Francis T. Maloney High SchoolCity of Meriden
May 5, 2011
Team Introductions:Team Introductions:Maloney High SchoolMaloney High School
Fletcher Thompson:Fletcher Thompson:Joe Costa, AIA, LEED AP Joe Costa, AIA, LEED AP –– Principal KPrincipal K--1212Curt Krushinsky, RA, LEED AP Curt Krushinsky, RA, LEED AP –– Project ManagerProject ManagerAngela Cahill, Angela Cahill, AIAAIA, , LEEDLEED AP AP –– Assistant PMAssistant PMDan Davis, AIA, LEED AP Dan Davis, AIA, LEED AP –– Director of DesignDirector of DesignMike Berger, LEED AP Mike Berger, LEED AP –– Senior DesignerSenior Designer
Blades and Goven:Blades and Goven:Earl Goven, ASLA Earl Goven, ASLA –– Landscape ArchitectLandscape Architect
Leach Consulting, LLCLeach Consulting, LLCKevin Leach, P.E. Kevin Leach, P.E. –– EstimatorEstimator
May 5, 2011May 5, 2011
Design Approach:Design Approach:High School High School –– ProgrammingProgramming
Program AnalysisProgram Analysis
Drawing on Our Expertise/Research/Tools
Communicating/Listening/Implementing
Program: Foundation of a Successful School
Avoiding Facilities That Are Not Needed
Space Allocation/Distribution Critical
Program Approved on April 7thProgram Approved on April 7
TOTAL: 271,553 SF
May 5, 2011May 5, 2011
Design Approach:Design Approach:Maloney High School Maloney High School –– Existing School PlanExisting School Plan
1970’s Original Building 1958
Addition 1970s
Code/Safety Issues
Hazardous Materials
Facility Needs Modernization
Enabling a 21 Century Curriculum
1958
Enabling a 21 Century Curriculum
May 5, 2011May 5, 2011
Design Approach:Design Approach:Maloney High School Maloney High School –– Existing School PlanExisting School Plan
May 5, 2011May 5, 2011
Design Approach:Design Approach:Maloney High School Maloney High School –– Challenges and OpportunitiesChallenges and Opportunities
Site Configuration
Entrance Drive/Fields/Parking
Loop Circulation Patterns
Distribution of Large Spaces
Community Uses of Facility
Construction PhasingConstruction Phasing
Coordination with Platt HS
d i ili
May 5, 2011May 5, 2011
Modernize Facility
Design Approach:Design Approach:Maloney High School Maloney High School –– Concept Design (Work in Progress)Concept Design (Work in Progress)
Site Influences Building Design
Entry/Graduation/Service
FIELDS
Zoning: Public/Private
Loop Circulation Patterns
Display History/Learning
Library/Media CenterFIELDS
GALLER
Y
Library/Media Center
Freshman Academy/Bridge
FIELDS
Natural Light Throughout
Improve Curb AppealGRADUATION
May 5, 2011May 5, 2011
Main Level PlanMain Level Plan
M i L l T lMain Level Total:
160,949 sf
May 5, 2011May 5, 2011
Upper Level PlanUpper Level Plan
U L l T lUpper Level Total:
38,422 sf
May 5, 2011May 5, 2011
Pool Level PlanPool Level Plan
P l L l T lPool Level Total:
48,344 sf
May 5, 2011May 5, 2011
Lower Level PlanLower Level Plan
L L l T lLower Level Total:
19,534 sf
May 5, 2011May 5, 2011
Building Area SummaryBuilding Area Summary
Upper Level:
f38,422 sf
Main Level:
160,949 sf
Pool Level:
48,344 sf
Lower Level:Lower Level:
19,534 sf
May 5, 2011May 5, 2011
Building Total: 267,249 sf
Building DesignBuilding Design
May 5, 2011May 5, 2011
Building DesignBuilding Design
May 5, 2011May 5, 2011
Building DesignBuilding Design
May 5, 2011May 5, 2011
Building DesignBuilding Design
May 5, 2011May 5, 2011
Phasing PlanPhasing Plan
EXISTING CLASSROOM WING TO REMAINPHASES 1 ‐ 4
May 5, 2011May 5, 2011
Phasing PlanPhasing Plan
PHASE 1• ACADEMIC CR WING ADDITION• CORRIDOR BRIDGE (STAIR & ELEV.)
