Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

SDMSDocID 2010534

Page 2: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

January 15, 2001

Ms. Susanna Trujillo, Project CoordinatorU.S. EPA Region IX75 Hawthorne Street (WST-7)San Francisco, CA 94105-3901

Dear Ms. Trujillo:

RE: Monthly Progress Report - January, 2001Order RCRA 7003-09-99-0005NOV/Order CWA-309-9-99-14

As required by the above referenced RCRA Order, specifically VI number 3 (page 9 of 22), thefollowing is the monthly progress report. If you should require a copy of past monthly activities,please contact me. The progress report items are numbered with the first three letters of themonth. This month's items are as follows:

Current Monthly Progress ReportRepublic DUMPCo continues to make progress in completing the tasks outlined in the WorkPlan. Three drill rigs are on site advancing boreholes, setting casings, and/or installing wells.These include the following: 1 Percussion Hammer (API000), 1 drill and drive (T4W), and aSonic (GP300 RS).

Jan.l: The exploratory borings were started on March 13, 2000. The following is the status ofthese exploratory borings. It should be noted that when a monitoring well has beeninstalled, the prefix for the location designation changes from GH to MW, and when themonitoring well has been developed, the prefix will be changed to PW. This is reflectedbelow. Furthermore, when a boring has been classified as being "abandoned," this meansthe boring as been plugged with bentonite and sealed. Once a boring as been classified inthis progress report as being "abandoned," the boring will not be included in the nextmonths progress report.

MW-1 A: Stopped at 102 feet below ground surface (bgs) at bed rock contact, and amonitoring well has been installed. (No water has been detected in this monitoring wellsince installation).

1

770 East Sahara Avenue • P.O. Box 98508 • Las Vegas, Nevada 89193-8508 • Telephone 735-5151 • Fax (702) 735-1986

I MADE WITH RECYCLED PAPER

Page 3: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

GH-1C: The sonic drill rig advanced this boring to 682' bgs. A well has been installed,and it is in the process of being developed.

MW-2A: A 2-inch and a 4-inch monitoring well were installed in this borehole whichwas advanced to a total depth of 215 feet bgs. Water has been measured at 197 feet bgsin the 2-inch, and 195 feet bgs in the 4-inch on May 5, 2000. Current water levelmeasurements indicate that the 4-inch and the 2-inch are dry.

MW-2B: A 4-inch monitoring well has been installed in this boring which was advancedto a total depth of 211.5' bgs. Water has been measured at 204' bgs on June 7, 2000.Current water level measurements indicate that this boring is dry.

PW-2C2: This boring was advanced to 263' bgs, and a 2-inch and 4-inch monitoringwell were installed. Water has been measured at 221' and 220' bgs respectively. As ofJanuary 15, 2001, both monitoring wells have been developed.

GH-2D: This boring has been advanced to 808' bgs with a temporary surface casing at260' bgs. Numerous water layers were encountered.

GH-3C: Barber Rig has advanced this boring to 500' bgs at this location. A seal wasinstalled at this zone, and this boring is on hold until an appropriate drill rig can beidentified.

PW-4A: This boring was advanced to 295 feet bgs, and a monitoring well installed. Thismonitoring well was developed on January 10, 2001.

GH-4B: This boring has been advanced to 806' bgs. A monitoring well is in the processof being installed.

GH-5B3: This boring has been advanced to 412' bgs. A seal casing was set to 412' bgs,but there are concerns regarding the setting of this seal. The bond logging data indicatedthat the seal was defective. This boring has been abandoned, and will not appear on thenext monthly progress report.

GH-5B4: This boring has been advanced to 733' bgs. This boring will be advanced whenanother appropriate drill rig is available.

PW-5C: This boring has been advanced to 154' bgs. Water has been measured at146.2' bgs. A monitoring well has been installed, and the well was developed onDecember 6, 2000.

PW-6B: This boring has been advanced to 227' bgs. Water has been measured at 208'bgs. The monitoring well at this located was developed on January 10, 2001.

Page 4: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

MW-6C: This boring has been advanced to 431' bgs, and monitoring well was installed.This monitoring well will be developed.

GH-7B: This boring has been advanced to 645' bgs with the Sonic Rig. Sonic hasreached a maximum depth with the 5" casing. Water has been encountered, but noconfining unit has been identified. When the appropriate drilling rig is available, thisboring will be advanced further in order to identify the confining unit.

GH-9A: This boring has been advanced to 572' feet bgs. A monitoring well will beinstalled at this location.

GH-1OA: This boring is located in the North East Canyon, and has been advanced to 622'bgs.

PW-11 A: This boring has been advanced to 407' bgs, a monitoring well was installed,and it was developed on December 28, 2000.

PW-1 IB: This boring was advanced to 260' bgs, a monitoring well was installed, and itwas developed on November 29, 2000.

PW-12A: This boring has been advanced to 252.5' bgs. Water has been measured at236.5' bgs. A monitoring has been installed. This monitoring well was developed onDecember 7, 2000.

GH-12B2: This boring is currently at 452' bgs, with a 14" conductor casing to 252' bgs.Appropriate well installation is being evaluated.

GH-13A: This boring was advanced to 477' bgs by the AP1000. The AP1000 could notadvance this boring beyond this depth. Need to evaluate a different drilling and samplingmethod in order to advance this boring further.

PW-14A: This boring has been advanced to 236' bgs, a monitoring well was installed,and it was developed on January 9, 2001.

GH-15 A: This boring has been advanced to 601' bgs with drill casing. This boring willbe sealed off, and advanced further.

Jan.2: The Northeast Canyon Waste Relocation project is 100% complete.

Jan. 3: The field work for the cover material evaluation is complete. A draft UNSAT-H reportwas submitted to EPA on October 17,2000, and the backup laboratory testing resultswere submitted to EPA on November 11, 2000.

Page 5: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

A clarification correspondence was provided to EPA on December 29, 2000, regardingslope stability, triaxial testing, and erosion analysis.

Jan.4: Waste Limit Determination: A waste boundary delineation map was provided to EPA onJune 30, 2000. This waste limit map included the waste limits for all areas, except for thecenter of the landfill area around the main aggregate stockpile. The IP lines that werecompleted over this area have been interpreted. After this evaluation of the IP lines,additional confirmation borings were done. A proposed final waste limit map was sent toEPA. This waste limit map may be require updating in the future, if other workplanactivities indicate changes.

Jan. 5: Stormwater Pollution Prevention Plan (SWPPP): A draft SWPPP was provided to EPA onJune 23, 2000, and then a Technical Memorandum regarding SWPPP evaluations wasprovided to EPA on November 30, 2000. In addition, on December 1, 2000, an updatedStormwater Monitoring Plan and Annual Stormwater Evaluation was provided to EPA.

Jan.6: Eastern Drop Off Channel Reconstruction: The plans have all been approved. However,based on field comments from EPA, this Interim Action has been put on hold. In theinterim, Republic is evaluating alternative protection scenarios for the area in the drop offchannel where Stormwater has historically impacted waste. Estimates have beenreceived.

If you have any questions, please contact me at (702) 734-5400.

Respectfully,

Alan Gaddy'rtiVice President

AG/tg

File#: 999901-062/Order 7484

CC: Mr. David Basinger (WTR - 7) Water Division Mr. Mark Morse, Field ManagerU.S. Environmental Protection Agency (Attention: Mike Moran)75 Hawthorne Street Bureau of Land ManagementSan Francisco, CA 94105 - 3901 4765 Vegas Valley Drive

Las Vegas, NV 89108

Page 6: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

Mr. Dave Emme, Chief Mr. John SchlegelBureau of Waste Management Clark County Comprehensive Plan.Nevada Division of Environmental Protection 500 S. Grand Central Pky333 W. Nye Lane, Room 138 Las Vegas, NV 89155-1745Carson City, NV 89706-0851

Mr. Clare Schmutz Ms. Sandy DotyClark County Health District SAIC625 Shadow Lane 5303 W. Oberlin Dr.Las Vegas, NV 89106 Denver, CO 80235

Page 7: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

February 15,2001

Ms. Susanna Trujillo, Project CoordinatorU.S. EPA Region IX75 Hawthorne Street (WST-7)San Francisco, CA 94105-3901

Dear Ms. Trujillo:

RE: Monthly Progress Report - February, 2001Order RCRA 7003-09-99-0005NOV/Order CWA-309-9-99-14

As required by the above referenced RCRA Order, specifically VI number 3 (page 9 of 22), thefollowing is the monthly progress report. If you should require a copy of past monthly activities,please contact me. The progress report items are numbered with the first three letters of themonth. This month's items are as follows:

Current Monthly Progress ReportRepublic DUMPCo continues to make progress in completing the tasks outlined in the WorkPlan. Three drill rigs are on site advancing boreholes, setting casings, and/or installing wells.These include the following: 1 Percussion Hammer (API000), 1 drill and drive (T4W), and aSonic (GP300 RS).

Feb.l: The exploratory borings were started on March 13, 2000. The following is the status ofthese exploratory borings. It should be noted that when a monitoring well has beeninstalled, the prefix for the location designation changes from GH to MW, and when themonitoring well has been developed, the prefix will be changed to PW. This is reflectedbelow. Furthermore, when a boring has been classified as being "abandoned," this meansthe boring as been plugged with bentonite and sealed. Once a boring as been classified inthis progress report as being "abandoned," the boring will not be included in the nextmonths progress report.

MW-1 A: Stopped at 102 feet below ground surface (bgs) at bed rock contact, and amonitoring well has been installed. (No water has been detected in this monitoring wellsince installation).

1

770 East Sahara Avenue • P.O. Box 98508 • Las Vegas, Nevada 89193-8508 • Telephone 735-5151 • Fax (702) 735-1986

I MADE WITH RECYCLED TOPER

Page 8: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

PW-1C: The sonic drill rig advanced this boring to 682' bgs. A well has been installed,and it was developed on January 31, 2001.

MW-2A: A 2-inch and a 4-inch monitoring well were installed in this borehole whichwas advanced to a total depth of 215 feet bgs. Current water level measurements indicatethat the 4-inch and the 2-inch are dry.

MW-2B: A 4-inch monitoring well has been installed in this boring which was advancedto a total depth of 211.5' bgs. Current water level measurements indicate that this boringis dry.

•K

PW-2C2: This boring was advanced to 263' bgs, and a 2-inch and 4-inch monitoringwell were installed. Water has been measured at 221' and 220' bgs respectively. As ofJanuary 15, 2001, both monitoring wells have been developed.

MW-2D: This boring has been advanced to 808' bgs with a temporary surface casing at260' bgs. A bentonite plug was placed up to 553' bgs, and a well will be installed.

GH-3C: Barber Rig has advanced this boring to 500' bgs at this location. A seal wasinstalled at this zone, and this boring is on hold until an appropriate drill rig can beidentified.

PW-4A: This boring was advanced to 295 feet bgs, and a monitoring well installed. Thismonitoring well was developed on January 10, 2001.

MW-4B: This boring has been advanced to 806' bgs. A monitoring well was installed,and it is in the process of being developed.

GH-5B4: This boring has been advanced to 733' bgs. This boring will be advanced whenanother appropriate drill rig is available.

PW-5C: This boring has been advanced to 154' bgs. Water has been measured at146.2' bgs. A monitoring well has been installed, and the well was developed onDecember 6, 2000.

PW-6B: This boring has been advanced to 227' bgs. Water has been measured at 208'bgs. The monitoring well at this located was developed on January 10, 2001.

PW-6C: This boring has been advanced to 431' bgs, a monitoring well was installed, andit was developed on January 29, 2001.

GH-7B: This boring has been advanced to 645' bgs with the Sonic Rig. Sonic hasreached a maximum depth with the 5" casing. Water has been encountered, but noconfining unit has been identified.

2

Page 9: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

When the appropriate drilling rig is available, this boring will be advanced further inorder to identify the confining unit.

GH-8A: This boring has been advanced to 398' bgs, and a monitoring well will beinstalled.

GH-8B: This boring has been advanced to 446' bgs. The drill string is stuck, and in theprocess of trying to remove the drill string.

MW-9A: This boring has been advanced to 572' bgs. A monitoring well has beeninstalled, and it is in the process of being developed.

GH-10A: This boring is located in the North East Canyon, and has been advanced to 720'bgs. A monitoring well will be installed.

PW-11 A: This boring has been advanced to 407' bgs, a monitoring well was installed,and it was developed on December 28, 2000.

PW-1 IB: This boring was advanced to 260' bgs, a monitoring well was installed, and itwas developed on November 29, 2000.

PW-12A: This boring has been advanced to 252.5' bgs. Water has been measured at236.5' bgs. A monitoring has been installed. This monitoring well was developed onDecember 7, 2000.

GH-12B2: This boring is currently at 452' bgs, with a 14" conductor casing to 252' bgs.Appropriate placement of screen intervals is being evaluated.

GH-13A: This boring was advanced to 477' bgs by the API000. The API000 could notadvance this boring beyond this depth. Need to evaluate a different drilling and samplingmethod in order to advance this boring further.

PW-14A: This boring has been advanced to 236' bgs, a monitoring well was installed,and it was developed on January 9, 2001.

GH-15A: This boring has been advanced to 601' bgs with drill casing. This boring willbe sealed off, and advanced further.

