41
National Perspective on Accelerated Bridge Construction Michael P. Culmo, P.E. CME Associates, Inc. East Hartford, CT

National Perspective on Accelerated Bridge Construction

  • Upload
    others

  • View
    9

  • Download
    0

Embed Size (px)

Citation preview

Page 1: National Perspective on Accelerated Bridge Construction

National Perspective on Accelerated Bridge Construction

Michael P. Culmo, P.E.CME Associates, Inc. East Hartford, CT

Page 2: National Perspective on Accelerated Bridge Construction

2

TECHNOLOGIES IN USE IN THE US

Page 3: National Perspective on Accelerated Bridge Construction

3

STATES USING ABC

2014 AASHTO Bridge Owners Survey (47 responses) Has your state used ABC for bridge projects? 43 Yes 3 No

If you answered “yes” to the above question, please provide your state’s policy for use of ABC: 44 ABC is considered at the project development stage 0 ABC is considered after contract execution by the contractor

A number of states have active ABC programs Massachusetts, New York, Utah, Pennsylvania, Vermont, Connecticut Note: Some are Accelerated Programs employing ABC

Page 4: National Perspective on Accelerated Bridge Construction

4

Work zone safety• Construction crews • Travelers

Work zones are designed to be safe, but…• We design for the minimums• Lane width• Shoulder widths• Drainage

Reality• In 2010: 37,476 injuries, 576 fatalities

Reduced construction time = Less Exposure

ABC and Work Zone Safety

Page 5: National Perspective on Accelerated Bridge Construction

5

NEED FOR SIMPLIFIED DETAILING

• Reduced risk during construction• Less chance of things not fitting• Faster construction• Less risk = Less cost

• Improved durability• Is durability a materials problem? Maybe• Is durability a detailing problem? Definitely

• Emulation of CIP concrete is good, but strict conversion to precast can be problematic

• Elimination of deck expansion joints should be a priority.

Page 6: National Perspective on Accelerated Bridge Construction

6

CIP DETAIL EXAMPLES

Page 7: National Perspective on Accelerated Bridge Construction

7

CIP DETAIL EXAMPLES

equals

Page 8: National Perspective on Accelerated Bridge Construction

8

DETAILING FOR SIMPLICITY• Investigate ways to simplify details without sacrificing

durability• Avoid complex 3D shapes• Avoid sloped surfaces if possible: Level is ok• Account for tolerances• If expansion joints are used, place them where they will not lead to

problems• If joints are required in sensitive areas, choose details that are

proven to be durable

Page 9: National Perspective on Accelerated Bridge Construction

9

PRECAST DECKS ON PS BEAMS

Page 10: National Perspective on Accelerated Bridge Construction

10

PRECAST DECKS ON STEEL FRAMING

Page 11: National Perspective on Accelerated Bridge Construction

11

ISSUES WITH PRECAST DECKSShear Connectors Concrete bridges Spacing of pockets can be more than 4 feet Steel bridges Cannot fit enough studs in the pockets

Negative moment regions Post-tensioned decks How do we accommodate LL stresses? Can get out of control Non-post-tensioned decks Leakage issues

Page 12: National Perspective on Accelerated Bridge Construction

12

Page 13: National Perspective on Accelerated Bridge Construction

13

GROUTED REINFORCING SPLICE COUPLERS

Page 14: National Perspective on Accelerated Bridge Construction

14

Latest Update Previous research in japan showed emulative behavior Recent new research has proven that this is the case Seismic testing at University of Nevada Reno and University of Utah Slightly different ductility behavior Consider placing couplers outside the columns Consider debonding a small portion of the coupler outside the sleeve

GROUTED REINFORCING SPLICE COUPLERS

Page 15: National Perspective on Accelerated Bridge Construction

15

MASSACHUSETTS PROJECT

Page 16: National Perspective on Accelerated Bridge Construction

16

GROUTED PT DUCTSGood for seismic connections

Based on Research in Texas, California and WashingtonNCHRP 12-74 (seismic)

Similar to grouted couplersGood for development into mass concrete

Lap splices?Check conflicts with transverse bars

Page 17: National Perspective on Accelerated Bridge Construction

17

CMP VOIDS

NCHRP 12-74 (seismic)Requires supplemental reinforcingRequires temporary support

Page 18: National Perspective on Accelerated Bridge Construction

18

INTEGRAL ABUTMENT BRIDGES

Superstructure resists soil forcesEliminated footingsUses fewer pilesJointlessConstruction in the dryVery cost effective

