Mining Guide Epc and Epcm Contracts 104178

Embed Size (px)

Citation preview

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    1/40

    Financial institutionsEnergyInfrastructure, mining and commoditiesTransportTechnology and innovationLife sciences and healthcare

    EPC and EPCM contractsA guide to EPC and EPCM contractsfor junior mining companies

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    2/40

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    3/40

    A Norton Rose Fulbright Guide

    EPC and EPCM contractsA guide to EPC and EPCM contractsfor junior mining companies

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    4/40

    Norton Rose Fulbright is a global legal practice. Weprovide the world’s pre-eminent corporations and

    financial institutions with a full business law service.

    We have more than 3800 lawyers based in over 50 cities

    across Europe, the United States, Canada, Latin America,

    Asia, Australia, Africa, the Middle East and Central Asia.

    Recognized for our industry focus, we are strong across

    all the key industry sectors: financial institutions;energy; infrastructure, mining and commodities;

    transport; technology and innovation; and life sciences

    and healthcare.

    Wherever we are, we operate in accordance with our

    global business principles of quality, unity and integrity.

    We aim to provide the highest possible standard of legalservice in each of our offi ces and to maintain that level of

    quality at every point of contact.

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    5/40

    Summary 04

    Introduction 05

    EPC Contracts 08

    Key lender requirements 09

    EPCM Contracts 19

    Appendix 1 29

    Contacts 35

    Contents

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    6/40

    04 Norton Rose Fulbright

    EPC and EPCM contracts

    Summary

    The importance of a robust strategy for the procurement of a mining project, from

    project inception through to construction implementation, can not be underestimated.

    Full consideration of the key procurement issues identied in this guide can often

    mean the dierence between achieving a ‘bankable’ project with optimal returns for the

    mining company, and an expensive project failure.

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    7/40

    Norton Rose Fulbright 05

    Introduction

    Introduction

    General

    This guide explores the key steps to be taken and considerations to be made by a junior

    mining company (the Sponsor) to achieve a project structure that is both bankable and

    able to deliver optimal returns for the Sponsor.

    On the assumption that the Sponsor has determined through a full and properfeasibility process that the project is economically viable, it must then consider how

    the project is to be delivered. We have produced several brieng papers on issues to be

    considered when looking to secure nance for projects in the mining sector, but a key

    aspect of securing such nance will be convincing lenders (or other backers) that the

    structure for project delivery is robust.

    In this guide we will look at the key considerations to be made by a Sponsor in terms

    of achieving a construction structure that is both bankable and economically viable.

    Bankability

    It is perhaps rst necessary to explain what we mean by the term ‘bankable’ or

    ‘bankability’. The terms are usually used to describe a lender’s view on the robustness

    of the project structure in terms of its ability to secure full repayment of outstanding

    debt, either through project delivery in accordance with Sponsor requirements or,

    in a default scenario, through appropriate recourse against the contractor (or other

    stakeholders (as appropriate)) responsible for project delivery.

    In the context of detailed engineering and construction delivery, lenders will prefer

    for one nancially robust party to accept full responsibility for the delivery of the works

    on time, on budget and to meet the required technical and performance specication.

    The key candidates in this regard are typically large internationally recognised

    engineering and construction contractors.

    The identity of the contractor can certainly have an impact on the lenders’ view

    on bankability.

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    8/40

    06 Norton Rose Fulbright

    EPC and EPCM contracts

    The importance of achieving this single point of responsibility relates to a desire bythe lenders to see the party with the ‘deepest pockets’ bearing the entire risk of project

    delivery. To the extent that more than one party is responsible for delivery of the works

    (in terms of direct liability to the Sponsor), lenders will be concerned that either:

    • there may be gaps in liability cover or

    • that there may be interface issues when it comes to identifying the party responsible

    for a failure; or, perhaps worst of all

    • that the party identied as being responsible for a failure can not be held to account

    either because its liability is limited in some way under the terms of its contract

    with either the Sponsor or the EPC contractor (as the case may be) or more generally

    because it does not have the balance sheet to meet the liabilities in question.

    Contract structures

    The preferred option for delivery of the single point responsibility solution describedabove will typically come in the form of a turnkey engineering, procurement and

    construction (EPC) contract.

    Whilst it is recognised that there are several internationally recognised forms of EPC

    contract, each oering a balanced approach to contracting risk, the hardening of

    the lending market in recent years (and especially post global nancial crisis (GFC))

    has seen a move away from use of these forms, in the context of a limited recourse

    project nance transaction, without signicant amendment. When procuring an EPC

    contractor, it is essential that there is transparency regarding likely lender requirements

    from the outset. Raising these points post selection of the preferred EPC contractor

    will place the Sponsor in a weak bargaining position if (and more likely, when), as a

    consequence, the EPC contractor proposes additional contingent risk pricing.

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    9/40

    Norton Rose Fulbright 07

    Introduction

    The development of detailed design at feasibility stage may undermine the Sponsor’sability to achieve a single point of responsibility solution without being exposed to

    inated construction pricing, either because there is a lack of appetite in the market to

    take on 3rd party design risk or because those parties willing to take on such design

    risk will only do so with a signicant amount of contingent risk pricing (see our

    guide titled ‘A Guide to Feasibility Planning for Junior Mining Companies’ for further

    consideration on these on these issues).

    In circumstances where the single point responsibility position described above cannot

    be achieved or is not necessary because the Sponsor is sophisticated and can itselfmanage residual risks or its achievement would adversely aect project economics such

    that the Sponsor may not want it, the Sponsor may look to alternative structures. In

    this respect, we will consider below, in the context of bankability considerations, the

    fundamental dierences between the EPC and the alternative engineering, procurement

    and construction management (EPCM) contracting structures. In particular, we will

    identify the likely challenges when opting to use the EPCM structure.

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    10/40

    08 Norton Rose Fulbright

    EPC and EPCM contracts

    EPC Contracts

    General

    Figure 1 below demonstrates a typical EPC contracting structure under which lenders

    and the Sponsor will look for the EPC contractor to accept single point responsibility for

    all aspects of design and construction.