Feb.2: The Northeast Canyon Waste Relocation project is 100% complete.

Feb.3: The field work for the cover material evaluation is complete. A draft UNSAT-H reportwas submitted to EPA on October 17, 2000, and the backup laboratory testing resultswere submitted to EPA on November 11, 2000. A clarification correspondence wasprovided to EPA on December 29, 2000, regarding slope stability, triaxial testing, anderosion analysis. Republic received a response to this clarification correspondence on

3

Page 10: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

February 9, 2001.

Feb.4: Waste Limit Determination: A waste boundary delineation map was provided to EPA onJune 30, 2000. This waste limit map included the waste limits for all areas, except for thecenter of the landfill area around the main aggregate stockpile. The IP lines that werecompleted over this area have been interpreted. After this evaluation of the IP lines,additional confirmation borings were done. A proposed final waste limit map was sent toEPA. This waste limit map may be require updating in the future, if other workplanactivities indicate changes.

Feb.5: Stormwater Pollution Prevention Plan (SWPPP): A draft SWPPP was provided to EPAon June 23, 2000, and then a Technical Memorandum regarding SWPPP evaluations wasprovided to EPA on November 30, 2000. In addition, on December 1, 2000, an updatedStormwater Monitoring Plan and Annual Stormwater Evaluation was provided to EPA.The February 9, 2001, response from EPA also clarified some issues with erosionanalysis.

Feb.6: Eastern Drop Off Channel Reconstruction: The plans have all been approved. However,based on field comments from EPA, this Interim Action has been put on hold. In theinterim, Republic is evaluating alternative protection scenarios for the area in the drop offchannel where Stormwater has historically impacted waste. Estimates have beenreceived.

If you have any questions, please contact me at (702) 734-5400.

Respectfully,

AG/tg

File#: 999901-062/Order 7484

CC: Mr. David Basinger (WTR - 7) Water Division Mr. Mark Morse, Field ManagerU.S. Environmental Protection Agency (Attention: Mike Moran)75 Hawthorne Street Bureau of Land ManagementSan Francisco, CA 94105 - 3901 4765 Vegas Valley Drive

Las Vegas, NV 89108

Page 11: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

Mr. Dave Emme, Chief Mr. John SchlegelBureau of Waste Management Clark County Comprehensive Plan.Nevada Division of Environmental Protection 500 S. Grand Central Pky333 W. Nye Lane, Room 138 Las Vegas, NV 89155-1745Carson City, NV 89706-0851

Mr. Clare Schmutz Ms. Sandy DotyClark County Health District SAIC625 Shadow Lane 5303 W. Oberlin Dr.Las Vegas, NV 89106 Denver, CO 80235

Page 12: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

Jiamtenmtce

March 15,2001

Ms Susanna Trujillo, Project CoordinatorL.S. EPA Region IX75 HavMhome Street (WST-7)San F'-ancisco, CA 94105-3901

R1E Monthly Progress Report - March, 2001Order RCRA 7003-09-99-0005NOV/Order CWA-309-9-99-14

As, lequired by the above referenced RCRA Order, specifically VI number 3 (page 9 of 22), thefo:i v.\ ing is the monthly progress report. If you should require a copy of past monthly activities,p'nse contact me. The progress report items are numbered w uh the first three letters of theiroi ih TJiis month's items are as follows:.

• - ' - - ->,-,"'- •• , - _ . • „ <.,._,. v _-

Current Monthly Progress ReportRepublic DUMPCo continues to make progress in completing the tasks outlined in the WorkPlan. Two drill rigs are on site advancing boreholes, setting casings, and'or installing wells.These include the following: 1 Percussion Hammer (AP1000), and a drill and drive (T4W).

Mar. 1: The exploratory borings were started on March 13, 2000. The following is the status ofthese exploratory borings. It should be noted that when a monitoring well has beeninstalled, the prefix for the location designation changes from GH to MW, and when themonitoring well has Heeu developed, the prefix will be changed to PVV. This is reflectedbelow. Furthermore, when a boring has been classified as being "abandoned," this meansthe boring as been plugged with bentonite and sealed. Once a boring as been classified inthis progress report as being "abandoned," the boring will not be included in the nextmonths progress report.

MW-1 A: Stopped at 102 feet below ground surface (bgs) at bed rock contact, and amonitoring well has been installed. (No water has been detected in this monitoring wellsince installation). -

• }-• PW-1C' The soiyCjdnlJ rig advanced this boring to 682' bgs. A well has been installed,- and it was developed on January 31, 2001.

1 '•""-•

770 East Sahara Avenue • P.O. Box 98508 • Las Vegas, Nevada 89193-8508 • Telephone 735-5151 • Fax (702) 735-1986

I MADE WITH RECYCLED PAPER

Page 13: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

MW-2A: A 2-inch and a 4-inch monitoring well were installed in this borehole whichwas advanced to a total depth of 215 feet bgs. Current water level measurements indicatethat the 4-inch and the 2-inch are dry.

MW-2B: A 4-inch monitoring well has been installed in this boring which was advancedto a total depth of 211.5' bgs. Current water level measurements indicate that this boringis dry.

PW-2C2: This boring was advanced to 263' bgs, and a 2-inch and 4-inch monitoringwell were installed. Water has been measured at 248' bgs within each well. As ofJanuary 15, 2001, both monitoring wells have been developed.

MW-2D: This boring has been advanced to 808' bgs with a temporary surface casing at260' bgs. A bentonite plug was placed up to 533' bgs, and a well was installed.

MW-2D2: This boring was advanced to 440' bgs, and a well was installed. Water hasbeen measured at 228' bgs.

GH-3C: Barber Rig has advanced this boring to 500' bgs at this location. A seal wasinstalled at this zone, and this boring is on hold until an appropriate drill rig can beidentified.

PW-4A: This boring was advanced to 295 feet bgs, and a monitoring well installed, andit was developed on January 26, 2001. Current water level has been measured at 185'bgs.

PW-4B: This boring has been advanced to 806' bgs. A monitoring well was installed, andit was developed on January 26, 2001. Current water level has been measured at 581'bgs.

GH-4C: This boring is currently at 360' bgs, and it is being advanced with the AP1000.A well will be installed.

GH-5B4: This boring has been advanced to 733' bgs. This boring will be advanced whenanother appropriate drill rig is available.

PW-5C: This boring has been advanced to 154' bgs. Water has been measured at146' bgs. A monitoring well has been installed, and the well was developed onDecember 6, 2000.

PW-6B: This boring has been advanced to 227' bgs. Water has been measured at 208'bgs. The monitoring well at this located was developed on January 10, 2001.

Page 14: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

PW-6C: This boring has been advanced to 431' bgs, a monitoring well was installed, andit was developed on January 29, 2001. Current water level is at 209' bgs.

GH-7B: This boring has been advanced to 645' bgs with the Sonic Rig. Sonic hasreached a maximum depth with the 5" casing. Water has been encountered, but noconfining unit has been identified. When the appropriate drilling rig is available, thisboring will be advanced further in order to identify the confining unit.

GH-8A: This boring has been advanced to 398' bgs, and a monitoring well will beinstalled.

MW-8B: This boring has been advanced to 492' bgs, and a well in being installed.Water has been measured at 430' bgs.

PW-9A: This boring has been advanced to 572' bgs. A monitoring well has beeninstalled, and it was developed on March 1, 2001. Water has been measured at 449' bgs.

MW-10A: This boring is located in the North East Canyon, and has been advanced to720' bgs. A monitoring well has been installed, and it is being developed. Water hasbeen measured at 668' bgs.

PW-11 A: This boring has been advanced to 407' bgs, a monitoring well was installed,and it was developed on December 28, 2000. Water has been measured at 194' bgs.

PW-1 IB: This boring was advanced to 260' bgs, a monitoring well was installed, and itwas developed on November 29, 2000. Water has been measured at 194' bgs.

PW-12A: This boring has been advanced to 252.5' bgs. Water has been measured at198' bgs. A monitoring has been installed. This monitoring well was developed onDecember 7, 2000.

GH-12B2: This boring is currently at 452' bgs, with a 14" conductor casing to 252' bgs.Appropriate placement of screen intervals is being evaluated.

GH-13A: This boring was advanced to 477' bgs by the AP1000. The AP1000 could notadvance this boring beyond this depth. Need to evaluate a different drilling and samplingmethod in order to advance this boring further.

PW-14A: This boring has been advanced to 236' bgs, a monitoring well was installed,and it was developed on January 9, 2001.

GH-15 A: This boring has been advanced to 601' bgs with drill casing. This boring willbe sealed off, and advanced further.

Mar.2: The Northeast Canyon Waste Relocation project is 100% complete.3

Page 15: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

Mar.3: The field work for the cover material evaluation is complete. A draft UNSAT-H reportwas submitted to EPA on October 17, 2000, and the backup laboratory testing resultswere submitted to EPA on November 11, 2000. A clarification correspondence wasprovided to EPA on December 29, 2000, regarding slope stability, triaxial testing, anderosion analysis. Republic received a response to this clarification correspondence onFebruary 9, 2001. Republic has requested an extension for the erosion analysis tocorrespond with the BMP evaluations.

Mar.4: Waste Limit Determination: A waste boundary delineation map was provided to EPA onJune 30, 2000. This waste limit map included the waste limits for all areas, except for thecenter of the landfill area around the main aggregate stockpile. The IP lines that werecompleted over this area have been interpreted. After this evaluation of the IP lines,additional confirmation borings were done. A proposed final waste limit map was sent toEPA. This waste limit map may be require updating in the future, if other workplanactivities indicate changes.

Mar.5: Stormwater Pollution Prevention Plan (SWPPP): A draft SWPPP was provided to EPAon June 23, 2000, and then a Technical Memorandum regarding SWPPP evaluations wasprovided to EPA on November 30, 2000. In addition, on December 1, 2000, an updatedStormwater Monitoring Plan and Annual Stormwater Evaluation was provided to EPA.Republic received a response from EPA on the Technical Memorandum for the NortheastCanyon in a February 27, 2001, correspondence. Republic has requested an extensionuntil May 22, 2001, to complete this.

Mar.6: Republic provided EPA with the Historical Report as outlined in the Work Plan onMarch 2, 2001.

If you have any questions, please contact me at (702) 734-5400.

Ian GaddVice Presi

AG/tg

File#: 999901-062/Order 7484

Page 16: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

CC: Mr. David Basinger (WTR - 7) Water DivisionU.S. Environmental Protection Agency75 Hawthorne StreetSan Francisco, CA 94105 - 3901

Mr. Dave Emme, ChiefBureau of Waste ManagementNevada Division of Environmental Protection333 W.Nye Lane, Room 138Carson City, NV 89706-0851

Mr. Mark Morse, Field Manager(Attention: Mike Moran)Bureau of Land Management4765 Vegas Valley DriveLas Vegas, NV 89108

Mr. John SchlegelClark County Comprehensive Plan.500 S. Grand Central PkyLas Vegas, NV 89155-1745

Mr. Clare SchmutzClark County Health District625 Shadow LaneLas Vegas, NV 89106

Ms. Sandy DotySAIC5303 W. Oberlin Dr.Denver, CO 80235

Page 17: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

April 16, 2001

Ms. Susanna Trujillo, Project CoordinatorU.S. EPA Region IX75 Hawthorne Street (WST-7)San Francisco, CA 94105-3901

Dear Ms. Trujillo:

RE: Monthly Progress Report - April, 2001Order RCRA 7003-09-99-0005NOV/Order CWA-309-9-99-14

As required by the above referenced RCRA Order, specifically VI number 3 (page 9 of 22), thefollowing is the monthly progress report. If you should require a copy of past monthly activities,please contact me. The progress report items are numbered with the first three letters of themonth. This month's items are as follows:

Current Monthly Progress ReportRepublic DUMPCo continues to make progress in completing the tasks outlined in the WorkPlan. Two drill rigs are on site advancing boreholes, setting casings, and/or installing wells.These include the following: 1 Percussion Hammer (API000), and a drill and drive (T4W).

Apr.l: The exploratory borings were started on March 13, 2000. The following is the status ofthese exploratory borings. It should be noted that when a monitoring well has beeninstalled, the prefix for the location designation changes from GH to MW, and when themonitoring well has been developed, the prefix will be changed to PW. This is reflectedbelow. Furthermore, when a boring has been classified as being "abandoned," this meansthe boring as been plugged with bentonite and sealed. Once a boring as been classified inthis progress report as being "abandoned," the boring will not be included in the nextmonths progress report. Republic received approval to give the drilling crews the week ofApril 9, 2001, off in order for them to spend time with their families during Easter.

MW-1 A: Stopped at 102 feet below ground surface (bgs) at bed rock contact, and amonitoring well has been installed. (No water has been detected in this monitoring wellsince installation).

PW-1C: The sonic drill rig advanced this boring to 682' bgs. A well has been installed,1

770 East Sahara Avenue • P.O. Box 98508 • Las Vegas, Nevada 89193-8508 • Telephone 735-5151 • Fax (702) 735-1986

1 MADE WITH RECYCLED PAPER

Page 18: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

and it was developed on January 31, 2001.

