Building the Future Current Activities this Week : Foundations : Area 4 Field Level – Backfill of foundations for “infill” area between Column Lines 39-1 is complete. Concrete Flatwork : Area 3 Field Level – Concrete for base slab at Cauldron Club is complete. Masonry : Area 3 – Masonry pilaster installation at Truck Dock is ongoing. Area 1, 2, 3 – Masonry installation is ongoing at Concession Buildings. Steel : Area 1, 2, 3 – Canopy decking installation is ongoing. Area 2 – Concession Building steel truss and decking installation is nearly complete. Area 1 – Elevator support steel installation is ongoing for F1. Roofing and Sheetmetal : Area 1, 3 – Canopy gutter installation is complete. Area 1 – Subgirt installation for metal panels is ongoing at West Building. Metal Stud Framing : Area 1 – Metal stud framing for Field, Concourse, Suite and Press Levels are ongoing. Drywall installation is is ongoing at Field and Mezzanine Levels To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner From: Brandon Valdez Office: Kansas City Date: 10.20.2010 Re: Wizards Stadium Project Update – Week of 10.18.2010 Field Level Area 3 – Cauldron Club base slab has been placed. Field Level Area 3 – Masonry pilaster installation at East Elevation (Truck Dock). Area 1 – Masonry and Densglas installation at Northwest corner of West Building.

Memo wizards 10-20-2010

Embed Size (px)

Citation preview

Page 1: Memo wizards 10-20-2010

Building the Future

Current Activities this Week:

Foundations:

Area 4 Field Level – Backfill of foundations for “infill”

area between Column Lines 39-1 is complete.

Concrete Flatwork:

Area 3 Field Level – Concrete for base slab at Cauldron

Club is complete.

Masonry:

Area 3 – Masonry pilaster installation at Truck Dock is

ongoing. Area 1, 2, 3 – Masonry installation is ongoing

at Concession Buildings.

Steel:

Area 1, 2, 3 – Canopy decking installation is ongoing.

Area 2 – Concession Building steel truss and decking

installation is nearly complete. Area 1 – Elevator

support steel installation is ongoing for F1.

Roofing and Sheetmetal:

Area 1, 3 – Canopy gutter installation is complete.

Area 1 – Subgirt installation for metal panels is ongoing

at West Building.

Metal Stud Framing:

Area 1 – Metal stud framing for Field, Concourse, Suite

and Press Levels are ongoing. Drywall installation is

is ongoing at Field and Mezzanine Levels

To: David Ficklin - OnGoal

Rory O’Connor – OnGoal

Lee Turner – OnGoal

Andy Heitmann – Turner

Dave Dudzik - Turner

From: Brandon Valdez

Office: Kansas City

Date: 10.20.2010

Re: Wizards Stadium Project

Update – Week of

10.18.2010

Field Level Area 3 – Cauldron Club base slab

has been placed.

Field Level Area 3 – Masonry pilaster

installation at East Elevation (Truck Dock).

Area 1 – Masonry and Densglas installation

at Northwest corner of West Building.

Page 2: Memo wizards 10-20-2010

Building the Future

Glass:

Area 1 - Curtainwall framing and glass installation is

ongoing at West Building on west, south and east

elevations. South “wing” framing is complete.

MEP Rough-in:

Area 4 – Underground MEP rough-in is ongoing.

West Building - Ductwork installation on

Concourse, Suite and Press Levels are ongoing.

Plumbing rough-in is ongoing on Suite and

Press Levels. Fire Protection rough-in is ongoing on

Concourse, Suite and Press Levels. Electrical rough-in is

ongoing on Concourse, Suite and Press Levels.

Projected Activities occurring next Week:

Concrete Flatwork:

Area 3 Field Level – Prep for Slab-on-Grade at Stair 1

will continue. Area 4 Field Level – Installation of on-grade

seating risers and intermediate stairs will continue.

Area 1 Concourse Level – Placement of topping slabs inside

Concession Buildings will begin.

Masonry:

Area 3 – Field level masonry installation will continue in

Area C and D. Area 1, 2, 3 – Concourse building

masonry installation will continue.

Steel:

Field Level Area 3 – Misc steel installation that supports

Burnished CMU will begin. Field Level Area 2 - Subroof

installation will continue.

Roofing and Sheetmetal:

Area 1 – Permanent roofing installation at West

Building will continue. Area 1 – Subgirt installation at

West Building will continue.

Metal Stud Framing:

Area 1 – Metal stud framing on Field Level will continue.

Area 1 - Drywall installation will continue at Field Level

Concourse Level Area 1 – Soffit construction

on SW Concourse Concession Buildings.

Mezzanine Level Area 4 – Slab prep is

ongoing for Mezzanine walkway.

Field Level Area 4 – Structural steel at infill

area is set and foundations are backfilled.

Page 3: Memo wizards 10-20-2010

Building the Future

and Mezzanine Level. Drywall installation will begin on

Suite Level.

Glass:

Area 1 – Curtain Framing and Glass installation around West

Building will continue. Curtainwall framing on Suite and

Press Level balconies will continue. Solar Innovations

recessed track will deliver.

MEP Rough-in:

MEP Rough-in at Concourse, Suite and Press Levels will

continue. Ductwork installation on Concourse, Suite, and

Press Level will continue. Fire Sprinkler installation will

continue on Concourse, Suite and Press Levels. MEP

rough-in will continue in Main Concourse Buildings.

Area 1 – Shot of the Field Side of the West

Building looking Northwest.

Area 1 – Shot of the west building showing

the progress of the exterior envelope.

Page 4: Memo wizards 10-20-2010

Building the Future

Additional Photos:

Concourse Level Area 2 – Plumbing carriers

set in Restrooms 03.19.01.

Field Level Area 2– Swithgear is set in

Electrical Service Room 01.20.01.

Field Level Area 3 – Emergency Generator is

set.

Concourse Level Area 1 – Stair 4 installation

is ongoing.

Concourse Level Area 4 – Installation of

metal decking is nearly complete at “infill”

area.

Field Level Area 1 – Metal stud framing is

ongoing in Wizards Locker room.