    Notwithstanding the fact that the Sponsor may be able to achieve this contractualstructure, the bankability of the contracting structure will depend also on satisfaction

    of certain key lender requirements under the terms of the EPC contract. These key

    requirements will establish the obligations on the EPC contractor in terms of project

    delivery and importantly, the recourse available against the EPC contractor in a

    default scenario.

    In order to gain a better understanding of the approach being seen more recently by

    lenders in the mining sector, it would be helpful for us to set out what we see as being

    those key commercial terms that lenders will typically be looking for under the terms ofan EPC contract.

     EPC Contract 

    Mining Company

    EPC Contractor

    Sub-contractor B Sub-contractor CSub-contractor A

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    11/40

    Norton Rose Fulbright 09

    Key lender requirements

    Key lender requirements

    Design riskThe lenders’ ideal position will be for the party delivering the works to be responsible

    for all aspects of the works, including design (whether or not produced by the party

    assuming responsibility for the works). This transfer of responsibility should even

    extend to mistakes in the Sponsor’s own stated initial design requirements. If this design

    risk transfer is not achieved, the risk to the Sponsor of cost overrun could be signicant

    since there is likely to be increased exposure to claims for additional time and moneyresulting from the requirement to remediate errors identied in 3rd party design.

    Since the liability for cost overruns in the circumstances described above may be

    signicant, it is unlikely that this risk may be backed o fully with the party ultimately

    responsible for producing the design in question. It is more likely therefore that the

    residual cost overrun risk will rest with the Sponsor. Whilst in the rst instance, this

    is clearly a concern for the Sponsor, lenders will also be concerned to see that the

    Sponsor is able to manage the potential nancial consequences. This may be achieved

    through use of a designated cost overrun facility or a request that the Sponsor providesadditional security.

    Whilst the intention of the parties may be for the EPC contractor to accept entire

    responsibility for the adequacy, accuracy and completeness of design, the lenders

    will nonetheless want to assess fully the extent to which design risk may lter back

    to the Sponsor under the terms of the EPC contract. An example of where this may

    happen is in circumstances where the Sponsor accepts the risk in certain sub-surface

    site conditions. For instance, the Sponsor may warrant the correctness of survey

    information relating to the site and accordingly the EPC Contractor will develop

    its detailed design and submit its tender price in accordance with the warranted

    information. However, if this information is incorrect, the risk in the design, and in

    particular the impact of the changes to the design required to reect actual sub surface

    conditions, will pass back to the Sponsor.

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    12/40

    10 Norton Rose Fulbright

    EPC and EPCM contracts

    In practice, the lenders’ technical adviser will review the risk prole proposed underthe terms of the EPC Contract generally and will advise the lenders as to the Sponsor’s

    potential exposure to cost overrun risk arising from circumstances of the type described

    above. It will ultimately be for the Sponsor to convince the lenders that any such risk

    identied may be managed by the Sponsor. The Sponsor should of course be aware that

    lenders may again seek additional ‘mitigation’ through use of a cost overrun facility or a

    request that the Sponsor provides additional security. In the alternative, Sponsors and/

    or their lenders will seek to push the risk in question back to the EPC contractor, which

    may of course have pricing consequences.

    Time and costWhilst we have discussed time and cost risk specically in relation to design above, as

    a general point of principle, lenders will want to limit to the fullest extent possible the

    EPC contractor’s ability to claim for additional time and/or money under the terms of

    the EPC contract. Again, lenders will be concerned about the ability of the Sponsor to

    manage the nancial consequences that will accompany these time and cost claims and

    more generally the extent to which exposure to such claims may impact on the delivery

    of the works in accordance with the requirements of the EPC contract.

    Many of the international forms of EPC contract contain scope for time and money

    claims being made by the contractor. For instance, FIDIC Silver Book places time

    and cost risk for the occurrence of changes in law, compliance with certain employer

    instructions and the discovery of objects of antiquity at the works site with the

    employer. Whilst on balance this may not appear unreasonable, the employer’s

    potential cost and loss of revenue exposure arising as a result of accepting these risks

    may be signicant. We have seen more recently lenders pushing back on the acceptance

    by a Sponsor of these types of risk, allowing for contractor time and money claims only

    in very limited circumstances.

    The key point to recognise is that the acceptance by the Sponsor of any aspect of

    time and/or cost risk will undermine the xed price assumption sought under the

    EPC structure. On the assumption that lenders can get comfortable with this type

    of risk being retained by the Sponsor, the Sponsor should itself think very carefully

    before accepting such risks. The potential exposure to additional costs will need to be

    appraised fully by the Sponsor as will any potential impact on the nancial model for

    the project. The Sponsor should ideally seek board buy-in to any such proposals, and

    in particular to the commitment of additional equity as may be required at an early

    stage in the project. Parent company buy-in may also be necessary particularly where

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    13/40

    Norton Rose Fulbright 11

    Key lender requirements

    parent company guarantees will be required. We would additionally expect the Sponsorto formulate a strategy for managing any such risks. A ‘let’s wait and see’ approach

    is unlikely to be satisfactory, since it is likely that prompt and pre-formulated action

    will be necessary on the occurrence of the risk in question if the Sponsor’s nancial

    exposure is to be mitigated to fullest extent possible.

    Delay damagesTo the extent that the works are completed on a date later than that xed under the

    terms of the EPC contract for reasons for which the EPC Contractor is responsible (or

    are within its agreed liability envelope), the contract will typically include provisionfor payment of liquidated and ascertained damages (LADs). These LADs will typically

    be paid at a daily rate to cover anticipated lost prots and costs (including debt service

    costs (as applicable)) during the period of delay. It would be unusual for the EPC

    contractor to accept unlimited exposure in this regard and any liability sub-cap agreed

    will typically be sized to the level of LADs payable up to the construction long stop date.

    Whether or not any such sub-cap will fall within the contractor’s overall liability cap is

    likely to be an area of debate between lenders, the Sponsor and the EPC contractor. This

    issue will tend to be considered by lenders in the context of the EPC security package as

    a whole and we will discuss this point in further detail below.

    Performance liabilityFollowing completion of construction and the handover of the works, the Sponsor and

    the lenders will be keen to ensure that any process system or plant forming part of the

    works is able to achieve certain minimum performance requirements. This is usually

    required in order to provide both parties with a degree of comfort that projected project

    revenues can be achieved by the completed plant over a sustained period. It is usual

    therefore for the EPC contract to also document the requirement for a post completion

    testing regime.

