M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

Embed Size (px)

Citation preview

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    1/52

     

    PROJECT ID: CEET/ 07/48

    KIGALI INSTITUTE OF SCIENCE AND TECHNOLOGY

    INSTITUT DES SCIENCES ET DE TECHNOLOGIE DE KIGALI 

    Avenue de l’ Armée, B.P. 3900 Kigali, Rwanda

    FACULTY OF ENGINEERING

    DEPARTMENT OF CIVIL ENGINEERING AND ENVIRONMENTAL TECHNOLOGY

    A PPROJECT

    ON

    submitted by

    ZIRIMWABAGABO LEODOMIR

    Under the Guidance of

    Mr. KAYINAMURA FRANCIS

    Submitted in partial fulfillment of the requirements for the award of

    BACHELOR OF SCIENCE DEGREE IN

    CIVIL ENGINEERING AND ENVIRONMENTAL TECHNOLOGY

    FEBRUARY 2008

    “ Comparison between concrete

    blocks and bricks from Ruliba” 

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    2/52

      1

    CHAPTER I : 1.0 : INTRODUCTION. 

    1.1: Statement of problem. 

    At the beginning as history tell it, people lived in a primitive way. They lived in caves

    and later small communities were developed and shelters were put up. At that time,

    natural building materials was easily available and have been used as the technology in

    construction of buildings were developed.

    Although, clay bricks and concrete blocks are improved in order to obtain safe and

    esthetic locations, their price are not affordable for every one. Since, raw materials for

    manufacturing building materials are cheap and rise day to day. For instance, one bag of

    Portland cement (50kg) was being bought at 5,000rwf ten years ago, but now costs

    13,000rwf . It means that, this increases 10% every year.

    Similarly, labor cost increases for a considerable rate. In addition, cutting trees for firing

    ceramic materials damages our forest which leads to environmental problems, and as a

    result, the sustainable development is not ensured.

    1.2 : Objectives of study.

    Due to cheapness of building materials and the environmental problems due to

    deforestation , this project intends to achieve the following objectives :

    •  To facilitate the community to select required structural materials in terms of

    stability, economy and esthetic;

    •  To learn which type of structural materials can be used to improve engineering

    structure at reasonable price;

    •  To decide what kind of structure to make;

    •  To minimize the deforestation rate due to cutting trees for firing the bricks;

    •  To make sure the safety of the building and to give a good appearance to a

     building;

    •  To enable individual to be familiar with before hand the outlay of the work.

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    3/52

      2

     

    1.3: Justification.

    The Engineering sector is in position to discover which bricks or blocks available in plenty, which can be utilized to put up the building structure of acceptable qualities, with

    low cost, thus necessitate the making comparison between concrete blocks and bricks

    from Ruliba, which are current building materials mostly used in Rwanda.

    It is not easy to decide which kind of structural materials to use in construction because

    of different building material made by diverse organizations which appear on market.

    Generally, some people prefer to use little cost structural material without consideration

    of other necessary properties. In fact, diverse factors should be considered such as

    economics, structural and environmental factors.

    Moreover, rural and urban communities have no required knowledge about building

    structure. For that matter it is important to inform them on structural blocks and bricks

    commonly available on market like concrete blocks and Ruliba bricks. 

    One of the government policy is to protect the environment by reducing the deforestation

    velocity due to use of timber in various purposes. Then, the production of ordinary bricks

    was reduced.

    As a solution, it is time to give the information on modern structural bricks and blocks

    which complete engineering requirements. The building development requires the

    construction of apparent building. For achieving this purpose it necessary to be familiar

    on face bricks most used in construction of houses like Ruliba bricks compared to

    concrete blocks.

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    4/52

      3

     

    1.4 : Scope of study.

    This study was conducted on manufacturing place as well as site of construction where

     bricks and blocks are considered as basic building materials. It includes the cost, some

     properties and technical specifications necessary to achieve the project.

    As the basic of this topic is Ruliba bricks and concrete blocks, that is reason why some

    experiments like laboratory test was conducted as well as considerable readings in

    relation to the topic was proceeded to compare the cost and the strength of both.

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    5/52

      4

    CHAPTER II. 2.0 : LITERATURE REVIEW.

    2.1 : Varieties of bricks and blocks.

    Bricks may be defined as small a cored building unit of rectangular shape that is

    composed of organic non-metallic substances of mineral origin hardened by heat or

    chemical action. Blocks are similar defined but have larger dimensions than that of

     bricks. Blocks are larger than bricks.

    2.1.1 : Clay bricks.

    Clay bricks like other ceramic products are based on clay, to which various amount of

    quartz and feldspar have been added. Selected proportions are mixed with water, shaped,

    dried and fired to produce the structural clay products of brick, roof and structural tiles

    etc.

    Types of bricks.

    Bricks of masonry units may be solid, hollow, or architectural terra cotta. All types can

    serve a structural function, a decorative function, or a combination of both. The various

    types differ in their formation and composition.

    Building bricks.

    Also called common or hard bricks, are made from ordinary clay and are fired in kilns.

    These bricks have no particular shoring, markings, surface texture, or color. Because

     building bricks are generally used as the burning courses in either solid or cavity brick

    walls, the harder and more durable type are preferred.

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    6/52

      5

    Face bricks.

    Face bricks are of better quality and has better durability and appearance than structural

     brick. Because of this, face bricks are used in exposed wall faces. The most common face

     brick colors are various shades of brown, red, gray, yellow, or white.

    Clinker brick.

    Clinker brick is over burned in the kiln. Clinker bricks are usually rough, hard, durable,

    and sometimes irregular in shape.

    Pressed brick.

    Pressed brick is made by a dry-press, rather than by kiln firing. Pressed brick have

    regular, smooth faces, sharp edges, and perfectly square corner. Normally, they are used

    like face brick.

    Glazed Brick.

    Glazed brick has one surface coated with a white or colored ceramic glazing. The glazing

    forms when mineral ingredients fuse together in glasslike coating during burning. Glazed

     bricks are particularly suited for walls or partitions in hospitals, dairies, laboratories. And

    other structures requiring sanitary conditions and ease of cleaning.

    Fire brick.

    Fire brick is made from a special type of clay. This clay is very pure and uniform and is

    able to withstand the high temperatures of fireplaces, boilers, and similar constructions.

    Fire bricks are generally larger than other structural bricks and are often hand-molded.

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    7/52

      6

    2.1.2 : Calcium silicate bricks.

    Raw materials: Siliceous aggregate, a high calcium lime and water; very fine aggregate

    :1.15 mm sieve.

    Size: 215 x 102.5 x 65 mm

    Density:1700 kg/ m3

    Strength:14-27.5 N/mm2

    2.2 : Bricks forming process.

    2.2.1 : Manufacture process.

    After raw clay has been screened and crashed, machine-made bricks are formed either by

    extrusion and cutting, or by pressing. Plastic clays may be extruded as continuous column

    of rectangular section (with or without perforations) which is cut into individual bricks by

    wire, acting like a chisel cutter, as it emerges from the die.

    2.2.2 : Firing.

    Firing transforms the raw clay brick into a rigid continuous (although usually porous

    ceramic by way of a complicated succession of physical and chemical changes. Water is

    lost rapidly as the kiln temperature rise above 1000C.

    The clay minerals decompose between 400 and 7000 c. At about 900

    0C crystalline silica,

    alumina and spinel compounds appear and the mineral mullite 3Al2O32SiO2 forms above

    about 10000

    C.

    The minor oxide constituents include Na2O, K 2O, MgO, CaO, and FeO produce relatively

    low melting eutectic mixtures with principal components of SiO2 and Al2O3, so that some

    melting may occur below 10000C.

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    8/52

      7

     

    2.3 : Technical specification of bricks.

    2.3.1: Strength of bricks.

    Bricks often have to withstand great compressive stresses. The durability of the masonry

    depends upon the strength of the bricks. Common building bricks should have a

    minimum strength of 35 kg/cm2 . Also, the compressive strength of any individual brick

    should not fall below the average compressive strength specified for the corresponding

    class of brick by more than 20% .