MW-2A: A 2-inch and a 4-inch monitoring well were installed in this borehole whichwas advanced to a total depth of 215 feet bgs. Current water level measurements indicatethat the 4-inch and the 2-inch are dry.

MW-2B: A 4-inch monitoring well has been installed in this boring which was advancedto a total depth of 211.5' bgs. Current water level measurements indicate that this boringis dry.

PW-2C2: This boring was advanced to 263' bgs, and a 2-inch and 4-inch monitoringwell were installed. Water has been measured at 248' bgs within each well. As ofJanuary 15, 2001, both monitoring wells have been developed.

MW-2D: This boring has been advanced to 808' bgs with a temporary surface casing at260' bgs. A bentonite plug was placed up to 533' bgs, and a well was installed.

MW-2D2: This boring was advanced to 440' bgs, and a well was installed. Water hasbeen measured at 228' bgs.

GH-3C: Barber Rig has advanced this boring to 500' bgs at this location. A seal wasinstalled at this zone, and this boring is on hold until an appropriate drill rig can beidentified.

PW-4A: This boring was advanced to 295 feet bgs, and a monitoring well installed, andit was developed on January 26, 2001. Current water level has been measured at 185'bgs.

PW-4B: This boring has been advanced to 806' bgs. A monitoring well was installed, andit was developed on January 26, 2001. Current water level has been measured at 581'bgs.

MW-4C: This boring is currently at 360' bgs, and it is being advanced with the API000.A well was installed on March 14, 2001, and it is being developed.

MW-5B4: This boring has been advanced to 733' bgs, and a well has been installed.

PW-5C: This boring has been advanced to 154' bgs. Water has been measured at146' bgs. A monitoring well has been installed, and the well was developed onDecember 6, 2000.

PW-6B: This boring has been advanced to 227' bgs. Water has been measured at 208'bgs. The monitoring well at this located was developed on January 10, 2001.

Page 19: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

PW-6C: This boring has been advanced to 431' bgs, a monitoring well was installed, andit was developed on January 29, 2001. Current water level is at 209' bgs,

GH-7B: This boring has been advanced to 645' bgs with the Sonic Rig. Sonic hasreached a maximum depth with the 5" casing. Water has been encountered, but noconfining unit has been identified. When the appropriate drilling rig is available, thisboring will be advanced further in order to identify the confining unit.

MW-8A: This boring has been advanced to 398' bgs, and a well was installed on March16,2001.

MW-8B: This boring has been advanced to 492' bgs, and a well has been installed.

PW-9A: This boring has been advanced to 572' bgs. A monitoring well has beeninstalled, and it was developed on March 1, 2001. Water has been measured at 449' bgs.

MW-10A: This boring is located in the North East Canyon, and has been advanced to720' bgs. A monitoring well has been installed, developed, and sampled. Water has beenmeasured at 668' bgs.

PW-11 A: This boring has been advanced to 407' bgs, a monitoring well was installed,and it was developed on December 28, 2000, Water has been measured at 194' bgs.

PW-1 IB: This boring was advanced to 260' bgs, a monitoring well was installed, and itwas developed on November 29,2000. Water has been measured at 194' bgs.

PW-12A: This boring has been advanced to 252.5' bgs. Water has been measured at198' bgs. A well has been installed. This monitoring well was developed on December7, 2000.

MW-12B2: This boring is currently at 452' bgs, with a 14" conductor casing to 252' bgs.A well was installed on March 29, 2001.

GH-13A: This boring was advanced to 477' bgs by the AP1000. The AP1000 could notadvance this boring beyond this depth. Need to evaluate a different drilling and samplingmethod in order to advance this boring further.

PW-14A: This boring has been advanced to 236' bgs, a monitoring well was installed,and it was developed on January 9, 2001.

GH-15A: This boring has been advanced to 601' bgs with drill casing. This boring willbe sealed off, and advanced further.

Apr2: The Northeast Canyon Waste Relocation project is 100% complete. However, Republicis continuing to improve existing drainage structures in the North East Canyon. The

3

Page 20: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

whole re-aligned face has been recovered with erosion cover.

Apr.3: The field work for the cover material evaluation is complete. A draft UNSAT-H reportwas submitted to EPA on October 17, 2000, and the backup laboratory testing resultswere submitted to EPA on November 11, 2000. A clarification correspondence wasprovided to EPA on December 29, 2000, regarding slope stability, triaxial testing, anderosion analysis. Republic received a response to this clarification correspondence onFebruary 9, 2001. Republic has requested an extension for the erosion analysis tocorrespond with the BMP evaluations. In an March 30, 2001, correspondence EPAapproved the extension request to May 22, 2001.

Apr.4: Waste Limit Determination: A waste boundary delineation map was provided to EPA onJune 30, 2000. This waste limit map included the waste limits for all areas, except for thecenter of the landfill area around the main aggregate stockpile. The IP lines that werecompleted over this area have been interpreted. After this evaluation of the IP lines,additional confirmation borings were done. A proposed final waste limit map was sent toEPA. This waste limit map may be require updating in the future, if other workplanactivities indicate changes.

Apr.5: Stormwater Pollution Prevention Plan (SWPPP): A draft SWPPP was provided to EPAon June 23, 2000, and then a Technical Memorandum regarding SWPPP evaluations wasprovided to EPA on November 30, 2000. On December 1, 2000, an updated StormwaterMonitoring Plan and Annual Stormwater Evaluation was provided to EPA. Republicreceived a response from EPA on the Technical Memorandum for the Northeast Canyonin a February 27, 2001, correspondence. In addition to the approval for the extension ofthe BMP analysis referenced above, in a separate correspondence Republic has requesteda meeting with EPA and an extension to the April 20, 2001, submittal requirement, inorder to discuss the February 27, 2001, correspondence with EPA.

Apr.6: Republic provided EPA with the Slope Stability report and a Landfill Gas Collection andControl Plan on April 6, 2001.

If you have any questions, please contact me at (702) 734-5400.

Respectfully,

Alan GEVice President

V

AG/tg

File#: 999901-062/Order 7484

Page 21: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

CC: Mr. David Basinger (WTR - 7) Water DivisionU.S. Environmental Protection Agency75 Hawthorne StreetSan Francisco, CA 94105 - 3901

Mr. Dave Emme, ChiefBureau of Waste ManagementNevada Division of Environmental Protection333 W. Nye Lane, Room 138Carson City, NV 89706-0851

Mr. Mark Morse, Field Manager(Attention: Mike Moran)Bureau of Land Management4765 Vegas Valley DriveLas Vegas, NV 89108

Mr. John SchlegelClark County Comprehensive Plan.500 S. Grand Central PkyLas Vegas, NV 89155-1745

Mr. Clare SchmutzClark County Health District625 Shadow LaneLas Vegas, NV 89106

Ms. Sandy DotySAIC5303 W. Oberlin Dr.Denver, CO 80235

Page 22: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

M:,y 14,2001

Ms Susanna Trujillo, Project Coordinatoi'<: S FPA Region IX?.•> Hawthorne Street (WST-7)San Francisco, CA 94105-3901

Ms. Trujillo:

i<Jr Monthly Progress Report - May, 2001Order RCRA 7003-09-99-0005NOV/Order CWA-309-9-99-14

As 'equired by the above referenced RCRA Order, specifically VI number 3 (page 9 of 22), thefollowing is the monthly progress report. If you should require a copy of past monthly activities,please contact me. The progress report items are nurnbere-J wnli the fust thiee letters of themonth. This month's items are as follows:

Current Monthly Progress ReportR?p,iHic DUMPCo continues to make progress in completing the tasks outlined in the WorkPlan A drill and drive (T4W) setting casing and/or installing wells.

iV!:\ 1: The exploratory borings were started on March 13, 2000. The following is the status ofthese exploratory borings. It should be noted that when a monitoring well has beeninstalled, the prefix for the location designation changes from GH to MW, and when themonitoring well has been developed, the prefix will be changed to PW. 1 his is reflectedbelow. Furthermore, when a boring has been classified MS being "abandoned," thib IP cansthe boring as been plugged with bentonite and sealed. Once a bonng as been classified mthis progress report as being "abandoned," the boring w 11 riot bo included in the nextmonths progress report. An * indicates that the slatus of this item has changed.

MW-1 A: Stopped at 102 feet below ground surface (bgs/ ai bed rock contact, and amonitoring well has been installed. (No water has been detected in this monitoring wellsince installation).

PW-1C: The sonic drill rig advanced this bo,ing to 682' !;>,.•>. A well has been installed,and it was developed on January 31, 2001.

1

770 East Sahara Avenue • P.O. Box 98508 • Las Vegas, Nevada 89193-8508 • Telephone 735-5151 • Fax (702) 735-1986

I MADE WITH RECYCLED PAPER

Page 23: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

MW-2A: A 2-inch and a 4-inch monitoring well were installed in this borehole whichwas advanced to a total depth of 215 feet bgs. Current water level measurements indicatethat the 4-inch and the 2-inch are dry.

MW-2B: A 4-inch monitoring well has been installed in this boring which was advancedto a total depth of 215' bgs. Current water level measurements are at 202.4' bgs.

PW-2C2: This boring was advanced to 263' bgs, and a 2-inch and 4-inch monitoringwell were installed. Water has been measured at 248' bgs within each well. As ofJanuary 15, 2001, both monitoring wells have been developed.

PW-2D: This boring has been advanced to 808' bgs with a temporary surface casing at260' bgs. A bentonite plug was placed up to 533' bgs. As of April 16, 2001, thismonitoring well has been developed and sampled.

PW-2D2: This boring was advanced to 440' bgs, and a well was installed. Water hasbeen measured at 228' bgs. As of March 21, 2001, this monitoring well has beendeveloped and sampled.

GH-3C: Barber Rig has advanced this boring to 500' bgs at this location. A seal wasinstalled at this zone, but current data indicate that the seal was not installedappropriately.

PW-4A: This boring was advanced to 295 feet bgs, and a monitoring well installed, andit was developed on January 26, 2001. Current water level has been measured at 185'bgs.

PW-4B: This boring has been advanced to 806' bgs. A monitoring well was installed, andit was developed on January 26, 2001. Current water level has been measured at 581'bgs.

MW-4C: This boring is currently at 470' bgs. A well was installed on March 14, 2001,and it is being developed.

MW-5B4: This boring has been advanced to 733' bgs, and a well has been installed.

PW-5C: This boring has been advanced to 154' bgs. Water has been measured at146' bgs. A monitoring well has been installed, and the well was developed onDecember 6, 2000.

PW-6B: This boring has been advanced to 227' bgs. Water has been measured at 208'bgs. The monitoring well at this located was developed on January 10, 2001.

PW-6C: This boring has been advanced to 431' bgs, a monitoring well was installed, and2

Page 24: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

it was developed on January 29, 2001. Current water level is at 209' bgs.

* GH-7B: This boring was advanced to 645' bgs with the Sonic Rig. Sonic has reached amaximum depth with the 5" casing. Water has been encountered, but no confining unithas been identified. This exploratory boring was abandoned.

MW-8A: This boring has been advanced to 398' bgs, and a well was installed on March16, 2001. Development is on going due to slow recharge rate.

MW-8B: This boring has been advanced to 492' bgs, and a well has been installed.Development is on going due to slow recharge rate.

PW-9A: This boring has been advanced to 572' bgs. A monitoring well has beeninstalled, and it was developed on March 1, 2001. Water has been measured at 449' bgs.

* PW-10A: This boring is located in the North East Canyon, and has been advanced to 720'bgs. A monitoring well has been installed, developed, and sampled. Water has beenmeasured at 668' bgs.

PW-11 A: This boring has been advanced to 407' bgs, a monitoring well was installed,and it was developed on December 28, 2000. Water has been measured at 194' bgs.

PW-1 IB: This boring was advanced to 260' bgs, a monitoring well was installed, and itwas developed on November 29, 2000. Water has been measured at 194' bgs.

PW-12A: This boring has been advanced to 252.5' bgs. Water has been measured at198' bgs. A well has been installed. This monitoring well was developed on December7, 2000.

* PW-12B2: This boring is currently at 452' bgs, with a 14" conductor casing to 252' bgs.A well was installed on March 29, 2001. As of April 24, 2001, this monitoring well hasbeen developed and sampled.

* GH-13A: This exploratory boring was advanced to 477' bgs and abandoned.

PW-14A: This boring has been advanced to 236' bgs, a monitoring well was installed,and it was developed on January 9, 2001.

* GH-15A: This exploratory boring was advanced to 601' bgs and abandoned.

May.2: The field work for the cover material evaluation is complete. A draft UNSAT-H reportwas submitted to EPA on October 17, 2000, and the backup laboratory testing resultswere submitted to EPA on November 11, 2000. A clarification correspondence wasprovided to EPA on December 29, 2000, regarding slope stability, triaxial testing, anderosion analysis. Republic received a response to this clarification correspondence on

3

Page 25: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

February 9, 2001. Republic has requested an extension for the erosion analysis tocorrespond with the BMP evaluations. In an March 30, 2001, correspondence EPAapproved the extension request to May 22, 2001.

May.3: Waste Limit Determination: A waste boundary delineation map was provided to EPA onJune 30, 2000. This waste limit map included the waste limits for all areas, except for thecenter of the landfill area around the main aggregate stockpile. The IP lines that werecompleted over this area have been interpreted. After this evaluation of the IP lines,additional confirmation borings were done. A proposed final waste limit map was sent toEPA. This waste limit map may be require updating in the future, if other workplanactivities indicate changes.

