38
AFRICAN DEVELOPMENT BANK PROJECT: THE NEW PORT OF WALVIS BAY CONTAINER TERMINAL PROJECT COUNTRY: THE REPUBLIC OF NAMIBIA PROJECT APPRAISAL REPORT OITC DEPARTMENT July 2013 Appraisal Team Sector Director: Amadou Oumarou, Officer-In-Charge, OITC Regional Director: Ebrima Faal, SARC Sector Manager: Amadou Oumarou, OITC.2 Team Leader: Mam Tut Wadda-Senghore, OITC.2

Namibia - The New Port of Walvis Bay Container Terminal Project · PDF file · 2013-07-232.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ... International Importance,

  • Upload
    vongoc

  • View
    227

  • Download
    3

Embed Size (px)

Citation preview

Page 1: Namibia - The New Port of Walvis Bay Container Terminal Project · PDF file · 2013-07-232.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ... International Importance,

AFRICAN DEVELOPMENT BANK

PROJECT: THE NEW PORT OF WALVIS BAY CONTAINER

TERMINAL PROJECT

COUNTRY: THE REPUBLIC OF NAMIBIA

PROJECT APPRAISAL REPORT

OITC DEPARTMENT

July 2013

Appraisal

Team

Sector Director: Amadou Oumarou, Officer-In-Charge, OITC

Regional Director: Ebrima Faal, SARC

Sector Manager: Amadou Oumarou, OITC.2

Team Leader: Mam Tut Wadda-Senghore, OITC.2

Page 2: Namibia - The New Port of Walvis Bay Container Terminal Project · PDF file · 2013-07-232.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ... International Importance,

TABLE OF CONTENTS

Currency Equivalents ............................................................................................................................... i

Acronyms and Abbreviations ................................................................................................................... i

Loan Information ..................................................................................................................................... ii

Project Summary .................................................................................................................................... iii

Results Based Logical Framework ......................................................................................................... iv

Project Timeframe ................................................................................................................................... v

I - STRATEGIC THRUST & RATIONALE ....................................................................................... 1

1.1 PROJECT BACKGROUND ............................................................................................................. 1

1.2 PROJECT LINKAGES WITH COUNTRY STRATEGY AND OBJECTIVES ............................................. 2

1.3 RATIONALE FOR BANK’S INVOLVEMENT ................................................................................... 2

1.4 DONORS COORDINATION ............................................................................................................ 3

II - PROJECT DESCRIPTION ............................................................................................................. 4

2.1 PROJECT DEVELOPMENT OBJECTIVES ......................................................................................... 4

2.2 PROJECT DESCRIPTION AND COMPONENTS ................................................................................. 4

2.3 TECHNICAL SOLUTION RETAINED AND OTHER ALTERNATIVES EXPLORED ................................ 4

2.4 PROJECT TYPE ............................................................................................................................. 5

2.5 PROJECT COST AND FINANCING ARRANGEMENTS ...................................................................... 5

2.6 PROJECT’S TARGET AREA AND BENEFICIARIES .......................................................................... 7

2.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION .................................. 7

2.8 BANK GROUP EXPERIENCE, LESSONS REFLECTED IN PROJECT DESIGN ...................................... 8

2.9 KEY PERFORMANCE INDICATORS ............................................................................................... 8

III - PROJECT FEASIBILITY ............................................................................................................... 8

3.1 ECONOMIC AND FINANCIAL PERFORMANCE ............................................................................... 8

3.2 ENVIRONMENTAL AND SOCIAL IMPACTS ................................................................................. 11

IV - IMPLEMENTATION ................................................................................................................... 12

4.1 IMPLEMENTATION ARRANGEMENTS ......................................................................................... 12

4.2 MONITORING ............................................................................................................................ 15

4.3 GOVERNANCE ........................................................................................................................... 16

4.4 SUSTAINABILITY ....................................................................................................................... 16

4.5 RISK MANAGEMENT.................................................................................................................. 17

4.6 KNOWLEDGE BUILDING ............................................................................................................ 17

V - LEGAL INSTRUMENTS AND AUTHORITY ........................................................................... 18

5.1 LEGAL INSTRUMENT ................................................................................................................. 18

5.2 CONDITIONS ASSOCIATED WITH BANK’S INTERVENTION ........................................................ 18

5.3 COMPLIANCE WITH BANK POLICIES ......................................................................................... 19

VI - RECOMMENDATION ................................................................................................................. 19

Appendix I. Country’s Comparative Socio-Economic Indicators

Appendix II. Table of ADB’s Portfolio in the Country

Appendix III. Key Projects Financed by the Bank and other DP in the Country

Appendix IV. Map of the Project Area

Page 3: Namibia - The New Port of Walvis Bay Container Terminal Project · PDF file · 2013-07-232.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ... International Importance,

Currency Equivalents March 2013

1.00 UA = ZAR 13.5555

NAD 1.00 = ZAR 1.00

Fiscal Year 01 April – 31

March

Weights and Measures 1metric tonne = 2204 pounds (lbs)

1 kilogramme (kg) = 2.200 lbs

1 metre (m) = 3.28 feet (ft)

1 millimetre (mm) = 0.03937 inch (“)

1 kilometre (km) = 0.62 mile

1 hectare (ha) = 2.471 acres

Acronyms and Abbreviations

AfDB African Development Bank

B/C Benefits to Cost Ratio

CSP Country Strategy Paper

DFI Development Finance Institution

DRC Democratic Republic of the Congo

EIRR Economic Internal Rate of Return

E&S Environmental & Social

ESIA Environmental and Social Impact

Assessment

ESMP Environmental and Social Management

Plan

EPC Engineering Procurement Construction

EPZ Export Processing Zone

FIATA International Federation of Freight

Forwarders Associations

FIDIC International Federation of Consulting

Engineers

FIRR Financial Internal Rate of Return

GDP Gross Domestic Product

GON Government of Namibia

HSE Health, Safety and Environment

IRR Internal Rate of Return

JAR Joint Annual Review

JIBAR Johannesburg Interbank Agreed Rate

JICA Japan International Cooperation Agency

ICB International Competitive Bid

KfW Kreditanstalt fur Wiederaufbau

MIC Middle Income Country

NAD /N$ Namibian Dollar

Namport Namibia Ports Authority

NDP National Development Plan

NPV Net Present Value

PCR Project Completion Report

PESC Project Executive Steering

Committee

PIC Project Implementation Committee

PIDA Programme for Infrastructure

Development in Africa

PIU Project Implementation Unit

PPP Public-Private Partnership

QGC Quay Gantry Crane

RAMSAR Convention on Wetlands of

International Importance, especially

as Waterfowl Habitat

RTG Rubber Tyred Gantry Crane

SACU South African Customs Unit

SADC Southern African Development

Community

STS Ship to Shore Cranes

SWAp Sector-Wide Approach

TEU Twenty-foot Equivalent Unit

TIPEEG Targeted Intervention Programme

for Employment and Economic

Growth

US$ United States Dollar

UA Unit of Account

WBCG Walvis Bay Corridor Group

WBNLD CMC Walvis Bay Ndola Lubumbashi

Development Management

Committee

ZAR South African Rand (currency)

Page 4: Namibia - The New Port of Walvis Bay Container Terminal Project · PDF file · 2013-07-232.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ... International Importance,

ii

LOAN INFORMATION

Client’s information

BORROWER: Namibian Ports Authority (Namport), with Sovereign Guarantee

from the Republic of Namibia

PROJECT NAME: The New Port of Walvis Bay Container Terminal Project

LOCATION: Walvis Bay, Namibia

EXECUTING AGENCY: Namibia Ports Authority (Namport)

Financing plan

ADB’s key financing information

Financing Details Loan Grant

Loan currency South African Rand (ZAR) UA

Loan Type Enhanced Variable Spread Loan MIC TA Grant

Lending Rate Base Rate + Funding Cost Margin +

Lending Spread NA

Base Rate Floating Base rate based on 3 month Jibar

with free option to fix the Base rate. NA

Funding Cost Margin *1 NA

Lending Spread 60 basis points (0.60%) NA

Commitment fee* N/A NA

Other fees* N/A NA

Repayment Semi-Annual NA

Tenor Up to 20 years NA

Grace period Up to 5 years NA

FIRR, NPV (base case) 15%, NAD216 million

EIRR (base case) 14.6%

Timeframe - Main Milestones (expected)

Concept Note approval March 2013

Project approval July 2013

Effectiveness January 2014

Completion June 2019

Grant closing date December 2017

Last Disbursement (loan) December 2019

First Repayment (loan) August 2019

Last repayment August 2033

1 The six-month adjusted average of the difference between (i) the refinancing rate of the Bank as to the

borrowings linked to 3-month JIBAR and allocated to all its floating interest loans denominated in ZAR and (ii)

3-month JIBAR ending on 30 June and on 31 December. This spread shall apply to 3-month JIBAR which resets

on 1 February, 1 May, 1 August and 1 November. The Funding Cost Margin shall be determined twice per year

on 1 July for the semester ending on 30 June and on 1 January for the semester ending on 31 December.

Source Amount (ZAR) Amount (UA) Instrument

ADB loan 2,982 million (87.2%) 219.91 million Project Loan

ADB MIC TA Grant 14.00 million (0.4%) 1.00 million Technical Assistance

Namport 173 million (5.1%) 12.77 million Counterpart Funding

Government Grant 250 million (7.3%) 18.44 million Counterpart Funding

TOTAL COST 3,419.00 million 252.12 million

Page 5: Namibia - The New Port of Walvis Bay Container Terminal Project · PDF file · 2013-07-232.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ... International Importance,

iii

PROJECT SUMMARY

Project Overview

The Port of Walvis Bay is operated by the Namibian Port Authority (Namport) and serves as a

gateway linking some of southern Africa’s major trading regions to international markets. In

response to increased trade-related traffic volumes, Namport is embarking on an expansion

program to raise the container throughput capacity from 355,000 TEUs to 1,005,000 TEUs.

The project scope comprises the construction of a new container terminal on reclaimed land

from the Walvis Bay channel supported by complementary initiatives on logistics and

capacity building. The total project cost estimate is ZAR3,419 million (UA252.12 million),

with 87.6% financed by the Bank through an ADB Sovereign Guarantee Loan of ZAR2,982

million (UA219.91 million) and a MIC TA Grant of UA1.00 million (ZAR14 million). The

remaining 12.4% of the total project estimate, or ZAR423 million (UA31.21) will be financed

by Namport including a grant from the Government of Namibia of ZAR250 million (7.3%).

The project implementation is over a period of three (3) years. The expected project outcomes

include improved efficiency of the port and increase in cargo volumes as a result of increased

trade in the region, spurring inter regional trade and regional integration, private sector

development, employment creation and promotion of inclusion, economic growth and poverty

reduction. The project’s beneficiaries are extensive, ranging from the populations and

governments of Namibia and the SADC countries, the trade and logistics industry, consumers

and exporters at national, regional and international level.

Needs Assessment

The necessity to expand the container terminal at the Port of Walvis Bay arises from the

significant growth in freight traffic in recent years and increasing demand for port capacity

due to increasing economic activities and trade in the SADC region and in Africa in general.

This trend is expected to continue and Namibia aims to maximise its potential and strategic

location to become a trade hub for the region thereby enhancing trade and regional integration

and yielding high and sustained economic growth; alleviating poverty in the country and the

SADC region as a whole. The port is currently operating at capacity and timing and urgency

are of the essence to take advantage of the opportunities on offer before this is lost to

competing ports / countries in the region.

Bank’s Added Value

The rationale for the Bank’s involvement is multifaceted: i) the Bank is proactive in the

development of major regional trade corridors, and brings to the project a wealth of

experience, providing a holistic outlook and wider reach in connecting the continent’s key

infrastructure and missing links; ii) the Bank is assisting in the diversification and distribution

of port facilities on the southern-west coast of Africa and provides the much needed

alternative (to South African ports) for the SADC landlocked countries to access international

markets; iii) the project is potentially serving up to seven major economies in the SADC

region influencing increased inter-regional and international trade and related activities.

Through this project, the Bank is promoting regional integration, private sector development

and jobs creation leading to significant economic development in the SADC region.

Knowledge Management

The project provides an excellent opportunity for new skills to be developed both within the

Bank and in Namibia. Within the Bank, it is an opportunity to further strengthen its

knowledge on ports and regional integration which will feed into the Bank’s knowledge

series. In Namibia, the project provides opportunities for trainings, skills transfers and

capacity building which help to increase the skills base in the country, help create sustainable

employment and reduce poverty.