    The average compressive strength of common burnt clay bricks is given

    in table 2.1.

    Class

    designation

    Average

    strength not

    less than

    kgf/cm2 

    (N/mm2) Compressive

    strength less

    than kgf/cm2 

    (N/mm2)

    350

    300

    250

    200

    175

    150

    125

    100

    75

    50

    35

    350

    300

    250

    200

    175

    150

    125

    100

    75

    50

    35

    (35)

    (30)

    (25)

    (20)

    (17.5)

    (15)

    (12.5)

    (10)

    (7.5)

    (5)

    (3.5)

    400

    350

    300

    250

    200

    175

    150

    125

    100

    75

    50

    (40)

    (35)

    (30)

    (25)

    (20)

    (17.5)

    (15)

    (12.5)

    (10)

    (7.5)

    (5)

    Table 2.1:Average compressive strength of common burnt clay bricks. IS :1077- 1976.

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    9/52

      8

     

    2.3.2: Test for compressive strength.

    The specimen brick is immersed in water for 24 hours. The frog of the brick is filled flush

    with 1:3 mortar and the brick is stored under damp jute bags for 24 hours followed by

    immersion in clean water for three days. The specimen is then placed between the plates

    of compression testing machine.

    Load is applied axially at a uniform rate of 14N/mm2(140Kg/cm

    2) and the maximum load

    at which the specimen fails is noted for determination of compressive strength of brick

    given by:

    Compressive strength = Maximum load at failure/Loaded Area of bricks (Average of

    five results shall be reported).

    2.3.3: Compressive strength and other mechanical properties.

    The compressive strength is the only mechanical property used in brick specification. It is

    the failure stress measured normal to the bed face. Bricks are tested wet, normally with

    frogs filled with hardened mortar. A considerable variation is found between individual

     bricks and a batch of ten is tested to obtain a mean strength.

    Generally, compressive strength decreases with increasing porosity, but strength is also

    influenced by clay composition and firing. The compressive strength is limited by brittle

    fracture and is sensitive to individual flows in the sample under test, including those

    associated with large particles, fissures formed during shaping, and shrinkage cracks. The

    young’s modulus of elasticity of brick ceramic lies usually in the range 5 to 30KN/mm2.

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    10/52

      9

     

    2.3.4: Factors affecting compressive strength.

    Arnold W. Hendry in structural masonry (1998) have stated the important factors in

    determining the compressive strength of masonry as follow:

    1.  Unit characteristics: Strength; type and geometry like solid, perforated, hollow,

    relative height; absorption.

    2.  Mortar characteristics: Strength developed by mix, water/ cement ratio, water

    retentivity; relative deformation and relative thickness.

    3.  Masonry: Bond; direction of stressing; local stress.

    Some of these factors, such as the unit characteristics, are determined in the

    manufacturing process, while others, such as mortar properties, are susceptible to

    variations in constituent materials, proportioning, mixing and accuracy of construction.

    2.3.5: Size of bricks.

    The International Standard states that the length of brick should be equal to two

    times width plus one joint size of 10mm. So that, the length = 2width+1 joint. Most

    commonly used bricks format are 215x102,5x65mm and 210x100x63mm with

    mortar joints of 10mm the size becomes respectively 225x112,5x75mm and

    220x110x73mm.

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    11/52

      10

    2.4: Concrete blocks features.

    2.4.1: Concrete block technology.

    Concrete block technology offers a speedier, cost effective, environmentally sound

    alternative to conventional walling materials like bricks, stones, compressed earth blocks,

    etc... It is based on the principle of densification of a lean concrete mix to make a regular

    shaped, uniform high performance masonry unit.

    Concrete block technology can be easily adapted to suit special needs of users by

    modifying design parameters such as mix proportion, water/cement ratio and type of

     production system. It is an effective means of utilizing wastes generated by stone

    crushers, quarrying and stone processing units. The technology has high potential in areas

    where raw materials are easily available.

    2.4.2: Business.

    The concrete block technology package is a highly profitable business for micro and

    small scale building material producers and construction companies. The market for

    concrete blocks is growing at a rapid rate, specially in the areas where burnt bricks are

    not easily available or are of poor quality.

    2.4.3: Product.

    The specifications and the characteristics of a concrete block depend on the machine usedto manufacture concrete blocks. The most common size of solid concrete blocks is

    300x200x150mm. The basic raw material is cement, fine aggregate and coarse aggregate.

    Very little water is used. This is possible only with mechanized compaction and vibration

    and gives the block high quality in spite of the lean mix, which uses very little cement.

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    12/52

      11

    Weight of a concrete blocks can be surface engineered by using pieces of stone or

    ceramic waste on their face. Another common type are hollow concrete blocks. They are

    made with a richer mix, but offer a number of advantages, such as lighter weight, easier

    handling and facility for conducting or reinforcement through the hollows.

    2.4.4: Unique features of concrete block technology :

    •  Cost effective compared to other traditional walling systems

    •  Maximum utilization of stones wastes and local resources

    •  Structural performance can be engineered

    •  Decentralized local production

    •  Offers business opportunities

    2.4.5: Production process.

    Concrete blocks are usually produced using a semi-mechanized stationary type machine.

    The other production systems are-manual moulds which require hand tamping, a mobile

    semi-mechanized egg-laying machine and fully mechanized system which combines

    compression and vibration.

    High quality machines provide optimum vibration in the mix so that the ratio of cement

    used can be reduced substantially without compromising on the strength of the blocks.

    The machine also compacts and consolidates the mix so that the blocks are uniform in

    size and attain desired physical properties.

    The blocks are cured for a minimum period of 14 days, before they are ready to use. On

    an average 600-800 blocks can be made in 8 hours by 1 skilled and 6-8 semi-skilled

    workers.

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    13/52

      12

    2.4.6:Building with concrete blocks.

    Concrete blocks can be used like any other masonry unit to build foundations, walls,

    arches and corbels, etc. A typical concrete block is equivalent to 4.5 bricks, thusconstruction is faster than with other masonry units. The mortar used is also less which

    results in cost saving. They are compatible with other materials like fired bricks, dressed

    stone and compressed earth blocks for composite wall construction.

    Acceptability of concrete blocks is very high in urban areas for all types of buildings.

    They are very popular as a long lasting, low maintenance and investment for institutional

    and industrial buildings. The permanence of a cement based product is making concrete

     blocks a preferred choice in rural areas as well.

    2.4.7: Perforated and hollow block units.

    A number of investigators have studied the effect of different types of units on

    compressive strength and an extensive series of tests were undertaken by West et Al. at

    the British Ceramic Research Association to examine the compressive strength of

     brickwork built with a variety of wire-cut bricks having different hole patterns with

     perforation ratios up to 20 per cent.

    The results of these tests showed that if the brickwork strength was calculated on the

     basis of a standard crushing test on the unit, the perforation pattern made little practical

    difference. In these tests, the perforations were either circular holes or slots with round

    ends, but in some tests reported by Monk the units had rectangular slots, and these tests

    showed reduced compressive strength in prisms. It would seem probable that such slots

    would introduce stress concentrations, not only in service but also in manufacture, which

    would be a source of weakness.

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    14/52

      13

    Schellbach has examined the strength of various types of highly perforated units and has

    found that the highest ratio of masonry strength to unit strength was obtained with a

     perforation ratio of 38-43 per cent. Schellbach’s study included examination of stress

    concentration factors associated with different perforation patterns, and he concluded that

    these remain within acceptable limits even with rectangular slots, provided that the

    corners are well rounded.

    Hollow block masonry may be built with the cores either unfilled or filled with concrete .

    In the former case the mortar joint may cover the whole of the bed face of the block (full-

     bedded) or only the outer shells (face-shell-bedded). These different construction

    methods result in considerable variations in structural behavior and this quite clearly

    results in a more complex situation than for solid units in assessing masonry strength.

