Minneapolis Fridley Filter Plant Split - awwand.orgawwand.org/docs/swtw2014/Wednesday Supply/Minneapolis Fridley... · Minneapolis Fridley Filter Plant Split Surface Water Treatment

Embed Size (px)

Citation preview

  • 6/24/2014

    1

    Minneapolis Fridley Filter Plant Split

    Surface Water Treatment Workshop

    April 29 May 1, 2014Fargo, ND

    Todays Presentation Fridley Filter Plant (FFP) History & Overview

    Why FFP split project? y p p j

    Project overview

    Planning efforts before construction

    Construction phase

  • 6/24/2014

    2

    History 1910 to 1913 Filtration plant construction at

    Columbia Heights site 1925 Filtration plant at Fridley site 1940 Lime softening plant at Fridley site 2005 C.H. membrane plant (CHMP) in service 2013 Upgrades to FFP begin

    Phase 1: FFP Split Project Phase 2: Fridley Filter Rehabilitation

    Process Schematic

    PUMP

    MississippiRIVER

    RECARB.MIX

    FILTERSCOAG / SETTLEMIX RESERVOIRS(and Distributionto Customers)

    Fridley campus . . . .

    SOFTENING

    RESERVOIRFILTERSCOAG / SETTLEMIX

    RESERVOIRS(and Distribution

    to Customers)Columbia Heights campus . . . . . .

    to Customers)

    PUMP

    ULTRAFILTRATION

  • 6/24/2014

    3

    System Capacity

    Population served = 500,000

    Fridley Softening Plant (Total Capacity) = 160 MGD CHMP Capacity = 75 MGD (summer)

    = 40 MGD (winter) FFP Capacity = 120 MGD

    Average Daily Demand = 60 MGD

    Project Drivers

    To improve operational redundancy Rehabilitate filters (with GAC in 2 phases)

    keeping half of the plant in servicekeeping half of the plant in service To enable taking portions of the plant

    out of service for other repairs and maintenance

  • 6/24/2014

    4

    Project Overview Lower Level

    REMOVE EXISTING GATE

    CONTROL CHAMBERVENTURI CHAMBER

    FILTERED WATERCONDUIT

    66 AND 84 PIPES FROM PS NO 6

    VALVE 182

    VALVE 183

    N

    FILT

    ERS

    ILTE

    RS

    FILT

    ERS

    ILTE

    RS

    COAG 2 COAG 3

    COAG 1 COAG 4

    WESTCLEARWELL

    EASTCLEARWELL

    BY-PASSVALVE

    MIXING CHAMBERS

    LEGEND

    NEW GATE (5X5)NEW WALLNEW SEGMENTAL WALL

    F F

    FILTERED WATERCONDUIT

    Project Overview Upper Level

    FILTER INFLUENTWATERCONDUIT

    S S

    N

    VOID

    FILT

    ERS

    FILT

    ERS

    FILT

    ERS

    FILT

    ERS

    COAG 2 COAG 3

    COAG 1 COAG 4

    COAGWATERCONDUIT MIXING

    CHAMBERS

    REMOVE EXISTING GATES AND SEAL ALL OPENINGS

    F F

    FILTERINFLUENT WATER CONDUIT

    LEGEND

    NEW WALL

    NEW STOP LOGS

    NEW GATE

  • 6/24/2014

    5

    Project Overview Lower Level

    CONTROL CHAMBERVENTURI CHAMBER

    FILTERED WATERCONDUIT

    66 AND 84 PIPES FROM PS NO 6

    VALVE 182

    VALVE 183

    N

    FILT

    ERS

    ILTE

    RS

    FILT

    ERS

    ILTE

    RS

    COAG 2 COAG 3

    COAG 1 COAG 4

    WESTCLEARWELL

    EASTCLEARWELL

    BY-PASSVALVE

    MIXING CHAMBERS

    LEGEND

    NEW GATE (5X5)NEW WALLNEW SEGMENTAL WALLNEW STOP LOGS

    F F

    FILTERED WATERCONDUIT

    Project Overview Critical phase construction

    Construction of approx. 500 feet of concrete dividing walls

    Modifications to water treatment chemical feed system Installation of 5 slide gates and 6 stop log gates

    Structural surface rehabilitation considered non-critical phase construction

  • 6/24/2014

    6

    Bringing C.H. Filter Plant On-line Why?