Page 19: National Perspective on Accelerated Bridge Construction

19

PRECAST INTEGRAL ABUTMENTS

Corrugated Pipe Void Pockets

Page 20: National Perspective on Accelerated Bridge Construction

20

CMP VOIDSCorrugated Void PocketsDeveloped in IowaTested for seismic connectionVery good shear capacity Footings Integral abutments Pier caps

Easy to form Reduces shipping weight

Page 21: National Perspective on Accelerated Bridge Construction

21

Charlemont, MA

Integral Abutment Project

Page 22: National Perspective on Accelerated Bridge Construction

22

CANTILEVER WALLSCMP Voids Used to: Reduce weightConnect cap to wall stemsConnect Stub Abutments to Footings

Page 23: National Perspective on Accelerated Bridge Construction

23

CANTILEVER ABUTMENTS• Connect cap piece with CMP Void

ConnectionComplex details left to one pieceSimplifies wall panelsLow moment demand connectionEasy construction

Page 24: National Perspective on Accelerated Bridge Construction

24

Worthington, MA

CANTILEVER ABUTMENTS

Page 25: National Perspective on Accelerated Bridge Construction

25

CANTILEVER ABUTMENTS

• Maine DOT Bridge

Page 26: National Perspective on Accelerated Bridge Construction

26

CIP Footing with Precast Column

Pile Supported Footings

Page 27: National Perspective on Accelerated Bridge Construction

27

Corrugated Column End• Based on FHWA Highways for LIFE Research in Washington• No reinforcing passing from column into footing• Good for pile supported foundations

Pile Supported Footings

Page 28: National Perspective on Accelerated Bridge Construction

28

PREFABRICATED SUPERSTRUCTURE - SPMT

Bridge Superstructure Installations

Page 29: National Perspective on Accelerated Bridge Construction

29

2 Superstructures replaced in 16 hours (including demolition of old bridges)

Bridge Superstructure Installations

Page 30: National Perspective on Accelerated Bridge Construction

30

ISSUES WITH SPMTS

Rental costs are still significant $50,000 to $1,000,000 depending on several factors

Availability is good, but not great This can affect the construction schedule

Risk is higher with SPMTsStill a viable option for high profile projects Bridges over high ADT Roadways

Page 31: National Perspective on Accelerated Bridge Construction

31

SLIDING/SKIDDING

Slide-in Bridge Construction (SIBC)

Page 32: National Perspective on Accelerated Bridge Construction

32

Superstructure – Sliding

Page 33: National Perspective on Accelerated Bridge Construction

33

BENEFITS OF SIBC

Costs are lower when compared to SPMTsSeveral ways to design the equipmentRisk is lowGreat for River Crossings Interstate bridges over local roads

Page 34: National Perspective on Accelerated Bridge Construction

34

MODULAR DECK BEAMS• 2 Beams with Precast Deck

Page 35: National Perspective on Accelerated Bridge Construction

35

MODULAR DECK BEAMS

Page 36: National Perspective on Accelerated Bridge Construction

36

LINK SLABS• Another option for multi-span bridges• Jointless, not continuous

Less complicated Less Expensive Great for prefabricated beam elements

• Used to accommodate the end rotations in the beams

Page 37: National Perspective on Accelerated Bridge Construction

37

NEXT BEAM• Precast Double Tee for Bridges• Developed by the PCI NE Bridge Tech Committee

Details at: www.pcine.org

Page 38: National Perspective on Accelerated Bridge Construction

38

DECK BULB TEES• Bulb Tee Beam with thicker top flange• Butted system

Page 39: National Perspective on Accelerated Bridge Construction

39

DURABILITY OF PREFABRICATED ELEMENTS• Utah DOT has studied performance of ABC projects• Projects built with latest details are performing very well•Connecticut DOT - Precast Decks (2)•Built in 1990•In excellent condition today•Florida DOT – Precast Piers•Built in extreme corrosive environment in 1995•In excellent condition today

Page 40: National Perspective on Accelerated Bridge Construction

40

CONCLUSIONS• The US is adopting the use of ABC on a wide scale• ABC is becoming standard practice• Improved safety is an added benefit• More states are implementing programs• Durability is not an issue• The technology is here and market ready• SHRP2 Products can be used for a wide variety of ABC projects

Page 41: National Perspective on Accelerated Bridge Construction

41

QUESTIONS

[email protected]