    It is usual to take the strength of hollow units which are to be laid full-bedded as the

    maximum test load divided by the gross area of the unit. This value is then used to

    determine the masonry strength as if the unit were solid.

    The stress conditions and mode of failure of shell-bedded hollow block masonry differ

    considerably from those in solid block masonry. They have been investigated by Shrive

    who has shown that tensile stresses are developed in the webs of the blocks, which

    eventually lead to failure.

    Hollow block work masonry is frequently built with the cores filled with concrete (grout).

    The compressive strength of this type of masonry is found to be considerably less than

    the sum of the strengths of the hollow block and concreted core tested separately, even

    when the materials are of approximately the same nominal strength.

    This is because there is a difference in the strains in block and fill materials at ultimate

    load.

    Thus Hamid and Drysdale have found the strain at ultimate strength of fill material used

    in their investigations to be about 0.0024 compared with the strains at failure of the block

    material of 0.0036. BY Arnold W. Handry in Structural Masonry (1998)

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    15/52

      14

    2.4.8: Benefit of using concrete blocks .

    It is faster to built with concrete blocks than with bricks and the amount of mortar is

    reduced to less than half. If face shell bedding is used, in which the mortar is placedonly along the edges of the blocks, the consumption of mortar is reduced by a further

    50%. However, the total cement required for the blocks and mortar is far greater than that

    required for the mortar in a brick wall.

    2.5: Concrete blocks forming process.

    2.5.1: Mix proportion of blocks.

    Concrete blocks are often made of 1:3:6 concrete with a maximum  aggregate size of

    10mm or a cement-sand mixture with a ratio of 1:7, 1:8  or 1:9. These mixture , if

     properly cured, give concrete blocks a compressive strength well above what is required

    in one-storey building.

    The blocks may be solid, cellular or hollow. Cellular blocks have cavities with one endclosed while in hollow the cavities pass through. Lightweight aggregate such as cracked

     pumice stone is sometimes used. Blocks are made to a number of coordinating sizes, the

    actual sizes being About 10mm less to allow for the thickness of the mortar. 

    2.5.2: Blocks manufacturing.

    Blocks can be made by using a simple block- making machine operated by an engine

    or by hand. They can also be made by using simple wooden moulds on a platform or

    floor. The mould can be lined with neat steel plate to prevent damage during

    tamping and to reduce wear on the mould. In large-scale production steel moulds are

    often used.

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    16/52

      15

     

    The wooden mould is initially oiled overnight and need not be oiled each time it is

    filled. It is sufficient to wipe it clean with a cloth. The concrete, of stiff or plastic

    consistency placed in layer is compacted with a 3 kg rammer. The mould has a

    steel plate cut to the shape of the Block which is put on as a lid and held dawn

    as the hollow-making pieces are then loosened and the sides of the mould removed

    with a swift motion. All parts of the mould should be slightly tapered so they can be

    easily removed from the block.

    Starting the day after the block have been made, water is sprinkled on them for two

    weeks during curing. After 48 hours the blocks can be removed for stacking. But the

    wetting is continued. After curing, the blocks are dried. If damp blocks are put in wall,

    they will shrink and cause cracks. To assure maximum drying, the blocks are dried. If

    damp blocks are stacked interspaced, exposed to the prevailing wind and in the case of

    hollow blocks, with the cavities laid horizontal to form a continuous passage for the

    circulating air.

    2.5.3: Decorative and Ventilating blocks.

    Decorative concrete or sand/cement blocks can serve several purposes:

    •  Provide light and security without installing windows, or shutters.

    •  Provide permanent ventilation.

    •  Give an attractive appearance.

    In addition, some are designed to keep out rain while others include mosquito-proofing.

    Blocks of simple shape can be made in a wooden mould by inserting pieces of wood to

    obtain the desired shape, but more complicated designs usually require a professionally

    made steel mould.

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    17/52

      16

     

    2.6.Mortar for jointing.

    Mortar is a plastic mixture of water and binding materials used to join concrete blocks,

     bricks or other masonry units. It is desirable for mortar to hold moisture, be plastic

    enough to stick to the trowel and the blocks or bricks and finally to develop adequate

    strength without cracking.

    Mortar need not be stronger than the units it joins. In fact cracks are more likely to appear

    in the blocks or bricks if the mortar is excessively strong. There are several types of

    mortars each suitable for particular applications and of varying costs. Most of these

    mortars include sand and ingredient.

    In all cases the sand should be clean, free of organic material, be well graded

    (a variety of sizes) and not exceed 3mm of silt in the sedimentation test. In most cases,

     particle size should not exceed 3mm as the mortar will be " hash″ and difficult to work

    with. Lime mortar is typically mixed 1 part lime to 3 of sand. Two types of lime are

    available.

    Hydraulic lime hardens quickly and should be used within an hour. It is suitable for both

    above and below ground applications. Non-hydraulic lime requires air to harden and can

    only be used above ground. If smoothed off while standing, a pile of this type of lime

    mortar can be stored for several days.

    Cement mortar is stronger and more waterproof than lime mortar, but is difficult to work

    with because it is not "fat″  or plastic and falls away from the blocks or bricks during

     placement. In addition, cement mortar is more costly than other types.

    Consequently it is used in only a few application such as dump-proof course or in

    some limited areas where heavy loads are expected. A 1:3 mix using fine sand is

    usually required to get adequate plasticity.

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    18/52

      17

    Compo mortar is made with cement, lime and sand. In some localities a 50:50

    cement-lime mix is sold as mortar cement. The addition of the lime reduces the cost

    and improves the workability. 1:2:9, cement-lime-sand mix is suitable for general

     purposes, while a 1:1:6 is better for exposed surfaces and a 1:3:12 can be used for

    interior walls or stone walls where the extra plasticity is helpful.

    Mortar can also be made using pozzolana, bitumen, cutback, or soil. A 1:2:9 Lime

     pozzolana-sand mortar about equals a 1:6 cement-sand mortar. Adobe and stabilized soil

     blocks are often laid in a mortar of the same composition as the blocks.

    Table 2.2 and 2.3 provide information on the materials required for a cubic Meter of

    various mortars and the amount of mortar per square meter for several building units.

    Starting with cement mortar, strength decreases with each type, although ability to

    accommodate movement increases.

    Table 2.2: Materials required per Cubic Meter of mortar.

    Type Cement bag Lime kg Sand m3 

    Cement mortar 1:5 6.0 - 1.1

    Compo mortar 1:1:6 5.0 100.0 1.1

    Compo mortar 1:2:9 3.3 13.5 1.1Cement mortar 1: 8 3.7 - 1.1

    Compo mortar 1:3:12 2.5 150.0 1.1

    Lime mortar 1:3 - 200.0 1.1

    Table 2.3: Mortar Required for Various Types of Walls.

    Type of wall Amount required per m2 wall

    11.5 cm brick wall 0.25 m3 

    22.2cm brick wall 0.51m3 

    10cm sand-cement block wall 0.008m3 

    15cm sand-cement block wall 0.011m3 

    20cm sand-cement block wall 0.015m3 

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    19/52

      18

    2.7 : Cost in structural materials. 

    2.7.1: Economy in construction.

    According to B.N. Dutta in estimation and costing in civil engineering, the construction

    should be done as economic as possible by organizing labor, materials, supervision etc.

    All designs and working drawing should be prepared well in advance. Requirement of

    materials should be worked out and materials should be organized, collected and stocked

    close to the site of working well in advance so that work is not held up for want of

    materials.

    Materials should be stored at suitable place so that they can be mixed and supplied to the

    mason and other artisans readily with least possible lead and delay.

    Laborers should be well organized to use then fully and the number of different category

    of labor should be controlled and their work supervised to get maximum work from them.

    The whole construction shall be completed as quickly as possible so that the supervision

    cost may be minimum possible.

    Over head costs should be as low as possible, local materials should be used as far as

     possible which will be cheap, and save cost of transport. Locally available stone, timber

    etc, should be used which will reduce cost of transport. As cement and steel are costly

    and are not readily available, stone slab may be use in roof slab instead of reinforced

    concrete.