    To the extent that the minimum performance required (or performance guarantees) can

    not be achieved for a sustained period of operations, the EPC contractor will typically

    be liable for payment of performance liquidated damages up to an agreed liability

    cap. The damages will usually be sized according to the loss of revenue and/or prot

    occasioned by the performance shortfall for a nite period of time.

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    14/40

    12 Norton Rose Fulbright

    EPC and EPCM contracts

    It would be unusual for the Sponsor to achieve a life of mine performance guarantee and,as such, it would be usual for the liability cap in relation to performance damages to be

    capped at the Sponsor’s loss prot and debt service costs for a specically negotiated

    period. Whilst residual liability will be a Sponsor risk, it would be usual for the Sponsor

    to manage this risk by building headroom into the nancial model for the project and

    through plant optimisation over time (including through lifecycle type maintenance).

    The pre and post-handover testing regime will be subject to scrutiny by the lenders’

    technical adviser. If, for instance, it is apparent prior to handover of the works that the

    plant is not going to achieve the lenders’ base case performance/output requirements,the lenders may look for a right to reject the plant in its entirety with full recourse

    against the EPC contractor for debt outstanding. For obvious reasons, EPC contractors

    will tend to resist any such position. They may, for example, look for an extended

    period of additional testing in order to rene the plant and to achieve the required

    performance levels. If this is permitted, time and cost impact of this additional testing

    will tend to be at the EPC contractor’s risk and the lenders will typically seek to retain

    the right to reject at the conclusion of any such repeated testing or any subsequent post-

    handover testing regime, if a required level of performance is not demonstrated.

    Again, where detailed process design is not provided by the EPC contractor, it may

    be more dicult to require this party to accept performance risk in full, particularly

    in circumstances where the technology is more complex in nature. Carving out these

    types of risks from the EPC contractor’s liability under the terms of the EPC Contract

    is however likely to make potential lenders nervous for the reasons discussed above.

    Whilst lenders may accept the interface risk in this liability gap being lled by the

    designer itself (whether under the terms of a design contract with the Sponsors or

    under the terms of a collateral warranty), it is often the case that the party providing the

    detailed process design is either unwilling or unable to accept the type and extent of

    liability for design failure that would usually rest with an EPC contractor under the terms

    of the EPC contract. If this is the case, lenders may require additional security from the

    Sponsor to bridge the liability gap and to help manage any additional interface risk.

    Limitations on liabilityAs indicated above, a key consideration for lenders when considering lending into

    a mining project will be the extent to which they will have recourse against the EPC

    contractor for debt outstanding in an EPC contractor default scenario.

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    15/40

    Norton Rose Fulbright 13

    Key lender requirements

    There is, as may be expected, a tension between the lenders’ requirement for full coverageof debt outstanding from the EPC contractor’s security package and the legitimate

    requirement of a contractor to limit its liability exposure. It is not unusual however for

    lenders in the current market to look for an aggregate liability cap of up to 100 per cent

    of the contract price, especially where the works include an unproven technical solution.

    The lenders may however accept a lower liability cap on the basis that liability for certain

    key risks is excluded from the aggregate liability cap. It is not uncommon for instance

    for lenders to seek to exclude liabilities that are the subject of a sub-cap, such as delay or

    performance liquidated damages, from the aggregate liability cap.

    The appropriate exclusions from the aggregate liability cap will be negotiated on a

    project specic basis by the lenders following adviser input. The list of exclusions will

    typically include those liabilities that are not able to be limited at law (and this will

    require local law advice), those liabilities that are uninsurable and those liabilities that

    are not quantiable (and therefore able to be reckoned in the sizing of the cap) at the

    date of contracting.

    Security packageAs we have discussed above, to the extent that the EPC contractor fails to deliver theworks, the lenders and, in the rst instance, the Sponsor, must have direct recourse

    against the EPC contractor to recover relevant losses. The lenders will ultimately control

    this process through restrictions placed on the Sponsor in the nance documentation.

    For instance, the lenders will not allow the Sponsors to use (and ultimately deplete) the

    EPC security package to replace a defaulting EPC contractor in circumstances where

    such replacement is unlikely, in itself, to secure delivery of the project. It is more likely

    in these circumstances that the lenders will look to call a default under the terms of the

    nance documentation, trigger its security over the project documentation and access

    the EPC security package to recover debt outstanding.

    The security provided by the EPC contractor in respect of its potential liabilities will

    typically be formed, in part, by a form or forms of liquid security.

    Liquid security and bondingWhen we talk of liquid security, we are talking about forms of security that should be

    as good as money in the bank for the Sponsor. The Sponsor should be able to claim any

    such monies by simply serving a demand on the party providing the security on behalf

    of the EPC contractor. Typical forms of liquid security are performance bonds, retention

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    16/40

    14 Norton Rose Fulbright

    EPC and EPCM contracts

    bonds and letters of credit, all usually provided by international banks with lenderapproved credit ratings.

    Leaving retention bonds to one side for the time being, the lenders in the current

    lending market will typically require the EPC contractor to procure performance

    security (ie, performance bonds and/or letters of credit) with a value no less than

    15-20 per cent of the contract sum, but this may vary on a project specic basis. The

    lenders are however likely to permit a step down in performance security coverage as

    the works progress to reect reduced risk in the project for the lenders. Typically, the

    level of performance security coverage may reduce by 50%, for instance, followingthe completion of operational testing and will usually be discharged completely upon

    expiry of the defects liability period (ie, 12-24 months post-handover of the works).

    In the UK domestic market, there has been a shift in recent years away from providing

    performance bonds of the type described above. This is not to say that such bonds are

    not available, however procuring them can be prohibitively expensive. Instead the

    UK has increasingly seen use of conditional bonds under which the beneciary must

    rst establish the right to make a claim and the quantum of any claim before a call is

    made on the bond. Whilst a fraudulent claim under an unconditional bond of the typedescribed above can be challenged, a conditional bond is less ‘liquid’ in nature and is

    more akin to a form of guarantee and for the reasons set below will be less attractive to

    both the Sponsor and its lenders.

