Upload
cutler
View
47
Download
1
Embed Size (px)
DESCRIPTION
Managing Flow Variability : Safety Inventory. Forecasts Depend on: (a) Historical Data and (b) Market Intelligence. Demand Forecasts and Forecast Errors Safety Inventory and Service Level Optimal Service Level – The Newsvendor Problem Demand and Lead Time Variability - PowerPoint PPT Presentation
Citation preview
1
Managing Flow Variability: Safety Inventory
Managing Flow Variability: Safety Inventory
Forecasts Depend on: (a) Historical Data and (b) Market Intelligence.
Demand Forecasts and Forecast ErrorsSafety Inventory and Service Level
Optimal Service Level – The Newsvendor ProblemDemand and Lead Time VariabilityPooling Efficiency through Centralization and
AggregationShortening the Forecast HorizonLevers for Reducing Safety Inventory
2
Managing Flow Variability: Safety Inventory
Four Characteristics of Forecasts
Forecasts are usually (always) inaccurate (wrong). Because of random noise.Forecasts should be accompanied by a measure of forecast error. A measure of forecast error (standard deviation) quantifies the manager’s degree of confidence in the forecast.Aggregate forecasts are more accurate than individual forecasts. Aggregate forecasts reduce the amount of variability – relative to the aggregate mean demand. StdDev of sum of two variables is less than sum of StdDev of the two variables. Long-range forecasts are less accurate than short-range forecasts. Forecasts further into the future tends to be less accurate than those of more imminent events. As time passes, we get better information, and make better prediction.
3
Managing Flow Variability: Safety Inventory
Within 200 time intervals, stockouts occur in 20. Probability of Stockout = # of stockout intervals/Total # of intervals = 20/200 = 0.1 Risk = Probability of stockout = 0.1 = 10%Service Level = 1-Risk = 1=0.1 = 0.9 = 90%.Suppose that cumulative demand during the 200 time intervals was 25,000 units and the total number of units short in the 20 intervals with stockouts was 4,000 units. Fill rate = (25,000-4,000)/25,000 = 21,000/25,000 = 84%.Fill Rate = Expected Sales / Expected Demand Fill Rate = (1- Expected Stockout )/ Expected Demand
Service Level and Fill Rate
4
Managing Flow Variability: Safety Inventory
μ and σ of Demand During Lead TimeDemand during lead time has an average of 50 tons.
Standard deviation of demand during lead time is 5 tons. Acceptable risk is no more than 5%. Find the re-order point.
Service level = 1-risk of stockout = 1-0.05 = 0.95.Find the z value such that the probability of a standard
normal variable being less than or equal to z is 0.95.
5
Managing Flow Variability: Safety Inventory
The table will give you z
Given a 95% SL95% Probability Normal
table
Up to the first digitafterdecimal
Second digitafter decimal
Probability
z
1.6
0.05
Z = 1.65
z Value using TableGo to normal table, look inside the table. Find a
probability close to 0.95. Read its z from the corresponding row and column.
