Milestone Project SA2

Embed Size (px)

Citation preview

  • 7/23/2019 Milestone Project SA2

    1/18

    ID Task

    Mode

    Task Name Duration Start Finish Predecessors

    1 AQUE Pool And

    Snooker Ordering

    System

    205 days Mon

    01-09-14

    Fri 12-06-15

    2 1.0. Chapter 1:

    Project

    Identification

    16 days Mon

    15-09-14

    Sun

    05-10-14

    3 1.1. Introduction 6 days Mon

    15-09-14

    Sun

    21-09-14

    4 1.2. Client

    background

    6 days Mon

    15-09-14

    Sun

    21-09-14

    3

    5 1.3. Client

    business

    description

    6 days Mon

    15-09-14

    Sun

    21-09-14

    4

    6 1.4.

    Organizatioinal

    chart

    6 days Mon

    15-09-14

    Sun

    21-09-14

    5

    7 1.5. IT utilization

    / Organization

    planning

    11 days Mon

    22-09-14

    Sun

    05-10-14

    6

    8 1.6. Problem

    statement

    0 days Sun

    05-10-14

    Sun

    05-10-14

    7

    9 2.0. Project Initiation

    and Planning

    26 days Mon

    06-10-14

    Sun

    09-11-14

    05-10

    S S M T W T F S S M

    24 Aug '14 14 Sep '14 05 Oct '14 26 Oct '14

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 1

    Project: milestone project

    Date: Mon 22-06-15

  • 7/23/2019 Milestone Project SA2

    2/18

    ID Task

    Mode

    Task Name Duration Start Finish Predecessors

    10 2.1. Introduction 11 days Mon 06-10-1 Sun 19-10-14

    11 2.2. Baseline

    project plan (BPP)

    11 days Mon

    06-10-14

    Sun

    19-10-14

    10

    12 2.2.1.

    Introduction

    11 days Mon

    06-10-14

    Sun

    19-10-14

    13 2.2.2. Project

    overview

    11 days Mon

    06-10-14

    Sun

    19-10-14

    12

    14 2.2.3.

    Recommendatio

    11 days Mon

    06-10-14

    Sun

    19-10-14

    13

    15 2.2.4. System

    description

    6 days Mon

    13-10-14

    Sun

    19-10-14

    14

    16 2.3. Feasibility

    assessment

    16 days Mon

    13-10-14

    Sun

    02-11-14

    11

    17 2.3.1. Economic

    analysis

    6 days Mon

    13-10-14

    Sun

    19-10-14

    18 2.3.2. Technical

    analysis

    6 days Mon

    13-10-14

    Sun

    19-10-14

    17

    19 2.3.3.

    Operational

    analysis

    6 days Mon

    13-10-14

    Sun

    19-10-14

    18

    20 2.3.4. Legal and

    contractual

    analysis

    6 days Mon

    13-10-14

    Sun

    19-10-14

    19

    S S M T W T F S S M

    24 Aug '14 14 Sep '14 05 Oct '14 26 Oct '14

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 2

    Project: milestone project

    Date: Mon 22-06-15

  • 7/23/2019 Milestone Project SA2

    3/18

    ID Task

    Mode

    Task Name Duration Start Finish Predecessors

    21 2.3.5. Political

    analysis

    6 days Mon

    13-10-14

    Sun

    19-10-14

    20

    22 2.3.6. Schedule,

    timeline and

    resource

    analysis

    6 days Mon

    27-10-14

    Sun

    02-11-14

    21

    23 2.4. Management

    issue

    11 days Mon

    27-10-14

    Sun

    09-11-14

    16

    24 2.4.1. Team

    configuration

    and

    6 days Mon

    27-10-14

    Sun

    02-11-14

    25 2.4.2.

    Communication

    plan

    6 days Mon

    03-11-14

    Sun

    09-11-14

    24

    26 2.4.3. Project

    standards and

    procedures

    6 days Mon

    03-11-14

    Sun

    09-11-14

    25

    27 2.4.4. Other

    project specific

    topics

    6 days Mon

    03-11-14

    Sun

    09-11-14

    26

    28 2.4.5. Statement

    of project scope

    6 days Mon

    03-11-14

    Sun

    09-11-14

    27

    S S M T W T F S S M

    24 Aug '14 14 Sep '14 05 Oct '14 26 Oct '14

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 3

    Project: milestone project

    Date: Mon 22-06-15

  • 7/23/2019 Milestone Project SA2

    4/18

    ID Task

    Mode

    Task Name Duration Start Finish Predecessors

    29 3.0. Chapter 3:

    Analysis

    21 days Mon

    10-11-14

    Sun

    07-12-14

    9

    30 3.1. Introduction 6 days Mon 10-11-1 Sun 16-11-14

    31 3.2. Determining

    system

    requirement

    6 days Mon

    10-11-14

    Sun

    16-11-14

    30

    32 3.2.1.

    Requirements

    collected from

    conversation /

    observation

    6 days Mon

    10-11-14

    Sun

    16-11-14

    33 3.2.2.