    It is usual for lenders to also require that a xed amount of any payment being made to

    the EPC contractor is retained and held by the Sponsor as security for the remedying of

    defects subsequently discovered in the works. Unlike the performance security which

    secures more general performance by the EPC contractor under the terms of the EPC

    contract, retentions are held for a specic and dened purpose. However, in reality

    this is somewhat of a falsity as lenders generally view retentions as part of the wider

    security package available to the Sponsor, and ultimately the lenders, as security for

    non-performance by the EPC contractor.

    The level of retention required by lenders will vary but typically will be between

    3-5 per cent of the contract sum. Instead of a cash retention being made on any

    payment to the EPC contractor, and to assist the EPC contractor’s cash ow, lenders will

    usually instead accept a form of retention bond as an alternative which will provide

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    17/40

    Norton Rose Fulbright 15

    Key lender requirements

    security for monies that would have otherwise been retained. Any such instrumentshould be in the same form as the performance bond discussed above, ie, provided

    by an international bank with an approved credit rating and permitting claims for

    payment upon the presentation by the Sponsor of a demand for payment. Again, any

    such bond should be as good as money in the bank for the Sponsor.

    To the extent that any advance payment is made to cover the cost of the ordering of

    plant and materials or mobilisation, lenders will expect the Sponsor to secure such

    payments by requiring the contractor to procure an advance payment bond. Again, any

    such bond should be unconditional and as good as cash in the bank for the Sponsor.

    Liquid security and guaranteesOutside of liquid forms of security, lenders will typically require a guarantee from the

    ultimate parent of the EPC contractor. The ultimate parent is usually a requirement as a

    shell holding company, for instance, with limited or no assets will not be acceptable to

    the lenders.

    In practice, lenders will carry out their own due diligence on the parent company

    proposed to ensure that it is suciently robust to meet its potential liabilities underthe guarantee.

    Unlike the forms of liquid security described above, a guarantee of this kind will

    usually rst require the establishment by the Sponsor of liability against the EPC

    contractor, which the EPC contractor has failed to discharge. Furthermore, the Sponsor

    will run the risk that any claim made under the guarantee will be subject to challenge

    by the guarantor. Far from being akin to cash in the banks, the pursuit of a claim

    under a parent company guarantee can be a lengthily process which is why claims

    under the liquid forms of security will usually be the Sponsor’s rst port of call (unless

    of course there are restrictions on the order in which claims may be made under the

    relevant documentation).

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    18/40

    16 Norton Rose Fulbright

    EPC and EPCM contracts

    TerminationLenders will tend to have certain minimum requirements in terms of the circumstances

    where they will expect the Sponsor to have the right to terminate the EPC contractor

    and access the EPC security package to either replace the defaulting EPC contractor and

    secure project continuance or bring the project to an end. As we have indicated earlier,

    the lenders will control the actions of the Sponsor in this regard through the restrictions

    imposed on the Sponsor under the terms of the nance documentation.

    It would be usual for lenders to look for the EPC contract to contain a right to terminate

    the EPC contractor in circumstances where recourse against the EPC contractor maybe limited in some way or where key requirements relating to performance are not

    achieved. Lenders will typically look for advance warning of any problems relating to the

    works so that armative action may be taken before the circumstances become critical.

    Lenders will be especially concerned to see that the losses recoverable on termination

    will (to the fullest extent possible) cover amounts outstanding under the terms of the

    nance documentation (ie, principal, interest and fees). The ability of lenders to recover

    these losses tends to be very dicult for the uninitiated to understand and accept

    this, but this is part and parcel of limited recourse project nancing where the lenders’security is limited to the project and those responsible for delivering it.

    EPC contracts – key point summary

    (a) In terms of delivery of the detailed engineering and construction phase of a

    project, lenders will usually prefer for one nancially robust party to accept full

    responsibility for the delivery of all aspects of the works on time, on budget and to

    meet the required technical and performance specication. In achieving this single

    point of responsibility position there will be reduced risk that:

     — there may be gaps in liability cover;

     — there may be interface issues when it comes to identifying the party responsible

    for a failure; or

     — the party identied as being responsible for a failure can not be held to account

    either because its liability is limited contractually or more generally because it

    does not have the balance sheet to meet the liabilities in question.

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    19/40

    Norton Rose Fulbright 17

    Key lender requirements

    (b) If the single point of responsibility position can not be achieved, and on theassumption that lenders accept this, the Sponsors must consider how they will

    themselves manage the risk(s) in question and in particular the concerns identied

    in sub-paragraph (a) above. The Sponsors should at an early stage plan for the

    management of the relevant risk(s) and obtain board approval to the provision of

    additional security or the need for any additional cost overrun facility.

    (c) The lenders will have key requirements in terms of:

    (i) the obligations on the EPC contract to deliver the works on time, on budget andto meet a required technical and performance specication; and

    (ii) the recourse available against the EPC contractor to the extent that it fails to

    discharge its obligations under the terms of the EPC contract.

    The preferred EPC contractor should be procured on the basis that these key

    requirements will be included in the form of EPC contract eventually signed. This will

    allow for certainty of EPC price at the conclusion of EPC procurement process and will

    mitigate the likelihood of price escalation following EPC contractor selection.

    General

    The acronym ‘EPCM’ is commonly mentioned in the same breath as the EPC structure

    described above. However, from both a structuring and risk allocation perspective, the

    two contracting solutions are fundamentally dierent. The confusion would appear

    to come from the shared use of the work ‘construction’ in their titles. It is important

    however to recognise that an EPCM contract is (amongst other things) essentially a

    design and construction management contract and that no physical construction will

    actually be carried out by the EPCM contractor.

    The EPCM structure has been used extensively in the mining sector, especially in the

    years leading up to the global nancial crisis (GFC) where the lending market became

    more contractor friendly in terms of both risk allocation and pricing. However, post GFC

    the lending market has hardened and the liquidity gap has meant that lenders have been

    increasingly risk averse and far more selective about the projects they are willing back.

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    20/40

    18 Norton Rose Fulbright

    EPC and EPCM contracts

    This being said, we have seen more recently the EPCM procurement route re-emerge asthe preferred procurement model in the mining sector.

