By M.V. RadhakrishnanANSALDOCALDAIE Boilers India Private Limited,
Conference – ENERGEX 2008 Date : 26-09-2008
3 Nos. 660 MW – coal fired Supercritical
INTRODUCTION
ANSALDO CALDAIE with consortium of Hitachi was awarded the boiler contract on 1 Dec 2004
Torrevaldaliga North- Power Station
CUSTOMER : ENEL POWERCONTRACT : LSTK
OVERVIEW OF HISTORY
Total gross electric power (Mwe) : 2,640 Net efficiency 39% SH outlet temp. 540°C RH outlet temp. 540°C SH outlet pressure 253 bar Fuel oil with 0.23% sulphur content Flue gas treatment
FGD NOSCR YES Filters electrostatic YES
Emission limits
SO2 mg/Nm3 guaranteed (Monthly average) 400NOx mg/Nm3 guaranteed (Monthly average) 200Dust mg/Nm3 guaranteed (Monthly average) 50
Source : ENEL data
4 X 660 MW oil fired supercritical units
Start-up between 1984 and 1986
OVERVIEW OF HISTORY
DRIVING FACTORS FOR CONVERSION
FUEL COST BEING HIGHER
LIFE OF PLANT EXAHUSTED
PRESENT STRINGENT EMISSION NORMS
REDUCTION OF GENERATION COST
KEY CHALLANGES
MEETING EU NEW EMISSION NORMS
UTILIZING SOME OF EXISTING PLANT HARDWARES
WIDE VARIETY OF COALS ##
SPACE CONSTRAINTS FOR STORAGE,ERECTION
## To maximize the usage of geographical location of plant near port
FEATURES OF NEW BOILER
Divided back pass with biasing dampers for RH outlet temp control
Spiral-wound waterwall tubes
Even heat absorption uniform water temp
distribution at outlet; Adequate mass velocity adequate margins against
DNB occurrence; Flow stability; Moderate pressure drop.
Start up and low load system Separators Water collecting vessel Recirculation pump Lower start up heat loss Ensures adequate cooling flow at
low load (below BENSON load)
FEATURES OF NEW BOILER
Boiler Parameters :
Unit type : Super Critical
SHO flow : 1918 t/h
SHO temp : 604 deg c
SHO pr : 252 bar
FW temp: 313 deg c
RH in / out : 370 / 612 deg c
RH flow : 1576 t/h
RH pr. : 58 bar
Furnace type : Balanced draft
Water wall : Spiral / Ribbed
Size : 22.5 m x 14.2 m
SH / RH stages : 3 / 2
SH temp control : Spray attemp.
RH temp control : Gas biasing
Economiser : Fin tubes
Fuel :
Design Fuel : COAL (South African)
Characteristics : HHV 26.4MJ/kg, Ash 13.6 %, Moisture 7.4 %
Start-up fuel : Natural Gas
Source of coal : Indonesia, Australia,South America,Poland, China
FEATURES OF NEW BOILER
Boiler Aux:
Mills : 5+1 (with rotary classifierBurners : Opposed wall - Low Nox
with OFAFans : 2 FD(axial)
2 PA(Radial) 2 ID (existing)
AH : 2 Nos. Tri-sector Lungstrom type
SB : Wall blowers Retractable for conv. Pass.(Medium : Air / SH steam)
SCR :
Outlet Nox : < 85 mg/Nm^3 (6% O2)
Catalyst type : Plate (can accommodate Honey comb also)
Reactor : Vertical downflow
Start-up philosophy:
At start-up & below 25 % load, steam water mixture is separated in the separator vessel & water flowing back to storage tank is re-circulated in economiser & furnace tubes by re-circulation pump.
Dismantling of existing oil fired boilers, SCR & precipitators
Installation of new boilers & relating auxiliaries , critical piping
Installation of new SCR systems
Installation of new FGD systems (By Owner)
Installation of sleeve filters (By Owner)
Installation of new ash removal systems (Fly ash by owner)
Installation of closed remote controlled coal bunkers
Construction of two docks
MAJOR CONTRACT ACTIVITIES
BOILER ISLAND SUPPLIES
BOILER PROPER (PR. PARTS AND START-UP SYSTEM)
STEEL STRUCTURES FOR BOILER, BUNKER BAY AND SCR
REGENERATIVE AIR HEATERS (trisector type)
FD FANS (axial type) and PA FANS (radial type)
COAL BUNKERS
COAL PULVERIZING AND FIRING SYSTEM
NATURAL GAS START-UP AND WARM-UP FIRING SYSTEM
SCR SYSTEM
BOTTOM ASH REMOVAL SYSTEM (DRY TYPE)
CRITICAL PIPING (from boiler headers to steel structures boundary)
PLANT PFD
PFD – TREATMENT
EmissionLimits according to
Italian lawTorrenord oil fired
units
European regulation for new plants(In force since
1/1/2008)
Limits as per authorization for
Torrenord coal fired plant
SO2mg/nm^3
400
200
100
Noxmg/nm^3
200
200
100
Dustmg/nm^3
50
30
15
A LOOK AT EU NORMS
Emissions reduced bySulphur oxide (SO2) - 82%
Nitric oxide (Nox) - 61%
Dust - 82%
BEFORE & AFTER CONVERSION
Source : Enel data
Before AfterGross power,MW 2640 1980Cycle Efficiency 39 % 45 %Fuel FO Coal
CONTRACT SCHEDULE MILESTONES MONTHS UNIT #1 PAC* 43 MONTHSUNIT #2 PAC 47 MONTHSUNIT #3 PAC 53 MONTHS
SCHEDULE BOILER WTS.
PR. PARTS 7000 T
NON. PR. PARTS 12000 T
TOTAL BOILER 26000 T
* Provisional Acceptance Certificate
CONSTRAINTS ENCOUNTERED
RAW MATERIALS FOR PR. PARTS PARTICULARLY HIGH ALLOY STEELS – T91, T92
MAIN STEEL STRUCTURAL COMPONENTS WITH HEAVY THICKNESS PLATES
COMPLEX AND COMPACT BOILER LAY-OUT DUE TO THE LIMITED SPACE
LIMITED MATERIAL STORAGE & PRE-ASSEMBLY AREAS
LIMITED SITE ROAD ACCESS
ERECTION CONSTRAINSTS DUE LACK OF ACCESS
PLANT TODAY