KHAIRI HAFIZI BIN KAMARUDIN 15077 CIVIL ENGINEERING MASS RAPID TRANSIT (MRT) SG BULOH-KAJANG LINE (UNDERGROUND WORKS)

MMC-GAMUDA KVMRT TUNNELING WORKS

Embed Size (px)

DESCRIPTION

This slide used by one of the interns that had completed his internship in MRT tunneling construction project.

Citation preview

Page 1: MMC-GAMUDA KVMRT TUNNELING WORKS

K H A I R I H A F I Z I B I N K A M A R U D I N

1 5 0 7 7

C I V I L E N G I N E E R I N G

MASS RAPID TRANSIT (MRT)

SG BULOH-KAJANG LINE (UNDERGROUND WORKS)

Page 2: MMC-GAMUDA KVMRT TUNNELING WORKS

COMPANY BACKGROUND

Core Business

Engineering

&

Construction

Infrastructure Concessions

Property Development

Page 3: MMC-GAMUDA KVMRT TUNNELING WORKS

MASS RAPID TRANSIT (MRT)

Why MRT?

Increasing traffic

Reduce traffic congestion in Kuala Lumpur

Connect two farthest and busiest point

Geographic profile (Hilly) – Solution?

Page 4: MMC-GAMUDA KVMRT TUNNELING WORKS

UNDERGROUND!

Page 5: MMC-GAMUDA KVMRT TUNNELING WORKS

SG BULOH-KAJANG LINE

Page 6: MMC-GAMUDA KVMRT TUNNELING WORKS

UNDERGROUND ROUTE

Page 7: MMC-GAMUDA KVMRT TUNNELING WORKS

UNDERGROUND ROUTE

Consists of: 1. Semantan North Portal

2. KL Sentral

3. Pasar Seni

4. Merdeka Station

5. Pudu Shaft

6. Bukit Bintang

7. Inai

8. Pasar Rakyat

9. Cochrane

10. Maluri South Portal

Page 8: MMC-GAMUDA KVMRT TUNNELING WORKS

SEMANTAN NORTH PORTAL

Page 9: MMC-GAMUDA KVMRT TUNNELING WORKS

What I‟ve been doing/learn so far?

1 • TBM‟s assembly sequence

2 • Tunnel‟s ring installation

3 • Primary and secondary

backfill grouting

Page 10: MMC-GAMUDA KVMRT TUNNELING WORKS

What I‟ve been doing/learn so far?

4 • TBM‟s Guidance System

5 • Process in dismantling

Page 11: MMC-GAMUDA KVMRT TUNNELING WORKS

TBM‟s Assembly Sequence

Page 12: MMC-GAMUDA KVMRT TUNNELING WORKS

TBM‟s Assembly Sequence

Lifting of front

shield onto cradle

Lifting of middle shield and connect with front shield

Lift & connect cutter head with

front shield

Page 13: MMC-GAMUDA KVMRT TUNNELING WORKS

TBM‟s Assembly Sequence

Assemble the segment erector

Place screw conveyor into

position and hold it

Lift tail shield and connect it to

middle shield

Page 14: MMC-GAMUDA KVMRT TUNNELING WORKS

TBM‟s Assembly Sequence

Install rails for backup gantries

to move on

Install backup gantries 1 to 6

Install backup gantries 7 to 11

Page 15: MMC-GAMUDA KVMRT TUNNELING WORKS

TBM‟s Assembly Sequence

Page 16: MMC-GAMUDA KVMRT TUNNELING WORKS

Tunnel‟s Ring Installation

One ring consists of 7 segments and 1 key segment.

Total ring that will be installed from Semantan North Portal to Pasar Seni:

Northbound : 1846 rings

Southbound : 1837 rings

Best record : 9 rings/day (14 July 2013)

Page 17: MMC-GAMUDA KVMRT TUNNELING WORKS

Tunnel‟s Ring Installation

Steps in ring installation:

Shoving

until reaches

distance of 1.4 m

Transferred segment

into the tail skin using segment magazine

Fixed segment by

using segment erector

Thrust cylinder will

push segment

Segment will be

bolted to tighten its position

Check „Steps & Lips‟ and tail skin

clearance

Page 18: MMC-GAMUDA KVMRT TUNNELING WORKS

Tunnel‟s Ring Installation

Page 19: MMC-GAMUDA KVMRT TUNNELING WORKS

Primary Backfill Grouting

Page 20: MMC-GAMUDA KVMRT TUNNELING WORKS

Primary Backfill Grouting

One of excavation process where we inject a type of LIQUID to stabilize the ground structure and hold the segmental lining.

Gro

ut

Liq

uid

Water

Cement

Stabilizer

Bentonite

Accelerator

Page 21: MMC-GAMUDA KVMRT TUNNELING WORKS

Primary Backfill Grouting

Fill up the gap

Prevent ground settlement

Stabilize segmental lining

Improve water tightness

Page 22: MMC-GAMUDA KVMRT TUNNELING WORKS

VMT: TBM‟s Guidance System

Unlike cars, TBM need to have a guidance system to ensure the TBM is always follow design tunnel alignment (DTA).

TBM used a guidance system called VMT.

Page 23: MMC-GAMUDA KVMRT TUNNELING WORKS

VMT: TBM‟s Guidance System

Page 24: MMC-GAMUDA KVMRT TUNNELING WORKS

VMT: TBM‟s Guidance System

1. Horizontal & vertical deviations (mm) 2. Horizontal & vertical tendencies (mm/m) 3. Chainage of front reference point (m) 4. Current advance number 5. Graphical representation of TBM. 6. Roll (mm/m). 7. Absolute pitch (mm/m). 8. Intensity of laser hitting the target. 9. Emitting intensity of laser in percent. 10. Actual computer date and time. 11. Displays for communication programs. 12. Name of project. 13. Shows the operating mode (advance, ring erection). 14. Area reserved for special project informations. 15. Function keys. 16. “Dialog Box”- Window for messages. 17. Last measurement of TBM position was made.

Page 25: MMC-GAMUDA KVMRT TUNNELING WORKS

Other than technical skills, what else?

Communication Skills

Learn on how to communicate with workers from China

China People: Mostly cannot speak English

Learn to communicate with other staff professionally.

Time Management

Task given by SV & internship task (logbook etc.)

Prepare to-do list every day

Complete task with high priority first

Page 26: MMC-GAMUDA KVMRT TUNNELING WORKS

Conclusions & Recommendations

Student Industrial Training is a good program to expose students to the real working-based situation.

Student will be more well-rounded; learn theoretical knowledge at campus and hands-on knowledge during internship.

Students are able to develop their soft skills; communication, critical thinking, time management etc.

Page 27: MMC-GAMUDA KVMRT TUNNELING WORKS

Conclusions & Recommendations

Things that could be improved by UTP:

Problem: Students having problem with last-minute amendment by CSIMAL.

Possible Solution: Finalize all things before conduct internship‟s briefing.

Page 28: MMC-GAMUDA KVMRT TUNNELING WORKS

Conclusions & Recommendations

Things that could be improved by Host Company:

Problem: Battery charging area produce unpleasant smell.

Possible Solution: Build wall-like structure to barricade those area.