6
Managing Flow Variability: Safety Inventory
The standard Normal Distribution F(z)
F(z)
z0
F(z) = Prob( N(0,1) < z)
Risk Service level z value0.1 0.9 1.280.05 0.95 1.650.01 0.99 2.33
z 0.01 0.02 0.03 0.04 0.05 0.06 0.07 0.08 0.090 0.5040 0.5080 0.5120 0.5160 0.5199 0.5239 0.5279 0.5319 0.53590.1 0.5438 0.5478 0.5517 0.5557 0.5596 0.5636 0.5675 0.5714 0.57530.2 0.5832 0.5871 0.5910 0.5948 0.5987 0.6026 0.6064 0.6103 0.61410.3 0.6217 0.6255 0.6293 0.6331 0.6368 0.6406 0.6443 0.6480 0.65170.4 0.6591 0.6628 0.6664 0.6700 0.6736 0.6772 0.6808 0.6844 0.68790.5 0.6950 0.6985 0.7019 0.7054 0.7088 0.7123 0.7157 0.7190 0.72240.6 0.7291 0.7324 0.7357 0.7389 0.7422 0.7454 0.7486 0.7517 0.75490.7 0.7611 0.7642 0.7673 0.7704 0.7734 0.7764 0.7794 0.7823 0.78520.8 0.7910 0.7939 0.7967 0.7995 0.8023 0.8051 0.8078 0.8106 0.81330.9 0.8186 0.8212 0.8238 0.8264 0.8289 0.8315 0.8340 0.8365 0.83891 0.8438 0.8461 0.8485 0.8508 0.8531 0.8554 0.8577 0.8599 0.86211.1 0.8665 0.8686 0.8708 0.8729 0.8749 0.8770 0.8790 0.8810 0.88301.2 0.8869 0.8888 0.8907 0.8925 0.8944 0.8962 0.8980 0.8997 0.90151.3 0.9049 0.9066 0.9082 0.9099 0.9115 0.9131 0.9147 0.9162 0.91771.4 0.9207 0.9222 0.9236 0.9251 0.9265 0.9279 0.9292 0.9306 0.93191.5 0.9345 0.9357 0.9370 0.9382 0.9394 0.9406 0.9418 0.9429 0.94411.6 0.9463 0.9474 0.9484 0.9495 0.9505 0.9515 0.9525 0.9535 0.95451.7 0.9564 0.9573 0.9582 0.9591 0.9599 0.9608 0.9616 0.9625 0.96331.8 0.9649 0.9656 0.9664 0.9671 0.9678 0.9686 0.9693 0.9699 0.97061.9 0.9719 0.9726 0.9732 0.9738 0.9744 0.9750 0.9756 0.9761 0.97672 0.9778 0.9783 0.9788 0.9793 0.9798 0.9803 0.9808 0.9812 0.98172.1 0.9826 0.9830 0.9834 0.9838 0.9842 0.9846 0.9850 0.9854 0.98572.2 0.9864 0.9868 0.9871 0.9875 0.9878 0.9881 0.9884 0.9887 0.98902.3 0.9896 0.9898 0.9901 0.9904 0.9906 0.9909 0.9911 0.9913 0.99162.4 0.9920 0.9922 0.9925 0.9927 0.9929 0.9931 0.9932 0.9934 0.99362.5 0.9940 0.9941 0.9943 0.9945 0.9946 0.9948 0.9949 0.9951 0.99522.6 0.9955 0.9956 0.9957 0.9959 0.9960 0.9961 0.9962 0.9963 0.99642.7 0.9966 0.9967 0.9968 0.9969 0.9970 0.9971 0.9972 0.9973 0.99742.8 0.9975 0.9976 0.9977 0.9977 0.9978 0.9979 0.9979 0.9980 0.99812.9 0.9982 0.9982 0.9983 0.9984 0.9984 0.9985 0.9985 0.9986 0.99863 0.9987 0.9987 0.9988 0.9988 0.9989 0.9989 0.9989 0.9990 0.9990
7
Managing Flow Variability: Safety Inventory
Excel: Given Probability, Compute z
8
Managing Flow Variability: Safety Inventory
Relationship between z and Normal Variable x
z = (x-Average x)/(Standard Deviation of x)x = Average x +z (Standard Deviation of x)LTD = Average lead time demand σLTD = Standard deviation of lead time demandROP = LTD + zσLTD
ROP = LTD + Isafety
9
Managing Flow Variability: Safety Inventory
Demand During Lead Time is Variable N(μ,σ)
Demand of sand during lead time has an average of 50 tons.
Standard deviation of demand during lead time is 5 tons
Assuming that the management is willing to accept a risk no more that 5%. Compute safety stock. LTD = 50, σLTD = 5
Risk = 5%, SL = 95% z = 1.65Isafety = zσLTD Isafety = 1.64 (5) = 8.2ROP = LTD + Isafety
ROP = 50 + 1.64(5) = 58.2
When Service level increases Risk decreases z increases
Isafety increases
Risk Service level z value0.1 0.9 1.280.05 0.95 1.650.01 0.99 2.33
10
Managing Flow Variability: Safety Inventory
Average Demand of sand during lead time is 75 units.Standard deviation of demand during lead time is 10
units.Under a risk of no more that 10%, compute SL,
Isafety, ROP.