May 5, 2011May 5, 2011
Phasing PlanPhasing Plan
PHASE 2• FRESHMAN ACADEMY RENOVATIONS• STAIR ADDITION
May 5, 2011May 5, 2011
Phasing PlanPhasing Plan
PHASE 3• NATATORIUM RENOVATIONS• PHYSICAL ED RENOVATIONS• PHYSICAL ED ADDITION NEW ELEVATOR• NEW ELEVATOR
May 5, 2011May 5, 2011
Phasing PlanPhasing Plan
PHASE 4RENOVATIONS & ADDITIONS:• CAFETERIA• KITCHEN / SERVERYCUSTODIAL• CUSTODIAL
• ART• TECHNOLOGY ED• AUDITORIUM• MUSIC • VOCATIONAL ED
May 5, 2011May 5, 2011
Phasing PlanPhasing Plan
PHASE 5RENOVATIONS & ADDITIONS:• ADMINISTRATION• HEALTH CLINICGUIDANCE• GUIDANCE
• LIBRARY• FRESHMAN SCIENCE• GALLERY DEMOLISH EXISTING
CLASSROOM WING
May 5, 2011May 5, 2011
Site DesignSite Design
May 5, 2011May 5, 2011
Site DesignSite Design
May 5, 2011May 5, 2011
Project Schedule:Project Schedule:Maloney High SchoolMaloney High School
Design Documents CompletedDesign Documents Completed Aug 2012 Aug 2012
BSF SubmissionBSF Submission Nov 2012Nov 2012
Bidding & AwardBidding & Award Feb 2013Feb 2013
Start ConstructionStart Construction Mar / Apr 2013Mar / Apr 2013
Ph 1 Ph 1 C i A d i Cl Addi iC i A d i Cl Addi i A 1 A 1 A 1A 1Phase 1 Phase 1 –– Construction: Academic Classroom AdditionConstruction: Academic Classroom Addition Apr 2013 Apr 2013 –– Aug 2014Aug 2014
Phase 2 Phase 2 –– Construction: Freshman Academy RenovationsConstruction: Freshman Academy Renovations June 2014 June 2014 –– Aug 2015Aug 2015
Phase 3 Phase 3 Construction: Natatorium & PE Renovations / AddConstruction: Natatorium & PE Renovations / Add June 2014 June 2014 Aug 2015Aug 2015Phase 3 Phase 3 –– Construction: Natatorium & PE Renovations / AddConstruction: Natatorium & PE Renovations / Add June 2014 June 2014 –– Aug 2015Aug 2015
Phase 4 Phase 4 –– Construction: Cafe, Vocational Ed, Auditorium & ArtConstruction: Cafe, Vocational Ed, Auditorium & Art June 2015 June 2015 –– Aug 2016Aug 2016
Phase 5 Phase 5 –– Construction: Admin, Heath, Library, Science, GalleryConstruction: Admin, Heath, Library, Science, Gallery June 2016 June 2016 –– Aug 2017Aug 2017Phase 5 Phase 5 Construction: Admin, Heath, Library, Science, GalleryConstruction: Admin, Heath, Library, Science, Gallery June 2016 June 2016 Aug 2017Aug 2017
Project CompletedProject Completed September 2017September 2017
May 5, 2011May 5, 2011
Cost / Budget Analysis:Cost / Budget Analysis:Maloney High SchoolMaloney High School
Hard Cost
Phase 1 Phase 1 –– Academic Classroom AdditionAcademic Classroom Addition $27,668,642$27,668,642
Hard Cost
Phase 2 Phase 2 –– Freshman Academy RenovationsFreshman Academy Renovations $ 7,959,221$ 7,959,221Phase 3 Phase 3 Natatorium & PE Renovations / AdditionsNatatorium & PE Renovations / Additions $18 112 910$18 112 910Phase 3 Phase 3 –– Natatorium & PE Renovations / AdditionsNatatorium & PE Renovations / Additions $18,112,910$18,112,910Phase 4 Phase 4 –– Cafeteria, Kitchen, Art, Tech Ed, AuditoriumCafeteria, Kitchen, Art, Tech Ed, Auditorium
Music & Vocational Education Renovation / AdditionMusic & Vocational Education Renovation / Addition $22,780,339$22,780,339Phase 5 Phase 5 –– Admin, Health Clinic, Library, Science, Gallery AdditionAdmin, Health Clinic, Library, Science, Gallery Addition $14,438,846$14,438,846y yy y
Subtotal: Subtotal: $90,959,958$90,959,958Site WorkSite Work $ 6,377,042$ 6,377,042
Hard Cost Subtotal: Hard Cost Subtotal: $97,337,000$97,337,000a d Cost Subtota : a d Cost Subtota : $9 ,33 ,000$9 ,33 ,000
Soft Cost
Fees, Expenses, Bonding, Printing, FF&EFees, Expenses, Bonding, Printing, FF&E $ 13,634,342$ 13,634,342Owner’s Contingency (5%)Owner’s Contingency (5%) $ 5,548,659$ 5,548,659
Subtotal: Subtotal: $19,183,000$19,183,000
May 5, 2011May 5, 2011
Total Project Budget:Total Project Budget: $116,520,000$116,520,000