May.4: Stormwater Pollution Prevention Plan (SWPPP): A draft SWPPP was provided to EPAon June 23, 2000, and then a Technical Memorandum regarding SWPPP evaluations wasprovided to EPA on November 30, 2000. On December 1, 2000, an updated StormwaterMonitoring Plan and Annual Stormwater Evaluation was provided to EPA. Republicreceived a response from EPA on the Technical Memorandum for the Northeast Canyonin a February 27, 2001, correspondence. In addition to the approval for the extension ofthe BMP analysis referenced above, in a separate correspondence Republic has requesteda meeting with EPA and an extension to the April 20, 2001, submittal requirement, inorder to discuss the February 27, 2001, correspondence with EPA.

May.5: Republic provided EPA with the Slope Stability report and a Landfill Gas Collection andControl Plan on April 6, 2001.

If you have any questions, please contact me at (702) 734-5400.

Respectfully,

Alan GaddyfVice President

AG/tg

File#: 999901-062/Order 7484

CC: Mr. David Basinger (WTR - 7) Water Division Mr. Mark Morse, Field ManagerU.S. Environmental Protection Agency (Attention: Mike Moran)75 Hawthorne Street Bureau of Land Management

4

Page 26: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

San Francisco, CA 94105 - 3901

Mr. Dave Emme, ChiefBureau of Waste ManagementNevada Division of Environmental Protection333 W. Nye Lane, Room 138Carson City, NV 89706-0851

4765 Vegas Valley DriveLas Vegas, NV 89108

Mr. John SchlegelClark County Comprehensive Plan.500 S. Grand Central PkyLas Vegas, NV 89155-1745

Mr. Clare SchmutzClark County Health District625 Shadow LaneLas Vegas, NV 89106

Ms. Sandy DotySAIC5303 W. Oberlin Dr.Denver, CO 80235

Page 27: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

June 15,2001

Ms. Susanna Trujillo, Project CoordinatorU.S. EPA Region IX75 Hawthorne Street (WST-7)San Francisco, CA 94105-3901

Dear Ms. Trujillo:

RE: Monthly Progress Report - June, 2001Order RCRA 7003-09-99-0005NOV/Order CWA-309-9-99-14

As required by the above referenced RCRA Order, specifically VI number 3 (page 9 of 22), thefollowing is the monthly progress report. If you should require- a <;opy of past monthly activities,please contact me. The progress report items are numbered with the first three letters of themonth. This month's items are as follows:

Current Monthly Progress ReportRepublic Services of Southern Nevada (RSSN) continues to make progress in completing thetasks outlined in the Work Plan. A drill and drive (T4W) setting casing and/or installing wells,and a smeal 5T is onsite for well development and sampling.

June.l: The exploratory borings were started on March 13, 2000. The following is the status ofthese exploratory borings. It should be noted that when a monitoring well has beeninstalled, the prefix for the location designation changes from GH to MW, and when themonitoring well has been developed, the prefix will be changed to PW. This is reflectedbelow. Furthermore, when a boring has been classified as being "abandoned," this meansthe boring as been plugged with bentonite and sealed. Once a boring as been classified inthis progress report as being "abandoned," the boring will not be included in the nextmonths progress report. An * indicates that the status of this item has changed.

MW-1 A: Stopped at 102 feet below ground surface (bgs) at bed rock contact, and amonitoring well has been installed. (No water has been detected in this monitoring wellsince installation).

* PW-1C: The sonic drill rig advanced this boring to 682' bgs. A well has been installed,and it was developed on January 31, 2001. Current water depth is 246.4' bgs.

1

770 East Sahara Avenue • Las Vegas, NV 89104 • Telephone (702) 735-5151 • Fax: (702) 735-1986

Page 28: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

MW-2A: A 2-inch and a 4-inch monitoring well were installed in this borehole whichwas advanced to a total depth of 215 feet bgs. Current water level measurements indicatethat the 4-inch is dry and the 2-inch has water at 202' bgs.

MW-2B: A 4-inch monitoring well has been installed in this boring which was advancedto a total depth of 215' bgs. Current water level measurements are at 202' bgs.

PW-2C2: This boring was advanced to 263' bgs, and a 2-inch and 4-inch monitoringwell were installed. Water has been measured at approximately 221' bgs within eachwell. As of January 15, 2001, both monitoring wells have been developed.

PW-2D: This boring has been advanced to 808' bgs and a bentonite plug was placed upto 533' bgs. As of April 16, 2001, this monitoring well has been developed and sampled.Current water level is 214' bgs.

PW-2D2: This boring was advanced to 440' bgs, and a well was installed. Water hasbeen measured at 228' bgs. As of March 21, 2001, this monitoring well has beendeveloped and sampled.

GH-2E: This boring has been advanced to 687 bgs, and is currently being reamed for wellinstallation.

GH-3C: Barber Rig has advanced this boring to 500' bgs at this location. A seal wasinstalled at this zone, but current data indicate that the seal was not installedappropriately.

PW-4A: This boring was advanced to 295 feet bgs, and a monitoring well installed, andit was developed on January 26, 2001. Current water level has been measured at 184'bgs.

PW-4B: This boring has been advanced to 802' bgs. A monitoring well was installed, andit was developed on January 26, 2001. Current water level has been measured at 199'bgs.

PW-4C: This boring is currently at 470' bgs. A well was installed on March 14, 2001,and developed on May 9, 2001. Currently water level is at 218' bgs.

MW-5B4: This boring has been advanced to 733' bgs. A well has been installed, and it iscurrently being developed air lifting.

PW-5C: This boring has been advanced to 154' bgs. Water has been measured at146' bgs. A monitoring well has been installed, and the well was developed onDecember 6, 2000.

Page 29: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

PW-6B: This boring has been advanced to 227' bgs. Water has been measured at 208'bgs. The monitoring well at this location was developed on January 10, 2001.

PW-6C: This boring has been advanced to 431' bgs, a monitoring well was installed, andit was developed on January 29, 2001. Current water level is at 209' bgs.

MW-8A: This boring has been advanced to 398' bgs, and a well was installed on March16, 2001. Development is on going due to slow recharge rate. Current water level is at388' bgs.

MW-8B: This boring has been advanced to 492' bgs, and a well has been installed.Development is on going due to slow recharge rate. Current water level is at 469' bgs.

PW-9A: This boring has been advanced to 535' bgs. A monitoring well has beeninstalled, and it was developed on March 1, 2001. Water has been measured at 449' bgs.

PW-9B: This boring has been advanced to 475' bgs. A monitoring well has beeninstalled and developed. Water has been measured at 449 bgs.

PW-10A: This boring is located in the North East Canyon, and has been advanced to 720'bgs. A monitoring well has been installed, developed, and sampled. Water has beenmeasured at 668' bgs.

PW-11 A: This boring has been advanced to 407' bgs, a monitoring well was installed,and it was developed on December 28, 2000. Water has been measured at 231' bgs.

MW-11C: This boring has been advanced to 828' bgs. A monitoring well has beeninstalled, and current water level is at 707' bgs.

PW-1 IB: This boring was advanced to 260' bgs, a monitoring well was installed, and itwas developed on November 29, 2000. Water has been measured at 192' bgs.

PW-12A: This boring has been advanced to 252.5' bgs. Water has been measured at210' bgs. A well has been installed. This monitoring well was developed on December7, 2000.

PW-12B2: This boring is currently at 484' bgs, with a 14" conductor casing to 252' bgs.A well was installed on March 29, 2001. As of April 24, 2001, this monitoring well hasbeen developed and sampled. Current water level is at 190' bgs.

MW-12D: This boring has been advanced to 810' bgs. A monitoring well has beeninstalled and it is being developed. Current water level measurements indicate water at787' bgs.

Page 30: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

PW-14A: This boring has been advanced to 226' bgs, a monitoring well was installed,and it was developed on January 9, 2001. Current water level is at 216' bgs.

Jun.2: The field work for the cover material evaluation is complete. A draft UNSAT-H reportwas submitted to EPA on October 17,2000, and the backup laboratory testing resultswere submitted to EPA on November 11, 2000.

Jun.3: Waste Limit Determination: A waste boundary delineation map was provided to EPA onJune 30, 2000. This waste limit map included the waste limits for all areas, except for thecenter of the landfill area around the main aggregate stockpile. The IP lines that werecompleted over this area have been interpreted. After this evaluation of the IP lines,additional confirmation borings were done. A proposed final waste limit map was sent toEPA. This waste limit map may be require updating in the future, if other workplanactivities indicate changes.

Jun.4: Stormwater Pollution Prevention Plan (SWPPP): A draft SWPPP was provided to EPAon June 23, 2000, and then a Technical Memorandum regarding SWPPP evaluations wasprovided to EPA on November 30, 2000. On December 1, 2000, an updated StormwaterMonitoring Plan and Annual Stormwater Evaluation was provided to EPA. Republicreceived a response from EPA on the Technical Memorandum for the Northeast Canyonin a February 27, 2001, correspondence. Based on meetings with EPA in San Franscisco,and at Sunrise, Republic is further evaluating the alternatives for the Northeast Canyon.Based on these evaluations the appropriate control measures for the eastern upper portionof the landfill and the Northeast canyon will be selected. Once these are selected, theSWPPP can be updated. On May 5, 2001, Republic provided EPA with revised erosionanalysis for the Southern Flats.

If you have any questions, please contact me at (702) 734-5400.

Respectfully,

AlanVice President

AG/tg

File#: 999901-062/Order 7484

Page 31: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

CC: Mr. David Basinger (WTR - 7) Water DivisionU.S. Environmental Protection Agency75 Hawthorne StreetSan Francisco, CA 94105 - 3901

Mr. Dave Emme, ChiefBureau of Waste ManagementNevada Division of Environmental Protection333 W. Nye Lane, Room 138Carson City, NV 89706-0851

Mr. Mark Morse, Field Manager(Attention: Mike Moran)Bureau of Land Management4765 Vegas Valley DriveLas Vegas, NV 89108

Mr. John SchlegelClark County Comprehensive Plan.500 S. Grand Central PkyLas Vegas, NV 89155-1745

Mr. Clare SchmutzClark County Health District625 Shadow LaneLas Vegas, NV 89106

Ms. Sandy DotySAIC5303W. OberlinDr.Denver, CO 80235

Page 32: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

770 East Sahara Avenue • P. O. Box 98508Las Vegas, NV 89193-8508

(702) 734-5400

July 12, 2001

Ms. Susanna Trujillo, Project CoordinatorU.S. EPA Region IX75 Hawthorne Street (WST-7)San Francisco, CA 94105-3901

Dear Ms. Trujillo:

RE: Monthly Progress Report - July, 2001Order RCRA 7003-09-99-0005NOV/Order CWA-309-9-99-14

As required by the above referenced RCRA Order, specifically VI number 3 (page 9 of 22), thefollowing is the monthly progress report. If you should require a copy of past monthly activities,please contact me. The progress report items are numbered with the first three letters of themonth. This month's items are as follows:

Current Monthly Progress ReportRepublic Services of Southern Nevada (RSSN) continues to make progress in completing thetasks outlined in the Work Plan. Currently, an air rotary (T4W) is drilling, setting casing and/orinstalling wells, and a smeal 5T is onsite for well development and sampling.

Jul.l: The exploratory borings were started on March 13, 2000. The following is the status ofthese exploratory borings. It should be noted that when a monitoring well has beeninstalled, the prefix for the location designation changes from GH to MW, and when themonitoring well has been developed, the prefix will be changed to PW. This is reflectedbelow. Furthermore, when a boring has been classified as being "abandoned," this meansthe boring as been plugged with bentonite and sealed. Once a boring as been classified inthis progress report as being "abandoned," the boring will not be included in the nextmonths progress report. An * indicates that the status of this item has changed.

MW-1 A: Stopped at 102 feet below ground surface (bgs) at bed rock contact, and amonitoring well has been installed. (No water has been detected in this monitoring well ,since installation).

PW-1C: The sonic drill rig advanced this boring to 682' bgs. A well has been installed,'and it was developed on January 31, 2001. Current water depth is 246.4' bgs.

1

Page 33: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

MW-2A: A 2-inch and a 4-inch monitoring well were installed in this borehole whichwas advanced to a total depth of 215 feet bgs. Current water level measurements indicatethat the 4-inch is dry and the 2-inch has water at 197' bgs.

MW-2B: A 4-inch monitoring well has been installed in this boring which was advancedto a total depth of 215' bgs. Current water level measurements are at 202' bgs.

PW-2C2: This boring was advanced to 263' bgs, and a 2-inch and 4-inch monitoringwell were installed. Water has been measured at approximately 219' bgs within eachwell. As of January 15, 2001, both monitoring wells have been developed.

PW-2D: This boring has been advanced to 808' bgs and a bentonite plug was placed upto 533' bgs. As of April 16, 2001, this monitoring well has been developed and sampled.Current water level is 237' bgs.

PW-2D2: This boring was advanced to 440' bgs, and a well was installed. Water hasbeen measured at 207' bgs. As of March 21, 2001, this monitoring well has beendeveloped and sampled.