    2.7.2: Unit cost.

    For a given production figure, fixed and variable costs are added together and total

    divided by the number of blocks produced giving the unit cost. This enables the price of

     blocks to be set at a sensitive level. It is useful to calculate the effect of changes in cost or

    in productivity on the unit cost. The costs of raw materials and stabilizer remain

    identical.

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    20/52

      19

    2.7.3: Cost estimating.

    The estimated cost is prepared in order to know the probable cost of construction before

    starting the project works. If the money available lower than the estimate, attempts must

     be made to reduce the cost, by reducing the work or by changing the specifications.

    In preparing the estimate the quantities of different items of work are calculated and from

    these quantities the cost is calculated. For that matter a knowledge of drawings is

    essential. The one who can understand and read a drawing can find out the dimensions in

    length, breadth, height or depth etc. Calculations consist mainly of a length x breadth x

    height for volumes and length x breadth or length x height for areas.

    In the preparation of estimates one has to go into details of each item however big a

    small it might be. Nothing should be left or missed. An estimator should picture the

    object (the structure in his mind from the study of drawings and specifications).

    Alternatively the estimate can be done by measuring the length, breadth and height

    from the existing structure.

    If estimate is exceeded it becomes difficult to the engineer to explains and account

    for additional money. Inaccuracy in preparing estimate; mission of items, changes

    in design improper rates etc.., are the reason for exceeding the estimate, throughincrease in the rates is one of the main reason.

    In forming a correct estimate, care should be taken to find out the dimensions of all

    items correctly, and to avoid omissions of any kind of work or part there of. The rate

    of each item should also be reasonable and workable.

    The rate in estimate provide for the complete work, which consist of the cost of

    materials, transport, cost of water, taxes, establishment and supervision cost

    reasonable profit of contractor, etc. In preparing estimate the principle to be followed

    is to make each item or dimension clear and intelligible so that they can be

    understood, checked or verified by any body. A remark column may be introduced

    and notes may be given where necessary.

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    21/52

      20

      2.7.4: Methods of estimating.

    1. Estimate  : Previous to stating the construction project it is compulsory to know its

     probable cost which is worked out by estimating. An estimation is a computation of the

    quantity required and payments expected to be incurred in the construction of a work.

    The estimate is the probable cost of a work and is determined theoretically by

    mathematical calculations based on the plans and drawings and current rates.

    Approximate estimate may be prepared by various methods but accurate estimate is

     prepared by detailed estimate method.

    2. Actual cost  : The actual cost of work is known at the completion of the work.

    Account of all expenditure is maintained day to day during the execution of work in the

    account section and at the actual cost should not differ much from the estimated cost

    worked out at the beginning.

    3. Detailed estimate  : Preparation of detailed estimate consists of working out the

    quantities of different items of work and then working out the cost. The estimate is

     prepared in two stages :

    a. Details of measurements and calculation of quantities.

    The whole work is divided into different items of work as earth work, concrete, etc.. and

    the items are classified and grouped under different sub-heads, and details of

    measurement of each item of work are taken out and the quantities under each item are

    computed in the prescribed form known as measurement form.

     b. Abstract of estimated cost.

    The cost under item of work is calculated from the quantities already computed at

    workable rate, and the total cost is worked out in prescribed form, abstract of estimate

    form. A 1.5% to 3% is also added for contingencies, to allow for petty contingent

    expenditures, unforeseen expenditures, changes in design, changes in rates, etc. Which

    may occur during the execution of work charge establishment.

    The grand total thus obtained is estimated cost of work.

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    22/52

      21

     

    3. Rates. Rates of different items in the estimate are the current rates for the completion

    of the items of work which include supply of materials, transport, labor, scaffolding

    overheads, contractor's profit, taxes, etc. 

    By IVOR H. Seeley in building construction technology.

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    23/52

      22

     

    CHAPTER III . 3.0 : RESEARCH METHODOLOGY.

    3.1 : Data collection techniques.

    The first and most important information was extracted from library and Web site. All

    most literature review concerning bricks and blocks Like sizes, strength, mix ratio,

    manufacture, raw materials etc are recorded from engineering published materials.

    The second data collection technique applied in this research is the site Visiting. The

    most concerned site is "BRIQUETERIE RWANDAISE RULIBA″ (BRR).The objective

    that visit was to Collect the data / information about the Bricks produced by that factory

    like technical specifications, cost, availability and the center of market. The information

    tabulated below was extracted from syllabus of Ruliba factory.

    Sizes of bricks/

    Blocks (mm)

    Mass (kg) Pieces/m2  cost/ piece

    (rwf)

    cost/m2

    (rwf)

    400 x 175 x 120 10.5 20 434.24 8684.8

    400 x 175 x 95 6.9 25 316.24 7906

    250 x 175 x 190 8.9 20 408.28 8165.6

    250 x 175 x 95 4.35 36 198.24 7136.64

    250 x 120 x 95 3.15 36 135.94 4893.84

    260 x 125 x 68 2.6 52 80.24 4172.48

    210 x 100 x 63 2 60 76.7 4602

    210 x 50 x 63 1 60 47.2 2832

    210 x 100 x 63 3 60 231.28 13876.8

    Table 3.1 : Variety of Ruliba bricks and their relatives prices.

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    24/52

      23

     

    The third data collection technique used is experiment like laboratory test. The crushing

    strength test was conducted in order to know the resistance of Ruliba bricks under applied

    load. Prepared sample is placed between the compressive machine plates and the load is

    applied regularly and axially to the sample. The maximum load at failure divided by the

    loaded area of the brick determine the crushing strength of the brick.

    The observation method are used to know attractive appearance that presented Ruliba

     bricks, the uniformity of color; surface and edges. Hand manipulation may necessary to

    test the roughness of materials surface.

    The visit was also been conducted on field were the construction works by using concrete

     blocks took place. The technical specifications like mix proportion, size and the strength

    was been recorded. The interview method were applied to know the real situation on the

    construction field.

    Production and construction cost.

    Estimation and costing of two typical walls is a benchmark of this study. Two typical

    walls were considered in order to make safe comparison . One is constructed with Ruliba

     blocks (210x100x63), the second with concrete blocks (400x200x150).

    Calculations consist mainly of a length x breadth x height for volumes

    and length x breadth or length x height for areas.

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    25/52

      24

     

    3.2 : Data organization for analysis.

    3.2.1 : Calculation of masonry unit cost.

    A) Bricks from Ruliba.

    For calculation of masonry unit cost for Ruliba bricks, four items are considered: The

    unit cost of bricks, transport, mortar for binding units and labor cost.

    1. Cost of bricks.

    The cost of Ruliba bricks are fixed according to their mass, sizes and properties. To be

    familiar on their unit cost, the price of one brick must be multiplied by the number of

     bricks required to make one cubic meter of masonry.

    Sizes (mm) Pieces/m3  cost/ piece

    (rwf)

    Cost/m3

    (rwf)

    400 x 175 x 120 114 434.24 49503.36

    400 x 175 x 95 143 316.24 45222.32

    250 x 175 x 190 114 408.28 46543.92

    250 x 175 x 95 206 198.24 40837.44

    250 x 120 x 95 300 135.94 40782

    260 x 125 x 68 433 80.24 34743.9

    210 x 100 x 63 600 76.7 46020

    210 x 50 x 63 1200 47.2 56640

    210 x 100 x 63 600 231.28 46256

    Table 3.2: Unit cost of Ruliba bricks.

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    26/52

      25

     

    2. Transport cost.

    The transport cost depends upon the distance of and the weight of materials. At

    reasonable distance, say from Ruliba to any where in Kigali city, one tour of five tones

    costs 35,000rwf of transport. In table below, the unit cost presented, is estimated

     basically to that information by calculation the transport cost of one kg per km multiply

     by the number of bricks contained in one cubic meter of masonry.

    In other Provinces, it is very strange to use Ruliba blocks because of high carrying price.