Page 6: Namibia - The New Port of Walvis Bay Container Terminal Project · PDF file · 2013-07-232.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ... International Importance,

iv

RESULTS BASED LOGICAL FRAMEWORK

Country and Project Name: Namibia – The Strategic Expansion of the Walvis Bay Container Terminal

Purpose of the Project: Establish the Port of Walvis Bay as the preferred African West coast port for southern and central African logistics operations

RESULTS CHAIN PERFORMANCE INDICATORS MEANS OF

VERIFICATION RISKS/MITIGATION MEASURES

Indicator Baseline Target

IMP

AC

T Improved economic

performance

Real GDP Growth

3.8% (2011) 5% - 6% (2020) African Economic

Outlook database Outcome Risks

i) Competing routes/ ports take over trade volumes;

ii) Government fails to implement its plans

iii) Regional logistics environment gets worse

Mitigation measures

i) sound strategies/ business plan; complementary

infrastructure; promote port and corridor use

ii) implement NDP4 action plan, develop and

implement logistics master plan.

iii) strengthen capacity on advocacy tackling regional

non-tariff barriers on corridors OU

TC

OM

ES

1.1 Improved efficiency of the

Port

1.2 Increased trade

1.3 Improved logistics

competence

1.1 i) Berthing moves per hour

(BMPH); ii) Vessel waiting time; iii)

Dwell time

1.2 Volume of containers handled

1.3 LPI: Logistics Performance Index

1.1 i) BMPH = 20; ii) 8

hours; iii) 14.5 days

average

1.2 334,000 TEU

1.3LPI = 2.65 out of 5

(89th out of 155

countries) (2012)

1.1 i) BMPH = 60; ii) less

than 8 hrs; iii) 8-10 days

average

1.2 70% growth TEU

1.3 LPI – at least 3.00/5

(2020)

Port Statistics

Corridor Group Data

World Bank Data

OU

TP

UT

S

Component A: New container

terminal constructed and STS

cranes installed and operational

Component B: RTG equipment

installed & operational

Component C: i) Pilots and

STS Operators trained for new

terminal and equipment; ii)

Nationals employed

Component D: i) Logistics

master plan study, ii) Road

Safety study, iii) Capacity

Building for WBNLD CMC

and WBCG completed,

iv)Freight forwarders trained

2.1 Size / capacity of new terminal and

No. of operational STS cranes

supplied

2.2 No. of operational RTG cranes

supplied

2.3 No. of Pilots and STS crane

operators trained;

2.4 No of Nationals employed in the

project

2.5 Logistics report

2.6 road safety action plan

2.7 Permanent Secretariat for Walvis

Bay-Ndola-Lubumbashi Corridor

established

2.8 No. of freight forwarders trained

2.1 TEU = 0; STS = 0

2.2 RTGs = 0

2.3 Pilots = 0, STS

Operators = 0,

2.4 Nationals = 0

2.5 Logistics report = 0

2.6 Permanent secretariat

= 0

2.7 Road safety action

pan = 0

2.8 Freight forwarders

trained = 0

(2012)

2.1 Capacity = 650,000

TEUs, STS cranes = 4

2.2 RTGs = 8

2.3 Pilots = 6, STS

Operators = 16

2.4 Nationals employed =

900 (including 300 women)

2.5 Logistics report = 1

2.6 Permanent secretariat

= 1

2.7 1 road safety action

plan = 1

2.8 freight forwarders

trained = 70 (40 women)

(2017)

Progress reports,

Bank supervision

reports,

Audit reports,

Midterm review

reports,

Namport quarterly

reports

Output Risks

i) Procurement delays and late project start up; ii)

Construction risks; iii) Environmental risks

Mitigation measures

i) Use of Advanced Contracting reduces procurement

delays; ii) Use of EPC fixed price lump-sum and

time certain contract plus effective project and risk

management mitigates against construction risks; iii)

Close supervision and effective implementation of

ESMP & E&S action plan mitigates against

environmental risks. (refer to section 4.5 for more

details)

KE

Y A

CT

IAV

ITIE

S

COMPONENTS INPUTS

Component A: Terminal construction

Component B: Equipment

Component C: Ancillary Activities

Component D: Logistics & Capacity Building

Costs ( UA million) ( ZAR million)

Terminal Construction 179.32 2,431.00

Equipment 12.84 174.00

Ancillary Activities 20.51 278.00

Logistics & Trade Facilitation 0.83 12.00

Base Cost 213.50 2,895.00 Physical Contingency (10%) 21.35 290.00

Price Contingency (2%FE, 5%LC) 17.27 234.00

Total 252.12 3,419.00

Sources of financing:

% UA million ZAR million

ADB loan [87.2%] 219.91 2,982.00

ADB MIC Grant [0.4%] 1.00 14.00

Namport [5.1%] 12.77 173.00

Government Grant [7.3%] 18.44 250.00

Total [100%] 252.12 3,419.00

Page 7: Namibia - The New Port of Walvis Bay Container Terminal Project · PDF file · 2013-07-232.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ... International Importance,

v

PROJECT TIMEFRAME

Page 8: Namibia - The New Port of Walvis Bay Container Terminal Project · PDF file · 2013-07-232.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ... International Importance,

1

REPORT AND RECOMMENDATION OF THE MANAGEMENT OF THE ADB GROUP

TO THE BOARD OF DIRECTORS ON A PROPOSED LOAN & GRANT TO NAMIBIAN

PORTS AUTHORITY (NAMPORT) FOR THE NEW PORT OF WALVIS BAY

CONTAINER TERMINAL PROJECT

Management submits the following Report and Recommendation on a proposed loan for ZAR

2,982 million (UA219.91 million) to the Namibian Ports Authority (Namport) to finance the

New Port of Walvis Bay Container Terminal Project in Namibia and a proposed MIC

Technical Assistance Fund Grant for UA1.00 million to the Republic of Namibia to finance

Logistics and Capacity Building activities complementing the Port Project.

I - STRATEGIC THRUST & RATIONALE

1.1 Project Background

1.1.1 Namibia is strategically located on the west coast of Southern Africa with 1,600km of

coastline on the Atlantic and bordering on the north, east and south with Angola, Zambia,

Botswana and South Africa respectively. The Ports of Walvis Bay and Lüderitz are Namibia’s

only ports with the former being Namibia’s main commercial port, located on the main

trading maritime corridor on the Atlantic. The Walvis Bay port is a sheltered deep-water

harbour protected by a natural bay and benefiting from a temperate climate with no delays due

to bad weather. The port has a designed container terminal capacity of 355,000 TEU and is

served by well maintained, safe and secure transit corridors providing fast and easy access to

the hinterland and neighbouring countries (see map in appendix iv). The port positions as

transhipment hub along the western African coastline and preferred access point into SADC

providing the shortest direct route to Europe and the Americas without the congestion delays

faced by competing ports in the region.

1.1.2 The Walvis Bay Port is operated and managed by a State Owned Enterprise (SOE) -

the Namibian Ports Authority (Namport) - under the “service port” model. Namport reports to

the Minister of Works and Transport as well as the State Owned Enterprises Governance

Council (SOEGC), which control its operations and port policies and regulations. As part of

ongoing reforms, Namport is investigating to further improve its efficiency by adopting the

“landlord port” model whereby the functions of the authority and operator are separated and

port operations are handled by a private entity.

1.1.3 The traffic at the Port of Walvis Bay and along its transport corridors has grown

significantly in the past few years. Cargo volumes almost doubled from 145,000 TEUs to

337,000TEUs between 2005 and 2012 with a record increase in revenue of N$755 million in

2012 (N$ 647 million in 2011), against a target of N$653 million. The increasing trade is

mainly in transit and transhipment which make the bulk of container traffic at the port.

Transshipment traffic has grown from 92,000 TEUs in 2006 to 218,000 TEUs in 2012 with an

average annual growth rate (AAGR) of 55%. Transit traffic has also grown over the same

period from 25,000 TEUs to 65,000TEUs with AAGR of 25%.

1.1.4 Namport’s strategy centers on adopting a hub and spoke distribution model for

transshipment serving the South, Central and West African coastline and a Gateway for transit

traffic for the SADC landlocked countries. To achieve this strategy and in order to sustain

future growth and attract new businesses, the expansion of the port and related facilities is

required. The port is currently operating at capacity and equipment use is at a maximum. It is

against this background that the Namibian Ports Authority submitted a request to the African

Development Bank to finance the expansion of the Walvis Bay container terminal to

accommodate additional 650,000 TEUs capacity.

Page 9: Namibia - The New Port of Walvis Bay Container Terminal Project · PDF file · 2013-07-232.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ... International Importance,

2

1.2 Project linkages with country strategy and objectives

1.2.1 The Walvis Bay port features as a regional hub in the SADC Regional Infrastructure

Development Master plan providing the region with the much needed west coast direct access

to regional and international markets and easing the exclusive dependence on the eastern ports

in South Africa, Mozambique and Tanzania. Namibia’s Vision 2030, the National Poverty

Reduction Action Plan and the National Development Plan (NDP 4) (2012/13 – 2016/17)

attributes considerable significance to the logistics and transport sector, geared towards

economic development and poverty reduction. This strategy is expanded in the transport

sector’s Integrated Transport Master Plan (2013-2023) and the Namport Business Plan 2013-

2017 (Corporate), of which this project is a priority, has been developed in the spirit of the

above national strategies.

1.2.2 The Southern African Development Community (SADC) is currently one of the

strongest RECs in Africa in terms of economic strength by country GDP. Economic growth

rates during the past few years averaged 5.9% making it one of the fastest growing developing

sub-regions with direct linkage to growth in trade. Total SADC trade almost quadrupled

between 2000 and 2011 from US$91,089.52 million in 2000, to US$353,636.4 million in

2011. Africa’s potential for growth is quite high and future freight demand is expected to

double by 2020 and increase by a factor of 6 by 2040. This corresponds to an average GDP

growth of 6% per year. Transit traffic from landlocked countries is expected to increase by

10-14 times over the next 30 years and for the SADC, this traffic will increase from 13

million to 148 million tons. This is a very large increase in demand and is the context and

rationale of the Namibian government’s efforts to maximise its potential and strategic location

to become a trade hub for the region. Timing and urgency are of essence in this regard, as

other countries within the region are also developing plans to take advantage of the

opportunities on offer.

1.2.3 One of the great opportunities for Namibia to be positioned as a logistics hub is its

strategic location within the SADC region, offering a gateway for trade. Secondly, Namibia’s

transport and communication infrastructure remains competitive in relation to what is

available in the region. Notwithstanding the developments of ports in the region, the Port of

Walvis Bay remains one of Africa’s most efficient and best equipped. Thirdly, safety and

security in the country also ensure that goods transported via road and rail, reach their

intended destinations without tampering. In addition to the facilitation of flows of imports,

exports and trans-shipments via Namibia, the availability of a good international logistics

network will also attract other industries to Namibia. Namibia’s business environment is

relatively conducive, thus logistics has the ability to create sustainable employment

opportunities, and contribute to economic prosperity and poverty reduction.

1.3 Rationale for Bank’s involvement

1.3.1 The port expansion project addresses three core operational priorities of the Bank’s

Ten Year Strategy (2013-2022). These are infrastructure development, regional integration

and private sector development.

i) Infrastructure development: the port of Walvis Bay is Namibia’s main commercial port

and links the country’s multimodal transport corridors to local, regional and

international markets. This project will bring a better distribution of port facilities on

the west coast of Africa and provides the much needed alternative (to South African

ports) for the SADC landlocked countries. It stimulates the development and upgrade of

multimodal transport corridors linking the port to the hinterland and to the SADC

region; improving the country’s transport and logistics chains, reducing transportation

costs and stimulating economic growth.

Page 10: Namibia - The New Port of Walvis Bay Container Terminal Project · PDF file · 2013-07-232.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ... International Importance,

3

ii) Regional integration: the project is potentially serving up to seven major economies

(Namibia, Angola, DRC, Zambia, Botswana, Zimbabwe and South Africa), each of

trade significance to the economy of the sub-Saharan sub-continent. One of the

rationales for the Bank’s involvement is geographical coverage of the economic

developmental impact that the project brings to the region through trade activities and

spill overs on business and jobs creation. The project also serves to foster South-South

cooperation, and provides the opportunity to strengthen commercial linkages and

promote new trading partners for the region.

iii) Private sector development: the spillover effects of this intervention are private sector

development and employment creation principally in the trade and logistics industry but

also in tourism. The project promotes the emergence of small to medium size

enterprises, scaling up of private investments, increasing productivity and

competitiveness, creation of employment opportunities and promotion of inclusion and

economic transformation.

1.3.2 Apart from the Bank’s ten year strategy, the project also aligns with the Southern

Africa Regional Integration Strategy Paper (RISP) 2011-2015 and the CSP 2009-2013,

through increased competitiveness and promoting intra and inter-regional trade. It is amongst

the PIDA priorities responding to Southern Africa’s challenge in developing sufficient port

capacity to handle future demand from both coastal and landlocked countries under the

Southern Africa Hub Port and Rail Programme.

1.4 Donors coordination

1.4.1 Donor coordination in Namibia is carried out at national and at sector level. At the

national level the National Planning Commission NPC (Director-General) co-chairs the

Annual High Level Development Partner Forum attended by Ministers of relevant Line

Ministries and representatives from Donors. At the sector level, sector working group

meetings are held bi-annually and key issues emanating from these discussions then feed into

the high level Forum. The Bank’s newly opened South Africa Resource Centre (SARC)

provides closer proximity to the Namibian clients and will permit stronger dialogue and Bank

presence in Namibia.

1.4.2 The World Bank and many of the UN Agencies scaled down their support to Namibia

following its classification as an upper MIC in 2009. Between 2008 and 2012, Germany

featured as the country’s largest donor (over N$2 billion), followed by the U.S. (NS$1.8

billion), China (N$1.6 billion), the European Commission (N$0.75 billion), Finland, Japan,

France (approximately N$0.5 billion each), the World Bank (N$0.1 billion) and others

including the African Development Bank (N$0.2 billion total).