    For all that has been said above around the need for a single point responsibility etc.,

    lenders may consider backing a project being procured on an EPCM basis provided that

    certain minimum requirements have been met. This is certainly the way we are seeing

    the market move.

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    21/40

    Norton Rose Fulbright 19

    EPCM Contracts

    EPCM Contracts

    The EPCM structure

    In contrast with an EPC contract (and as mentioned above), the EPCM contractor does

    not undertake primary responsibility for delivery of the construction works. The EPCM

    contract is essentially a professional services contract under which the EPCM contractor

    will typically carry out the following services:

    • Engineering services – the EPCM contractor will typically be the party producing

    the basic design at feasibility stage or will be appointed post feasibility under the

    terms of the EPCM contract to complete the basic design developed by or on behalf

    of the Sponsor. The EPCM contractor will typically be responsible for overall co-

    ordination of design for the project to ensure that the completed works meet the

    required technical and performance specication (but note Appendix 1 to this guide

    describing the limited liability typically accepted by EPCM contractors in this regard).

    • Procurement services – the EPCM contractor will be responsible for the overallprocurement strategy and will source contractors, consultants and the necessary

    plant and equipment in accordance with the Sponsor’s requirements and the

    assumptions established at feasibility stage. The EPCM will advise on the timing

    of the letting of the relevant packages and will advise the Sponsor on the terms

    available and will negotiate the contract packages on the Sponsor’s behalf.

    • Construction Management services – the EPCM contractor will typically be

    responsible for overall management of the carrying out and completion of the works.

    This will include the co-ordination of the works and services being procured on the

    Sponsor’s behalf to achieve completion of the works in accordance with the project

    schedule, the project budget and to meet the required technical and performance

    specication (but again, note Appendix 1 to this guide and the limited liability

    typically accepted by EPCM contractors in this regard). The construction management

    services will also typically include the management of health and safety at the

    site, the establishment of quality assurance systems and the management of the

    remedying of defective works and or services provided by other parties.

    Some Sponsors are adopting a slight variant to the EPCM arrangement which is

    essentially a split EP & CM structure. Under this variant the Sponsor will appoint a

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    22/40

    20 Norton Rose Fulbright

    EPC and EPCM contracts

    rm generally with greater expertise in engineering design and, possibly procurement,as the EP Contractor. The Sponsor will then appoint a specialist ‘construction

    management’ rm to appoint and manage the trade contractors and the rest of supply

    chain (including the engineering designer). This assists getting lenders comfortable

    that an appropriate party will be in place having expertise in procurement to ensure the

    best chance of success and avoiding cost overruns.

    Whilst the EPCM contractor will negotiate the terms of the contract packages, whether

    for delivery of works, services or the provision of plant and equipment, it is usual

    that the Sponsor will enter into direct contractual relations with the relevant thirdparties and assume the rights and obligations under the relevant contracts. We have

    however seen arrangements under which the EPCM Contractor will itself enter into the

    contracts with the third parties as agent for the Sponsor. Whilst this is perfectly ne,

    consideration will be required on the provisions necessary to protect the Sponsor and to

    maintain the supply chain arrangements should the EPCM Contractor be terminated.

    For reference, we have set out below the typical EPCM structure.

     EPC Contract 

    EPCM ContractorMining Company

    Contractor B Contractor CContractor A

    As we have indicated above, the EPCM structure may be considered by a Sponsor where

    the single point of responsibility EPC structure can not be achieved or is not attractive

    for one reason or another. This may be because:

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    23/40

    Norton Rose Fulbright 21

    EPCM Contracts

    • The securing of the single point of responsibility EPC solution may expose theSponsor to inated pricing which may have an impact on project aordability and

    which may not be considered by the Sponsor to oer value for money.

    • There may be a general lack of appetite in the market to take on the project in

    question on a turn key EPC basis.

    • The Sponsor has a good track record in project delivery and has a large internal

    management resource and as a result prefers to adopt the EPCM structure to

    signicantly reduce overall outturn cost and increase equity returns.

    In the context of a mining project, the EPCM contractor will typically be the party

    developing the basic design at feasibility stage. This party may then be retained

    to develop the nal design and to provide the other relevant EPCM services for the

    construction phase of the project. This structure will obviously generate continuity

    in design responsibility throughout works planning and implementation and will

    typically allow for greater employer inuence in design evolution than would otherwise

    be available under the EPC structure.

    In considering the use of an alternative structure (eg, EPCM) (and on the assumption

    that an EPC structure is otherwise achievable) the Sponsor will typically balance,

    amongst other things, the increased cost and reduced equity return that is likely

    to accompany use of the single point of responsibility EPC solution against the

    corresponding key benets, namely, price certainty for project delivery and the

    increased likelihood of securing project nance. If the negatives of the EPC solution

    outweigh the positives, the Sponsor may be inclined to consider use of an alternative

    contracting structure.

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    24/40

    22 Norton Rose Fulbright

    EPC and EPCM contracts

    EPCM and bankabilityThe fundamental point for the Sponsor to consider will however be the extent to which

    the EPCM solution may be considered bankable by potential lenders.

    A key dierence between the EPC and the EPCM solutions is that the EPCM solution

    does not oer a single point of responsibility for delivery of the works. There will be

    multiple interfaces which must be carefully managed by the EPCM contractor and the

    Sponsor and there will remain a risk that there may be gaps in liability or that a party

    identied as be liable for a failure will not, on its own or collectively with other culpable

    parties, be willing to accept the measure of liability typically recoverable by a Sponsorwhen using the EPC structure.

    The provisions of the EPCM contract, in terms of both scope (as identied above) and

    liability for the services provided, will dier fundamentally from the terms seen in a

    typical EPC contract. To illustrate these dierences, we have provided at Appendix 1

    to this guide a comparison between the key requirements under the EPC structure and

    the corresponding terms and risk allocation typically achieved in the context of an

    EPCM structure.