Example 2; total demand during lead time is variable
What is the Service Level?Service level = 1-risk of stockout = 1-0.1 = 0.9What is the corresponding z value? SL (90%) Probability of 90% z = 1.28Compute the safety stock?Isafety = 1.28(10) = 12.8ROP = LTD + Isafety
ROP = 75 + 12.8 = 87.8
11
Managing Flow Variability: Safety Inventory
Service Level for a given ROP Example
Compute the service level at GE Lighting’s warehouse, LTD = 20,000, sLTD = 5,000, and ROP = 24,000ROP = LTD + I safety 24000 = 2000 + I safety I safety = 4,000 I safety = z sLTD
4000 = z(5000) z = 4,000 / 5,000 = 0.8 SL= Prob (Z ≤ 0.8) from Normal Table
12
Managing Flow Variability: Safety Inventory
Given z, Find the Probability
Given z
Table returns probability
Up to the first digitafterdecimal
Second digitafter decimal
Probability
z
0.8
0.00
z = 0.8 Probability = 0.7881Service Level (SL) = 0.7881
13
Managing Flow Variability: Safety Inventory
Service Level for a given ROP
SL = Prob (LTD ≤ ROP)
LTD is normally distributed
LTD = N(LTD, sLTD )
ROP = LTD + zσLTD
ROP = LTD + Isafety
Isafety = z sLTD
z = Isafety /sLTD
Then we go to table and find the probability
14
Managing Flow Variability: Safety Inventory
Excel: Given z, Compute Probability
15
Managing Flow Variability: Safety Inventory
If Lead Time is fixed and Demand is variable
μ and σ of Demand Per Period and Fixed Lead Time
L: Lead TimeR: Demand per PeriodR: Average Demand per PeriodAverage Demand During Lead Time LTD = L×R R : Standard Deviation of Demand per PeriodStandard Deviation of Demand During Lead Time = LTD
LTD = L R LTD = LR
16
Managing Flow Variability: Safety Inventory
Average demand of a product is 50 tons per week. Standard deviation of the weekly demand is 3 tons. Lead time is 2 weeks. Assume that the management is willing to accept a risk no more that 10%.z = 1.28
μ and σ of demand per period and fixed Lead Time
L= 2 weeks, R= 50 tons per week, R = 3 tons per weekLTD = LR LTD = 2(50) = 100
LTD = L R LTD =2 3 = 4.24 ROP = LTD + Isafety = LTD + z LTD
ROP = 100 + 1.28 × 4.24 ROP = 100 + 5.43
17
Managing Flow Variability: Safety Inventory
If Demand is fixed and Lead Time is variable
μ and σ of Lead Time and Fixed Demand per Period
R: Demand per PeriodL: Lead TimeL: Average Lead TimeAverage Demand During Lead Time LTD = L×R L : Standard Deviation of Lead Time Standard Deviation of Demand During Lead Time = LTD
LTD = R L LTD = LR
18
Managing Flow Variability: Safety Inventory
Lead Time Variable, Demand fixed Demand of sand is fixed and is 50 tons per week. The
average lead time is 2 weeks. Standard deviation of lead time is 0.5 week. Under a risk of no more that 10%, compute ROP and Isafety.
