New BC3 RF Building. LIU-SPS 200 MHz RF power upgrade. New proposed area : BC3. Close to BA3 + BB3 = BC3. BC3 New RF Amplifiers. 929 RF workshop. All main RF equipments around Close to RF workshop - PowerPoint PPT Presentation

Citation preview

Page 1: New BC3 RF Building

New BC3 RF BuildingLIU-SPS 200 MHz RF power

upgrade

Page 2: New BC3 RF Building

New proposed area : BC3

Page 3: New BC3 RF Building

All main RF equipments around

Close to RF workshop

Take advantage of ‘nearly empty’ GT10 gallery to install 350 mm RF coaxial transmission linesEasiest path to the pit

Access through 929 RF workshop

Reserved place for BB3 transformers

if needed in the future to replace oil transformers to cast resin transformers

Close to BA3 + BB3 = BC3

La dalle pour nouveaux transformateurs 28m x 4m

BAE3 PhilipsBA3 Siemens

RF Faraday Cage

BB3800 MHz

929 RFworkshop

BC3 New RF Amplifiers

GT10 Gallery

Page 4: New BC3 RF Building

Total surfaces: Basement : 19.5 m x 36.5 m = 710 m2 Mezzanine : 475 m2 Total = 1185 m2

Total surfaces for RF: Basement = 550 m2 Mezzanine = 475 m2 Total = 1025 m2

RF amplifiers :

Tubes solution : 1030 m2 Tubes & combiners = 330 m2 Drivers & controls = 200 m2 Power supplies = 300 m2 Cooling = 200 m2

SSA solution : 1185 m2 SSA = 825 m2 Controls = 180 m2 Power supplies & cooling = 180 m2

Surfaces

36.5 m

19.5 m

Page 5: New BC3 RF Building

Schedule2011 2012 2013 2015 2016 2017 20192014

StudiesTendering

ConstructionInstallation

CommissioningStart up

2018

StudiesConstruction

coaxial lines, Pickups

New power couplers

Cavities

Pickups

vacuumCV, EL

StudiesAuthorizatio

nsConstruction

Services (CV, EL) #2

Spare sections

LLRF Design and proto

LLRF TestsLLRF Series

New RF Building

LSS3 Tunnel Integration

New RF Power Amplifiers and LLRF

2012 : Authorizations

2013 : Construction, NOT linked with LS1

Building ready end 2014 before first amplifier installation

Services ready six months later for commissioning

Page 6: New BC3 RF Building

BudgetItem Staff

FTE yearsTotal price

(FSU included) kCHF

Building Civil Engineering(Michael Poehler)

Basement (30 x 30) m2 x 4000 CHF/m2

First floor (15 x 30) m2 x 2000 CHF/m2

2.5 4’500

Building Ventilation(Mauro Nonis, based on Isolde last study)

1.5 1’000

Electrical Network High Power(Joel Lahaye)

Study, documentations, HV transformers 2 x 2 MVA, HV

cubicles, HV cabling, HV accessories

1.5 800

RF Power Amplifiers(including: RF power, Cooling, HVPS, Controls)

800 kW cw (1600 kW pulsed) x 5.0 CHF/W

(based on 800 MHz 2010 prices, 5.5 CHF/W for 60 kW, not including

combiners)

(RF power) 6.0(HVPS) 1.5

(CV) 2.5(RF Controls) 1.5

11’500

Coaxial lines 2 x 25 x 6 m x 6500 CHF/6m 1.0 500

Cavities modifications 4 x 150 kCHF + 2 x 100 kCHF 2.0 800

Main power Couplers 10 x 100 kCHF 2.0 1’000

Beam Control 2 x 700 kCHF 3.0 1’400

Total 28 26’500

Initial estimate (all inclusive)

Basement 900 m2 + Mezzanine 450 m2 = 4’500 kCHF / 2.5 FTE

CV & EL = 1’800 kCHF / 3.0 FTE

Total = 6’300 kCHF / 5.5 FTE

Building will be a bit smaller, budget difference will be useful for ‘un-scheduled’ issues

Page 7: New BC3 RF Building

Dep-Group Persons

BE-RF

Eric Montesinos, Thomas Bohl, Wolfgang Höfle, Urs Wehrle, Elena Shaposhnikova, Philippe Baudrenghien, SPS power team

BE-ABP Patrick Bestmann, Yannis Papaphilippou

BE-ASR Paula Carvalho Correia, Emmanuel Paulat

BE-BI Christian Boccard, Patrick Odier

DGS-SEE Guillaume Fontana, Cécile Pinto

EN-CV Michel Obrecht, Mauro Nonis

EN-ELGuillaume Gros, Joël Lahaye, Christophe Crombez

EN-HE Caterina Bertone, Pascal Brunero, Serge Pelletier, Yann Seraphin

Teams in charge

EN-MEF Frédéric Galleazzi, Yvon Muttoni, David McFarlane

GS-SELuz-Anastasia Lopez-Hernandez, Evelyne Crocci-Torti, Antoine Kosmicki

TE-VSC Paolo Chiggiato, Antonio Mongelluzzo

TE-MSC Jérémie Bauche