    The reader should note that the summary at Appendix 1 provides only a high level

    overview for the purposes of comparing the risk allocation typically seen under the

    EPC and EPCM structures. There will of course be exceptions to these positions on a

    case-by-case basis. To provide a more detailed picture, we provide our clients with

    EPC and EPCM risk matrices that essentially show the positions taken on the key risk

    issues on recent projects closed in the mining sector. These invaluable tools allow us to

    quickly identify the market position on any given risk and more particularly show how

    a particular risk allocation has been banked (if at all).

    From the high level summary at Appendix 1, it is apparent that the usual risk prole

    under the EPCM solution is far less favourable from the Sponsor’s (and ultimately the

    lenders’) perspective when compared with the position typically secured by Sponsors

    under the EPC structure. It is perhaps a little unfair to compare the two on a like-for-like

    basis given the material dierences in what each structure seeks to achieve.

    It is easy to see however why lenders may prefer the certainty and security that comes

    with the EPC solution and also why many of the key principles under that solution

    may gain support from the Sponsor. However, whilst risk allocation considerations are

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    25/40

    Norton Rose Fulbright 23

    EPCM Contracts

    very important, the Sponsor will also be looking at the commercial imperative of (a)bringing a project to market where, for instance, the EPC structure is not achievable

    and, (b) maximising equity returns from the project by securing a signicantly lower

    construction cost.

    EPCM – key requirementsIf the EPCM solution is to be considered, it will be important for the Sponsor to rst

    satisfy itself and ultimately the lenders that the proposed solution can oer a robust

    structure for project delivery. The following requirements will, in the writers’ view, be

    key to demonstrating a robust EPCM structure best equipped to secure project delivery:

    (a) The selected EPCM contractor should be a robust experienced organisation with

    a strong track record of securing project delivery on an EPCM basis in the mining

    sector. The terms of the EPCM contract should reect an appropriate risk transfer to

    the EPCM contractor.

    (b) In view of the more limited liability typically accepted by an EPCM contractor

    under the EPCM structure, the Sponsor should appoint a full time experienced and

    well resourced owner’s team to monitor and manage the execution of the projectin order to ensure that the Sponsor’s key requirements are being achieved and

    to permit early identication of issues that may impact on project delivery. There

    should be developed a clear internal strategy for the management and resolution of

    all risks retained in part or whole by the Sponsor.

    (c) The contractors, service providers and equipment and plant suppliers should also

    be robust entities with experience and a track record of project delivery in the

    mining sector. Where possible, these contracts should be nalised on a xed price

    basis with any limits on liability and security requirements being appropriately

    determined in accordance with the role assumed by the relevant party.

    (d) The Sponsor should identify possible interface issues and put in place an

    appropriate mechanism to co-ordinate the completion of the works and to address

    the allocation of risks that may impact on delivery of the work. This mechanism

    should provide for prompt resolution of the relevant circumstances in a manner

    which does not detract in any material respect from project delivery.

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    26/40

    24 Norton Rose Fulbright

    EPC and EPCM contracts

    Whilst the points identied above will be important in developing robustness in thestructure for project delivery, there is little doubt that potential lenders will seek from

    the Sponsor security for the residual risks that may be retained at Sponsor level under

    the EPCM solution.

    In the rst instance this is usually achieved through use of a designated cost overrun

    facility to meet likely cost and/or time overrun exposure.

    A more robust view on EPCM risk transfer

    As Sponsors and contractors operating in the mining sector are usually large

    sophisticated entities, it is perhaps surprising that the approach taken to risk transfer in

    the context of EPCM solutions has traditionally been relatively simplistic in nature when

    compared to the approach taken in other sectors. This approach is however changing.

    Given that the role of an EPCM (or EP&CM) contractor will be fundamentally dierent to

    that adopted by an EPC contractor and given, as a consequence, the signicantly lower

    price paid for EPCM services when compared with that payable under a typical EPCcontract, the wholesale transfer of risk from the Sponsors to the EPCM contractor will

    not be appropriate.

    However, use of more innovative ways to transfer risk to the contractor, without

    necessarily seeing a dollar for dollar pricing consequence, are getting more serious

    consideration in the mining context. Whilst use of these solutions will not, in

    themselves, secure a bankable position for the Sponsors, they will however create a more

    robust EPCM structure by ensuring that the EPCM contractor has ‘skin in the game’ and

    is further motivated to secure project delivery in accordance with Sponsor requirements.

    IncentivisationA key aspect of EPCM risk allocation is the concept of incentivisation.

    Incentivisation provisions will typically provide for EPCM contractors accepting

    nancial risk and reward in the achievement of key project requirements, including,

    completion of the works within the agreed project budget, completion of the works

    in accordance with the project programme, achievement of certain health and safety

    targets and the nal works achieving key performance and other quality requirements.

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    27/40

    Norton Rose Fulbright 25

    EPCM Contracts

    Whilst these risks are not passed to the EPCM contractor in full, the EPCM contractorwill be accepting a degree of liability in the relevant risk, so will be more motivated

    to manage it. The key point to understand is that the EPCM contractor will usually be

    responsible for the nancial downside of the incentivisation provisions irrespective

    of whether it has used reasonable skill and care in managing the risk in question.

    There is a therefore clear imperative for the EPCM contractor taking ownership of the

    management of the risk in question from that date of contract to secure project delivery

    in accordance with the Sponsors requirements.

    There would ordinarily be concerns that the EPCM contractor will simply price the riskin question on a contingent basis, and this will of course not oer value for money for

    the Sponsor, particularly if the risk never materialises. These concerns however tend

    to be mitigated by the fact that the EPCM contractor’s risk in the project will be limited

    to its agreed prot margin on which there should, in theory, be absolute transparency

    beyond the actual agreed cost for providing the EPCM services.

    Conversely, there will also typically be a bonus structure under which the EPCM

    contractor will receive additional payments (up to an agreed cap) for meeting and

    surpassing key project delivery requirements.

    EPCM – key points summary

    (a) An EPCM contract is essentially a professional services contract under which the

    contractor will not accept primary responsibility for the carrying out of the works.

    (b) The EPCM contractor will be responsible for:

     — completion of detailed engineering;

     — the procurement of contractors, service providers and plant and equipment

    suppliers on behalf of the Sponsor; and

     — management of the carrying out and completion of the works on behalf of the

    Sponsor.