    Requirements

    collected fromwritten

    information

    6 days Mon

    10-11-14

    Sun

    16-11-14

    32

    34 3.2.3. Listing /

    summary of

    requirements

    6 days Mon

    10-11-14

    Sun

    16-11-14

    33

    35 3.3. Structuring

    systems

    requirements:

    Process Modeling

    11 days Mon

    17-11-14

    Sun

    30-11-14

    31

    S S M T W T F S S M

    24 Aug '14 14 Sep '14 05 Oct '14 26 Oct '14

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive TaskInactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-onlyFinish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 4

    Project: milestone project

    Date: Mon 22-06-15

  • 7/23/2019 Milestone Project SA2

    5/18

    ID Task

    Mode

    Task Name Duration Start Finish Predecessors

    36 3.3.1. Context

    Data Flow

    Diagram (DFD)

    6 days Mon

    24-11-14

    Sun

    30-11-14

    37 3.3.2. DFD of

    new logical

    system

    6 days Mon

    24-11-14

    Sun

    30-11-14

    36

    38 3.3.3. Thorough

    descriptions of

    DFD

    components

    6 days Mon

    24-11-14

    Sun

    30-11-14

    37

    39 3.4. Structuring

    systems

    requirements:

    Conceptual Data

    Modeling

    11 days Mon

    24-11-14

    Sun

    07-12-14

    35

    40 3.4.1. Entityrelarionship

    diagram (ERD)

    6 days Mon01-12-14

    Sun07-12-14

    41 4.0. Chapter 4:

    Design

    48 days Tue

    03-03-15

    Thu

    07-05-15

    29

    42 4.1. Introduction 5 days Fri 13-03-15 Thu 19-03-15

    43 4.2. Database

    design

    15 days Fri 13-03-15 Thu

    02-04-15

    42

    S S M T W T F S S M

    24 Aug '14 14 Sep '14 05 Oct '14 26 Oct '14

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive TaskInactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-onlyFinish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 5

    Project: milestone project

    Date: Mon 22-06-15

  • 7/23/2019 Milestone Project SA2

    6/18

    ID Task

    Mode

    Task Name Duration Start Finish Predecessors

    44 4.2.1.

    Conceptual data

    model

    15 days Fri 13-03-15 Thu

    02-04-15

    45 4.2.1.1.

    Relational

    database

    model

    5 days Fri 13-03-15 Thu

    19-03-15

    46 4.2.1.2.

    Logical data

    model

    5 days Fri 20-03-15 Thu

    26-03-15

    45

    47 4.2.1.3.

    Physical file

    and database

    design (Data

    Dictionary)

    5 days Fri 27-03-15 Thu

    02-04-15

    46

    48 4.3. Forms and

    report design

    15 days Fri 20-03-15 Thu

    09-04-15

    43

    49 4.3.1. Narrative

    overview

    5 days Fri 20-03-15 Thu

    26-03-15

    50 4.3.2. Sample

    design

    5 days Fri 27-03-15 Thu

    02-04-15

    49

    51 4.3.3. Testing

    and usabilityassessment

    5 days Fri 03-04-15 Thu

    09-04-15

    50

    S S M T W T F S S M

    24 Aug '14 14 Sep '14 05 Oct '14 26 Oct '14

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive TaskInactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-onlyFinish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 6

    Project: milestone project

    Date: Mon 22-06-15

  • 7/23/2019 Milestone Project SA2

    7/18

    ID Task

    Mode

    Task Name Duration Start Finish Predecessors

    52 4.4. Interface and

    dialogue design

    30 days Fri 27-03-15 Thu

    07-05-15

    48

    53 4.4.1. Narrative

    overview

    10 days Fri 27-03-15 Thu

    09-04-15

    54 4.4.2. Sample

    design

    10 days Fri 10-04-15 Thu

    23-04-15

    53

    55 4.4.3. Testing

    and usability

    assessment

    10 days Fri 24-04-15 Thu

    07-05-15

    54

    56 5.0. Chapter 5:

    Implementation

    48 days Fri 10-04-15 Tue

    16-06-15

    41

    57 5.1. Introduction 5 days Fri 10-04-15 Thu 16-04-15

    58 5.2. Program /

    coding design

    30 days Fri 17-04-15 Thu

    28-05-15

    57

    59 5.3. Testing 6 days Fri 29-05-15 Fri 05-06-15 58

    60 5.3.1. Test plan 3 days Fri 29-05-15 Tue 02-06-15

    61 5.3.2. Test data 3 days Wed 03-06-1 Fri 05-06-15 60

    S S M T W T F S S M

    24 Aug '14 14 Sep '14 05 Oct '14 26 Oct '14

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive TaskInactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-onlyFinish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 7

    Project: milestone project

    Date: Mon 22-06-15

  • 7/23/2019 Milestone Project SA2

    8/18

    ID Task

    Mode

    Task Name Duration Start Finish Predecessors

    62 5.4. Installation 6 days Wed 03-06-1 W ed 10-06-1 5 9

    63 5.4.1. User guide 3 days Wed 03-06-1 Fri 05-06-15

    64 5.4.2. User

    training manual

    3 days Mon

    08-06-15

    Wed

    10-06-15

    63

    65 5.5.