Acceptable risk; 10% z = 1.28 R: 50 tons, L = 2 weeks, L = 0.5 week
LTD = LR LTD = 2(50) = 100
LTD = R L
ROP = 100 + 1.28 × 25 ROP = 100 + 32
ROP = LTD + Isafety = LTD + z LTD
LTD = 50 ×0.5 = 25
19
Managing Flow Variability: Safety Inventory
Both Demand and Lead Time are Variable
R: demand rate per period R: Average demand rateσR: Standard deviation of demand
L: lead time L: Average lead timeσL: Standard deviation of the lead time
LTD: demand during the lead time (a random variable) LTD: Average demand during the lead time σLTD: Standard deviation of the demand during lead time
=
20
Managing Flow Variability: Safety Inventory
Both Demand and Lead Time are Variable
Lead time has mean of 10 days and a stddev of 2 days. Demand per day has a mean of 2000 and stddev of 1581. How much safety inventory is needed in order to provide a 95% service level?R: Average demand rate= 2000 units
σR: Standard deviation of demand = 1581 L: Average lead time = 10 daysσL: Standard deviation of the lead time = 2 days = 10(2000) = 20000
==6402.78 =1.65
=1.65(6402.78) = 10565
21
Managing Flow Variability: Safety Inventory
Optimal Service Level: The Newsvendor ProblemAn electronics superstore is carrying a 60” LEDTV for the upcoming Christmas holiday sales. Each TV can be sold at $2,500. The store can purchase each unit for $1,800. Any unsold TVs can be salvaged, through end of year sales, for $1,700. The retailer estimates that the demand for this TV will be Normally distributed with mean of 150 and standard deviation of 15. How many units should they order? Note: If they order 150, they will be out of stock 50% of the time.Which service level is optimal? 80%, 90%, 95%, 99%??Cost =1800, Sales Price = 2500, Salvage Value = 1700Underage Cost = Marginal Benefit = p-c = 2500-1800 = 700Overage Cost = Marginal Cost = c-v = 1800-1700 = 100Optimal Service Level = P(R≤ROP) = MB/(MB+MC)
22
Managing Flow Variability: Safety Inventory
Optimal Service Level: The Newsvendor ProblemUnderage Cost =Cu = 2500-1800 = 700Overage Cost = Co = 1800-1700 = 100Optimal Service Level = P(R≤ROP) = MB/(MB+MC)SL = 700/800 = 0.875
1.15
Probability of excess inventory
0.875
Probability of shortage
0.125
R =N(150,15)ROP = LTD + Isafety= LTD + zσLTD= 150+1.15(15)Isafety = 17.25 = 18ROP = 168Risk = 12.5%
23
Managing Flow Variability: Safety Inventory
Optimal Service Level: The Newsvendor ProblemDemand for a product in the upcoming period is normally distributed with mean of 4000 and standard deviation of 1000.Unit Revenue = Sales Price = p = 30.Unit purchase cost = c = 10.Salvage value = v = 6. Goodwill cost = g = 1R = N(4000,1000)Overage Cost = Marginal Cost = MC = 10-6 = 4Underage Cost = Marginal Benefit = p-c + v = 30-10 +1 = 21Optimal Service Level = P(R≤ROP) = MB/(MB+MC)SL* = 21/25 = 0.84 Z(0.84) =
24
Managing Flow Variability: Safety Inventory
Optimal Service Level: The Newsvendor Problem
0.99Probability of
excess inventory
0.84
Probability of shortage
0.16
ROP = LTD + Isafety = LTD + zσLTD
ROP = 4000+0.99(1000)ROP = 4999Risk = 16%
25
Managing Flow Variability: Safety Inventory
Centralization and ROPThere are N warehouses. Each with lead time demand
of LTD and with standard deviation of lead time demand of σLTD.
If demand in each warehouse is independent of demand in other warehouses.
If they order all together and have a centralized safety stock then
The average demand during lead time for all the warehouses is N(LTD).