1.4.3 In the roads subsector, the Government moved to Sector-Wide Approach (SWAp)

with the German Government and the European Union (EU) being the main partners. In

aviation, the Bank is providing support through a MIC TA Grant (UA0.59million) for a study

of 8 Namibian Airports including the main international airport. In maritime, financial support

has mainly come from the government and through loans from local commercial banks. The

German cooperation (KfW), JICA and the EIB have provided grants for various studies for

the Walvis Bay port expansion project. The Government allocates between 8% - 10% of the

national budget to the transport sector and over the Medium-Term Expenditure Framework

covering the period 2011/12-2013/14 allocated NAD8.2 billion for, among others:- expansion

of the port of Walvis Bay, rehabilitation and railway infrastructure management, and

development and maintenance of national roads infrastructure.

Page 11: Namibia - The New Port of Walvis Bay Container Terminal Project · PDF file · 2013-07-232.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ... International Importance,

4

II - PROJECT DESCRIPTION

2.1 Project development objectives

2.1.1 The sector goal of the project is to promote trade and regional integration. The

expected long-term impact of the project includes increased and sustained trade between

SADC and the outside world.

2.1.2 The objective of the project is to increase the capacity and efficiency of the Walvis

Bay Port to respond to the growing freight demand whilst promoting an alternative maritime

access on the Southwestern coast of Africa to serve the SADC landlocked countries. The

expected outcomes of the project include: improved port efficiency, increased cargo volumes,

improved logistics performance and increased inter-regional and international trade.

2.2 Project description and components

The project will expand the Walvis Bay port container terminal on reclaimed land

from the Walvis Bay channel, to increase the annual throughput capacity from 355,000TEUs

to 1,005,000TEUs. The Project will also include a logistics and capacity building component

to complement the port expansion project. The project components are presented in Table 2.1.

Table 2.1 : Project Components

Component (ZAR

Million)

(UA

Million) Component Description

A. New terminal

construction on

reclaimed land

2,871 211.75 Construction of a modern container terminal consisting of quay

walls, STS (ship-to-shore) cranes, paved areas, buildings, roads,

railway lines and services reticulation.

B. Equipment 206 15.15 Supply and installation of RTG (rubber tired gantry) cranes and

relocation of the existing from the current container terminal.

C. Ancillary

activities

328 24.22 Supply and installation of terminal operating system, communication

system, workstations, electricity supply upgrade, pilot and operator

trainings, etc. to complete the terminal expansion project

D. Logistics and

Capacity

Building

14 1.00 The component includes i) developing a national logistics master

plan, ii) a road safety program on transit corridors, iii) capacity

building for the Walvis Bay Corridor Group and the Walvis Bay-

Ndola-Lubumbashi Development Corridor Management Committee

and iv) a specialised training for freight forwarders (FIATA training)

Total Project

Cost 3,419 252.12

2.3 Technical solution retained and other alternatives explored

The technical solution retained was influenced by three determining factors: i) project

location, ii) contract type and iii) financing package. The solution retained was after series of

studies, investigations and consultations by Namport and its consultants. The solution retained

is a port expansion project located southwest of the current port terminal on reclaimed land

from the Walvis Bay channel. The project location allows fulltime works with minimal

disruption to normal operation and scope for future expansion. The contract type for the main

civil works is an EPC contract allowing an integrated solution, whilst the financing is an ADB

Sovereign Guarantee loan to Namport which responds to the urgency to implement the project

without any further delays. Private financing would have required the finalisation of the PPP

framework and reform of the port to transfer its operations to a private developer. This

solution was found to be technically, economically, financially and environmentally the most

sustainable. Table 2.2 summarises the alternatives explored and reasons for their rejection.

Page 12: Namibia - The New Port of Walvis Bay Container Terminal Project · PDF file · 2013-07-232.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ... International Importance,

5

Table 2.2 : Project Alternatives Considered and Reasons for Rejection

Alternative Brief Description Reasons For Rejection

Project location

Current

terminal

Extending the existing

container quays north-

eastwards

Limited length of quay extension

Significant impact on port operations and existing

factories

Enormous costs for expropriations and compensation

Little scope for future expansions

Fishing port

area

Developing a new

container terminal at the

fishing port area

Significant environment and social impacts on the

fishing business

Enormous costs for expropriations and compensation

Little scope for future expansions

Project contract

Traditional

Contracts

Procuring detailed

design and construction

separately

Significant risk exposure due to technical complexity

of the project

No overlap of design and construction

Lengthy process

Financing package

PPP – Full

concession

private sector–sponsored

project developing the

new container terminal

as a standalone business

unit

To privatize such a strategic national asset at this

point in time was seen not to be in the country’s best

interest

There is currently no PPP legal framework for port

projects in Namibia

Time to setup the legal framework is a lengthy

process; when the project is urgently needed

Possible backlash with labour organisation

2.4 Project type

The ADB financing will support the construction and rehabilitation of identified

economic and social infrastructure. The investments against which funds are to be disbursed

are well defined and specific. Therefore, the specific project loan has been chosen as the most

appropriate instrument for the intervention of the Bank in this port expansion project. In the

same regard, the MIC TA Grant has been determined to be the most appropriate instrument to

finance the logistics and capacity building activities.

2.5 Project cost and financing arrangements

2.5.1 The total project cost at appraisal (net of all taxes/duties) including physical and price

contingencies, is ZAR3,419 million (UA252.12 million) of which ZAR2,083 million

(UA153.63 million) or 61% of the total cost estimate is in foreign exchange and ZAR1,336

million (UA98.5 million) or 39% of the total cost estimate is in local currency.

2.5.2 The project cost estimates were based on feasibility studies conducted in 2010, by the

design consultants; taking into account international norms, prevailing rates and contract risk

distributions. The costs were updated in 2012 after series of supplementary studies conducted

to reconfirm the project’s feasibility. Also, during appraisal, the Mission and Namport

carefully reviewed and confirmed the quantities and unit rates of each project component and

included contingencies for execution and price escalation. The project components and costs

are presented in table 2.3.

Page 13: Namibia - The New Port of Walvis Bay Container Terminal Project · PDF file · 2013-07-232.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ... International Importance,

6

Table 2.3: Project costs by component (Net of Taxes)

Components

ZAR (million) UA (million) Foreign

Exchange

% Foreign

Exchange

Local

Currency Total

Foreign

Exchange

Local

Currency Total

A. New terminal

construction

1,487 944 2,431 109.71 69.61 179.32 61%

B. Equipment 154 20 174 11.36 1.48 12.84 89%

C. Ancillary activities 118 160 278 8.71 11.80 20.51 42%

D. Logistics & Capacity

Building 5 7 12 0.31 0.52 0.83 37%

Total Base Cost 1,764 1,131 2,895 130.10 83.41 213.50 61%

Physical contingencies 176 114 290 13.01 8.34 21.35

Price escalation 143 91 234 10.52 6.75 17.27

Total Project Cost 2,083 1,336 3,419 153.63 98.50 252.12 61%

2.5.3 The expansion of the port will be co-financed by the Bank, Namport and the

Government of Namibia. The Bank will finance 87.6% of the total project cost amounting to

ZAR 2,996 million or UA220.91 million. The Bank’s financing will be in the form of an ADB

Sovereign Guarantee Loan of ZAR 2,982 million (UA219.91 million) and MIC TA Grant of

UA1.00 million (ZAR14 million). Namport’s counterpart contribution is 12.4% of total

project cost estimate, comprising a grant from the Government of Namibia of ZAR250

million (UA18.44million) or 7.3% of total project cost estimate and Namport contribution of

ZAR173 million (UA12.77 million). Namport has indicated that there are other project

activities up to a total of ZAR300 million which will be financed by Namport. The source of

financing and the project expenditure schedule are summarised in table 2.4 and 2.5

respectively and justification of the Bank’s contribution of more than 50% of total project cost

estimate is provided in annex I.

Table 2.4: Sources of financing

Source

ZAR (million) UA (million) Total

Project

(%) Foreign

Exchange

Local

Currency Total

Foreign

Exchange

Local

Currency Total

ADB (Loan ) 1,839.00 1,143.00 2,982.00 135.60 84.31 219.91 87.2%

ADB (MIC Grant) 5.00 9.00 14.00 0.40 0.60 1.00 0.4%

Namport 98.16. 74.84 173.00 7.21 5.56 12.77 5.1%

Government Grant 141.84 108.16 250.00 10.42 8.02 18.44 7.3%

Total Project Cost 2,083.00 1,336.00 3,419.00 153.63 98.50 252.12 100%

Table 2.5: Source of financing by component

Components

ZAR (million) % Bank

contribution

% Namport

& GON

contribution Total

Cost

ADB

Loan

MIC TA

Grant

Namport

& GON

A. New terminal construction 2,431 2,236 - 195 92% 8%

B. Equipment 174 171 - 3 98% 2%

C. Ancillary activities 278 118 - 160 42% 58%

D. Logistics & Capacity Building 12 - 12 - 100% 0%

Total base cost 2,895 2,525 12 358 87.6% 12.4%

Physical contingencies 290 253 1 36

Price escalation 234 204 1 29

Total Project Cost 3,419 2,982 14 423 87.6% 12.4%

Page 14: Namibia - The New Port of Walvis Bay Container Terminal Project · PDF file · 2013-07-232.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ... International Importance,

7

Table 2.6: Project cost by category of expenditure

Category

ZAR (million) UA (million) % of

total base

cost Foreign

Exchange

Local

Currency Total

Foreign

Exchange

Local

Currency Total

Goods 191.00 59.00 250.00 14.06 4.33 18.39 9%

Works 1,487.00 1,031.00 2,518.00 109.71 76.04 185.75 87%

Services 86.00 41.00 127.00 6.33 3.03 9.36 4%

Total Base Cost 1,764.00 1,131.00 2,895.00 130.10 83.41 213.50 100%

Physical

contingencies 176.00 114.00 290.00 13.01 8.34 21.35 10%

Price escalation 143.00 91.00 234.00 10.52 6.75 17.27 7%

Total Project Cost 2,083.00 1,336.00 3,419.00 153.63 98.50 252.12

2.6 Project’s target area and beneficiaries

2.6.1 In general, the project will affect the SADC region and countries on the southern West

African coastline up to Ghana; therefore the project impact footprint covers the Southern,

Central and West Africa subcontinent.

2.6.2 Poverty is one of the major development challenges in Africa including the SADC

region and is reflected in the high level of unemployment, low levels of income and high

levels of human deprivation with 40% of the SADC’s population living below the

international poverty line of US$1 per day. The main economic objective of the SADC region

is therefore on the development of an environment, conducive to regional integration,

economic growth, poverty eradication and establishment of a sustainable path of

development. By so doing, the region will emerge as competitive in the world economy. The

development prospects by the project contribute towards the development agenda above as

the project will directly benefit the people, the governments and the private sector in Namibia,

Angola, Zambia, Botswana, DRC, Zimbabwe and South Africa. The benefits include

increased opportunities for trade, jobs creation and capacity building resulting in inclusive

growth and economic transformation promoting poverty alleviation in the SADC region.

2.7 Participatory process for project design and implementation

2.7.1 The formulation, design and financing of the project benefited from the wide

consultations carried out by Namport and its consultants and the Bank project appraisal team,

through bilateral and town hall meetings, and sharing of interim and final project reports. The

key stakeholders consulted include government ministries and agencies relating to the sector,

municipal and regional government, the logistics industry including freight forwarders,

international shipping lines, other ports in the region, transport operators and shippers

associations, corridor group, local businesses, local residents, NGOs and specific interest and

the donor community. The consultations served to inform stakeholders of the project and its

direct and indirect impacts and to obtain the stakeholders’ perspectives. The project’s design

and implementation modalities have been shaped by the concerns that were raised.

2.7.2 Amongst the outcomes of these consultations is the confirmation of the Namibian

Government that the project is a national priority and that the government will provide a

guarantee for the ADB loan to Namport. It has also influenced the technical solution retained

to ensure minimal disruption to the ports operations and avoid negative impacts to

neighbouring businesses with adequate measures put in place for environment and social

monitoring. The consultations also resulted in the inclusion of the MIC TA Grant into the

project to support the government’s efforts in logistics and capacity building.

Page 15: Namibia - The New Port of Walvis Bay Container Terminal Project · PDF file · 2013-07-232.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ... International Importance,

8

2.8 Bank Group experience, lessons reflected in project design

2.8.1 The Bank has extensive operational knowledge in developing infrastructure projects in

Africa. In the maritime subsector, the Bank has experience in design and implementation of

the following port projects: – Lekki Tolaram Port, Lomé container terminal, Djibouti bulk

terminal, Damietta port, Dakar container terminal, and Banjul port. The Bank’s African

Development Report 2010 also provides valuable information on ports in Africa.

2.8.2 In Namibia, the Bank commenced operations since 1992 and financed a total of five

operations in the transport sector amounting to UA71 million including the Trans-Kalahari

road study, Northern railway extension project, Aush-Rosh Pinah Road project, Kamanjab -

Omakange Road Project and the Namibian Airports study. All the operations have been

completed except the airports study which is currently on-going. These operations have

significantly contributed to strengthening Namibia’s transport network and have led to

opening up of isolated areas to access markets as well as link with neighbouring countries.

2.8.3 Through the interventions mentioned above, the Bank has gained significant

experience in the design, preparation and implementation of transport projects in Namibia.