MW-2E: This boring has been advanced to 687 bgs. A well has been installed, and itneeds to be developed. Current water level measurements are at 231' bgs.

GH-2E2: This boring was drilled to 330 bgs, and while being advanced, communicationwith 2C2 was noticed. Air was coming out of 2C2. Drilling was stopped, and EPAcontacted. It was decided that this boring would be grouted up to the bottom of PW-2C2,and a well installed. This was done in order to save 2C2 if sloughing had occurred. Thecalculations indicate that some sloughing did occur above 265 bgs. This boring will becompleted as a monitoring well.

GH-3C: Barber Rig has advanced this boring to 500' bgs at this location. A seal wasinstalled at this zone, but current data indicate that the seal was not installedappropriately. In a June 12, 2001, email to EPA, Republic has proposed a possiblesolution to this problem.

PW-4A: This boring was advanced to 295 feet bgs, and a monitoring well installed, andit was developed on January 26, 2001. Current water level has been measured at 184'bgs.

PW-4B: This boring has been advanced to 802' bgs. A monitoring well was installed, andit was developed on January 26, 2001. Current water level has been measured at 180'bgs.

PW-4C: This boring is currently at 470' bgs. A well was installed on March 14, 2001,and developed on May 9, 2001. Currently water level is at 218' bgs.

2

Page 34: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

PW-5B4: This boring has been advanced to 733' bgs. A well has been installed anddeveloped. Currently, water level is at 178' bgs.

PW-5C: This boring has been advanced to 154' bgs. Water has been measured at146' bgs. A monitoring well has been installed, and the well was developed onDecember 6, 2000.

PW-6B: This boring has been advanced to 227' bgs. Water has been measured at 208'bgs. The monitoring well at this location was developed on January 10, 2001.

PW-6C: This boring has been advanced to 431' bgs, a monitoring well was installed, andit was developed on January 29, 2001. Current water level is at 209' bgs.

MW-8A: This boring has been advanced to 398' bgs, and a well was installed on March16, 2001. Development is on going due to slow recharge rate. Current water level is at388' bgs.

MW-8B: This boring has been advanced to 492' bgs, and a well has been installed.Development is on going due to slow recharge rate. Current water level is at 471' bgs.

PW-9A: This boring has been advanced to 535' bgs. A monitoring well has beeninstalled, and it was developed on March 1, 2001. Water has been measured at 449' bgs.

PW-9B: This boring has been advanced to 475' bgs. A monitoring well has beeninstalled and developed. Water has been measured at 449 bgs.

PW-10A: This boring is located in the North East Canyon, and has been advanced to 720'bgs. A monitoring well has been installed, developed, and sampled. Water has beenmeasured at 668' bgs.

PW-11 A: This boring has been advanced to 407' bgs, a monitoring well was installed,and it was developed on December 28, 2000. Water has been measured at 211' bgs.

MW-11C: This boring has been advanced to 828' bgs. A monitoring well has beeninstalled, and current water level is at 512' bgs.

PW-1 IB: This boring was advanced to 260' bgs, a monitoring well was installed, and itwas developed on November 29, 2000. Water has been measured at 192' bgs.

PW-12A: This boring has been advanced to 252.5'bgs. A well has been installed. Thismonitoring well was developed on December 7, 2000. Water has been measured at 200'bgs.

PW-12B2: This boring has been advanced to 484' bgs. A well was installed on March3

Page 35: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

29, 2001. As of April 24, 2001, this monitoring well has been developed and sampled.Current water level is at 176' bgs.

* MW-12D: This boring has been advanced to 810' bgs. A monitoring well has beeninstalled and it is being developed. Current water level measurements indicate water at697' bgs.

PW-14A: This boring has been advanced to 226' bgs, a monitoring well was installed,and it was developed on January 9, 2001. Current water level is at 216' bgs.

Jul.2: The field work for the cover material evaluation is complete. A draft UNSAT-H reportwas submitted to EPA on October 17, 2000, and the backup laboratory testing resultswere submitted to EPA on November 11, 2000. EPA provided Republic with commentson the cover study on June 28, 2001. The correspondence indicates that Republic andEPA should meet to discuss the next step.

Jun.3: Republic provided EPA with a proposed drilling plan for locations 7, 13, and 15 on July10,2001.

Jun.4: Stormwater Pollution Prevention Plan (SWPPP): As discussed with EPA, Republicwould provide EPA with less formal submittals called "check points." The initial checkpoints are designed to further guide the development of appropriate control measures forthe Stormwater run-on and run-off from the North East Canyon because this impacts thedevelopment of the SWPPP. Check point #1 was provided to EPA on July 11, 2001.

If you have any questions, please contact me at (702) 734-5400.

Respectfully,

Vice President

AG/tg

File#: 999901-062/Order 7484

Page 36: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

CC: Mr. David Basinger (WTR - 7) Water DivisionU.S. Environmental Protection Agency75 Hawthorne StreetSan Francisco, CA 94105 - 3901

Mr. Dave Emme, ChiefBureau of Waste ManagementNevada Division of Environmental Protection333 W. Nye Lane, Room 138Carson City, NV 89706-0851

Mr. Mark Morse, Field Manager(Attention: Mike Moran)Bureau of Land Management4765 Vegas Valley DriveLas Vegas, NV 89108

Mr. John SchlegelClark County Comprehensive Plan.500 S. Grand Central PkyLas Vegas, NV 89155-1745

Mr. Clare SchmutzClark County Health District625 Shadow LaneLas Vegas, NV 89106

Ms. Sandy DotySAIC5303 W. Oberlin Dr.Denver, CO 80235

Page 37: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

August 14, 2001

Ms. Susanna Trujillo, Project CoordinatorU.S. EPA Region IX75 Hawthorne Street (WST-7)San Francisco, CA 94105-3901

Dear Ms. Trujillo:

RE: Monthly Progress Report - August, 2001Order RCRA 7003-09-99-0005NOV/Order CWA-3 09-9-99-14

As required by the above referenced RCRA Order, specifically VI number 3 (page 9 of 22), thefollowing is the monthly progress report. If you should require a copy of past monthly activities,pjease contact>me. The progress report items are numbered with ihe first three letters of themonth. This month's items are as follows:

Current Monthly Progress ReportRepublic Services of Southern Nevada (RSSN) continues to make progress in completing thetasks outlined in the Work Plan. Currently, an air rotary (T4W) is drilling, setting casing and/orinstalling wells, and a smeal 5T is onsite for well development and sampling.

Aug.l: The exploratory borings were started on March 13, 2000. The following is the status ofthese exploratory borings. It should be noted that when a monitoring well has beeninstalled, the prefix for the location designation changes from GH to MW, and when themonitoring well has been developed, the prefix will be changed to PW. This is reflectedbelow. Furthermore, when a boring has been classified as being "abandoned," this meansthe boring as been plugged with bentonite and sealed. Once a boring as been classified inthis progress report as being "abandoned," the boring will not be included in the nextmonths progress report. An * indicates that the status of this item has changed.

t

MW-1A: Stopped at 102 feet below ground surface (bgs) at bed rock contact, and £monitoring well has been installed. (No water has been detected in this monitoring wellsince installation).

PW-1C: The sonic drill rig advanced this boring to 682' bgs. A well has been installed,and it was developed on January 31, 2001. Current water depth is 246.4' bgs.

1

770 East Sahara Avenue • Las Vegas, NV 89104 • Telephone (702) 735-5151 • Fax: (702) 369-2206

Page 38: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

MW-2A: A 2-inch and a 4-inch monitoring well were installed in this borehole whichwas advanced to a total depth of 215 feet bgs. Current water level measurements indicatethat the 4-inch is dry and the 2-inch has water at 197' bgs.

MW-2B: A 4-inch monitoring well has been installed in this boring which was advancedto a total depth of 215' bgs. Current water level measurements are at 202' bgs.

PW-2C2: This boring was advanced to 263' bgs, and a 2-inch and 4-inch monitoringwell were installed. Water has been measured at approximately 219' bgs within eachwell. As of January 15, 2001, both monitoring wells have been developed.

PW-2D: This boring has been advanced to 808' bgs and a bentonite plug was placed upto 533' bgs. As of April 16, 2001, this monitoring well has been developed and sampled.Current water level is 237' bgs.

PW-2D2: This boring was advanced to 440' bgs, and a well was installed. Water hasbeen measured at 207' bgs. As of March 21, 2001, this monitoring well has beendeveloped and sampled.

MW-2E: This boring has been advanced to 687 bgs. A well has been installed, and itneeds to be developed. Current water level measurements are at 231' bgs.

GH-2E2: This boring was drilled to 330' bgs, and while being advanced, communicationwith 2C2 was noticed. Air was coming out of 2C2. Drilling was stopped, and EPAcontacted. This boring was grouted up to the bottom of PW-2C2, and a well installed.This was done in order to save 2C2 if sloughing had occurred. The calculations indicatethat some sloughing did occur above 265 bgs.

GH-2E3: This boring has been advanced to 442' bgs where a seal is being installed.

GH-3C: Barber Rig has advanced this boring to 500' bgs at this location. A seal wasinstalled at this zone, but current data indicate that the seal was not installedappropriately. In a June 12, 2001, email to EPA, Republic has proposed a possiblesolution to this problem.

PW-4A: This boring was advanced to 295 feet bgs, and a monitoring well installed, andit was developed on January 26, 2001. Current water level has been measured at 184'bgs.

PW-4B: This boring has been advanced to 802' bgs. A monitoring well was installed, andit was developed on January 26, 2001. Current water level has been measured at 180'bgs.

PW-4C: This boring is currently at 470' bgs. A well was installed on March 14, 2001,2

Page 39: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

and developed on May 9, 2001. Currently water level is at 218' bgs.

PW-5B4: This boring has been advanced to 733' bgs. A well has been installed anddeveloped. Currently, water level is at 178' bgs.

PW-5C: This boring has been advanced to 154' bgs. Water has been measured at146' bgs. A monitoring well has been installed, and the well was developed onDecember 6, 2000.

PW-6B: This boring has been advanced to 227' bgs. Water has been measured at 208'bgs. The monitoring well at this location was developed on January 10, 2001.

PW-6C: This boring has been advanced to 431' bgs, a monitoring well was installed, andit was developed on January 29, 2001. Current water level is at 209' bgs.

MW-8A: This boring has been advanced to 398' bgs, and a well was installed on March16, 2001. Development is on going due to slow recharge rate. Current water level is at388' bgs.

MW-8B: This boring has been advanced to 492' bgs, and a well has been installed.Development is on going due to slow recharge rate. Current water level is at 471' bgs.

PW-9A: This boring has been advanced to 535' bgs. A monitoring well has beeninstalled, and it was developed on March 1, 2001. Water has been measured at 449' bgs.

PW-9B: This boring has been advanced to 475' bgs. A monitoring well has beeninstalled and developed. Water has been measured at 449 bgs.

PW-10A: This boring is located in the North East Canyon, and has been advanced to 720'bgs. A monitoring well has been installed, developed, and sampled. Water has beenmeasured at 668' bgs.

PW-11 A: This boring has been advanced to 407' bgs, a monitoring well was installed,and it was developed on December 28, 2000. Water has been measured at 211' bgs.

MW-11C: This boring has been advanced to 828' bgs. A monitoring well has beeninstalled, and current water level is at 512' bgs.

PW-1 IB: This boring was advanced to 260' bgs, a monitoring well was installed, and itwas developed on November 29, 2000. Water has been measured at 192' bgs.

PW-12A: This boring has been advanced to 252.5'bgs. A well has been installed. Thismonitoring well was developed on December 7, 2000. Water has been measured at 200'bgs.

Page 40: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

PW-12B2: This boring has been advanced to 484' bgs. A well was installed on March29, 2001. As of April 24, 2001, this monitoring well has been developed and sampled.Current water level is at 176' bgs.

MW-12D: This boring has been advanced to 810' bgs. A monitoring well has beeninstalled and it is being developed. Current water level measurements indicate water at697' bgs.

PW-14A: This boring has been advanced to 226' bgs, a monitoring well was installed,and it was developed on January 9, 2001. Current water level is at 216' bgs.

Aug.2: The field work for the cover material evaluation is complete. A draft UNSAT-H reportwas submitted to EPA on October 17, 2000, and the backup laboratory testing resultswere submitted to EPA on November 11, 2000. EPA provided Republic with commentson the cover study on June 28, 2001. The correspondence indicates that Republic andEPA should meet to discuss the next step.

Aug.3: Republic provided EPA with a revised drilling plan for locations 7,13, and 15 on August8,2001.

Aug.4: Stormwater Pollution Prevention Plan (SWPPP): As discussed with EPA, Republicwould provide EPA with less formal submittals called "check points." The check pointsare designed to further guide the development of appropriate control measures for theStormwater run-on and run-off from the North East Canyon because this impacts thedevelopment of the SWPPP. Check point #1 was provided to EPA on July 11, 2001.

If you have any questions, please contact me at (702) 734-5400.