    For instance, In districts like Musanze (North); Nyanza (south); Kayonza (Eastern) and

    Karongi(Western), the transport costs lie between 60,000rwf and 80,000rwf per trip. The

    table bellow illustrates the estimated transportation cost for different sizes.

    Sizes (mm) Mass (kg) Bricks

     per trip

    Bricks per

    one m3

    cost/kg/km

    (Rwf)

    Cost/m3/km

    (Rwf)

    Unit cost at

    20 km

    400 x 175 x 120 10.5 476 114 3.7 421.8 8436

    400 x 175 x 95 6.9 725 143 2.4 343.2 6864

    250 x 175 x 190 8.9 562 114 3.1 353.4 7068

    250 x 175 x 95 4.35 1149 206 1.5 309 6180

    250 x 120 x 95 3.15 1587 300 1.1 330 6600

    260 x 125 x 68 2.6 2500 433 0.7 303.1 6062

    210 x 100 x 63 2 2500 600 0.7 420 8400

    210 x 50 x 63 1 5000 1200 0.35 420 8400

    210 x 100 x 63 3 1667 600 1.0 600 12000

    Table 3.2: Unit cost of transport at 20km distance of various size of Ruliba bricks.

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    27/52

      26

     3. cost of mortar.

    Ratio: 1:4

    One part of cement over four parts of sand:

    Volume of brick with joint = 0.220 x 0.110 x 0.073 = 0.0017666m3

     Number of bricks = 1/0.001766 = 566 bricks

    Volume of net brick = 0.210 x 0.100 x 0.063 = 0.001323m3

    Total volume of bricks : 566 x 0.001323 = 0.749m3

    Volume of mortar : 1- 0.749 = 0.251m3

    Unit volume of cement : 1/5 x 0.251 = 0.0502 m3

    Mass of cement : = 0.0502 x 1500 = 75.3 kg

    Unit cost of cement = 12000/50 x 75.3 = 18072 rwf

    Unit volume of sand : 4/5 x 0.251 = 0.2008m3

    Unit cost of sand : 35000/5 x 0.2008 = 1405.6 rwf

    Unit cost of mortar = Unit cost of cement + Unit cost of sand

    = 18072 +1405.6

    =19477.6rwf

    4.  Labor cost.

    Sizes (mm) Built

     bricks

     per day.

     Number of

     bricks in m3.

    Labor Cost of

    one brick (rwf)

    Labor cost of

    one m3(rwf)

    400 x 175 x 120 19 114 353.68 40239

    400 x 175 x 95 24 143 280 40040

    250 x 175 x 190 19 114 353.68 40239

    250 x 175 x 95 38 206 176.84 36429

    250 x 120 x 95 56 300 120 36000260 x 125 x 68 84 433 80 34640

    210 x 100 x 63 120 600 56 33600

    210 x 50 x 63 240 1200 28 33600

    210 x 100 x 63 120 600 56 33600

    Table 3.4 : Unit labor cost of masonry for various sizes of bricks.

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    28/52

      27

     

    One mason is paid 560rwf / hour

    One porter is paid 280rwf/ hour

    Total = 840rwf/ hour i.e. 840 x 8 =6720rwf.

    One porter and one mason can built 120 bricks of 210 x 100 x 63 mm sizes per day.

    B) Concrete blocks.

    Three main items must be taken into account in estimation of unit cost of wall made with

    concrete blocks. Then, the unit cost of wall =(Cost of blocks + labor cost +cost of

    mortar). It is more economic to make blocks on place of work to avoid the transport cost

    of finished units.

    The cost of blocks combines both the cost of raw materials and which of former. So that,

    his is paid around 40rwf per block. For that case, the transport fees of raw materials may

     be considered. On market, one trip of sand bought between 35,000rwf and 40,000rwf,

    while one bag of cement costs 11,0000rwf for imported Hima Portland cement and

    13,000rwf for local Portland cement.

    For labor cost, one mason and one porter can build about 60 blocks of 400 x 200 x 170

    mm sizes per day. The day of work is equivalent of eight hours. Most employers does not

    consider the security and other taxes for their employees which is wrong. Then, the labor

    cost of one mason is 560rwf per hour, while the porter paid 280rwf per hour.

    The cost of mortar for binding concrete blocks units is estimated like the cost of blocks.

    The difference lies in their mix proportion ratio in which, that of mortar is one part of

    cement to four parts of aggregate.

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    29/52

      28

    1.Unit cost of blocks.

     Net volume of blocks in one cubic meter of wall.

     Net volume of one block: 0.40 x 0.20 x 0.17 = 0.0136 m3.

    Volume of block with 10 cm joint : 0.41 x 0.21 x 0.18 = 0.0155m3.

     Number of blocks : 1/0.0155 = 64.5 blocks.

     Net volume of blocks in 1m3:0.0136 x 64.5 = 0.877m3.

    2.Unit cost of raw materials.

    Mix proportion : 1: 14.

    Unit volume of cement : 1/15 x 0.877 = 0.058 m3.

    Mass of cement: 0.058 x 1500 = 87 kg.

    Cost of cement: 12000/50 x 87 = 20880rwf.

    Unit volume of sand: 14/15 x 0.877 = 0.818m3.

    5m3 costs 35000rwf i.e. 7000rwf/m3.

    Unit cost of sand: 0.818 x 7000 = 5726rwf.

    Former unit cost: 40 x 64.5 = 2580rwf.

    unit cost of blocks = 20,880 + 5,726 +2,580 =29,186rwf.

    3.Unit cost of mortar for binding materials.

    Ratio: 1:4

    Unit volume of mortar : 1- 0.877 = 0.123 m3

    Unit volume of cement :1/5 x 0.123 = 0.024m3

    Mass of cement: 0.024 x 1500 = 36 kgUnit cost of cement: 12000/50 x 36 = 8,640rwf

    Unit volume of sand: 4/5 x 0.123 = 0.098 m3

    Unit cost of sand: 35000/5 x 0.098 = 686rwf

    Total unit cost of mortar: 8,640 + 686 =9,326rwf.

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    30/52

      29

     

    4.Labor unit cost.

    One mason is paid to 560rwf / hour and one porter is paid 280rwf/ hour.Labor cost = 840rwf/ hour i.e. 840 x 8 = 6,720rwf

    As said above, one unit of volume contains 64.5 blocks sized to

    400mm x 200mm x170mm.Then, the output of one mason is 60/64.5=

    0.930m3 per day.

    From this, the determination of unit labor cost is simple. That must be

    equal to 6,720/ 0.930 x 1=7,226rwf. 

    The unit cost of blocks wall = 29,186 + 9,326 + 7,226 = 45,738rwf.

    Table 3.5 : Unit cost comparison of Ruliba bricks wall and concrete wall.

    Ruliba bricks (1m3) Concrete blocks (1m

    3)

    Descriptions Unit cost(rwf.) Descriptions Unit cost (rwf.)

    1. Bricks unit cost 45,172 Blocks unit cost 29,186

    2. Trans. Unit cost 7,779 Trans. Unit cost -3.Mortar unit cost 19,477.6 Mortar unit cost 9,326

    4. Labor unit cost 36,487 Labor unit cost 7,226

    Total unit cost 108,915.6 Total unit cost 45,738

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    31/52

      30

    3.2.2: Data related to technical specifications.

    A)Technical specification of Ruliba bricks.

    Report of laboratory test for strength and density.

    Purpose: This laboratory test is conducted in order to state some mechanical properties

    of Ruliba bricks like compressive strength and the density . This test will help us to make

    comparison of Ruliba bricks properties with that of concrete blocks.

    Hypothesis.Each structural wall must withstand against natural and artificial action like compressive

    stress, capillarity, etc. That will depend on resistance of its structural materials say bricks.

    The problem behind is to know the ability of these materials to support the applied loads

    in order to make safe design. As the Ruliba brick is the case study, it required to know the

    crushing strength of that product.

    Materials and apparatus. 

    - Two Ruliba bricks samples;

    - Balance;

    - Ruler;

    - Crushing- machine.

    Procedure.