Lessons drawn from the Bank’s previous interventions were taken into consideration in the

design of this project by making the following provisions: i) advanced procurement is used on

the main civil works which helps to gain time of up to 12 months; ii) the main civil works is

packaged under an EPC contract including the supply and installation of STS cranes to ensure

a smooth interface and assign a single point of responsibility for the project delivery; iii)

Namport will continuously monitor the ESMP and outcome indicators to ensure timely

response to any emerging concerns and facilitate measurement of the project’s outcomes; and

v) the Bank is providing a MIC TA Grant for logistics and capacity building to help increase

the skills base in the sector.

2.9 Key performance indicators

The performance indicators linked to the project’s outcome will be determined under

the following areas: (i) berthing moves per hour (BMPH); (ii) vessel waiting time; (iii) dwell

time; iv) volume of containers handled; and (v) logistics competence. The output indicators

include amongst others: i) size of the new port, ii) equipment supplied, iii) pilots and

operators trained for the new terminal, iv) nationals employed, and v) reports from the

logistics and road safety studies. The baseline data for these indicators are readily available

from the port’s data records which are periodically collected as part of the port’s operations.

Collection, monitoring and evaluation of the indicators (disaggregated by gender) will be

under the responsibility of the Namport Project Manager and his team. The Bank will also

monitor during supervision missions, mid-term review and at project completion.

III - PROJECT FEASIBILITY

3.1 Economic and financial performance

Traffic Demand

3.1.1 A consultant commissioned by Namport, undertook a market study for the project in

2011. The study assessed the overall competitiveness of Namport vis-à-vis other competing

ports in the Southern Africa region, namely, the ports of Luanda and Lobito in Angola and

ports of Durban and Cape Town in South Africa. While ports in Angola face congestion in the

foreseeable future, those in South Africa cater mostly for local and transit cargo. Neither will

pose a major threat to Namport which is oriented to being a transhipment hub and an

alternative gateway for transit trade in the SADC region.

Page 16: Namibia - The New Port of Walvis Bay Container Terminal Project · PDF file · 2013-07-232.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ... International Importance,

9

3.1.2 The consultant prepared traffic forecasts that are disaggregated by three submarkets:

domestic, transit and transhipment. Transhipment accounts for a major share of the traffic

(60% of container traffic) and has increased rapidly in recent years with an average annual

growth of 55%. In the base case, Namibia is expected to have a compounded GDP growth

rate of 6% from 2014 to 2030. Without the expansion project, Namport will be constrained by

its maximum capacity of 355k TEU.

Table 3.1 : Base Case Volume Traffic Projections (kTEU)

2013 2014 2015 2016 2017 2018 2019 2020 2025 2030

Import 78 80 110 125 142 159 171 183 230 230

Export 62 69 95 114 134 151 161 172 230 230

Transhipment 186 190 223 254 284 315 346 377 369 403

Total 327 339 428 493 561 625 678 732 829 863

Economic Analysis

3.1.3 Three major sources of direct economic benefits have been identified: i) time costs

savings for vessels calling at the port; ii) new employment opportunities for nationals; iii)

time costs savings for freight trucks that transport cargo from and to the port. Estimation of

the third benefit is constrained by the scarcity of relevant statistics and is therefore omitted.

However, given that 50% of the total traffic is transshipment that requires no intermodal

operations, the omission of the time savings to trucks is unlikely to lead to a significant

underestimation of the total economic benefits.

3.1.4 Time costs savings is expected to be shared by Namibian and regional consumers and

exporters, and by international shipping lines. Additional traffic translates into higher earnings

for Namport and its staff, which contribute to additional corporate income tax and labour

income tax for the government. The government will also collect more value added tax

revenue from traffic, and indirect taxes, that would otherwise not materialize in the project’s

absence. While taxes are transfers and should not be counted as an economic benefit, they

have a distributional impact and are thus captured in the stakeholder analysis, to explore how

the economic benefits are distributed among stakeholders. These are summarized in table 3.2.

Table 3.2 : Allocation of Projected Benefits among Stakeholders (Present Value, million NAD)

Namibia 2,839

Government 323

Additional labour income 12

Consumers 1,503

Exporters 1,002

Southern African Region 1,252

Consumers 877

Exporters 376

International shipping lines 1,252

3.1.5 The expansion will attract new customers and greater volume from existing ones,

further strengthening Namport’s role as a transshipment hub and spurring economic activities

in related industries. While the foregoing is important in its own right, the benefits identified

in the previous paragraphs are the most immediate, and can be reasonably well quantified. In

this analysis, additional benefits are omitted thus yielding a more conservative estimate. In

general, the expansion project is estimated to generate for Namibia externalities equivalent to

NAD2,839 million with an economic NPV of NAD498 million and EIRR of 14.6%.

Page 17: Namibia - The New Port of Walvis Bay Container Terminal Project · PDF file · 2013-07-232.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ... International Importance,

10

Financial Analysis

3.1.6 From Namport’s recent audited financial statements, revenues show the impact of the

world trade slow-down owing to the financial crisis. Thus, revenues decreased from NAD 616

million in 2009 to NAD566 million in 2010, but bounced up to NAD755 million in 2012. The

EBITDA exhibited a similar pattern. For the past several years, the debt-equity ratio has been

at low healthy levels and dropped to 0.21 in 2012, indicating strong capacity for additional

borrowing. Since 2011, Namport has been assigned a long term credit rating at A- by Fitch

Ratings and in May 2013, Fitch Ratings reaffirmed Namport’s credit rating and further

upgraded their outlook from Stable to Positive on account of strong government support and

Namport’s strategic importance in the Namibian economy. The company has maintained a

high level of liquidity; on average, cash or cash equivalent has been 61% of sales. The

following table presents Namport’s historical financial indicators and their forecasts.

Table 3.3 : Namport Selected Financial Indicators (million NAD)

Actual Forecast

2009 2010 2011 2012 2014 2016 2018 2020 2022 2024

TEU (000s) 266 256 224 292 339 493 625 732 779 822

Total Revenue 616 566 647 755 856 1,046 1,622 2,030 2,449 2,917

EBITDA 342 241 119 423 687 259 671 737 1,175 1,494

Debt to Equity Ratio 0.31 0.35 0.34 0.21 0.19 1.50 1.61 1.04 0.63 0.35

CF available for debt service N/A N/A N/A N/A 622 435 586 619 1,036 1,328

Total debt service 75 113 171 205 254 253 228 281 441 407

DSCR N/A N/A N/A N/A 2.45 1.72 2.57 2.21 2.35 3.27

3.1.7 A detailed financial model for Namport corporate financial flows was developed by

their financial advisor for this project. Cash flows of the expansion project were integrated

into the corporate financials. The key indicators for financial and economic performance are

derived from the consolidated corporate model of Namport. The average DSCR, based on

consolidated cash flows and both existing and new debt, is estimated to be 2.02x and the

minimum DSCR is 1.30x in 2015. The second debt service period starts with the first

principal repayment of the new loan in 2019, until 2034. Overall, the projections confirm the

strong debt service capacity of Namport.

3.1.8 While debt service capacity has been evaluated based on overall Namport financials,

the investment viability of the expansion plan is assessed on incremental basis, ensuring that

the expansion decision is judged on its own merit, independently from the existing operations

of the port. Under the base case scenario, the Equity NPV for the expansion project is

NAD216 million at a 12% discount rate (real). The Project IRR for the expansion project is

calculated to be 8.5% while the Equity IRR is estimated to be 15.0% in real terms.

3.1.9 Table 3.4 summarises the key financial and economic indicators for the expansion

project confirming that the new terminal expansion is economically and financially viable.

The forecasts indicate that the project generates sufficient operating cash flow to recoup initial

investment costs and to service debt. The project will also bring additional benefits to other

stakeholders. Furthermore, sensitivity analysis results presented in the technical annex shows

that the project is viable despite adverse shocks.

Table 3.4 : Key Financial Performance Indicators

Economic NPV at 12% EOCK (real) 498 million NAD

Economic IRR (real) 14.6%

Equity NPV at 12% ROE (real) 216 million NAD

Equity IRR (real) 15.0%

Project IRR (real) 8.5%

Page 18: Namibia - The New Port of Walvis Bay Container Terminal Project · PDF file · 2013-07-232.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ... International Importance,

11

3.2 Environmental and Social impacts

3.2.1 The project has been classified as Category 1 in accordance with the Bank’s

Environmental and Social (E&S) Assessment Procedures. Relevant E&S documentation was

prepared, and an Executive Summary of the Environmental and Social Impact Assessment

(ESIA) was disclosed on the Bank’s website on 22nd March 2013. The project will result in

environmental and social (E&S) impacts, although some of these will be low in the nature of

their significance.

3.2.2 An Environmental Management Plan (EMP) has been prepared by Namport to address

these impacts. The Bank has requested Namport to develop a more comprehensive

Environmental and Social Management Plan (ESMP) which would integrate a detailed waste

management plan; a business continuity plan; baseline studies on the effects on the lagoon; a

hazards (especially technological) management plan; an emergency response plan; and a

detailed plan for better assessing and monitoring the socio-economic impacts, amongst other

features. Namport will also undertake additional measures, such as a cumulative impacts

assessment; detailed baselines studies on the effects on the lagoon (siltation and inflow and

outflow rates), sea level rise and climate change impacts; and detailed analysis of the project’s

impacts on utilities. Namport has engaged the services of a consulting firm and is currently

addressing the E&S gaps. The outstanding E&S reports and plans will be submitted to the

Bank as part of the E&S Action Plan, by 30th

September 2013. Once a comprehensive ESMP

is developed building upon the existing EMP, the ultimate costs for mitigating and enhancing

E&S impacts will be known with greater certainty.

Climate Change

3.2.3 The Walvis Bay area is characterized by a chance of 30 cm sea level rise, which

highlights the importance of climate change considerations by the project. A national climate

change action plan has been prepared, and includes strategies for addressing disasters.

Namport is undertaking baseline studies to examine climate change impacts linked to the

project and its business continuity plan and emergency preparedness plan will be aligned to

the National Climate Change Action Plan.

Gender

3.2.4 Following the Bank’s recommendation, Namport is undertaking a gender analysis to

better understand the gender considerations it should appropriately address through the project

and its Corporate Social Responsibility (CSR) initiatives. The project area is characterized by

gender inequities and disparities. To ensure that women benefit from the project,

considerations will need to be introduced, such as job profiles and potential quotas, to

encourage women’s participation in the project’s employment opportunities. Gender-based

violence and the influence of patrilineal traditions are of national concern. Measures will be

enacted to limit a potential rise in the commercial sex industry by the project. Awareness

campaigns on sexually transmitted infections, such as HIV/ AIDS, will integrate gender

sensitive components targeting Namport employees and local communities. The training of

women freight forwarders is an initiative included in the project following concerns raised

during stakeholder consultations whilst further initiatives on gender mainstreaming will be

assessed upon completion of the gender analysis mentioned above.

Social

3.2.5 The project is expected to result in multiple socio-economic benefits including direct

and indirect employment opportunities for Namibians during the construction and operational

phases; educational and training opportunities; skills development options; the promotion of

entrepreneurship; increased trade and economic activities benefiting the construction,

Page 19: Namibia - The New Port of Walvis Bay Container Terminal Project · PDF file · 2013-07-232.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ... International Importance,

12

transport, hospitality and tourism industries; a growth in new small and medium size

enterprises; and an increased scope for the marina development.

3.2.6 The project will also result in social risks, such as an influx of workers, truckers and

sailors which would add pressure on available resources and infrastructure; an increased risk

of communicable diseases like HIV/AIDS; behavioural changes leading to greater theft,

prostitution and alcoholism; road safety concerns due to increased traffic; and an inability of

local businesses, with leases in the area being targeted for the marina development, to realize

the full value of their recent investments. Through the comprehensive ESMP it is developing

and the CSR initiatives initiated through Namport’s Social Investment Fund, Namport will

work to address and diminish the impact of these social risks.

Involuntary Resettlement

3.2.7 The project will not involve either the physical or economic displacement of any

project affected persons. The expansion works will be undertaken on land belonging to the

Government of Namibia with the terminal facility built on reclaimed land inside current port

limits.

IV - IMPLEMENTATION

4.1 Implementation arrangements

Borrower and Executing Agencies

4.1.1 Namport, a body corporate established under the Namibian Ports Authority Act, 1994

(Act No. 2 of 1994) and operating under the State-owned Enterprises Governance Act, 2006

(Act No. 2 of 2006), will be the sole beneficiary of the loan. Namport has operated as the

National Port Authority in Namibia since 1994, and manages the Port of Walvis Bay, the Port

of Lüderitz, and a Syncrolift (dry dock facility). Under the terms of the Namibian Ports

Authority Act, 1994, Namport has, in addition to the specific powers vested in it under the

Act, all the powers that may be exercised by a company under Namibia’s Companies Act.

These powers include, among others, the power to enter into contracts, including contracts

outside of Namibia, and the power to borrow.

4.1.2 Namport has a two-tier governance structure consisting of the Board of Directors and

the executive management. The Minister of Works and Transport appoints Namports’s Board

of Directors. The Board of Directors has overall responsibility for the affairs of Namport. The

Board comprises five independent non-executive directors whose terms of office are three

years each. The Board of Directors appoints a Chief Executive Officer (CEO) on a five-year

contract that is renewable at the discretion of the Board. The CEO is responsible for the

execution of strategy and management at Namport, and is assisted by members of senior

management. Under the State-owned Enterprises Governance Act, the Minister of Works and

Transport must enter into a Governance Agreement with Namport’s Board of Directors that

sets out the roles, responsibilities and obligations of the Ministry and Namport; the latest such

Governance Agreement was entered into on 20th

May 2010 for a period of five years.