Respectfully,

Alan GAdflyVice Pt^sident

AG/tg

File#: 999901-062/Order 7484

Page 41: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

CC: Mr. David Basinger (WTR - 7) Water DivisionU.S. Environmental Protection Agency75 Hawthorne StreetSan Francisco, CA 94105 - 3901

Mr. Dave Emme, ChiefBureau of Waste ManagementNevada Division of Environmental Protection333 W. Nye Lane, Room 138Carson City, NV 89706-0851

Mr. Mark Morse, Field Manager(Attention: Mike Moran)Bureau of Land Management4765 Vegas DriveLas Vegas, NV 89108

Mr. John SchlegelClark County Comprehensive Plan.500 S. Grand Central PkyLas Vegas, NV 89155-1745

Mr. Clare SchmutzClark County Health District625 Shadow LaneLas Vegas, NV 89106

Ms. Sandy DotySAIC5303 W. Oberlin Dr.Denver, CO 80235

Page 42: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

REPUBLIC SERVICES770 East Sahara Avenue • P. O. Box 98508

Las Vegas, NV 89193-8508(702) 734-5400

September 14, 2001

Ms. Susanna Trujillo, Project CoordinatorU.S. EPA Region IX75 Hawthorne Street (WST-7)San Francisco, CA 94105-3901

Dear Ms. Trujillo:

RE: Monthly Progress Report - September, 2001Order RCRA 7003-09-99-0005NOV/Order CWA-3 09-9-99-14

As required by the above referenced RCRA Order, specifically VI number 3 (page 9 of 22), thefollowing is the monthly progress report. If you should require a copy of past monthly activities,please contact me. The progress report items are numbered with the first three letters of themonth. This month's items are as follows:

Current Monthly Progress ReportRepublic Services of Southern Nevada (RSSN) continues to make progress in completing thetasks outlined in the Work Plan. Currently, an air rotary (T4W) and a Schramm are drilling,setting casing and/or installing wells. A Smeal 5T is onsite for well development and sampling.

Aug. 1: The exploratory borings were started on March 13, 2000. The following is the status ofthese exploratory borings. It should be noted that when a monitoring well has beeninstalled, the prefix for the location designation changes from GH to MW, and when themonitoring well has been developed, the prefix will be changed to PW. This is reflectedbelow. Furthermore, when a boring has been classified as being "abandoned," this meansthe boring as been plugged with bentonite and sealed. Once a boring as been classified inthis progress report as being "abandoned," the boring will not be included in the nextmonths progress report. An * indicates that the status of this item has changed.

MW-1A: Stopped at 102 feet below ground surface (bgs) at bed rock contact, and amonitoring well has been installed. (No water has been detected in this monitoring wellsince installation).

* PW-1C: The sonic drill rig advanced this boring to 682' bgs. A well has been installed,and it was developed on January 31, 2001. Current water elevation is 1763.7.

1

Page 43: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

MW-2A: A 2-inch and a 4-inch monitoring well were installed in this borehole whichwas advanced to a total depth of 215 feet bgs. Current water level measurements indicatethat the 4-inch is dry and the 2-inch has a water elevation of 1688.93.

PW-2B: A 4-inch monitoring well has been installed in this boring which was advancedto a total depth of 215' bgs. Water elevation is at 1700.

PW-2C2: This boring was advanced to 263' bgs, and a 2-inch and 4-inch monitoringwell were installed. Water elevation for both wells is at approximately 1700.

PW-2D: This boring has been advanced to 808' bgs and a bentonite plug was placed upto 533' bgs. As of April 16, 2001, this monitoring well has been developed and sampled.Water elevation is at 1710.55.

PW-2D2: This boring was advanced to 440' bgs, and a well was installed. Water hasbeen measured at 207' bgs. As of March 21, 2001, this monitoring well has beendeveloped and sampled. Water level elevation is at 1714.76.

MW-2E: This boring has been advanced to 687 bgs. A well has been installed, and itneeds to be developed. Water level elevation is at 1239.79.

GH-2E2: This boring was drilled to 330' bgs, and while being advanced, communicationwith 2C2 was noticed. Air was coming out of 2C2. Drilling was stopped, and EPAcontacted. This boring was grouted up to the bottom of PW-2C2, and a well installed.This was done in order to save 2C2 if sloughing had occurred. The calculations indicatethat some sloughing did occurred above 265 bgs. Water level elevation is at 1709.91.

GH-2E3: This boring has been advanced to around 480' bgs into an apparent confiningunit. Geophysics was completed, and a packer test was attempted, but the packer burst.A transducer was placed in 2D2, and it is believed that this water bearing zone isconnected to the one in 2D2. The drill rig has moved off of this location to re-tool, andwill start advancement at location 13 according the approved drill plan for 7, 13, and 15.Republic will be evaluating all of the data obtained at location 2 and conducting tests inorder to determine the next step at this location.

GH-3C: Barber Rig has advanced this boring to 500' bgs at this location. A seal wasinstalled at this zone, but current data indicate that the seal was not installedappropriately. In a June 12, 2001, email to EPA, Republic has proposed a possiblesolution to this problem.

PW-4A: This boring was advanced to 295 feet bgs, and a monitoring well installed, andit was developed on January 26, 2001. Water elevation is at 1679.

PW-4B: This boring has been advanced to 802' bgs. A monitoring well was installed, and2

Page 44: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

it was developed on January 26, 2001. Water elevation is at 1699.

PW-4C: This boring is currently at 470' bgs. A well was installed on March 14, 2001,and developed on May 9, 2001. Water level elevation is at 1693.

PW-5B4: This boring has been advanced to 733' bgs. A well has been installed anddeveloped. Water level elevation is at 1726.43.

PW-5C: This boring has been advanced to 154' bgs. Water level elevation is at 1753.43.A monitoring well has been installed, and the well was developed on December 6, 2000.

PW-6B: This boring has been advanced to 227' bgs. Water level elevation is at 1763.The monitoring well at this location was developed on January 10, 2001.

PW-6C: This boring has been advanced to 431' bgs, a monitoring well was installed, andit was developed on January 29, 2001. Water level elevation is at 1762.45.

MW-8A: This boring has been advanced to 398' bgs, and a well was installed on March16, 2001. Development is on going due to slow recharge rate. Water level elevation is at1768.

MW-8B: This boring has been advanced to 492' bgs, and a well has been installed.Development is on going due to slow recharge rate. Water level elevation is at 1693.31.

PW-9A: This boring has been advanced to 535' bgs. A monitoring well has beeninstalled, and it was developed on March 1, 2001. Water level elevation is at 1765.

PW-9B: This boring has been advanced to 475' bgs. A monitoring well has beeninstalled and developed. Water level elevation is at 1765.

PW-10A: This boring is located in the North East Canyon, and has been advanced to 720'bgs. A monitoring well has been installed, developed, and sampled. Water levelelevation is at 1761.

PW-11 A: This boring has been advanced to 407' bgs, a monitoring well was installed,and it was developed on December 28, 2000. Water level elevation is at 1692.

PW-1 IB: This boring was advanced to 260' bgs, a monitoring well was installed, and itwas developed on November 29, 2000. Water level elevation is at 1677.86.

MW-11C: This boring has been advanced to 828' bgs. A monitoring well has beeninstalled, and the water level elevation is at 1211.67.

Page 45: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

* PW-12A: This boring has been advanced to 252.5'bgs. A well has been installed. Thismonitoring well was developed on December 7, 2000. Water level elevation is at1680.47.

* PW-12B2: This boring has been advanced to 484'bgs. A well was installed on March29, 2001. As of April 24, 2001, this monitoring well has been developed and sampled.Water level elevation is at 1719.38.

* MW-12D: This boring has been advanced to 810' bgs. A monitoring well has beeninstalled and it is being developed. Water level elevation is at 1532.

* PW-14A: This boring has been advanced to 226' bgs, a monitoring well was installed,and it was developed on January 9, 2001. Water level elevation is at 1694.46.

* Location 16: At the direction of EPA, two borings were advanced through trash with a36" bucket auger rig. Seals were set at least 10' into the base material under the trash.Water was encountered at 16A at approximately 231 bgs. The boring was advanced to anapparent confining zone at 287' bgs. Geophysics has been completed, and the boring isbeing reamed. Republic is evaluating the data to determine the appropriate wellscreening.

Sep.2: The field work for the cover material evaluation is complete. A draft UNSAT-H reportwas submitted to EPA on October 17, 2000, and the backup laboratory testing resultswere submitted to EPA on November 11, 2000. EPA provided Republic with commentson the cover study on June 28, 2001. The correspondence indicates that Republic andEPA should meet to discuss the next step.

Sep.3: Republic has provided EPA with "Geo-hydro Data Logs," an updated groundwateranalytical file, and completed Schoeller Plots.

Sept.4: Stormwater Pollution Prevention Plan (SWPPP): As discussed with EPA, Republicwould provide EPA with less formal submittals called "check points." The check pointsare designed to further guide the development of appropriate control measures for theStormwater run-on and run-off from the North East Canyon because this impacts thedevelopment of the SWPPP. Check point #1 was provided to EPA on July 11, 2001.

Page 46: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

If you have any questions, please contact me at (702) 734-5400.

Respectfully,

AlanVice Present

AG/tg

File#: 999901-062/Order 7484

CC: Mr. David Basinger (WTR - 7) Water DivisionU.S. Environmental Protection Agency75 Hawthorne StreetSan Francisco, CA 94105 - 3901

Mr. Dave Emme, ChiefBureau of Waste ManagementNevada Division of Environmental Protection333 W. Nye Lane, Room 138Carson City, NV 89706-0851

Mr. Mark Morse, Field Manager(Attention: Mike Moran)Bureau of Land Management4765 Vegas DriveLas Vegas, NV 89108

Mr. John SchlegelClark County Comprehensive Plan.500 S. Grand Central PkyLas Vegas, NV 89155-1745

Mr. Clare SchmutzClark County Health District625 Shadow LaneLas Vegas, NV 89106

Ms. Sandy DotySAIC5303 W. Oberlin Dr.Denver, CO 80235

Page 47: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

October 13,2001

Ms. Susanna Trujillo, Project CoordinatorU.S EPA Region IX75 Hawthorne Street (WST-7)San Francisco, CA 94105-3901

D.-;ar Ms. Trujillo:

RE: Monthly Progress Report - October, 2001Order RCRA 7003-09-99-0005NOV/Order CWA-3 09-9-99-14

As required by the above referenced RCRA Order, specifically VI number 3 (page 9 of 22). thefollowing is the monthly progress report. If you should require a copy of past monthly actn ;tiesplease contact me. The progress report items are numbered with the first three letters of themonth. This month's items are as follows:

Current Monthly Progress ReportRepublic Services of Southern Nevada (RSSN) continues to make progress in completing thetasks outlined in the Work Plan. Currently, an air rotary (T4W) and a Schramm are drilling,setting casing and/or installing wells. A Smeal 5T is onsite for well development and sampling

Oct.l: The exploratory borings were started on March 13, 2000. The following is the status ofthese exploratory borings. It should be noted that when a monitoring well has beeninstalled, the prefix for the location designation changes from GH to MW, and when themonitoring well has been developed, the prefix will be changed to PW, This is reflectedbelow. Furthermore, when a boring has been classified as being "abandoned," this meansthe boring as been plugged with bentonite and sealed. Once a boring as been classified inthis progress report as being "abandoned," the boring will not be included in the nextmonths progress report. An * indicates that the status of this item has changed.

i

MW-1 A: Stopped at 102 feet below ground surface (bgs) at bed rock contact, and amonitoring well has been installed. (No water has been detected in this monitoring \\ ellsince installation).

PW-1 C: The sonic drill rig advanced this boring to 6S2' bgs. A well has been installed,and it was developed on January 31, 2001. Current water eleyation is 1763.7.

1

770 East Sahara Avenue • Las Vegas, NV 89104 • Telephone (702) 735-5151 • Fax: (7O2) 369-2206

Page 48: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

MW-2A: A 2-inch and a 4-inch monitoring well were installed in this borehole whichwas advanced to a total depth of 215 feet bgs. Current water level measurements indicatethat the 4-inch is dry and the 2-inch has a water elevation of 1691.

PW-2B: A 4-inch monitoring well has been installed in this boring which was advancedto a total depth of 215' bgs. Water elevation is at 1692.

PW-2C2: This boring was advanced to 263' bgs, and a 2-inch and 4-inch monitoringwell were installed. Water elevation for both wells is at approximately 1698.

PW-2D: This boring has been advanced to 808' bgs and a bentonite plug was placed upto 533' bgs. As of April 16, 2001, this monitoring well has been developed and sampled.Water elevation is at 1599.

PW-2D2: This boring was advanced to 440' bgs, and a well was installed. Water hasbeen measured at 207' bgs. As of March 21, 2001, this monitoring well has beendeveloped and sampled. Water level elevation is at 1709.

MW-2E: This boring has been advanced to 687 bgs. A well has been installed, and itneeds to be developed. Water level elevation is at 1256.

MW-2E2: This boring was drilled to 330' bgs, and while being advanced,communication with 2C2 was noticed. Air was coming out of 2C2. Drilling wasstopped, and EPA contacted. This boring was grouted up to the bottom of PW-2C2, anda well installed. This was done in order to save 2C2 if sloughing had occurred. Thecalculations indicate that some sloughing did occurred above 265 bgs. Water levelelevation is at 1699.