    Documentatioin

    5 days Wed

    03-06-15

    Tue

    09-06-15

    62

    66 5.5.1. User

    manual /

    documentation

    5 days Wed

    03-06-15

    Tue

    09-06-15

    67 5.6. Training

    manual

    5 days Wed

    10-06-15

    Tue

    16-06-15

    65

    68 5.7. User support 10 days Wed 03-06-1Tue 16-06-1567

    69 5.7.1. Help desk 5 days Wed 03-06-1 Tue 09-06-15

    70 5.7.2. Online

    help

    5 days Wed

    10-06-15

    Tue

    16-06-15

    69

    71 Final Documentation 2 days Wed10-06-15

    Thu11-06-15

    S S M T W T F S S M

    24 Aug '14 14 Sep '14 05 Oct '14 26 Oct '14

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive TaskInactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-onlyFinish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 8

    Project: milestone project

    Date: Mon 22-06-15

  • 7/23/2019 Milestone Project SA2

    9/18

    ID Task

    Mode

    Task Name Duration Start Finish Predecessors

    72 System Presentation 1 day Fri 12-06-15 Fri 12-06-15S S M T W T F S S M

    24 Aug '14 14 Sep '14 05 Oct '14 26 Oct '14

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 9

    Project: milestone project

    Date: Mon 22-06-15

  • 7/23/2019 Milestone Project SA2

    10/18

    12-06

    T W T F S S M T W T F S S M T W T F S S M T W T F S S M T

    16 Nov '14 07 Dec '14 28 Dec '14 18 Jan '15 08 Feb '15 01 Mar '15 22 Mar '15 12 Apr '15 03 May '15 24 May '15 14 Jun '15

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 10

    Project: milestone project

    Date: Mon 22-06-15

  • 7/23/2019 Milestone Project SA2

    11/18

    T W T F S S M T W T F S S M T W T F S S M T W T F S S M T

    16 Nov '14 07 Dec '14 28 Dec '14 18 Jan '15 08 Feb '15 01 Mar '15 22 Mar '15 12 Apr '15 03 May '15 24 May '15 14 Jun '15

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 11

    Project: milestone project

    Date: Mon 22-06-15

  • 7/23/2019 Milestone Project SA2

    12/18

    T W T F S S M T W T F S S M T W T F S S M T W T F S S M T

    16 Nov '14 07 Dec '14 28 Dec '14 18 Jan '15 08 Feb '15 01 Mar '15 22 Mar '15 12 Apr '15 03 May '15 24 May '15 14 Jun '15

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 12

    Project: milestone project

    Date: Mon 22-06-15

  • 7/23/2019 Milestone Project SA2

    13/18

    T W T F S S M T W T F S S M T W T F S S M T W T F S S M T

    16 Nov '14 07 Dec '14 28 Dec '14 18 Jan '15 08 Feb '15 01 Mar '15 22 Mar '15 12 Apr '15 03 May '15 24 May '15 14 Jun '15

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 13

    Project: milestone project

    Date: Mon 22-06-15

  • 7/23/2019 Milestone Project SA2

    14/18

    T W T F S S M T W T F S S M T W T F S S M T W T F S S M T

    16 Nov '14 07 Dec '14 28 Dec '14 18 Jan '15 08 Feb '15 01 Mar '15 22 Mar '15 12 Apr '15 03 May '15 24 May '15 14 Jun '15

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 14

    Project: milestone project

    Date: Mon 22-06-15

  • 7/23/2019 Milestone Project SA2

    15/18

    T W T F S S M T W T F S S M T W T F S S M T W T F S S M T

    16 Nov '14 07 Dec '14 28 Dec '14 18 Jan '15 08 Feb '15 01 Mar '15 22 Mar '15 12 Apr '15 03 May '15 24 May '15 14 Jun '15

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 15

    Project: milestone project

    Date: Mon 22-06-15

  • 7/23/2019 Milestone Project SA2

    16/18

    T W T F S S M T W T F S S M T W T F S S M T W T F S S M T

    16 Nov '14 07 Dec '14 28 Dec '14 18 Jan '15 08 Feb '15 01 Mar '15 22 Mar '15 12 Apr '15 03 May '15 24 May '15 14 Jun '15

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 16

    Project: milestone project

    Date: Mon 22-06-15

  • 7/23/2019 Milestone Project SA2

    17/18

    11-06

    T W T F S S M T W T F S S M T W T F S S M T W T F S S M T

    16 Nov '14 07 Dec '14 28 Dec '14 18 Jan '15 08 Feb '15 01 Mar '15 22 Mar '15 12 Apr '15 03 May '15 24 May '15 14 Jun '15

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 17

    Project: milestone project

    Date: Mon 22-06-15

  • 7/23/2019 Milestone Project SA2

    18/18

    12-06

    T W T F S S M T W T F S S M T W T F S S M T W T F S S M T

    16 Nov '14 07 Dec '14 28 Dec '14 18 Jan '15 08 Feb '15 01 Mar '15 22 Mar '15 12 Apr '15 03 May '15 24 May '15 14 Jun '15

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 18

    Project: milestone project

    Date: Mon 22-06-15