4.1.3 The implementation arrangements for the Loan and the MIC TA Grant would be

separated whereby Namport would be the executing agency for all the project components

financed under the ADB Loan and the Walvis Bay Corridor Group (WBCG) would be the

executive agency for the component on logistics and capacity building financed under the

MIC TA Grant.

4.1.4 Namport has an existing structure comprising a Project Executive Steering Committee

(PESC) chaired by Namport’s CEO who oversee strategic decision making and report to the

Board of Directors. The Project Implementation Committee (PIC), headed by the Port

Page 20: Namibia - The New Port of Walvis Bay Container Terminal Project · PDF file · 2013-07-232.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ... International Importance,

13

Engineer and Projects Manager is responsible for the day to day management and supervision

of project activities and report to the PESC. The PIC comprises Namport experts in all

disciplines for the project’s activities, supported by external consultants providing specialist

advisory service. The PESC and PIC already exist and most key appointments have been

made with the remaining positions expected to be filled prior to project commencement. The

Walvis Bay Corridor Group has experience in the implementation of DFI financed projects

and the Project Manager for Spatial Development Initiatives will head the implementation

unit for supervision of this project. The Ministry of Works and Transport and the Ministry of

Finance have identified focal persons who will be responsible for ministerial oversight and

support for this project.

Procurement

4.1.5 Procurement activities will be carried out by Namport and by the WBCG for project

components financed under the ADB Loan and the MIC TA Grant respectively.

4.1.6 The Procurement Unit in Namport is still in the formative stage as it is only 3 years

old and Namport is in the process of filling up the vacant positions. Given the complexity of

the current EPC tender for the port expansion project (detailed below), a specialized team of

consultants have helped Namport to design the EPC procurement process and is currently

carrying out the evaluation. The consultants work under the supervision of the Project

Executive Steering Committee with recommendations presented to the Namport Board for

final decision at each stage.

Procurement for the EPC Works Contract to Construct the New Container Port Terminal

4.1.7 The procurement action for the expansion of the container terminal was initiated in

September 2012. At that time, Namport and the Government of Namibia expected project

financing to be arranged by the bidders though finance from development financial

institutions was also being contemplated. It did not appear that, at that time Namport had any

intention of seeking financing from the African Development Bank and therefore had no

reason to follow the Bank’s procurement policies and procedures. The situation changed when

the identification mission from the Bank visited them in December 2012 and they were made

aware of the more attractive conditions (including loans in ZAR) that the Bank was offering.

Namport and the Government of Namibia then approached the Bank to provide finance to the

extent of almost 87.6% of the cost of the project.

4.1.8 Invitations to bid for this procurement were locally and internationally advertised in

the print media and online on the Namport website. The bids were received on 18th February

2013 and are under evaluation. The bidding process has gone through stringent diligence

including a mandatory pre-bid meeting and site-inspection by the bidders. The questions from

the bidders were promptly answered.

4.1.9 The current situation that Namport is facing is unprecedented- the Bank’s support has

been requested for an important para-statal midway through a large and nationally (and

regionally) critical project and the Bank has had no major previous engagement in the country

for large investment lending in this sub-sector. The project is already delayed and the

Authorities have made a compelling case that re-launching of the tender will be very costly

for Namport and Namibia.

4.1.10 As the GoN and Namport have requested the Bank to finance a procurement that has

not been conducted using the Bank’s Procurement Rules, the Bank undertook independent

reviews and due diligence of the procurement process to ascertain if the procurement is likely

to meet global industry standards and the Bank’s procurement principles. For this purpose, the

Bank commissioned two independent procurement consultants to support Bank Procurement

Specialists in carrying out the due diligence. The review has concluded that while the

Page 21: Namibia - The New Port of Walvis Bay Container Terminal Project · PDF file · 2013-07-232.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ... International Importance,

14

procurement process was rigorous and detailed, and did not appear to deliberately favor any

bidder or set of bidders, there were departures from the Bank’s procurement principles. (Some

of the deviations included (i) Namibian dollars as the payment currency irrespective of the

nationality of the bidder;(ii) the contract prices being fixed despite the contract period being

three years; (iii) bid-evaluation that allowed Namport to use unspecified criteria if it felt it was

in its best interest; (iv) bespoke contract provisions that transferred significant risks to

contractors; (v) commercial arbitration to take place in Namibia and not in a neutral place.

4.1.11 The Walvis Bay expansion project has evident economic benefits for the region and

timely completion of the project is key for such benefits to be realized. The preferred

alternative (of the Bank) of rebidding of this procurement would mean a delay of many

months in the commissioning schedule for the project. This would have serious and

unacceptable impact on the economy of Namibia and the region and is not acceptable to

Namport and the Government of Namibia. A flexible and pragmatic approach, may therefore,

be necessary for this first time engagement with Namport. It would, therefore, appear that

there might be merit to allow the present process to be completed as started and to ask for

modifications in some key contractual provisions to include Bank’s rights with respect to

Fraud and Corruption and for the Bank’s right to audit.

4.1.12 Given on the need to speedily execute the above project and the diligence to ensure

that the contractors and subcontractors who would be awarded the contracts are not debarred

or suspended at the time of contract award or signing, and the incorporation of F&C and

Audit Rights provisions in the contracts before signature, Board approval is sought to grant a

waiver from the application of the Bank’s Procurement Rules and to approve to finance the

EPC works contract for construction of the new container terminal at Walvis-Bay to be

awarded by Namport using a bespoke procurement process and contract. This waiver is being

sought only for the EPC works contract.

Procurement of equipment, ancillary services and logistics and capacity building

4.1.13 With the exception of the EPC main works contract, the procurement of all project

components namely: equipment, ancillary services and logistics and capacity building support

will be done in accordance with the applicable Bank’s Rules and Procedures for the

procurement of Goods and Works and the Bank’s Rules for the use of Consultants. The

details of the procurement arrangements are summarised in the technical annex.

Financial Management

4.1.14 The Project loan’s financial management will be implemented by Namport within its

existing set-up for project implementation under the overall management of the Board of

Directors whereas WBCG will be responsible for the Grant. An assessment of Namport’s and

WBCG’s financial management arrangements for the implementation of the project (which

included a review of the budgeting, accounting, internal controls, flow of funds, financial

reporting and auditing arrangements) indicates that they satisfy the Bank’s minimum

requirements to ensure that the funds made available for the financing of the project are used

economically and efficiently and for the purpose intended. In addition, internal and external

audit requirements are further measures towards effective corporate governance.

4.1.15 In accordance with the Bank’s reporting and auditing requirements, Namport and

WBCG will be required to submit Quarterly Progress Reports (within 30 days after the end of

each quarter) and annual audit reports with financial information for the Loan and Grant

respectively. Furthermore, separate annual audit reports with financial information (with the

audit done in accordance with a Bank approved audit ToR) will be prepared by the respective

implementing entities in compliance with their internal legal requirements. The audit costs

will be borne by the respective implementing entity and the audit reports together with the

Page 22: Namibia - The New Port of Walvis Bay Container Terminal Project · PDF file · 2013-07-232.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ... International Importance,

15

auditor’s management letter indicating any weakness in internal control including the

responses from management will be sent to the Bank within six (6) months of the end of the

respective fiscal year. (A draft audit TOR that can be used as a guide has been availed to

Namport). In addition, Namport’s annual audited financial statements will also be submitted

together with the project audit report and the project management letter.

Disbursement Arrangements

4.1.16 The Loan will be disbursed for two categories of expenditure including Works and

Goods with a provision for future consulting services, if any. The MIC TA Grant will be

disbursed for two categories of expenditure including Goods and Services. The Direct

Payment and Reimbursement Guarantee Methods will be used as payment method under the

ADB loan and the Special Account method will be applied for the MIC TA Grant.

Disbursements under the Loan and Grant would be made in accordance with the list of goods,

works and services and the Bank’s rules and procedures as laid-out in the Disbursement

Handbook insofar as may be applicable.

4.2 Monitoring

4.2.1 The outline of the project implementation schedule takes into account the relevant

experience of the PIC and WBCG in managing works implementation deadlines and that of

the Bank in processing previous similar projects. According to the estimates, project activities

will start (upon approval of the loan and grant) in the last quarter of 2013 and end towards the

end of 2016. The grant and loan closing dates are scheduled for end of 2017 and 2019

respectively. At the level of the Bank, the activities planned following loan and grant approval

will be closely monitored, in accordance with the schedule in Table 4.1 below.

Table 4.1 : Schedule for Project Monitoring

Timeframe Milestone Monitoring process / feedback loop

Q4 – 2013 Project Launching Field Mission, Progress Reporting

Q2 – 2014 Construction start + 6 months Field Mission, Progress Reporting

Q4 – 2014 Construction + 14 months Field Mission, Progress Reporting

Q2 – 2015 Construction start + 20 months Mid-Term Review, Progress Reporting

Q4 – 2015 Construction start + 26 months Field Mission, Progress Reporting

Q2 – 2016 Construction start + 32 months Field Mission, Progress Reporting

Q4 – 2016 Construction start + 36 months Project Completion, Completion Report

Q4 – 2017 Defects Liability and end of 1st yr Project Evaluation, M & E Report

4.2.2 Apart from the schedule for monitoring activities, the PIC will regularly provide the

Bank with quarterly project progress reports covering all project activities including

implementation of the ESMP and the status of the log-frame indicators, annual audit reports

as well as the final project report; all in the Bank’s standard format. The comprehensive

ESMP and other actions in the E&S Action Plan will be implemented by Namport (by the

Environmental Manager and Officer) and the selected contractor (by Environment, Health and

Safety, Fire and Waste Management Officers). The Ministry of Environment and Tourism as

the ESIA licencing authority will monitor environmental and social performance on the basis

of the required ESMP compliance reports. Project monitoring will be carried out by the

Bank’s supervision missions, in line with the Bank’s Operations Manual.

Page 23: Namibia - The New Port of Walvis Bay Container Terminal Project · PDF file · 2013-07-232.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ... International Importance,

16

4.3 Governance

4.3.1 Namibia has consistently ranked among the top African countries on good

governance. The country has consistently scored at least 4 out of 5 in all the categories of

Bank Group’s Country Policy and Institutional Assessment (CPIA), with the exception of

property rights and rule based governance. In addition, Namibia has been ranked: i) between

the 50th-75th percentile out of the 212 countries by the World Bank’s 2011 Worldwide

Governance Indicators; ii) 6th out of 53 African countries, with an overall score of 67.3 out of

100, by the 2010 Mo Ibrahim Index of African Governance; and iii) 4th and 5th least corrupt

country in Southern Africa and SSA, respectively, by the 2010 Corruption Perception Index

by Transparency International.

4.3.2 Namport has adopted the principles of good corporate governance as contained in the

King Report 2009 (“King III”). The Authority is overseen, managed and controlled by a

Board of Directors on behalf of the government and has overall responsibility and

accountability for the affairs and performance of the Authority. The Authority’s Board is

appointed by the portfolio Minister of Works and Transport (MWT) who has the overall

responsibility for policy and regulation, and the Ministry of Finance who has an oversight role

in Namport’s financial and project development activities. The specific governance risk

mitigation measures of the present project include: (i) the appointment of financial and

technical audit firms to ensure that funds are used efficiently and for the intended purposes;

(ii) Bank prior review and approval of all project procurement activities; and (iii) the use of

direct disbursement methods to channel project funds to contractors and service providers.

4.4 Sustainability

The expansion of the port is expected to be a long-term self-sustaining economic

activity that generates sufficient financial return to cover all operating costs, taxes,

maintenance expenses, and repayment of debt and recovery of capital costs. While regular

maintenance costs for both terminals are planned to be funded by operating cash flows, the

business plan for the new terminal explicitly makes a provision for a Maintenance Reserve

Account (MRA) that will be accumulating the necessary amount of funds for equipment

replacement and purchases of additional equipment. The accumulation of funds will be spread

over five years prior to the expected time of maintenance activities, which minimizes the risk

of dependency on cash flows of a single year. Table 4.2 presents the actual, past and projected

maintenance costs, for the existing and the new terminal. It is noted that the same trend of

maintenance expenditures is expected to continue.

Table 4.2 : Historic and Projected Terminal Maintenance Costs

Actual Projection

Maintenance costs 2009 2010 2011 2012 2016 2017 2020 2025 2030

Existing terminal 24 34 29 32 42 44 53 71 95

New terminal N/A N/A N/A N/A 27 114 137 214 286

Revenue 616 566 647 755 1,046 1,418 2,030 3,118 4,239

Operating costs 280 344 362 465 701 865 1,063 1,447 1,909

Assets 2,031 2,288 2,879 2,606 5,553 5,355 6,002 9,395 16,372

As % of revenue 3.8% 6.0% 4.5% 4.3% 6.6% 11.2% 9.3% 9.1% 9.0%

As % of operating

costs 8.4% 10.0% 8.1% 6.9% 6.0% 5.1% 5.0% 4.9% 5.0%

As % of assets 1.2% 1.5% 1.0% 1.2% 0.8% 0.8% 0.9% 0.8% 0.6%

Page 24: Namibia - The New Port of Walvis Bay Container Terminal Project · PDF file · 2013-07-232.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ... International Importance,

17

4.5 Risk management

4.5.1 The successful implementation of the project and achievement of its development

objectives predicates on several assumptions, each of which may constitute a potential risk:

4.5.2 Risk posed by competing Routes and Ports: The risk of competing ports and corridors

in the region taking over transhipment and transit trade from the Port of Walvis Bay is

mitigated through: i) comprehensive analysis of the competition and market trends and

development of sound strategies to meet the planned objectives; ii) the Government and

Namport consolidating efforts to develop the entire transport and logistics chain and soft

issues to enable safe and efficient transport through the Walvis Bay corridors and across the

borders; iii) appointment of the Walvis Bay Corridor Group to promote the corridors and

spearhead tri-partite agreements and partnerships, to foster closer collaboration and promote

the use of the Walvis Bay port and corridors. These initiatives are already yielding positive

results translating to increased trade volumes and motivating further efforts by the country.