The standard deviation of the lead time demand for all warehouses is (σLTD)
26
Managing Flow Variability: Safety Inventory
Centralization and ROP
Demand N(80,10)
Warehouse A
Demand N(80,10)
Warehouse B
SL = 95%Isafety each =
1.65(10)Isafety each = 16.5Isafety all = 33
Demand N(160,)=N(160,14.14)
Warehouse A
Warehouse B
SL = 95%Isafety all =
1.65(14.14)Isafety all = 23.33
27
Managing Flow Variability: Safety Inventory
Independent Lead time demands at two locations
GE lighting with 7 warehouses. LTD for each warehouse has mean of 20,000 units and StdDev of 5,000 units and. Compute total Isafety at SL= 95% service level for centralized and decentralized systems. Isafety = 1.65×5000= 8250
𝐼 𝑠𝑎𝑓𝑒𝑡𝑦𝐷𝑒𝑐𝑒𝑛𝑡𝑟𝑎𝑙𝑖𝑧𝑒𝑑=7 (8250 )=57,750 is not 7(5000)(
13250
28
Managing Flow Variability: Safety Inventory
independent Lead time demands at N locations
In Waiting Line; Centralization , or Polling, leads to (i) flow time reduction and (ii) throughput improvement.In Inventory; Centralization leads to reduction in (i) cycle inventory, (ii) safety inventory, and (iii) flow time. If centralization reduces inventory, why doesn’t everybody do it?
― Longer response time― Higher shipping cost― Less understanding of customer needs― Less understanding of cultural, linguistics, and regulatory
barriersThese disadvantages may reduce the demand.
29
Managing Flow Variability: Safety Inventory
Principle of Aggregation and polling Inventory
Inventory benefits due to principle of aggregation.Statistics: Standard deviation of sum of random
variables is less than the sum of the individual standard deviations.
Physical consolidation is not essential, as long as available inventory is shared among various locations Polling Inventory– Virtual Centralization– Specialization– Component Commonality– Delayed Differentiation– Product Substitution
30
Managing Flow Variability: Safety Inventory
Virtual Centralization
Location AExceeds Available
stock1. Information about product demand and availability must be available at both locations
2. Shipping the product from one location to a customer at another location must be fast and cost effective
Location BLess than Available
stock
Virtual Centralization: inventory polling is facilitated using information regarding availability of goods and subsequent transshipment between locations.
polling is achieved by keeping the inventories at decentralized locations.
31
Managing Flow Variability: Safety Inventory
Component CommonalityWe discussed aggregating demand across various geographic
locations, either physical or virtual Aggregating demand across various products has the same
benefits.Computer manufacturers: offer a wide range of models, but
few components are used across all product lines.Replace Make-to-stock with make Make-to-Order Commonality + MTO: Commonality: Safety inventory of the common components
much less than safety inventory of unique components stored separately.
MTO: Inventory cost is computed in terms of WIP cost not in terms of finished good cost (which is higher).
32
Managing Flow Variability: Safety Inventory
Postponement (Delayed Differentiation)
Forecasting Characteristic: Forecasts further into the future tends to be less accurate than those of more imminent events.
Since shorter-range forecasts are more accurate, operational decisions will be more effective if supply is postponed closer to the point of actual demand.
Two Alternative processes (each activity takes one week)- Alternative A: (1) Coloring the fabric, (2) assembling T-
shirts- Alternative B: (1) Assembling T-shirts, (2) coloring the
fabricNo changes in flow time. Alternative B postponed the color
difference until one week closer to the time of sale. Takes advantage of the forecasting characteristic: short-Range forecast more accurate.
33
Managing Flow Variability: Safety Inventory
Postponement (Delayed Differentiation)
Two advantages: Taking advantage of two demand forecasting characteristics
- Commonality Advantage: At week 0; Instead of forecast for each individual item, we forecast for aggregates item – uncolored T-shirt. Forecast for aggregate demand is more accurate than forecast for individual item. It is easier to more accurately forecast total demand for different colored T-shirts for next week than the week after the next.
- Postponement Advantage: Instead of forecasting for each individual items two weeks ahead, we do it at week 1. Shorter rang forecasts are more accurate. It is easier to more accurately forecast demand for different colored T-shirts for next week than the week after the next.
34
Managing Flow Variability: Safety Inventory
Lessons Learned
Levers for Reducing Safety Inventory Reduce demand variability through improved
forecasting Reduce replenishment lead time Reduce variability in replenishment lead time poll safety inventory for multiple locations or
products Exploit product substitution Use common components Postpone product-differentiation processing until
closer to the point of actual demand