    Extended FFP shut down needed for FFP Split construction

    CHMP capacity (Nov. to Jan.): 40 50 mgdWater demand (Nov. to Jan.): 50 60 mgd

    Preparation work Checked manually-operated valves for each filter. 17 out of 24 filters available for service Recommissioned turbidimeters for each filter. Addressed post treatment.

    Notified MDH.

    Planning Efforts Before Construction Engineer: CH2M Hill

    Contractor: Municipal Builders, Inc (MBI)Subcontractor: PciRoads

    Hazardous analysis & notification of Minneapolis Fire Dept. Confined space Hazardous chemicals (Cl2, NH3)

    Coordination with MWW operations & detailed LOTO proceduresp

    Detailed site walkthrough to discuss the construction process

    Detailed day-to-day construction schedule from MBI

  • 6/24/2014

    7

    Construction Timeline Sept 30, 2013 Dec 13, 2013: Critical phase construction and

    elective concrete repair/crack injection work Critical phase construction completed in 37 days

    Jan. 2014: FFP restarted

    Jan. 2014 Apr. 2014: Remaining concrete repair/crack injection work & misc. other work

    A 2014 95% f i l Apr. 2014: 95% of construction complete

    Concrete Dividing Wall Construction Adverse construction condition

    Confined space Ventilation requirements Lighting requirements Lighting requirements 5-ft tall finished water conduit

    On-site construction manager from CH2M Hill performs quality control & special inspections

    28-day cast-in-place concrete strengths: Requirements: 4,500 psi Testing results: 5,500 psi

  • 6/24/2014

    8

    Concrete Dividing Wall ConstructionControlChamberDividerWall

    (41longx18tall)

    UpperFlumeDividerWall

    (96 long x 10 tall) FinishedWaterConduitDividerWall

    (300longby5tall)

    (96 longx10 tall)

    Chemical Feed System Modifications Double feed in the finished water conduit (poly, Cl2,

    Fluoride)

    N i f CFE d PE i i h New instruments for CFE and PE monitoring on the west side

    SCADA integration of the new instruments by In Control, Inc.

    New CFE and PE sampling pumps

    Essentially two separate plant effluents

  • 6/24/2014

    9

    Chemical Feed and Sampling Before-Split Scheme

    Chemical Feed and Sampling Post-Split Scheme

  • 6/24/2014

    10

    Chemical Feed System Modifications

    East/WestPoly,Cl2 FluorideCl2,FluorideFeedSystems

    NewCFESamplePumps

    Slide Gates and Stop Log Gates Installation

    5 slide gates and 6 stop llog gates

    Build outs for battered wall

    MixingChamberSlideGate

    UpperFlumeStopLogGate

  • 6/24/2014

    11

    Slide Gates and Stop Log Gates Installation

    Old Control ChamberInfluent Gate

    New Control Chamber Slide Gate

    Removal of Coagulation Basin No. 5

    Demolition of CoagBasin No. 5

    Backfill with granular fill

  • 6/24/2014

    12

    Structural Surface Rehabilitation Quantities:

    Wall repair: 530 ft2 Slab repair: 1,650 ft2

    C k/J i R i 2 360 f Crack/Joint Repair: 2,360 ft

    Utilized plant shut down for 80% of concrete repair/crack injection work

    Structural Surface Rehabilitation

    10,000 psi high pressure water wash

    FWC Pre-project

    Rehabilitated FWC

  • 6/24/2014

    13

    Structural Surface RehabilitationRemovalofLooseandDelaminated

    Concrete

    ReinforcingRebar

    CrackRepair

    FFP Split Project

    Operational redundancy achieved Aggressive yet flexible schedule met Safety issues for challenging construction

    conditions addressed Looking forward to 75 more years of effective

    filt tifilter operations

  • 6/24/2014

    14

    Questions?

    AnnikaBankstonAnnikaBankstonAnnika.Bankston@[email protected]

    61261266166149754975

    [email protected]@minneapolismn.gov

    61261266166149044904