4.5.3 Risk of Government failure to implement its infrastructure development plans that

complement the project: The Government of Namibia is committed to its development plans

in NDP4 and has developed a detailed action plan for implementing these initiatives and

allocated the budget to commence the implementation of these actions. It has also

incorporated Monitoring and Evaluation on a periodic basis to inform on progress. In

addition, the Bank is providing support through a MIC TA Grant.

4.5.4 Risk of an adverse regional logistics environment: Road transport operators need

workable access to other countries regionally. If non-tariff barriers hinder operations too

much, transport rates may be increased and the overall competitiveness of the corridors may

be compromised. As mitigation measure the Project will support the Walvis Bay Corridor

Group, which will increase the capacity to deal with these problems.

4.5.5 Risk of procurement delays and late project start up: in order to avoid delays due to

procurement, the project has opted for advanced procurement for the main terminal

construction as well as EPC contract for the main civil works to avoid separate procurements

for design and construction gaining almost 12 months in the procurement timeline.

4.5.6 Construction risks (including technical risks, delays and cost overrun): the selection

process for contractors ensures that only skilled and specialised companies with sufficient

capacity and financial standing are awarded this contract and the use of a fixed price lump

sum contract with a defined completion date will mitigate against cost overrun and delays.

The dedicated Project Implementation Unit constituting various experts for project control

and supervision as well as a Bank supervision team for monitoring of project progress also

builds on mitigating against construction risks.

4.5.7 Environmental and social risks: The comprehensive ESMP and the E&S Action Plan

will be implemented and monitored by the E&S specialists of Namport, authorities and the

selected contractor. The Bank’s task team will follow up on a periodic basis. In addition, the

Bank’s decentralization strategy will also have positive impact in assisting the Executing

Agency.

4.6 Knowledge building

4.6.1 The project provides an excellent opportunity for new skills to be developed both

within the Bank and in Namibia. Within the Bank, it is an opportunity to further strengthen its

knowledge on ports and regional integration which will feed into the Bank’s knowledge

series. At Namport level, the project incorporates specialised training which helps to build the

skills-base of the company. The project has influence to build-up local capacity through

employment of nationals for skilled and unskilled jobs related to the project’s activities.

Page 25: Namibia - The New Port of Walvis Bay Container Terminal Project · PDF file · 2013-07-232.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ... International Importance,

18

4.6.2 The logistics master plan will provide a comprehensive logistics policy and system

development plan for Namibia with the target year of 2030 that will be a shared vision and

common implementation platform for the public and private sectors. Freight forwarders are

often the “one-stop-shop” interface between shipping lines, customs and road carriers. It is

therefore important to ensure that the professional competence of the industry is up-to-date

and meets customers’ requirements. The Project will address this by organizing FIATA

training particularly for female in-service freight forwarders and persons who intend to enter

this business.

V - LEGAL INSTRUMENTS AND AUTHORITY

5.1 Legal instrument

The Bank instruments to finance this project are:

(i) a loan agreement between Namport and the Bank for a loan to Namport with a

sovereign guarantee provided by the Republic of Namibia,

(ii) a guarantee agreement between the Republic of Namibia and the Bank, and

(iii) a letter of agreement between the Republic of Namibia and the Bank for a MIC

Technical Assistance Fund Grant to the Republic of Namibia.

5.2 Conditions associated with Bank’s intervention

5.2.1 Conditions Precedent to the Entry into Force of the ADB Loan Agreement &

Guarantee Agreement: The Loan Agreement and the Guarantee Agreement shall enter into

force upon signature by the parties thereto in accordance with the provisions of Section 12.01

of the General Conditions Applicable to the African Development Bank Loan Agreements

and Guarantee Agreements (Non Sovereign Entities).

5.2.2 Conditions Precedent to the Entry into Force of the MIC Grant Letter of

Agreement: The Letter of Agreement shall enter into force upon signature by the parties

thereto.

5.2.3 Conditions Precedent to First Disbursement of the ADB Loan: The obligation of

the Bank to make the first disbursement of the Loan shall be conditional upon:

(i) entry into force of the Loan Agreement and the Guarantee Agreement in accordance

with Section 5.2.1 above and

(ii) fulfillment by the Borrower and Guarantor of the provisions of Section 12.02 of the

General Conditions.

5.2.4 Conditions Precedent to First Disbursement of the MIC Grant: The obligation of

the Bank to make the first disbursement of the MIC Grant shall be conditional upon:

(i) entry into force of the Letter of Agreement in accordance with Section 5.2.2 above and

the fulfillment, in form and substance satisfactory to the Bank, of the following

conditions:

(ii) a United States Dollar special account (the “Special Account”) has been opened in a

bank acceptable to the Bank for receipt of the proceeds of the Grant;

(iii) entry into force of the Loan Agreement between the Namibian Ports Authority

(Namport) and the Bank and the Guarantee Agreement between the Recipient and the

Bank for the New Port of Walvis Bay Container Terminal Project;

(iv) the Recipient providing the Bank with the names of the person(s) authorized to sign

withdrawal applications for the Grant on behalf of the Recipient together with

authenticated specimen signatures of each such designated person.

Page 26: Namibia - The New Port of Walvis Bay Container Terminal Project · PDF file · 2013-07-232.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ... International Importance,

19

5.2.5 Other Conditions of the Loan:

(i) The Borrower shall, not later than 30th

September 2013, submit to the Bank each item

listed under the Environment and Social Action Plan set forth as annex V hereto, each

in form and substance satisfactory to the Bank;

(ii) The Borrower shall, within one (1) month of the closing of each budget cycle

commencing with its 2012-2013 budget and throughout the duration of the Project,

provide evidence in form and substance satisfactory to the Bank of the annual

budgetary allocation for the Namport contribution to project financing;

(iii) The Borrower shall, within three (3) months of the signing of this Agreement, provide

evidence in form and substance satisfactory to the Bank that the grant to the Borrower

from the Guarantor has been duly concluded, together with evidence of annual

budgetary allocations on the part of the Guarantor for such grant amount.

5.2.6 Undertakings:

(i) implement, and report to the Bank on a semi-annual basis in a form acceptable to the

Bank, on the implementation of the comprehensive Environmental and Social

Management Plan;

(ii) inform the Bank of any significant environmental and social incidents within ten (10)

days of their occurrence and, within thirty (30) days of such occurrence, provide

details on corrective actions which the Borrower will implement to address each such

incident;

(iii) maintain (a) the Project Implementation Committee with terms of reference,

composition and a Project Manager acceptable to the Bank and (b) the Project

Executive Steering Committee with terms of reference and composition acceptable to

the Bank;

(iv) incorporate the Bank’s standard provisions on Fraud and Corruption and Audit Rights

in the EPC works contract for the construction of the new terminal prior to its

signature with the successful bidder; and

(v) promptly notify the Bank of any material modifications to the EPC works contract.

5.3 Compliance with Bank Policies

This project complies with all applicable Bank policies except for the waiver being

requested for the EPC main works contract.

VI - RECOMMENDATION

6.1.1 Management recommends that the Board of Directors approve:

(i) the proposed loan of ZAR 2,982 million to Namibia Ports Authority (Namport), with

the guarantee of the Republic of Namibia for the purposes and subject to the

conditions stipulated in this report; and

(ii) the proposed MIC Technical Assistance Fund grant of UA 1.00 million to the

Republic of Namibia for the purposes and subject to the conditions stipulated in this

report; and

(iii) a waiver from application of the Bank Group’s Rules and Procedures for Procurement

of Goods and Works solely with respect to the EPC main works contract for the

construction of the new terminal which was procured using a bespoke procurement

process and contract adopted by the Borrower.

Page 27: Namibia - The New Port of Walvis Bay Container Terminal Project · PDF file · 2013-07-232.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ... International Importance,

Indicator Year Namibia AfricaDeveloping

Countries

Developed

CountriesCharts

Basic Indicators

Area ('000 Km²) 824.3 30,046.4 80,976.0 54,658.4

Total Population (millions) 2012 2.4 1,068.4 5,628.5 1,068.7

Urban Population (% of Total) 2012 39.2 40.8 44.8 77.7

Population Density (per Km²) 2012 2.8 34.5 66.6 23.1

GNI per Capita (US $) 2010 4,500.0 1,548.9 2,780.3 39,688.1

Labor Force Participation - Total (%) 2012 40.3 37.8 0.0 0.0

Labor Force Participation - Female (%) 2012 46.2 42.5 39.8 43.3

Gender -Related Development Index Value 2007 0.7 0.5 .. 0.9

Human Develop. Index (Rank among 169 countries) 2012 128.0 3,972.0 .. ..

Popul. Living Below $ 1 a Day (% of Population) 2004 31.9 158.1 25.0 ..

Demographic Indicators

Population Growth Rate - Total (%) 2012 1.7 2.3 1.4 0.7

Population Growth Rate - Urban (%) 2012 3.3 3.4 2.4 1.0

Population < 15 years (%) 2012 35.5 40.0 29.2 17.7

Population >= 65 years (%) 2012 3.8 3.6 6.0 15.3

Dependency Ratio (%) 2012 64.8 77.3 52.8 ..

Sex Ratio (per 100 female) 2012 98.9 100.0 934.9 948.3

Female Population 15-49 years (% of total population) 2012 26.0 48.6 53.3 47.2

Life Expectancy at Birth - Total (years) 2012 62.6 58.1 65.7 79.8

Life Expectancy at Birth - Female (years) 2012 63.0 59.4 68.9 82.7

Crude Birth Rate (per 1,000) 2012 25.4 34.2 21.5 12.0

Crude Death Rate (per 1,000) 2012 8.2 10.9 8.2 8.3

Infant Mortality Rate (per 1,000) 2012 30.4 70.8 53.1 5.8

Child Mortality Rate (per 1,000) 2012 40.6 111.3 51.4 6.3

Total Fertility Rate (per woman) 2012 3.1 4.3 2.7 1.8

Maternal Mortality Rate (per 100,000) 2010 200.0 402.3 440.0 10.0

Women Using Contraception (%) 2012 57.1 31.6 61.0 75.0

Health & Nutrition Indicators

Physicians (per 100,000 people) 2010 37.4 53.6 77.0 287.0

Nurses (per 100,000 people)* 2007 277.5 905.0 98.0 782.0

Births attended by Trained Health Personnel (%) 2007 81.4 1,472.2 39.0 99.3

Access to Safe Water (% of Population) 2010 93.0 65.7 84.0 99.6

Access to Health Services (% of Population) 2000 59.0 65.2 80.0 100.0

Access to Sanitation (% of Population) 2010 32.0 39.8 54.6 99.8

Percent. of Adults (aged 15-49) Living with HIV/AIDS 2011 13.4 4.6 161.9 14.1

Incidence of Tuberculosis (per 100,000) 2011 723.0 234.6 .. ..

Child Immunization Against Tuberculosis (%) 2011 89.0 81.7 89.0 99.0

Child Immunization Against Measles (%) 2011 74.0 76.6 76.0 92.6

Underweight Children (% of children under 5 years) 2007 17.5 63.6 27.0 0.1

Daily Calorie Supply per Capita 2009 2,151.0 2,568.8 2,675.2 3,284.7

Public Expenditure on Health (as % of GDP) 2010 6.8 5.9 4.0 6.9

Education Indicators

Gross Enrolment Ratio (%) .. .. .. ..

Primary School - Total 2010 106.8 101.9 106.0 101.5

Primary School - Female 2010 106.1 98.1 104.6 101.2

Secondary School - Total 2007 64.0 42.3 62.3 100.3

Secondary School - Female 2007 69.3 38.5 60.7 100.0

Primary School Female Teaching Staff (% of Total) 2010 68.2 43.7 .. ..

Adult Literacy Rate - Total (%) 2010 88.8 67.0 19.0 ..

Adult Literacy Rate - Male (%) 2010 88.5 58.3 .. ..

Adult Literacy Rate - Female (%) 2010 89.0 75.8 .. ..

Percentage of GDP Spent on Education 2010 8.3 5.3 .. 5.4

Environmental Indicators

Land Use (Arable Land as % of Total Land Area) 2011 1.0 8.4 9.9 11.6

Annual Rate of Deforestation (%) 2000 0.9 0.6 0.4 -0.2

Annual Rate of Reforestation (%) .. .. .. ..

Per Capita CO2 Emissions (metric tons) 2009 1.6 1.2 .. ..

Last update: April 2013

Namibia

Comparative Socio-Economic Indicators

Sources : ADB Statistics Department Databases; World Bank: World Development Indicators

UNAIDS; UNSD; WHO, UNICEF, WRI, UNDP; Country Reports.

Note : n.a. : Not Applicable ; … : Data Not Available.