    •  Preparation of samples;

    •  Measurement of loaded area;

    •  The brick is then weighted ;

    •  The specimen is then compressed between the plates of testing machine.

    •  The maximum load at failure is noted as the crushing load of the brick.

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    32/52

      31

     

    Results and data. 

    Sample 1: Length (L1) = 26 cm

    Width (W1)= 12.5 cm

    Height (H1)= 6.8 cm

     Number of Hollow (N)= 6

    Length of hollow (l1) = 7.8 cm

    Width (w1) = 2.7 cm

    Height (h1) = 6.8 cm

    Crushing load = 240 KN

    Loaded area = (L1 x W1) – (l1 x w1) x N

    = (26 x 12.5) – (7.8 x 2.7) x 6 = 199 cm2 

    Crushing strength = Crushing load / loaded area of brick.

    = 240/199

    = 1.21 KN/cm2 

    Sample 2 : Length (L2) = 26 cm

    Width (W2)= 12.5 cm

    Height (H2)= 6.8 cm

     Number of Hollow (N)= 6

    Length of hollow (l2) = 7.8 cm

    Width (w2) = 2.7 cm

    Height (h2) = 6.8 cm

    Crushing load = 440 KN

    Loaded area = (L2 x W2) – (l2 x w2) x N

    = (26 x 12.5) – (7.8 x 2.7) x 6 = 199 cm2 

    Crushing strength = Crushing load / loaded area of brick.

    = 440/199

    = 2.21 KN/cm2 

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    33/52

      32

     

    Density:

    Sample 1: Total volume of brick = 26 x 12.5 x 6.8 = 2210 cm3

    Total volume of voids = 7.8 x 2.7 x 6.8 = 143.208 cm3

    Total volume of solid = 2210 – 143.208 = 2066.792 cm3

    Density = Weight (W1)/ Total volume of solid

    = 2.633/2066.792 x 10-6

     = 1273.95 Kg/m3

    Sample 2: Total volume of brick = 26 x 12.5 x 6.8 = 2210 cm3

    Total volume of voids = 7.8 x 2.7 x 6.8 = 143.208 cm3

    Total volume of solid = 2210 – 143.208 = 2066.792 cm3

    Density = Weight (W2)/ total volume of solid

    = 2.643/2066.792 x 10-6

    = 1278.79 Kg/m3

    Average Density = (D1 + D2)/2

    = (1273.95 + 1278.79)/2

    = 1276.37 Kg/cm3

    Conclusion and recommendation.

    The result of test show that there is a great difference between the crushing strength of

    sample number 1 and that of sample number 2 . The previous observations made on

    samples was shown that there was small crack on sample 1, which is the reason of that

    difference in strength. So that, result given by the corresponding sample must be ignored

    and consider the second result as the crushing strength of Ruliba bricks.i.e.2.21 KN/cm2.

    As density, the average of two solutions gives the density of 1276.37 kg/cm3.

    As recommendation, it better to control carefully the samples before testing and to take

    more samples during laboratory test.

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    34/52

      33

     

    Table 3.6: Technical specifications of Ruliba bricks.

    Types Sizes (cm) Mass(kg) Mass density

    (kg/m3)

    Average compressive

    strength (kg/cm2)

    Hollow block 40 x 17.5 x 12 10.5 1250 2.16

    Hollow block 40 x 17.5 x 9.5 6.9 1037.6 1.79

    Hollow block 25 x 17.5 x 19 8.9 1070.6 1.85

    Hollow block 25 x 17.5 x 9.5 4.35 1046.6 1.81

    Hollow block 25 x 12 x 9.5 3.15 1666.7 2.88

    Hollow block 26 x 12.5 x 6.8 2.6 1276.37 2.21

    Hollow brick 21 x 10 x 6.3 2 1511.7 2.62

    Hollow brick 21 x 5 x 6.3 1 1511.7 2.62

    Fire brick 21 x 10 x 6.3 3 2267.6 3.92

    B)Technical specification of concrete blocks.

    Table3.7: Technical specifications of concrete blocks.

    Parameters Description

    Typical size 300 x 200 x 150

    Average compressive strength at 28

    days.

    50-110 kg/cm2

    Mix proportion 1:12-14 (1 part of cement: 12:14 part

    sum graded aggregate)

    Water absorption in 24 hours Less than 10% by weight

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    35/52

      34

     

    3.3 : Results presentation.

    3.3.1: Strength and density.

    The result from laboratory test show that the crushing strength and the density of Ruliba

     bricks are respectively equivalent to 2.21kg/m2, and 1276.37 kg/m

    3.While

    the compressive strength of concrete blocks varies from 50 to 110 kg/m2. Those

     parameters recorded after 28 day of manufacture, depends on method of manufacture, the

    quality and mix proportion of raw materials. Then, the compressive strength of blocks

    made by block-making machine is greater than that of man- made blocks.

    3.3.2: Cost. 

    All most costs of bricks from Ruliba are not affordable by every one in this country. But

    are reasonable depending on raw materials used, modern technology used and the esthetic

    aspect presented by those products.

    All costs of Ruliba bricks fixed according to their Functions, sizes and mass are tabulated

     below:

    Table 3.8: Total unit cost of masonry for various sizes of bricks.

       S   i  z  e  s   (  m  m   )

      4   0   0  x   1   7   5  x   1   2   0

       4   0   0  x   1   7   5  x   9   5

       2   5   0  x   1   7   5  x   1   9   0

      2   5   0  x   1   7   5  x   9   5

      2   5   0  x   1   2   0  x   9   5

      2   6   0  x   1   2   5  x   6   8

       2   1   0  x   1   0   0  x   6   3

       2   1   0  x   5   0  x   6   3

       2   1   0  x   1   0   0  x   6   3

    Bricks unit cost 49,503 45,222 46,544 40,837 40,782 34,744 46,020 56,640 46,256

    Trans. Unit cost 8,436 6,864 7,068 6,180 6,600 6,062 8,400 8,400 12,000

    Mortar unit cost 19,478 19,478 19,478 19,478 19,478 19,478 19,478 19,478 19,478

    Labor unit cost 40,239  40,040  40,239 36,429 36,000 34,640 33,600  33,600  33,600

    Total unit cost 117,656 111,604 113,329 102,924 102,860 94,924 107,498 118,118 111,334

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    36/52

      35

    The cost of concrete block is influenced by which of its constituents and the production

    cost. For a ratio of 1:14, one bag of cement is used to produce 36 blocks with sizes 400 x

    200 x 200mm.Also, for sand, one trip of five tones costs 35,000rwf. The production cost

    is 40rwf per block. (man-made block.). For that, total cost of concrete block is about

    500rwf.

    3.3.3: Availability.

    Ruliba bricks are available at Ruliba factory(B.R.R) situates at Nyabarongo bridge in

     Nyarugenge District in Kigali city Province. They are obtained in abundance in different

    form , function and sizes. 

    Concrete blocks are easily available, because they can be produced on work site. The

    advantage of producing blocks on site is to avoid the transport cost, to control the quality

    of raw materials, to organize the proportion mix process and to save money. 

    Some peoples produce blocks and sell them at 500-700rwf per block but, the mix

     proportion of raw materials is critical because they want to gain more profit.

    3.3.4: Materials used.

    The clay and shale are the basic raw materials used in Ruliba bricks making. The use of

    fuel has replaced that of wood in order to reduce the deforestation velocity.

    Raw materials for producing concrete blocks are cement, sand and aggregate with ratio of

    1:3:6. The maximum aggregate size is 10 mm. The quality of raw materials must be well

    controlled in order to get final product of good properties.

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    37/52

      36

    3.3.5: Method of manufacture.

    Bricks from Ruliba factory are made mechanically by using machine. Prepared plastic

    clay are extracted as continuous column of rectangular section with or without

     perforations which is cut into individual bricks by wire.

    Continuously, those bricks are fired up to 900 - 11000  C .Below that temperature, all

    components react and dissolves ones with others , forming monolithic material.