GH-2E3: This boring has been advanced to around 480' bgs into an apparent confiningunit. Geophysics was completed, and a packer test was attempted, but the packer burst.A transducer was placed in 2D2, and it is believed that this water bearing zone isconnected to the one in 2D2. The drill rig has moved off of this location to re-tool, andwill start advancement at location 13 according the approved drill plan for 7, 13, and 15.Republic will be evaluating all of the data obtained at location 2 and conducting tests inorder to determine the next step at this location. Water level elevation is at 1505 in theopen borehole.

GH-3C: Barber Rig has advanced this boring to 500' bgs at this location. A seal wasinstalled at this zone, but current data indicate that the seal was not installedappropriately. In a June 12, 2001, email to EPA, Republic has proposed a possiblesolution to this problem. Republic received approval for this proposal on September 28,2001, through step number 4.

PW-4A: This boring was advanced to 295 feet bgs, and a monitoring well installed, and2

Page 49: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

it was developed on January 26, 2001. Water elevation is at 1677.

PW-4B: This boring has been advanced to 802' bgs. A monitoring well was installed, andit was developed on January 26, 2001. Water elevation is at 1643.

PW-4C: This boring is currently at 470' bgs. A well was installed on March 14, 2001,and developed on May 9, 2001. Water level elevation is at 1439.

PW-5B4: This boring has been advanced to 733' bgs. A well has been installed anddeveloped. Water level elevation is at 1723.

PW-5C: This boring has been advanced to 154' bgs. Water level elevation is at 1753. Amonitoring well has been installed, and the well was developed on December 6, 2000.

PW-6B: This boring has been advanced to 227' bgs. Water level elevation is at 1763.The monitoring well at this location was developed on January 10, 2001.

PW-6C: This boring has been advanced to 431' bgs, a monitoring well was installed, andit was developed on January 29, 2001. Water level elevation is at 1762.45.

PW-8A: This boring has been advanced to 398' bgs, a well was installed, and it has beendeveloped. Water level elevation is at 1768.

MW-8B: This boring has been advanced to 492' bgs, and a well has been installed.Development is on going due to slow recharge rate. Water level elevation is at 1660.

PW-9A: This boring has been advanced to 535' bgs. A monitoring well has beeninstalled, and it was developed on March 1, 2001. Water level elevation is at 1765.

PW-9B: This boring has been advanced to 475' bgs. A monitoring well has beeninstalled and developed. Water level elevation is at 1765.

PW-10A: This boring is located in the North East Canyon, and has been advanced to 720'bgs. A monitoring well has been installed, developed, and sampled. Water levelelevation is at 1761.

PW-11 A: This boring has been advanced to 407' bgs, a monitoring well was installed,and it was developed on December 28, 2000. Water level elevation is at 1692.

PW-1 IB: This boring was advanced to 260' bgs, a monitoring well was installed, and itwas developed on November 29, 2000. Water level elevation is at 1696.

MW-11C: This boring has been advanced to 828' bgs. A monitoring well has beeninstalled, and the water level elevation is at 1249. Development is in progress.

Page 50: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

PW-12A: This boring has been advanced to 252.5' bgs. A well has been installed. Thismonitoring well was developed on December 7, 2000. Water level elevation is at 1680.

PW-12B2: This boring has been advanced to 484' bgs. A well was installed on March29, 2001. As of April 24, 2001, this monitoring well has been developed and sampled.Water level elevation is at 1670.

PW-12D: This boring has been advanced to 810' bgs. A monitoring well has beeninstalled and developed. Water level elevation is at 1590.

MW-13C: This boring has been advanced to 182' bgs, and a monitoring well has beeninstalled. Water level elevation is at 1712,

GH-13D: This boring is currently being reamed in order to seal off the water zoneencountered at 13C, and will be advanced to the next water bearing zone.

PW-14A: This boring has been advanced to 226' bgs, a monitoring well was installed,and it was developed on January 9, 2001. Water level elevation is at 1694.46.

MW-16A: This boring has been advanced to 287' bgs. A 2" and 4" monitoring wellinstalled. Water has been measured at 231 bgs. Water level elevation in both wells is at1754.

GH-16B: This boring is being reamed to seal off the water zone encountered in 16A, andwill be advanced to the second water bearing zone.

Oct.2: The field work for the cover material evaluation is complete. A draft UNSAT-H reportwas submitted to EPA on October 17, 2000, and the backup laboratory testing resultswere submitted to EPA on November 11, 2000. In a September 27, 2001,correspondence Republic provided EPA with a response to their June 28, 2001,comments on the draft cover evaluation.

Oct.3: As requested by EPA in a September 27, 2001, Republic continues to provide EPA withhydrogeologic data including groundwater samples as they are received.

Oct.4: Stormwater Pollution Prevention Plan (SWPPP): As discussed with EPA, Republicwould provide EPA with less formal submittals called "check points." The check pointsare designed to further guide the development of appropriate control measures for theStormwater run-on and run-off from the North East Canyon because this impacts thedevelopment of the SWPPP. Check point #2 was provided to EPA on October 8, 2001.

Page 51: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

If you have any questions, please contact me at (702) 734-5400.

Respectfully.

Alan yadflyVice President

AG/tg

File#: 999901-062/Order 7484

CC: Mr. David Basinger (WTR - 7) Water DivisionU.S. Environmental Protection Agency75 Hawthorne StreetSan Francisco, CA 94105 - 3901

Mr. Dave Emme, ChiefBureau of Waste ManagementNevada Division of Environmental Protection333 W. Nye Lane, Room 138Carson City, NV 89706-0851

Mr. Mark Morse, Field Manager(Attention: Mike Moran)Bureau of Land Management4765 Vegas DriveLas Vegas, NV 89108

Mr. John SchlegelClark County Comprehensive Plan.500 S. Grand Central PkyLas Vegas, NV 89155-1745

Mr. Clare SchmutzClark County Health District625 Shadow LaneLas Vegas, NV 89106

Ms. Sandy DotySAIC5303 W. Oberlin Dr.Denver, CO 80235

Page 52: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

November 14, 2001

Ms. Susanna Trujillo, Project CoordinatorU.S. EPA Region IX75 Hawthorne Street (WST-7)San Francisco, CA 94105-3901

Dear Ms. Trujillo:

RE: Monthly Progress Report - November, 2001Order RCRA 7003-09-99-0005NOV/Order CWA-3 09-9-99-14

As required by the above referenced RCRA Order, specifically V number 3 (page 9 of 22), thefollowing is the monthly progress report. If you should require a copy of past monthly actn Hies,please contact me. The progress report hems ar^ numberc .1 with ihc first three letters of themonth. Ehis'month's items are as follows:

Current Monthly Progress ReportRepublic Services of Southern Nevada (RSSN) continues to nuke- p~ngr>?ss in completing thetasks outlined in the Work Plan. Currently, an air rotary ( f4 W) nd a Schramm are drilling,setting casing and/or installing wells. A Smeal 5T is onsite for \\ ell development and sampling.Approximately 22087 feet have been drilled.

Nov.l: The exploratory borings were started on March 13, 2000. The following is the status ofthese exploratory borings. It should be noted that when a monitoring well has beeninstalled, the prefix for the location designation changes from GH to MW, and when themonitoring well has been developed, the prefix will be changed to PW. This is reflectedbelow. Furthermore, when a boring has been classified as being "abandoned," this meansthe boring as been plugged with bcntonite and sealed. Once a boring as been classified inthis progress report as being "abandoned," ihe boring will not be included in the nextmonths progress report. An * indicates that the status of this item has changed.

c

MW-1 A: Stopped at 102 feet below ground surface (bgs) at bed rock contact, and amonitoring well has been installed (No water has been detected in this monitoring wellsince installation).

PW-1C: The sonic drill rig advanced this boring to 682' bgs. A well has been installed,1

770 East Sahara Avenue • Las Vegas, NV 89104 • Telephone (702) 735-5151 • Fax: (702) 369-2206

Page 53: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

and it was developed on January 31, 2001. Current water elevation is 1763.7.

MW-2A: A 2-inch and a 4-inch monitoring well were installed in this borehole whichwas advanced to a total depth of 215 feet bgs. Current water level measurements indicatethat the 4-inch is dry and the 2-inch has a water elevation of 1688.93.

PW-2B: A 4-inch monitoring well has been installed in this boring which was advancedto a total depth of 215' bgs. Water elevation is at 1695.

PW-2C2: This boring was advanced to 263' bgs, and a 2-inch and 4-inch monitoringwell were installed. Water elevation for both wells is at approximately 1700.

PW-2D: This boring has been advanced to 808' bgs and a bentonite plug was placed upto 533' bgs. As of April 16, 2001, this monitoring well has been developed and sampled.Water elevation is at 1710.55.

PW-2D2: This boring was advanced to 440' bgs, and a well was installed. Water hasbeen measured at 207' bgs. As of March 21, 2001, this monitoring well has beendeveloped and sampled. Water level elevation is at 1710.

MW-2E: This boring has been advanced to 687 bgs. A well has been installed, anddevelopment is ongoing. Water level elevation is at 1239.79.

GH-2E2: This boring was drilled to 330' bgs, and while being advanced, communicationwith 2C2 was noticed. Air was coming out of 2C2. Drilling was stopped, and EPAcontacted. This boring was grouted up to the bottom of PW-2C2, and a well installed.This was done in order to save 2C2 if sloughing had occurred. The calculations indicatethat some sloughing did occurred above 265 bgs. Water level elevation is at 1700.

GH-2E3: This boring has been advanced to around 480' bgs into an apparent confiningunit. Geophysics was completed, and a packer test was attempted, but the packer burst.A transducer was placed in 2D2, and it is believed that this water bearing zone isconnected to the one in 2D2. The drill rig has moved off of this location to re-tool, andwill start advancement at location 13 according the approved drill plan for 7, 13, and 15.Republic will be evaluating all of the data obtained at location 2 and conducting tests inorder to determine the next step at this location. There have been a few transducerproblems that have prevented the completion of this evaluation. The problems have beencorrected. Water level elevation is at 1524.

GH-3C: Barber Rig has advanced this boring to 500' bgs at this location. A seal wasinstalled at this zone, but current data indicate that the seal was not installedappropriately. In a June 12, 2001, email to EPA, Republic has proposed a possiblesolution to this problem. In a September 28, 2001, email EPA approved Republic'sproposal through step number 4. Additional downhole geophysics has been completed.The geophysical data is being evaluated.

2

Page 54: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

PW-4A: This boring was advanced to 295 feet bgs, and a monitoring well installed, andit was developed on January 26, 2001. Water elevation is at 1679.

PW-4B: This boring has been advanced to 802' bgs. A monitoring well was installed, andit was developed on January 26, 2001. Water elevation is at 1669.

PW-4C: This boring is currently at 470' bgs. A well was installed on March 14, 2001,and developed on May 9, 2001. Water level elevation is at 1528.

PW-5B4: This boring has been advanced to 733' bgs. A well has been installed anddeveloped. Water level elevation is at 1726.43.

PW-5C: This boring has been advanced to 154' bgs. Water level elevation is at 1753.43.A monitoring well has been installed, and the well was developed on December 6, 2000.

PW-6B: This boring has been advanced to 227' bgs. Water level elevation is at 1763.The monitoring well at this location was developed on January 10, 2001.

PW-6C: This boring has been advanced to 431' bgs, a monitoring well was installed, andit was developed on January 29, 2001. Water level elevation is at 1762.45.

PW-8A: This boring has been advanced to 398' bgs, and a well was installed on March16, 2001. Development is complete, and water level elevation is at 1764.

MW-8B: This boring has been advanced to 492' bgs, and a well has been installed.Development is on going due to slow recharge rate. Water level elevation is at 1668.

PW-9A: This boring has been advanced to 535' bgs. A monitoring well has beeninstalled, and it was developed on March 1, 2001. Water level elevation is at 1765.

PW-9B: This boring has been advanced to 475' bgs. A monitoring well has beeninstalled and developed. Water level elevation is at 1765.

PW-10A: This boring is located in the North East Canyon, and has been advanced to 720'bgs. A monitoring well has been installed, developed, and sampled. Water levelelevation is at 1751.

PW-11 A: This boring has been advanced to 407' bgs, a monitoring well was installed,and it was developed on December 28, 2000. Water level elevation is at 1696.

PW-1 IB: This boring was advanced to 260' bgs, a monitoring well was installed, and itwas developed on November 29, 2000. Water level elevation is at 1697.

MW-11C: This boring has been advanced to 828' bgs. A monitoring well has been3

Page 55: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

installed, and the water level elevation is at 1155.

PW-12A: This boring has been advanced to 252.5' bgs. A well has been installed. Thismonitoring well was developed on December 7, 2000. Water level elevation is at1680.47.

PW-12B2: This boring has been advanced to 484' bgs. A well was installed on March29, 2001. As of April 24, 2001, this monitoring well has been developed and sampled.Water level elevation is at 1706.

PW-12D: This boring has been advanced to 810' bgs. A monitoring well has beeninstalled and developed. Water level elevation is at 1629.

PW-13C: This boring was advanced to 183' bgs. A monitoring well was installed, anddeveloped. Current water elevation is 1713.

MW-13D: This boring has been advanced to 283' bgs. The water chemistry, rechargerates, and water elevation all indicate that this is a separate water bearing zone than 13C.A well is in the process of being installed.