0

1000

2000

3000

4000

5000

200

0

200

1

200

2

200

3

200

4

200

5

200

6

200

7

200

8

200

9

201

0

GNI per Capita (US $)

Namibia Africa

0

0.5

1

1.5

2

2.5

201

0

201

1

201

2

Population Growth Rate - Total (%)

Namibia Africa

0

10

20

30

40

50

60

70

80

90

100

200

0

200

1

200

2

200

3

200

4

200

5

200

6

200

7

200

8

200

9

201

0

Access to Safe Water (% of Population)

Namibia Africa

0

20

40

60

80

100

120

140

200

0

200

1

200

2

200

3

200

4

200

5

200

6

200

7

Secondary School - Total

Namibia Africa

Appendix I. Country’s comparative socio-economic indicators

Page 28: Namibia - The New Port of Walvis Bay Container Terminal Project · PDF file · 2013-07-232.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ... International Importance,

Appendix II. Table of ADB’s Portfolio in the Country

Project Name Main

Sector

Window Approval

Date

Disburse

Deadline

Amount

Approved

(UA m)

Amount

Disbursed

(UAm)

Disbursed

Rate

(%)

Support to Aquaculture

Development

Agriculture

(OSAN)

MIC

Fund 05.06.09 30.05.12 0.26 0.26 99.2

Namibia Airport Study Transport

(OITC)

MIC

Fund 20.07.10 31.12.12 0.59 0.08 13.1

Human Resources

Development Plan

Institutional

Support

(OSHD)

MIC

Fund 09.10.09 31.03.12 0.60 0.54 89.5

Statistical Capacity Building

(SCB-II)

Institutional

Support

(ESTA)

MIC

Fund 07.07.11 31.12.13 0.49 0.00 0.00

TRUSTCO Finance

Private

Sector

(OPSM)

Private

Sector 07.12.12 TBD 4.8 3.29 68.5

MIC Grant Application

for Establishment of the

National Medical Benefit

Fund

Health

(OSHD)

MIC

Fund 12.03.12 31.12.13 0.50 0.00 0

Total 7.24 4.16 57.5%

Page 29: Namibia - The New Port of Walvis Bay Container Terminal Project · PDF file · 2013-07-232.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ... International Importance,

Appendix III. Key Projects financed by the Bank and other DP in the country

Table Summarising Grants

Development

Partner

Subsectors/Programmes Commitments for

2011/2012 (N$) China Aquaculture, Construction, Equipment, Defence, Capacity building & Health 132,752,400.00

France Social Development Fund, Decentralization, ICT, Culture, Governance 5,374,469.38

Germany National Parks, Community Forest, Land Reform, Water Resource Management,

Environment and tourism, Education, Capacity Building, Roads, Transport,

Public Finance Management, HIV/AIDS

425,014,800.00

Spain Fishery, Health, Water, Education, Disaster Management & HIV/AIDS 55,216,179.00

Sweden Human rights and Democracy, Environment and Climate, Gender Equality and

Economic Growth

35,790,045.69

USA USAID, MCA, PEPFAR, Health, Education, Environment 401,808,861.00

Multilateral UN Agriculture, Housing, Education & Training, Safety & Security, Gender Equality

& Women Employment, Child Protection & Welfare, Health, Tourism,

Emergency Preparedness and Impact Mitigation, Immigration and Refugees

Affairs, Social Development, Governance, Skills Transfer and Capacity

Development, and Environment.

91,685,175.00

European

Union

Water Supply & Sanitation, Parliamentary Support Programme, Performance

Management System, Public Finance Management Programme, Rehabilitation of

Roads in the North, MDG Initiative, Civil Society Capacity Building Programme

256,161,168.00

World Bank Namibia National Statistical System, National Integrated Resource Plan, Namibia

Crisis Management Plan, Corridor Facilitation Programme, Open Africa North

South Tourism Corridor

20,130,273.09

GRAND TOTAL 1,423,933,371.16

Table Summarising Concessional Loans

Development

Partner

Subsectors / Programmes Commitments for

2011/2012 (N$)

China Construction 177,680,000.00

Finland Fisheries 320,000,000.00

Germany Transport, Finance, Energy 285,207,300.00

Japan Transport 343,096,716.53

TOTAL 1,125,984,016.53

Page 30: Namibia - The New Port of Walvis Bay Container Terminal Project · PDF file · 2013-07-232.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ... International Importance,

Appendix IV. Map of the Project Area

Page 31: Namibia - The New Port of Walvis Bay Container Terminal Project · PDF file · 2013-07-232.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ... International Importance,

Annex I

I. REVIEW OF COUNTRY PARAMETERS FOR ELIGIBILITY FOR BANK FINANCING

1.1 Country’s Commitment

Has the Government demonstrated willingness to participate in project financing by efficiently

mobilizing Counterpart Funding?

Yes. The Government is providing: i) a Sovereign Guarantee against the ADB loan to Namport and

ii) providing a grant to the project of 250 million NAD (7.3% of total project cost).

Is the Government interested and actively involved in the implementation of the project?

Yes. Namport is under the purview of the Ministry of Works and Transport and its board is

appointed by the Minister and regularly reports to him. The project also includes a component on

logistics and trade facilitation funded by a Bank MIC TA Grant. This activity will involve different

government stakeholders including the National Planning Commission and Ministry of Works and

Transport during project implementation.

Is the project in a sector of priority under the Poverty Reduction Strategy?

Yes. The development agenda of the Government is contained in the Fourth National Development

Plan (NDP4), covering the period 2012/13-2016/17. NDP4 has identified logistics, as one of the

economic priorities and the Walvis Bay Port Expansion Project is clearly identified as one of the

national priorities under the Logistics pillar.

Has there been progress in achieving the Poverty Reduction Strategy objectives?

Yes. Namibia has made significant progress in addressing many development challenges. Access to

basic education, primary health care services, and safe water is high and growing. Sound public

policies are helping to lay the foundation for gender equality. Namibia maintains social safety net

programs for the elderly, disabled, orphans, vulnerable children, and war veterans, and has enacted a

Social Security Act that provides for maternity leave, sick leave, and medical benefits to Namibians.

Although Namibia is on track to meet the Millennium Development Goals on education,

environment and gender, the severity of the HIV/AIDS epidemic is frustrating efforts to meet the

Millennium Development Goals (MDGs) to reduce child mortality (MDG4), improve maternal

health (MDG5), and combat HIV/AIDS, malaria and other diseases (MDG6).

1.2 Country’s Financial Allocation to Sector

Is the country’s public expenditure allocation giving high priority to the sector concerned?

Yes. The Government has in the past few years allocated between 8%-10% of the national budget to

the transport sector. The sector is allocated NAD8.2 billion over the Medium-Term Expenditure

Framework covering the period 2011/12-2013/14 for, among others:- expansion of the port of

Walvis Bay, rehabilitation and railway infrastructure management, and development and

maintenance of national roads infrastructure.

1.3 Country’s Debt Level and Budget Situation

Can the country sustain additional debt and how is the current debt being managed?

The authorities project total debt stock to remain at about 27% of GDP in 2012, below Namibia’s

35% statutory debt-to-GDP threshold. Namibia’s debt levels remain sustainable, and can therefore

sustain additional debt. For Namport, an analysis on its capacity to borrow for this project shows

high debt service coverage ratios (DSCRs). For the existing loans that fully mature in 2018, the

average DSCR is 2.02x while the minimum is 1.30x. For the new loan, the average DSCR is 3.55x

and the minimum is 1.82x. The project is self-sufficient in debt servicing and no additional debt

burden is expected to fall on the government.

To what extent is the Government receiving co-financing from other donors?

Many bilateral donors scaled down their support to the country following its classification as an

upper MIC. The level of co-financing from donors is not significant relative to the national budget.

Page 32: Namibia - The New Port of Walvis Bay Container Terminal Project · PDF file · 2013-07-232.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ... International Importance,

Annex II

II. NAMIBIA - COUNTRY OUTLOOK

General Overview

Namibia is a middle income country that has enjoyed considerable successes since it gained independence

from South Africa in 1990 resulting from sound economic management, good governance, basic civic

freedoms, and respect for human rights. Namibia inherited a well-functioning physical infrastructure, a

market economy, rich natural resources, and a relatively strong public administration. The country also

inherited extreme social and economic inequities, however, which have left Namibia with a highly dualistic

society. Namibia’s per capita income of US$4,700 (2011, Atlas method) places it in the World Bank’s

upper-middle income grouping. However income distribution is among the most unequal in the world, with

a Gini coefficient estimated at 0.5971 by the latest (2009/10) household survey. Poverty incidence is high,

although it has declined somewhat during the past decade: 29% of individuals had consumption below the

national poverty line in 2009, compared to 69% in 1993.2

Economic Overview

Namibia’s economy is closely linked to South Africa’s economy through trade, investment, and common

monetary policies. The Namibian dollar is pegged to the South African rand, making economic trends

(including inflation) closely follow those in South Africa. The Namibian economy slowed down in 2011

with a GDP growth rate of 3.8%3, down from 6.6% in 2010, reflecting modest performances in mining and

agricultural activities. Prospects for the medium-term remain favourable with GDP growth projected to

continue on its path of recovery to an average of 4.2 percent for the years 2012 and 2013, driven by

construction, livestock and crop farming, manufacturing and mining. After years of fiscal surpluses arising

from prudent macroeconomic policies, the fiscal situation has deteriorated substantially, reflecting the

global economic crisis and expansionary policies to support growth. The budget for 2011/12 provides for

the continuation of the expansionary fiscal policy for the fourth successive year as the Government

commences the implementation of the three-year Targeted Intervention Programme for Employment and

Economic Growth (TIPEEG), totaling 14.7 billion Namibian dollars (NAD), aimed at creating and retaining

104, 000 jobs. As a result, the fiscal deficit is expected to widen, averaging nearly 6.5% of GDP between

2011/12 and 2012/13. The deficit is financed by domestic borrowing and foreign debt. Namibia’s debt

levels have risen in recent years, but remain sustainable and below the 30% threshold, despite the

expansionary fiscal policy.

Development Plans

In July 2012, the GRN launched the Fourth National Development Plan (NDP4), which will guide policies

through 2017. Economic growth, job creation, and increased income equality are the three overarching

objectives of NDP4. It proposes to achieve these objectives through industrial policies to stimulate growth

in tourism, regional trade logistics, agriculture and manufacturing (primarily through greater processing of

primary commodities). Reducing extreme poverty and improving education, health, infrastructure, and the

business environment enter into NDP4 as “basic enablers” that support the economic priorities. NDP4

presents ten “desired outcomes,” each accompanied by an indicator for measuring attainment of the

outcome, broad strategies expected to achieve the outcome, and a ministry that will serve as the champion.

This selectivity stands are in stark contrast to previous NDPs, whose agendas spanned the entire public

policy space.

2 World Bank Country Overview – Namibia 2013

3 African Economic Outlook – Namibia 2012

Page 33: Namibia - The New Port of Walvis Bay Container Terminal Project · PDF file · 2013-07-232.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ... International Importance,

- 1 -

Annex III

III. THE WALVIS BAY PORT

Ports and maritime in Namibia

Namport operates as the National Port Authority in Namibia since 1994 and manages both the Port of

Walvis Bay and the Port of Lüderitz in Namibia. The Port of Walvis Bay is situated at the west Coast of

Africa and provides an easier and much faster transit route between Southern Africa, Europe and the

Americas. The Port of Walvis Bay is Namibia's largest commercial port, receiving approximately 3,000

vessel calls each year and handling about 5 million tonnes of cargo. The port has good port infrastructures

which can be ranked among the best in Africa; together with tariffs which are still competitive compared

with their main competitors. These enable Walvis Bay to take advantage of the congestion and poor

productivity in Eastern and Southern African Ports (Tanzania, Mozambique, Angola and to a lesser extent

South Africa).

Recent performance

Namport achieved a record throughput of containers in 2012 of more than 337,000 TEU’s4 and overall

cargo volumes exceeding the 6 million ton mark for the first time ever. Revenue concomitantly also

exceeded N$700 million. Namport has regained higher volumes per vessel and the number of container

vessels has plateaued at around 46 per month on average (annualised at 560). This is the maximum number

of vessels that can be handled at present.

Namport’s opportunity and key differentiator remains in the SADC region. The economic growth in the

region exceeds that of most traditional markets and is the key to the company’s sustainability. The

opportunity remains in expanding intra-regional trade which is currently well below potential due to poor

infrastructure, lack of harmonisation of trade policies and cumbersome border procedures. The appointment

of the Walvis Bay Corridor Group to spearhead the recently established tri-partite Walvis Bay – Ndola –

Lubumbashi Development Corridor is testimony to the commitment of Namibia’s neighbouring countries to

regional integration.

Nature of the Transhipment Business at Namport

A significant share of the traffic in Walvis Bay is transhipment traffic (constituting 60% of container traffic)

particularly to / from ports in western and central Africa (including Angola) and transit traffic to/from

neighbouring countries (mainly South Africa and Angola) constitutes 34% of total shipments. The main

trading partner for imports are China (34%), Germany (16%) and USA (4%) and exports Spain (27%),

4 Namport Annual Report 2012

Page 34: Namibia - The New Port of Walvis Bay Container Terminal Project · PDF file · 2013-07-232.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ... International Importance,

- 2 -

China (11%), Germany and UK (7% each). Transshipment traffic has grown from 92,000 TEUs in 2006 to

218,000 TEUs in 2012 with an average annual growth rate (AAGR) of 55%. Transit traffic has also grown

over the same period from 25,000 TEUs to 65,000TEUs with AAGR of 25%. Some of the capacity issues

that Namport experience are largely a result of the increasing transhipment business. Transhipment demand

relates to a broader, regional market and in Namport’s case to the development of the countries to the north

of Namibia, right up to Ghana in West Africa. It is a function of the hub-and-spoke distribution model,

employed increasingly by the large international shipping lines.