    Blocks may be made by using machine or hand after mixing raw materials at required

    ratio. The obtained product is cured during two weeks by sprinkling water up to it

    maximum strength. Produced blocks can be solid ,cellular or hollow depending on mould

    used.

    3.3.6: sizes.

    Ruliba bricks are available in various sizes. Each client buy the products according to his

    appreciation . The bricks of greatest sizes are similar to those of blocks are commonly

    used in construction of contour walls. Small bricks are used in construction of building

    walls.

    Products Function Sizes (cm)

    Hollow block Face wall 40 x 17.5 x 12

    Hollow block Face wall 40 x 17.5 x 9.5

    Hollow block Face wall 25 x 17.5 x 19

    Hollow block Face wall 25 x 17.5 x 9.5

    Hollow block Face wall 25 x 12 x 9.5

    Hollow block Face wall 26 x 12.5 x 6.8

    Hollow brick Face wall 21 x 10 x 6.3

    Hollow brick Face wall 21 x 5 x 6.3

    Fire brick Fire resistant 21 x 10 x 6.3

    Table 3.9: Different sizes of Ruliba bricks.

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    38/52

      37

     

    Sizes are that the main difference between blocks and bricks. The fist one have great

    sizes while the second one have small sizes. so that, common sizes of blocks are 400 x

    200 x 200mm; 400 x 200 x 175mm; 400 x 200 x 150mm; 300 x 200 x 150mm etc.  

    3.3.7 : Center of market. 

    The center of market is Kigali city, because of reasonable distance from Ruliba. It is not

    easy to get market in others provinces or district for reason of high transport cost. In

    addition, most richest people and companies live in Kigali town.

    Concrete blocks are popular because of its cheapness and resistance. In addition, it

    manufacturing process not requires high technology and more instruments. Even if the

     binder like cement is cheap, their cost is affordable comparatively to other structural

    materials.

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    39/52

      38

     

    CHAPTER IV . 4.0 : DISCUSSIONS.

    4.1: Cost comparison.

    Let us to consider two structural wall of 10m length, 3m height, and 0.20 m thick

    constructed respectively with Ruliba bricks and concrete blocks.

    The abstracts of estimation and costing of those walls are presented bellow.

    4.1:Abstract of estimation and costing of typical wall made in Ruliba bricks.

    SN Items of work Units Quantities Rate Total cost (rwf)

    1 Bricks work

    with cement

    mortar

    m3 6 108,916 653,496

    2 Jointing outside

    and inside

    m2 60 4000 240,000

    3 Varnishing m2 60 2,500 150,000

    Total 1,043,496

    Table 4.2:Abstract of estimating and costing of typical wall made in concrete blocks.  

    SN Items of work Units Quantities Rates(rwf) Total cost(rwf)

    1 Blocks work with

    cement mortar

    m3 6 45,738 274,428

    2 Plastering with

    cement mortar

    m2 60 4,000 240,000

    3 Painting m2 60 2,500 150,000

    Total 664,428

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    40/52

      39

    As seen in above tables, only three items are considered in each case. It is observed that

    the total cost of wall made with concrete blocks is lower than that which is constructed in

    Ruliba bricks.

    4.2:Compressive strength comparison.

    Brick/Block Sizes in mm. Compressive

    Strength(kg/cm2)

    Density(kg/m3)

    Concrete block 300x200x150 50-110 2250

    Bricks from

    Ruliba

    260x125x68 22.1 1276.37

    Table 4.3:Size, compressive strength, density of concrete blocks and bricks from Ruliba

    factory.

    General comparison of concrete blocks with Bricks from Ruliba.

    Concrete blocks Bricks from Ruliba

    High Compressive strength

    Less cost

    Can be produced on site

    Has not good appearance

    Are most available

    Are require plastering

    Are not require jointing

    The manufacturing process is not

    complicated

    Less variability of sizes

    Machine and hand made products

    Are not burned

    Their density is high

    Low compressive strength

    High cost

    Are produced on factory

    Has good appearance

    Are only available on factory

     Not requires the plastering

    It requires jointing

    The manufacturing process is

    complicated.

    Most variable of sizes.

    Machine-made products

    Are burned

    Their density is low

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    41/52

      40

    CHAPTER V. 5.0 : CONCLUSION AND RECOMMENDATIONS.

    5.1 : Conclusion.

    According to results obtained and the discussion made, it is shown that the Concrete

     blocks should be preferable before bricks from Ruliba because of it durability and it low

    cost. But, in point of view architectural aspect, the bricks from Ruliba are dominant

     because of it good looking when is used in construction of wall. That is due to their

    regular corners and joint when Portland cement mortar is used in jointing.

    The unit cost of wall made with Bricks is greatest due to its transport cost, method of

    manufacture and it availability. The time required to built the structural wall with each of

     both materials is different. In addition, it is not easy to use Ruliba bricks for people who

    lives away of Kigali city and its surrounding in reason of transport price.

    For that case, most people prefer to use concrete blocks in their construction project.

    Also, the concrete blocks are most used in internal and external wall where the plaster is

    required. As environmental sector, the problem are similar for both materials when the

    engines used produce gas waste which is very dangerous to the atmosphere.

    As conclusion, the results of this project show that concrete blocks are compressive

    resistant, less expensive but less esthetic comparatively to Ruliba bricks. So that, it is

    advantageous to use concrete blocks fist of Ruliba bricks.

    5.2 : Recommendations.

    After the completion of this project, the recommendations given are follow:

      The concrete blocks should be adopted in construction of buildings fist to Ruliba

     bricks because of they durability as well as they cheapness.

      The price of Ruliba bricks should be minimized as possible in order to facilitate

    the population to construct the esthetic building with low cost .

      The mix proportion of Ruliba bricks should be controlled in order to improve they

    qualities.

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    42/52

      41

     

    REFERENCES.

    A. Books.

    1.Arnold W. Handry (2003)“ Structural Masonry” Addison Wesley longmen

    limited , England.

    2. E. Paul Degarmo, JT.Black and Ronarld A. KOHSER (1997) “Materials and

     processes in manufacturing”, New delhi.

    3. Ivor H. Seely, (1992) “Building technology”, customer services department,

    mac millan Distribution Ltd. England.

    4. Prof. BN Dutta, “Estimating and costing in civil Engineering” UBS

    Distributors Pvt Ltd.

    5. Tata Mc (2003) “Civil Engineering materials”, Graw- hill publishing company

    Limited, New-delhi.

    B. Web sites:

    http://www. Google.com

    http:// www.scoland.gov.uk

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    43/52

      42

     

    APPENDICES.

    The information below, was given by one of mason of B. L HARBET RWANDA

    Limited. The Structural materials used are Reinforced concrete, modern bricks and

     blocks.

    Statement of calculation of monthly salary for mason.

    Enterprise : B.L HARBERT RWANDA Limited 

    Works : Construction of New American Embassy

    Site: KACYIRU

    Rate to pay 560rwf/hour

    Pay type FRW Rate Hours worked Total

    RT Basic 560 152.00 85,120

    Over time 1.5 840 83 69,720

    Over time 1.7 952 47 44,744

    Double Time 1,120 22 24,640

    Gross to pay 224,224Frw

    PAYE Per Tax table 51267.2

     NSSF 3% of Gross Pay 6726.72

    FARG 1% of basic 851.20

     Net to pay 165,378.88Frw

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    44/52

      i

    DECLARATION.

    I, ZIRIMWABAGABO Léodomir, declare that the project entitled “ COMPARISON

    BETWEEN CONCRETE BROCKS AND BRICKS FROM RULIBA” is my own work.

    It has never been presented any where in Institute or University for the same purpose.

    ZIRIMWABAGABO Léodomir………………………………

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    45/52

      ii

     

    Dedication.

    To:

    My God;

    My family;

    All who have contributed to this work.

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    46/52

      iii

     

    ACKNOWLEDGEMENT.

    The author is grateful to all who contributed to the successfulness of the

     present study, in particular way thanks goes to Mr. KAYINAMURA Francis

    who provided guidance to the present research work.

