS1 PS & PSBDescription Date

End of shutdown work 19th February 2014

Commissioning new access system 6th January 2014 to 19th February 2014

Hardware test period 20th February to 14th March 2014

Patrols with new access system 15th March to 19th March 2014

Beam to PSB 20th March 2014

Beam to PS 10th April 2014

Beam to SPS 1st May 2014

Page 7: LS1 Day: The Injectors

LS1 Day: The Injectors 7

Key dates at the end of LS1 SPSDescription Date

All Water circuits back online and in service 31st January 2014

SPS Ring Patrol 3rd to 5th February 2014

HV magnet test 6th February

Hardware test period 7th February to 17th April

DSO tests 22nd to 24th April 2014

Start-up of the SPS 25th April 2014

Beam available from the PS 1st May 2014

SPS/TI2/TI8 Operational 9th June 2014

Page 8: LS1 Day: The Injectors

LS1 Day: The Injectors 8

Note for the end of 2014

• LHC will restart with beam in autumn 2014

• It is not planned to have a stop of LHC beam operation at Christmas 2014– 1 week of standby for LHC & Injectors– Consequences for maintenance activities???– FT programs will have a normal stop from

December 2014 to April 2015.

Page 9: LS1 Day: The Injectors

LS1 Day: The Injectors 9

What will run in 2013?

EN/MEF Coordination teams

Page 10: LS1 Day: The Injectors

LS1 Day: The Injectors 10

What will run in 2013?• Main constraint is CV maintenance

– PS Complex water off in May, June & July• LINAC3

– Test with new ions for NA61 2014 operation– Mid-January for 13 weeks (Argon)– Early August for 13 weeks (Xenon)

• CTF3– March to November– Stop 3 months in summer

• ISOLDE – REX-IBIS

• 3MeV test stand– February to April – August to December with a new source

Page 11: LS1 Day: The Injectors

LS1 Day: The Injectors 11

Reminder: What will not be done…

Page 12: LS1 Day: The Injectors

LS1 Day: The Injectors 12

Reminder: What will not be done…

• SPS Cable clean up around BA5• Replacement of irradiated cables BA1• Replacement of all irradiated cables TCC2 & TDC2

– Look at replacing a limited number of cables to avoid duplication of work and reduce overall dose?

• All preparations for the connection of Linac4 to the PSB before LS2

• PSB cable clean-up (requested but never formally agreed)– Some preparatory work to at least identify cables?

• EAST Area cabling• NA62 ventilation in NORTH Area

– Must be done in the 2014/15 NORTH Area stop

Page 13: LS1 Day: The Injectors

LS1 Day: The Injectors 13

What will be done• Consolidation and maintenance work

– all groups• Replacement of PS Complex access system

– 28 access points, 100 doors– Both systems to run in parallel during 2014…– The time critical activity

• New PSB Interlock system• Replacement of the PS tunnel ventilation system

– Requires sealing of PS tunnel & TT2 (not a trivial exercise!)• New PS beam imminent warning system (BIW)• Addition of shielding over the Route Goward at the PS

– Major Civil engineering project which will complicated access to the PS area.• Removal of 4 PS main magnets• TT2 magnet renovation

Page 14: LS1 Day: The Injectors

LS1 Day: The Injectors 14

• Vertical re-alignment of SPS between 5 & 6 – Needs displacement of the support jacks

• Full re-alignment of all machines• Replacement of the SPS main power supply transformers• Replacement of approximately 15 SPS main magnets• Change of 12 additional SPS main magnets for e-cloud vacuum chamber coating

What will be done

Page 15: LS1 Day: The Injectors

LS1 Day: The Injectors 15

How are we organised

• Now we have the list of things to do– Aim to produce a first resource loaded realistic schedules for

Injectors– Planning and Coordination meetings – Detailed discussions with Groups (dedicated contact people)

• Machine Coordinators = the Usual suspects– AD & PSB: Nicolas Gilbert – (PSB: D Hay handover date to be defined)– PS: Ray Brown– SPS: David McFarlane– Other problems concerns: Vinod Chohan or Simon Baird

Page 16: LS1 Day: The Injectors

LS1 Day: The Injectors 16

How are we organised?

• We will start from the information already collected and all the approved activities entered into the PLAN database

• Please inform us about new activities• Major new activities must also be entered in PLAN

– Management approval• IMPACT tool will be used as part of the planning once we

have the baseline schedule– Access Control– Activity completion– Documentation control ECR’s etc

Page 17: LS1 Day: The Injectors

LS1 Day: The Injectors 17

How are we organised?

A situation to avoid….

Page 18: LS1 Day: The Injectors

LS1 Day: The Injectors 18

A few outstanding questions to be addressed

• No cable clean-up in BA5 – Is there an issue for cabling for new installations around BA5 (SPS)– BI requests….

• No cable clean-up in PSB – Again is there an issue for cabling for new installations– BI equipment– EPC new power converters– Interlock systems– New ABT equipment…

• Renovation of TT2 magnets– Can we really remove renovate and re-install up to 39 magnets??– Can we do this work in situ?

Page 19: LS1 Day: The Injectors

LS1 Day: The Injectors 19

AD (on top of “standard” activities)

• RF and Stochastic cooling consolidation• Removal of a main dipole– Preparation of a magnet consolidation program for AD

• Removal of unused transfer lines (7000, 8000, ATP) and general clean up to prepare for ELENA

• A delay of AD shutdown 2014/15 is under discussion to allow for a delay of…– Additional works for ELENA & Gbar installation– New building (kickers storage etc…)

Page 20: LS1 Day: The Injectors

LS1 Day: The Injectors 20

NORTH Area

• NA62 ventilation separation is delayed until 2014/15 North area shutdown– 2014 run for NA62 will need RP mitigation measures – Reduced beam intensity – Long flushing periods before access to experimental cavern

• GIF++ installation in H4• NORTH Area long-term consolidation– Prioritized plan starts in 2013 and continues …– In 2013 TCC2 & TDC2 works (with a limited replacement of

irradiated cables t.b.c…)

Page 21: LS1 Day: The Injectors

LS1 Day: The Injectors 21

EAST Area

• DIRAC will be removed to make way for a new irradiation facility

• This is the first step in the EAST Area renovation as presented at the EAST Area Day

Page 22: LS1 Day: The Injectors

LS1 Day: The Injectors 22

Conclusions

• Now we can get started – Business as usual = Coordination meetings…– PS Complex access system is the time critical item– SPS: Two major activities have been removed– Please inform us of changes to your needs (MEF Coordinators and

PLAN)• Some questions

– BA5 and PSB: Will we install equipment without new cables?– TDC2/TCC2 Can we make a limited cable replacement campaign?– TT2 magnet renovation?– Is non-stop operation from early 2014 to the end of 2015 a

concern?– …..

Page 23: LS1 Day: The Injectors

LS1 Day: The Injectors 23

Conclusions