African Shipping Activity

There are 24 container liner shipping operators in the West Coast of Africa region. This trade is dominated

by 3 large shipping lines: Maersk, CMA CGM and MSC in order of their respective share of trade capacity.

Combined, they offer 73% of all trade capacity in this region with Maersk and CMA CGM being the most

dominant. These 24 shipping lines operate 71 services to-and-from the region with a calculated trade

capacity of 3 656 000 TEU’s annually. The largest carrier by trade capacity is Maersk with 38% market

share.

i) This region is further separated into service types of:

ii) West Africa – Far East

iii) West Africa – Middle East / Indian Subcontinent

iv) West Africa – Southern Africa

It is in the latter region that Walvis Bay dominates. Walvis Bay and Cape Town account for 80% of the

region’s trade capacity. This goes some way towards explaining Namport and Walvis Bay’s rapid

improvement in another important shipping index: Liner Shipping Connectivity Index. In the past 7 years,

Namibia has improved from position 102 (out of 148 countries surveyed) to position 75. That is the same

positioning as countries like Kenya and Tanzania that enjoy centuries’ old trade routes

Competing Ports

Walvis Bay port has good port infrastructures which can be ranked among the best in Africa together with

tariffs which are still competitive compared with their main competitors. This enables the port to take

advantage of the congestion and poor productivity in Eastern and Southern African Ports (Mozambique,

Angola and to a lesser extent South Africa) and position itself as a transhipment port whilst also competing

for transit traffic with the other ports in the region. Out of South Africa’s eight ports, two are likely

competitors for Namibian ports, namely, Durban (for the traffic generated by the Gauteng province via the

trans-Kalahari) and Cogea for the transhipment traffic. The ports of Luanda, Lobito and Namib are

Angola’s main ports but considered not to pose significant threat in the short term due to its obsolete

infrastructure and inefficiencies (40 days waiting before berthing has been reported). A market study

conducted by Nathan Associates on the competing ports in the region has shown Walvis Bay’s potential to

become a regional hub port if it takes advantage of its current window of opportunity to expand and capture

the rising market demand whilst the government provides the complementary support of hard and soft

infrastructure. Other ports considered include the ports of Lagos/Apapa, Dar es Salaam Port, Port of Cape

Town, Port Elizabeth and Port of East London. Whereas some of these ports mostly serve local

import/export or transit, Walvis Bay is mainly focusing on transhipment cargo whilst also promoting the use

of its transport corridors to transit cargo for its landlocked neighbours and including the hinterlands of

Angola though the transcunene corridor. Although Cape Town is the closest South African port to Walvis

Bay and therefore could be considered its main competitor, it handles a very small volume of transshipment

and its capacity is limited.

The Walvis Bay Corridors and Group

The Walvis Bay Corridor Group is a public-private partnership established to promote the utilisation of the

Walvis Bay Corridors. This allows it to pool resources and authorities of both transport regulators and

transport operators, thus effectively serving as a facilitation center and one-stop shop coordinating trade

along the Walvis Bay Corridors and linking Namibia and its ports to the rest of the Southern African region.

Page 35: Namibia - The New Port of Walvis Bay Container Terminal Project · PDF file · 2013-07-232.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ... International Importance,

- 3 -

The Walvis Bay Corridor Group, is governed by a Board of Directors drawn from the different public and

private stakeholders within the transport and logistics sector. The Strategic focus and mandate of the WBCG

is: Business Development, Trade Facilitation, Infrastructure Development, Wellness service and Spatial

Development Initiatives (SDI’S) for the Walvis Bay Corridors

Logistics and Trade Facilitation

International comparisons show that, Namibia is one of the most efficient logistic environments of southern

Africa ranked 89th worldwide (and 3rd position in the SADC region in 2012) after South-Africa (ranked

24th) and Botswana (ranked 68th)). Many improvements have been made in the last few years on

infrastructures, logistics competences and customs facilitation. Logistics issues in Namibia relate more with

international than with domestic traffics. In this regard, Namibia promotes several international transport

corridors crossing the country mainly from the port of Walvis Bay. Since Namibian roads along these

transport corridors are still in relatively good condition, in particular as compared with African standards,

the main challenge is the improvement of cross-border facilitation procedures. Namibian authorities are

very proactive and significant progresses have been made to simplify and harmonize custom procedures.

The following main achievements and on-going projects must be mentioned:

A Single Administrative Document (SAD) has been adopted and is used on the trans-Kalahari corridor.

The development of a One-Stop Border Post (OSBP) is on-going on the main corridor (trans-Kalahari) as

a “pilot project”. It is planned to be operational in 2013 and it is contemplated that this system is

extended in the future to other border crossing on the trans-Cunene and trans- Caprivi.

Implementation of an electronic data exchange system between countries is under discussion and is

planned to be operational in 2013 at the OSBP between Namibia and Botswana.

The development of dry ports has started within the port of Walvis Bay. Even though the opportunity of

developing such dry ports within the perimeter of the port where there is a serious shortage of storage

areas, in particular for dry cargo, may be questionable, it is time now to take full benefit of these

facilities and to optimize their functioning.

Creation of the Walvis Bay Corridor Group (WBCG), a public and private sector collaboration, is aimed

to promote development of corridor infrastructure, businesses and trade facilitation, corridor best

practices and safe trade and transport corridors is continuing to yield results

Increasing presence in the region and internationally through WBCG regional offices in Lusaka,

Johannesburg, Lubumbashi and Sao Paulo is increasingly drawing businesses through the Walvis Bay

corridors;

Formulation of formal tripartite MoUs and partnerships on the Trans-Kalahari and Trans-Caprivi

corridors

The next steps forward include the following:

i) Increase volume and speed to maximize advantage:

Port of Walvis Bay becomes a regional hub port

Increase transportation capacity to inland (strengthen resource based bulk cargo)

Better trade facilitation (set up OSBP at all borders)

ii) Preparation for Strategic Master Plans for Logistics and Regional Urban Centres

iii) Global promotion of Walvis Bay to attract logistics/ distribution companies.

iv) Implementation of Development of Strategic Hubs

Development of logistics hubs based upon “National Logistics Master Plan”, further promotion of

trade facilitation (Single Window & Port Community System).

Development of regional urban centres based upon “Master plan on development of regional urban

centres” (Land Use Plan, Urban Infrastructure).

v) Diversification of Industries

Attract diverse industries due to excellent position as an international logistics hub.

Optimise growth of transit as well as transhipment traffic via the Port of Walvis Bay.

Page 36: Namibia - The New Port of Walvis Bay Container Terminal Project · PDF file · 2013-07-232.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ... International Importance,

Annex IV

IV. PROJECT DESCRIPTION

New Terminal Construction:

The proposed project is the strategic expansion of the Walvis Bay Container Terminal that will see the

creation of 30 hectares of new land reclaimed from channel at Walvis Bay. The new reclaimed land will be

created by dredging/deepening the port and using the sand obtained from deepening to form the new land.

The reclaimed land will be linked to the existing port land by a causeway. A new modern container terminal

will then be built on top of the newly reclaimed land and will consist of quay walls, paved areas, buildings,

roads, railway lines, ship to shore quay cranes, rubber tired gantry cranes, etc. The new container terminal

will have a capacity of 650,000TEU p.a. to complement the 355,000TEU p.a. capacity of the existing

container terminal, giving the Port a total capacity of 1,050,000TEUs with adequate space for optimisation

and future expansion. The project will not only provide increased container handling capacity in Walvis

Bay, but will also increase the port’s bulk and break handling capacity by freeing up the existing container

terminal to become a multi-purpose terminal. Once built, the conversion of the existing container berths into

a multipurpose terminal would open the port up for increased scope to accommodate a wide range of

additional bulk cargo vessels and even passenger liners.

Most of the quay wall infrastructure in the Port of Walvis Bay is very old and some of these reinforced

concrete structures have already reached the end of their design life. Namport has thus scheduled major

rehabilitation of these structures to occur within the next 10 years. The new container terminal project will

add an additional 600m of quay wall length to the existing 1800m and this will enable major rehabilitation

of existing quay walls to occur with minimal disruption to normal operations. The business case for the

project has been proven in a number of comprehensive studies that were undertaken as far back as 1980 and

of which the last of these preparatory studies were completed in November 2011. To date more than N$60

million has been committed to this project in conducting preparatory studies and investigations. The project

implementation period is three years

Logistics and Capacity Building financed by the Bank’s MIC TA Grant:

National Logistics Master Plan: The study will provide a comprehensive logistics policy and a system

development plan for Namibia with the target year of 2030. The activity includes amongst others: 1)

review of current situation of logistics; 2) analysis on prevailing business models of international logistics in

SADC; 3) analysis of commodity flow service in Namibia; 4) analysis of potential industries and business

models; 5) prefeasibility study on inland logistics park and on “One Stop Border Post”; 6) Integration of

ICT to facilitate and accelerate the growth in the transport and logistics sector and 7) Formulation of an

Action Plan for implementation and monitoring of the Logistics Master plan. The period of implementation

is 9 months.

Road Safety Program in SADC: The road safety program will replicate the Safe Trade and Transport

Corridors Project (executed on the Trans-Kalahari and Trans-Caprivi Corridors) on the Trans-Cunene

Corridor (TCuC) between Namibia and Angola. The activity will include: 1) support WBCG for the design

and implementation of a road safety action plan; 2) design and implementation of a road safety

assessments/audits; 3) design and implement a monitoring system to measure the impact of the road safety

action plan in the TCuC; 4) organize meetings with the authorities concerned and the public parties involved

to ensure adequate cooperation; and 5) disseminate information about the road safety action plans. The

project implementation is 9 months spread over a period of three years.

Capacity & Institutional Building for Walvis Bay-Ndola-Lubumbashi Corridor Management Committee

(WBNLD CMC): The WBNL or Trans Caprivi Corridor via Namibia is important for the Democratic

Republic of the Congo and Zambia. The Walvis Bay Corridor Group (WBCG) serve as the secretariat for

this corridor co-operation and hosts dialogue and meetings among the three countries based on a trilateral

Memorandum of Understanding. The Interim Secretariat hosted by the WBCG will be supported by

Page 37: Namibia - The New Port of Walvis Bay Container Terminal Project · PDF file · 2013-07-232.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ... International Importance,

providing technical assistance over a period of three years. This activity will also cover coordination,

hosting of meetings, travel and procurement of Information Technology Equipment and Software, Digital

Cameras, Scanners, Data Projectors and DVD Player / Recorders for the Committee.

Capacity and Institutional Building for WBCG Projects Development & Funding Department: This activity

builds capacity and support to the Walvis Bay Corridor Group Projects Development & Funding

Department to ensure ongoing transport facilitation advocacy activities on the country’s regional corridors.

The activity includes: 1) Technical assistance during three years, 2) travel & lodging, 3) organizing and

participating in conferences / Workshops / Seminars to present WBCG project portfolio, 4) Short-term

trainings and 5) Procurement of Information Technology Equipment and Project Management Software,

and Digital Cameras, Scanners, Data Projectors and DVD Player / Recorders. The implementation is over a

period of 3 years.

FIATA Training Program for Freight Forwarders: This activity will strengthen the professional competence

of Namibian freight forwarders in order to ensure that affordable and high-quality logistics services are

available for the needs of the users of the Walvis Bay corridors. The activity will: 1) assess detailed training

needs of registered freight forwarders in Namibia, 2) provide minimum 70 freight forwarders with FIATA

certified training, 3) compile a report for future actions in promoting logistics competence among freight

forwarders in Namibia. Priority in access to the training will be given to (i) female in-service freight

forwarders, (ii) female persons in related industries that are likely to benefit from the FIATA training and

(iii) female persons who intend to enter freight forwarding business. The target number of women to receive

the FIATA training is 40 out of the 70 trainees.

Page 38: Namibia - The New Port of Walvis Bay Container Terminal Project · PDF file · 2013-07-232.7 PARTICIPATORY PROCESS FOR PROJECT DESIGN AND IMPLEMENTATION ... International Importance,

Annex V

V. ENVIRONMENT AND SOCIAL

Environment and Social Action Plan (to be fulfilled before 30th

September 2013 as a condition of the

Loan):

i) A consultation/communications plan for the entire life of the project.

ii) A report on the analysis of the impacts of the project on services such as water, electricity, health

services.

iii) A plan of how the inclusion of the projects workforce will be serviced by the currently existing

HIV/AIDS programs.

iv) An comprehensive Environmental and Social Management Plan (ESMP), that must among others

entail a detailed waste management plan; a business continuity plan; a hazards (especially

technological) management plan; and a detailed plan for better assessing and monitoring the socio-

economic impacts of the project.

v) A report on the cumulative impact assessment for the project considering all other developments

planned for the foreseeable future.

vi) A report on gender analysis and a plan in order to align with the country’s gender equality plans and

if none exist in the country, the regional or international best standards to be applied.

vii) A climate change adaptation plan for the project that is in line with the National Climate Change

Action Plan.