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    28/40

    26 Norton Rose Fulbright

    EPC and EPCM contracts

    (c) The contracting structure under an EPCM solution is fundamentally dierent tothat adopted under a typical EPC solution. Unlike the EPC solution, it will usually

    be the Sponsor, not the contractor (but see our comments above where this can be

    an option), that will enter into contractual relations with the contractors, service

    providers and plant and equipment suppliers responsible for delivery of the works.

    (d) The risk prole under an EPCM solution is substantially more onerous from a

    Sponsor perspective when compared with the EPC structure. In order to attract

    project nance the Sponsor will need to:

     — demonstrate an allocation of risk between the Sponsor and the EPCM contractor

    appropriate in the post GFC lending market; and

     — demonstrate to potential lenders how the risks retained by the Sponsors will be

    managed (eg, through use of cost overrun facilities etc.).

    Bribery Act – new legislation for companies with UK links

    Whilst not an issue that will directly aect the nancing of a mining project or more

    generally its economic viability, any Sponsor incorporated in the UK or carrying out

    business or any part of their business in the UK should from now be considering very

    carefully the requirements of the Bribery Act 2010 (the Act).

    The Act will make it a criminal oence, for persons to whom the Act relates, to bribe

    another person or to be bribed, but perhaps most signicantly it also introduces a new

    criminal oence for corporates of ‘failing to prevent bribery’.

    Corporate entities can be guilty of this oence if an ‘associated person’, which given

    the scope of this denition is likely to include any EPC or EPCM contractor, otaker or

    operator, carries out an act of bribery when acting on their behalf. It is important to

    recognise that the ‘associated person’ does not need to be incorporated in the UK or

    indeed have any business connection with the UK.

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    29/40

    Norton Rose Fulbright 27

    EPCM Contracts

    The only defence for an entity being prosecuted for failing to prevent bribery is to showthat it had ‘adequate procedures’ in place designed to prevent bribery being carried out

    on its behalf. Whilst the precise meaning of ‘adequate measures’ is not clear, the UK

    Government has made available guidance as to the key principles to be followed.

    Given the signicant scope and extraterritorial reach of the Bribery Act, it will be

    extremely important for Sponsors to rstly ensure that they have robust internal

    policies in place to guard against bribery and secondly to ensure that its supply chain

    members have robust anti-corruption compliance programmes and are subject to

    appropriate due diligence and monitoring.

    Specic advice should be sought by Sponsors having any particular concerns about

    the scope and implications of the Act.

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    30/40

    28 Norton Rose Fulbright

    EPC and EPCM contracts

    NoteThe reader should note that this summary provides only a high level overview for the

    purposes of comparing the risk allocation typically seen under the EPC and EPCM

    structures. There will of course be exceptions to these positions on a case by case

    basis. To provide a more detailed picture, we provide our clients with EPC and EPCM

    risk matrices that essentially show the positions taken on the key risk issues on recent

    projects closed in the mining sector. These invaluable tools allow us to quickly identify

    the market position on any given risk and more particularly show how a particular risk

    allocation has been banked (if at all).

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    31/40

    Norton Rose Fulbright 29

    Appendix 1

    Appendix 1

    EPC risk

    allocation

    Typical EPCM position EPCM risk

    allocation

    Risk typically

    transferred

    to the

    contractor

    EPC EPCM

    Contractor to be

    responsible forcompleting the

    works on time.

    The EPCM contractor will not usuallyguarantee delivering the works on time

    and will therefore not usually have

    responsibility for the payment of delay

    liquidated damages in this regard.

    Any damages recoverable from other

    contractors, who are identied as being

    responsible for delayed completion of the

    works, will not typically be of the order

    recoverable under the EPC structure

    (either because of quantum or cappingarrangements agreed).

    Nominal delay liquidated damages

    may be payable by the EPCM contractor

    to the extent that the design, or otherdeliverables for which the EPCM

    contractor is responsible, are delivered

    otherwise than in accordance with the

    project programme.

    The EPCM contractor will be responsible

    for managing the overall works

    programme and any failure to use

    reasonable skill and care in doing so will

    give rise to liability. Any such liability

    will usually be restricted to a contractualdamages claim and will be subject to the

    limitations on liability identied below.

    As the delay

    damages

    recoverable

    from the EPCM

    contractor,

    and any other

    contractors

    identied

    as being

    responsible

    for delayed

    completion of

    the works, will

    not be sucient

    to cover theSponsor’s

    potential loss

    in revenue and

    debt service

    costs occasioned

    by such delay,

    the nancial

    risk of delayed

    completion of

    the works will

    ultimately rest

    with the Sponsor.

    ✔ ✗

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    32/40

    30 Norton Rose Fulbright

    EPC and EPCM contracts

    EPC riskallocation

    Typical EPCM position EPCM riskallocation

    Risk typicallytransferred

    to the

    contractor

    EPC EPCM

    Completion

    of works for

    a lump sumxed price.

    The EPCM contractor will not usually

    guarantee the overall outturn cost ofthe works.

    The EPCM contract will provide for the

    EPCM contractor setting the budgetand managing adherence to the budget.

    Any failure by the EPCM contractor to use

    reasonable skill and care in doing so

    will give rise to liability. Given the

    limits on the EPCM contractor’s liability

    typically agreed under the terms of an

    EPCM contract (see below), it is unlikelythat liability for any signicant cost

    overrun will be recoverable from the

    EPCM contractor.

    In procuring the works, services andplant and equipment supply packages

    on behalf of the Sponsor, the EPCM

    should attempt to procure such packages

    on a xed price basis. However, this is

    not always possible. Notwithstanding

    the fact that xed price solutions maybe achieved, the multiple interfaces

    will however widen the scope for timeand money claims by the third party

    contractors which will be a Sponsor risk

    to the extent that the liability giving rise

    to any such claim can not backed o fully

    with other contractors.

    Payments to the EPCM contractor for

    services performed are typically made on

    a monthly basis based on actually costsincurred at agreed rates (ie, payment is

    on a fully reimbursable basis).

    The Sponsor will

    ultimately accept

    the risk of any

    material cost

    overrun.