    Special thanks go to KIST Staff and students for their immeasurable

    technical assistance and their availability to assist in application of class

    theories and practices.

    I m grateful to the staff of Ruliba factory who provided me with useful data

    that made this study possible. The bless of God for all who gave a helping

    hand to the successful completion of the present work.

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    47/52

      iv

     

    ABSTRACT. 

    The current technology involves the construction of building with update

    materials require low cost and stability. Given that, some one who

    desires to construct a building, the common question to be asked for is how

    to get cheap and esthetic building materials.

    Raw materials for manufacturing concrete blocks are expensive. For

    instance, on one bag of local Portland cement costs 13.000rwf .On the other

    hand, cutting trees for firing clay bricks leads to deforestation which affectsour environment.

    The bed rock of this project is to take out the confusion during the choice of

    sustainable building materials, the best objective in building design, as well

    as to show how it is possible to build up the buildings using materials which

    may resist against natural actions.

    Main assumption of this project, are the selection of structure materials,

    require low cost and durability; the ability to withstand against the

    expensiveness of raw material and the design for environment.

    In order to make excellent comparison, different techniques were employed.

    Information about topic from libraries, website field visit of Ruliba factory

    BRR   was tracked down. The crushing strength test was conducted in order

    to check the resistance of Ruliba bricks. In addition, the cost of two typical

    walls constructed in materials under comparison was estimated.

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    48/52

      v

     

    TABLE OF CONTENTS.

    Certificate

    Declaration………………………………………………………………………………..i

    Dedication………………………………………………………………………………...ii

    Acknowledgement……………………………………………………………………….iii

    Abstract…..…………………………………………………..…………………………..iv

    Table of contents……………………………………........................................................v

    List of tables……………………………………………………………………………..vi

    List of symbols and abbreviations …………………………………………………….vii

    Appendices

    CHAPTER I .

    1.0 : Introduction ……... ……... ……... ……... ……... ……... ……………………..1

    1.1 : Statement of problem……………………………………………………...…………1

    1.2 : Objectives of study… ……... ……….…….............................................................1

    1.3 : Justification………………………………………………………………………......2

    1.4 : Scope of study………………………………………………………………………..3

    CHAPTER II .

    2.0 : Literature review…………………………………………......................................4

    2.1: Varieties of bricks and blocks ……………………………………………………..4

    2.1.1 : Clay bricks……………………………………………………...………….4

    2.1.2 : Calcium silicate bricks ………………………………...…………………..6

    2.2 :Bricks forming process………………………………………………...…………….6

    2.2.1 : Manufacture process……………………………………………………….6

    2.2.2 : Firing……………………………………………………………………….62.3 : Technical specification of bricks…………………………………………...………..7

    2.3.1 : Strength of bricks …………………………………………………..……...7

    2.3.2 : Test for compressive strength ……………………………………..……...8

    2.3.3 : Compressive strength and other mechanical properties……………….…..8

    2.3.4 : Factors affecting compressive strength……………...................................9

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    49/52

      vi

    2.3.5 : Size of bricks ………………………………………..................................9

    2.4 : Concrete blocks features……………………………………………………..........10

    2.4.1 : Concrete block technology…………………………………………...…..10

    2.4.2 : Business ……………………………………………………………….....10

    2.4.3 : Product ………………………………………...........................................10

    2.4.4 : Unique features of concrete block technology……...................................11

    2.4.5 : Production process ……………………………………………………….11

    2.4.6 : Building with concrete ………………………………………………...…12

    2.4.7 : Perforated and hollow blocks…………………………………………….12

    2.4.8 : Benefit of using concrete blocks………………………………………….14

    2.5 : concrete blocks forming process……………………………………………………14

    2.5.1 : Mix proportion of blocks ………………………………………………...14

    2.5.2 : Blocks manufacturing ……………………………………………………14

    2.5.3 : Decorative and ventilating blocks….. ……... ……... ……………………15

    2.6 : Mortar for jointing…………………………….........................................................16

    2.7: Cost in structural materials………………………………………………………….18

    2.7.1 : Economy in construction ………………………………………………...18

    2.7.2 : Unit cost ………………………………………………………………….18

    2.7.3 : Cost estimating …………………………………………………………19

    2.7.4 : Method of estimating …………………………………………………….20

    CHAPTER III .

    3.0 : Research Methodology ……………………………………………………..........22

    3.1 : Data collection techniques………………………………………………………….22 

    3.2 : Data organization for analysis……………………………………………………...24

    3.2.1 : Calculation of masonry unit cost…………………………………………24

    3.2.2 : Data related to technical specifications……………..................................30

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    50/52

      vii

     

    3.3 : Results presentation………………………………………………………………...34

    3.3.1 : strength and density………………………………………………………34

    3.3.2 : Cost……………………………………………………………………….34

    3.3.3 : Availability…………………………...……………..................................35

    3.3.4 : Materials used…………………………………………………………….35

    3.3.5 : Method of manufacture………………...…………………………………36

    3.3.6 : Sizes…………………………………...……….........................................36

    3.3.7 : Center of market……………………………..…………………………...37

    CHAPTER IV .

    4.0 : Discussions ………………………….………….…………………………………38

    4.1 : Cost comparison……………………………………………………………………38

    4.2 : Compressive strength comparison…………..…………….......................................39 

    CHAPTER V.

    5.0 : Conclusion and recommendations……………..….………………………..........40

    5.1 : Conclusion .……………………….……………….................................................40

    5.2 : Recommendations…………………………………………………………..............40

    References……………………………………………………………………………….41 

    Appendices

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    51/52

      viii

     

    LIST OF TABLES.

    Table 2.1:Average compressive strength of common burnt clay bricks…………………..7Table 2.2: Materials required per Cubic Meter of mortar………………………………..17

    Table 2.3: Mortar Required for Various Types of Walls………………………………...17

    Table 3.1 : Varieties of BRR Bricks/ blocks and their relative prices………………...…22

    Table 3.2 : Unit cost of Ruliba bricks……………………………………………………24

    Table 3.3 : Unit cost of transport at 20km distance of various size of

    Ruliba bricks………………………………………………………………...25

    Table 3.4 : Unit labor cost of masonry for various sizes of bricks………………………26

    Table 3.5 : Unit cost comparison of Ruliba bricks wall and concrete wall……………...29

    Table 3.6: Technical specifications of Ruliba bricks…………………………………….33

    Table 3.7 : Technical specifications of concrete blocks…………………………………33

    Table 3.8 : Total unit cost of masonry for various sizes of bricks……………………….34

    Table 3.9 : Different sizes of Ruliba bricks ……………………………………………..36

    Table 4.1 : Abstract of estimation and costing of typical wall made in

    Ruliba bricks………………………………………………………………...38

    Table 4.2 : Abstract of estimating and costing of typical wall made in

    concrete blocks………………………………………………………………38

    Table 4.3 : Size, compressive strength, density of concrete blocks and ………….........39

     bricks from Ruliba factory.

  • 8/21/2019 M 2008 CEET 28 ZIRIMWABAGABO Leodomir GS20020131.pdf

    52/52

      ix

     

    List of symbols and abbreviations.

    Abbreviations Descriptions units

    KIST Kigali Institute of Sciences and Technology

    B.R.R Briqueterie Rwandaise Ruliba

    CEET Civil Engineering and Environmental Technology

    L1  Length of brick for sample number 1 cm

    L2  Length of brick for sample number 2 cm

    W1  Width of brick for sample number 1 cm

    W2  Width of brick for sample number 2 cm

    H1  Height of brick for sample number 1 cm

    H2 Height of brick for sample number 2 cm

     N Number of hollows -

    l1  Length of hollows for sample number 1 cm

    l2  Length of hollows for sample number 2 cm

    w1  Width of hollows for sample number 1 cm

    w2  Width of hollows for sample number 2 cm

    h1  Height of hollows for sample number 1 Cm

    h2  Height of hollows for sample number 2 Cm

    D1  Density of brick for sample number 1 Kg/cm3 

    D2  Density of brick for sample number 2 Kg/cm3