PW-14A: This boring has been advanced to 226' bgs, a monitoring well was installed,and it was developed on January 9, 2001. Water level elevation is at 1694.46.

GH-15B: This boring is in being advanced.

* Location 16: At the direction of EPA, two borings were advanced through trash with a36" bucket auger rig. Seals were set at least 10' into the base material under the trash.

* MW-16A: Water was encountered at 16A at approximately 231 bgs. The boring wasadvanced to an apparent confining zone at 287' bgs. A 4" and 2" monitoring well wereinstalled, and current water level in both monitoring wells is at 230' bgs.

* GH-16B: This boring has been advanced to 365'bgs. Water has been measured at 302'bgs. Groundwater samples have been obtained, and geophysics will be completed. Oncethe data is obtained, it will be analyzed to determine if this is a different water bearingzone than MW-16A.

Nov.2: The field work for the cover material evaluation is complete. A draft UNSAT-H reportwas submitted to EPA on October 17, 2000, and the backup laboratory testing resultswere submitted to EPA on November 11, 2000. EPA provided Republic with commentson the cover study on June 28, 2001, Republic responded with a clarificationcorrespondence on September 27, 2001, and EPA responded to this on October 23, 2001.An extension until November 26, 2001, has been approved for submittal of this CoverReport.

4

Page 56: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

Nov.3: Republic has provided EPA with "Geo-hydro Data Logs," an updated groundwateranalytical file, and completed Schoeller Plots. A QA/QC report on 10% of the lithologylogs will be provided to EPA by November 23, 2001.

Nov.4: Stormwater Pollution Prevention Plan (SWPPP): As discussed with EPA, Republicwould provide EPA with less formal submittals called "check points." The check pointsare designed to further guide the development of appropriate control measures for theStormwater run-on and run-off from the North East Canyon because this impacts thedevelopment of the SWPPP. Check point #1 was provided to EPA on July 11, 2001, andCheck point #2 was provided to EPA on October 5, 2001,

Nov.5: A Final Slope Stability Report was provided to EPA on November 14, 2001.

If you have any questions, please contact me at (702) 734-5400.

Alan GaddyVice President

AG/tg

File#: 999901 -062/Order 7484

CC: Mr. David Basinger (WTR - 7) Water DivisionU.S. Environmental Protection Agency75 Hawthorne StreetSan Francisco, CA 94105 - 3901

Mr. Dave Emme, ChiefBureau of Waste ManagementNevada Division of Environmental Protection333 W. Nye Lane, Room 138Carson City, NV 89706-0851

Mr. Mark Morse, Field Manager(Attention: Mike Moran)Bureau of Land Management4765 Vegas DriveLas Vegas, NV 89108

Mr. John SchlegelClark County Comprehensive Plan.500 S. Grand Central PkyLas Vegas, NV 89155-1745

Page 57: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

Mr. Clare Schmutz Ms. Sandy DotyClark County Health District SAIC625 Shadow Lane 5303 W. Oberlin Dr.Las Vegas, NV 89106 Denver, CO 80235

Page 58: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

December 14, 2001

Ms. Susanna Trujillo, Project CoordinatorU.S. EPA Region IX75 Hawthorne Street (WST-7)San Francisco, CA 94105-3901

Dear Ms. Trujillo:

RE: Monthly Progress Report - December, 2001Order RCRA 7003-09-99-0005NOV/Order CWA-309-9-99-14

As required by the above referenced RCRA Order, specifically VI number 3 (page 9 of 22), thefollowing is the monthly progress report. If you should require a copy of past monthly activities,please contact me. The progress report items are numbered with rhe first three letters of themonth. This month's items are as follows:

Current Monthly Progress ReportRepublic Services of Southern Nevada (RSSN) continues to make progress in completing thetasks outlined in the Work Plan. Currently, an air rotary (T4W) and a Schramm are drilling,setting casing and/or installing wells. A Smeal 5T is onsite for well development and sampling.Approximately 22087 feet have been drilled since March, 2000.

Dec.l: The exploratory borings were started on March 13, 2000. The following is the status ofthese exploratory borings. It should be noted that when a monitoring well has beeninstalled, the prefix for the location designation changes from GH to MW, and when themonitoring well has been developed, the prefix will be changed to PW. This is reflectedbelow. Furthermore, when a boring has been classified as being "abandoned," this meansthe boring as been plugged with bentonite and sealed. Once a boring as been classified inthis progress report as being "abandoned," the boring will not be included in the nextmonths progress report. An * indicates that the status of this item has changed.

fi

MW-1 A: Stopped at 102 feet below ground surface (bgs) at bed rock contact, and amonitoring well has been installed. (No water has been detected in this monitoring wellsince installation).

PW-1C: The sonic drill rig advanced this boring to 682' bgs. A well has been installed.1

770 East Sahara Avenue • Las Vegas, NV 89104 • Telephone (702) 735-5151 • Fax: (702) 369-2206

Page 59: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

and it was developed on January 31, 2001. Current water elevation is 1763.7.

MW-2A: A 2-inch and a 4-inch monitoring well were installed in this borehole whichwas advanced to a total depth of 215 feet bgs. Current water level measurements indicatethat the 4-inch is dry and the 2-inch has a water elevation of 1688.93.

PW-2B: A 4-inch monitoring well has been installed in this boring which was advancedto a total depth of 215' bgs. Water elevation is at 1695.

PW-2C2: This boring was advanced to 263' bgs, and a 2-inch and 4-inch monitoringwell were installed. Water elevation for both wells is at approximately 1700.

PW-2D: This boring has been advanced to 808' bgs and a bentonite plug was placed upto 533' bgs. As of April 16, 2001, this monitoring well has been developed and sampled.Water elevation is at 1710.55.

PW-2D2: This boring was advanced to 440' bgs, and a well was installed. Water hasbeen measured at 207' bgs. As of March 21, 2001, this monitoring well has beendeveloped and sampled. Water level elevation is at 1710.

MW-2E: This boring has been advanced to 687 bgs. A well has been installed, anddevelopment is ongoing. Water level elevation is at 1281.

GH-2E2: This boring was drilled to 330' bgs, and while being advanced, communicationwith 2C2 was noticed. Air was coming out of 2C2. Drilling was stopped, and EPAcontacted. This boring was grouted up to the bottom of PW-2C2, and a well installed.This was done in order to save 2C2 if sloughing had occurred. The calculations indicatethat some sloughing did occurred above 265 bgs. Water level elevation is at 1700.

GH-2E3: This boring has been advanced to around 480' bgs into an apparent confiningunit. Geophysics was completed, and a packer test was attempted, but the packer burst.A transducer was placed in 2D2, and it is believed that this water bearing zone isconnected to the one in 2D2. The drill rig has moved off of this location to re-tool, andwill start advancement at location 13 according the approved drill plan for 7, 13, and 15.Republic will be evaluating all of the data obtained at location 2 and conducting tests inorder to determine the next step at this location. There have been a few transducerproblems that have prevented the completion of this evaluation. The problems have beencorrected. Water level elevation is at 1580.

GH-3C: Barber Rig has advanced this boring to 500' bgs at this location. A seal wasinstalled at this zone, but current data indicate that the seal was not installedappropriately. In a June 12, 2001, email to EPA, Republic has proposed a possiblesolution to this problem. In a September 28, 2001, email EPA approved Republic'sproposal through step number 4. Additional downhole geophysics has been completed.The geophysical data is being evaluated, and Layne will attempt to perforate the casing.

2

Page 60: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

PW-4A: This boring was advanced to 295 feet bgs, and a monitoring well installed, andit was developed on January 26, 2001. Water elevation is at 1679.

PW-4B: This boring has been advanced to 802' bgs. A monitoring well was installed, andit was developed on January 26, 2001. Water elevation is at 1700.

PW-4C: This boring is currently at 470' bgs. A well was installed on March 14, 2001,and developed on May 9, 2001. Water level elevation is at 1586.

PW-5B4: This boring has been advanced to 733' bgs. A well has been installed anddeveloped. Water level elevation is at 1726.43.

PW-5C: This boring has been advanced to 154' bgs. Water level elevation is at 1753.43.A monitoring well has been installed, and the well was developed on December 6, 2000.

PW-6B: This boring has been advanced to 227' bgs. Water level elevation is at 1763.The monitoring well at this location was developed on January 10, 2001.

PW-6C: This boring has been advanced to 431' bgs, a monitoring well was installed, andit was developed on January 29, 2001. Water level elevation is at 1762.45.

PW-8A: This boring has been advanced to 398' bgs, and a well was installed on March16, 2001. Development is complete, and water level elevation is at 1764.

MW-8B: This boring has been advanced to 492' bgs, and a well has been installed.Development is on going due to slow recharge rate. Water level elevation is at 1668.

PW-9A: This boring has been advanced to 535' bgs. A monitoring well has beeninstalled, and it was developed on March 1, 2001. Water level elevation is at 1765.

PW-9B: This boring has been advanced to 475' bgs. A monitoring well has beeninstalled and developed. Water level elevation is at 1765.

PW-10A: This boring is located in the North East Canyon, and has been advanced to 720'bgs. A monitoring well has been installed, developed, and sampled. Water levelelevation is at 1761.

PW-11 A: This boring has been advanced to 407' bgs, a monitoring well was installed,and it was developed on December 28, 2000. Water level elevation is at 1696.

PW-1 IB: This boring was advanced to 260' bgs, a monitoring well was installed, and itwas developed on November 29, 2000. Water level elevation is at 1697.

PW-11C: This boring has been advanced to 828' bgs. A monitoring well has been3

Page 61: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

installed, developed, and sampled. The water level elevation is at 1190.

PW-12A: This boring has been advanced to 252.5' bgs. A well has been installed. Thismonitoring well was developed on December 7, 2000. Water level elevation is at1680.47.

PW-12B2: This boring has been advanced to 484' bgs. A well was installed on March29, 2001. As of April 24, 2001, this monitoring well has been developed and sampled.Water level elevation is at 1718.

PW-12D: This boring has been advanced to 810' bgs. A monitoring well has beeninstalled and developed. Water level elevation is at 1674.

PW-13C: This boring was advanced to 183' bgs. A monitoring well was installed, anddeveloped. Current water elevation is 1713.

MW-13D: This boring has been advanced to 283' bgs. The water chemistry, rechargerates, and water elevation all indicate that this is a separate water bearing zone than 13C.A well has been installed, and current water level elevation is at 1618.

PW-14A: This boring has been advanced to 226' bgs, a monitoring well was installed,and it was developed on January 9, 2001. Water level elevation is at 1694.46.

GH-15B: This boring has been advanced to 314' bgs, and a proposed monitoring wellinstallation will be forwarded to EPA based on the drill plan. Current water levelelevation is at 1633.

Location 16: At the direction of EPA, two borings were advanced through trash with a36" bucket auger rig. Seals were set at least 10' into the base material under the trash.

* MW-16A: Water was encountered at 16A at approximately 231 bgs. The boring wasadvanced to an apparent confining zone at 287' bgs. A 4" and 2" monitoring well wereinstalled, and current water elevation in both monitoring wells is 1764.

* GH-16B: This boring has been advanced to 365' bgs. Water has been measured at 304'bgs. Groundwater samples have been obtained, and geophysics will be completed. Thedata collected from this boring is not conclusive, therefore an approved temporary well isin the progress of being installed. Data will be collected from this temporary monitoringwell in order to determine if it is a different water bearing zone that 16A.

Dec. 2: The field work for the cover material evaluation is complete. A revised Cover Reportdated November 21, 2001, was provided to EPA based on EPA's comments.

Dec.3: Republic has provided EPA with a revised hydrogeologic schedule, and the 10% re-log4

Page 62: Monthly progress rpts (1/2001-12/2001) · RE: Monthly Progress Report - January, 2001 Order RCRA 7003-09-99-0005 NOV/Order CWA-309-9-99-14 As required by the above referenced RCRA

report in a November 29, 2001, correspondence.

Dec.4: Check point #2 was provided to EPA on October 5, 2001, and on November 20, 2001,Republic received EPA comments. Based on EPA's comments, Republic provided EPAwith a request for clarification dated December 6, 2001. Based on this request, EPA'scorrespondence dated December 10, 2001, and Republic correspondence of December 112001, a meeting is being scheduled as soon as possible at Sunrise.

If you have any questions, please contact me at (702) 734-5400.

Respectfully,

AVice Preside:

AG/tg

File#: 999901-062/Order 7484

CC: Mr. David Basinger (WTR - 7) Water DivisionU.S. Environmental Protection Agency75 Hawthorne StreetSan Francisco, CA 94105 - 3901

Mr. Dave Emme, ChiefBureau of Waste ManagementNevada Division of Environmental Protection333 W. Nye Lane, Room 138Carson City, NV 89706-0851

Mr. Mark Morse, Field Manager(Attention: Mike Moran)Bureau of Land Management4765 Vegas DriveLas Vegas, NV 89108

Mr. John SchlegelClark County Comprehensive Plan.500 S. Grand Central PkyLas Vegas, NV 89155-1745

Mr. Clare SchmutzClark County Health District625 Shadow LaneLas Vegas, NV 89106

Ms. Sandy DotySAIC5303 W. Oberlin Dr.Denver, CO 80235