    ✔ ✗

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    33/40

    Norton Rose Fulbright 31

    Appendix 1

    EPC riskallocation

    Typical EPCM position EPCM riskallocation

    Risk typicallytransferred

    to the

    contractor

    EPC EPCM

    EPC contractor

    to provide

    performance

    guarantees

    in respect ofthe completed

    plant.

    The EPCM contractor typically accepts

    full responsibility for the nal design

    and for it meeting the required technical

    and performance requirements and will

    usually be responsible for coordinatingthe design produced by other parties.

    Establishing that a performance failure

    has resulted from the design produced

    by the EPCM contractor and not fromthe implementation of such design by

    other contractors may not always be

    straightforward.

    The liability of the EPCM contractor for

    design failure will however be limitedas set out below.

    Due to interface

    issues relating to

    identifying the

    party responsible

    for performancefailure and the

    more limited

    liabilities

    accepted by

    parties under theEPCM structure,

    it is more likely

    that the majority

    of the liability for

    any substantiveperformance

    failure willretained by

    the Sponsor.

    ✔ ✗

    Any limit

    on liability

    to provide

    sucient

    coveragefor recovery

    of amounts

    outstanding

    under the terms

    of the nancedocumentation.

    Appropriate

    carve outs

    to be agreed

    in respect ofwhich the EPC

    contractor’sliability will

    be unlimited.

    The EPCM contractor’s liability willtypically be limited to anything from

    10-20 per cent the EPCM contract price

    (which will typically equate to the EPCM

    Contractor’s prot margin).Carve outs from the liability cap are

    usually limited to those liabilities than

    can not be limited at law.

    Sums recoverable from the other

    contractors in the aggregate (on the

    assumption that the parties responsible

    can be held to account) are unlikely to be

    of the order of sums recoverable from an

    EPC contractor under the EPC structure.

    The Sponsor’s

    (and ultimately

    the lenders’)

    recourse for

    recovery of debtoutstanding andother losses in a

    project default

    scenario will

    be limited. The

    residual liability

    in this regardwill ultimately be

    a Sponsor risk.

    ✔ ✗

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    34/40

    32 Norton Rose Fulbright

    EPC and EPCM contracts

    EPC riskallocation

    Typical EPCM position EPCM riskallocation

    Risk typicallytransferred

    to the

    contractor

    EPC EPCM

    Security

    package to

    include liquid

    performance

    security,retentions

    and parent

    company

    guarantees.

    Whilst parent company guarantees tend

    to be procured, it would be less usual for

    EPCM contractors in the mining sector to

    provide other liquid forms of security.

    The EPCM position in this regard is

    symptomatic of the nature and extent

    of liability being accepted by the EPCM

    contractor.

    The nature and extent of the security

    package obtainable from contractors,

    services providers and plant andequipment suppliers will be determined

    on a project specic basis.

    Sponsors accept

    cash ow riskduring the period

    in which a claim

    is establishedagainst the

    EPCM contractor

    and sums for

    which the EPCMcontractor

    is liable are

    recovered from

    the parent

    company.

    ✔ ✔/ ✗

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    35/40

    Norton Rose Fulbright 33

    Appendix 1

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    36/40

    34 Norton Rose Fulbright

    EPC and EPCM contracts

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    37/40

    Norton Rose Fulbright 35

    Contacts

    Martin McCann

    Global head of mining,

    infrastructure and commodities

    Norton Rose Fulbright LLP

    Tel +44 20 7444 3573

    [email protected]

    Mark Berry

    Partner, London

    Norton Rose Fulbright LLP

    Tel +44 20 7444 3531

    [email protected]

    Matthew Hardwick

    Senior associate, London

    Norton Rose Fulbright LLPTel +44 20 7444 5550

    [email protected]

    Contacts

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    38/40

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    39/40

    Norton Rose Fulbright

    Norton Rose Fulbright is a global legal practice. We provide the world’s pre-eminent

    corporations and nancial institutions with a full business law service. We have morethan 3800 lawyers based in over 50 cities across Europe, the United States, Canada, Latin

    America, Asia, Australia, Africa, the Middle East and Central Asia.

    Recognized for our industry focus, we are strong across all the key industry sectors:nancial institutions; energy; infrastructure, mining and commodities; transport;

    technology and innovation; and life sciences and healthcare.

    Wherever we are, we operate in accordance with our global business principles of quality,unity and integrity. We aim to provide the highest possible standard of legal service in each

    of our o ces and to maintain that level of quality at every point of contact.

    Norton Rose Fulbright LLP, Norton Rose Fulbright Australia, Norton Rose Fulbright CanadaLLP, Norton Rose Fulbright South Africa (incorporated as Deneys Reitz Inc) and Fulbright

    & Jaworski LLP, each of which is a separate legal entity, are members (‘the Norton Rose

    Fulbright members’) of Norton Rose Fulbright Verein, a Swiss Verein. Norton Rose Fulbright

    Verein helps coordinate the activities of the Norton Rose Fulbright members but does not

    itself provide legal services to clients. This publication was produced prior to June 3, 2013when Fulbright & Jaworski LLP became a member of Norton Rose Fulbright Verein.

    References to ‘Norton Rose Fulbright’, ‘the law rm’, and ‘legal practice’ are to one or more of the Norton Rose Fulbright members

    or to one of their respective a liates (together ‘Norton Rose Fulbright entity/entities’). No individual who is a member, partner,

    shareholder, director, employee or consultant of, in or to any Norton Rose Fulbright entity (whether or not such individual is

    described as a ‘partner’) accepts or assumes responsibility, or has any liability, to any person in respect of this communication. Any

    reference to a partner or director is to a member, employee or consultant with equivalent standing and qualications of the relevant

    Norton Rose Fulbright entity. The purpose of this communication is to provide information as to developments in the law. It does notcontain a full analysis of the law nor does it constitute an opinion of any Norton Rose Fulbright entity on the points of law discussed.

    You must take specic legal advice on any particular matter which concerns you. If you require any advice or further information,

    please speak to your usual contact at Norton Rose Fulbright.

    © Norton Rose Fulbright LLP NRF15991 06/13 (UK) Extracts may be copied provided their source is acknowledged.

  • 8/17/2019 Mining Guide Epc and Epcm Contracts 104178

    40/40

    nortonrosefulbright.com