New Construction

PROGRESS UPDATE

June 2019

Brook Park Elementary School

Page 2: New Construction - Berea City School District€¦ · rook Park Elementary School project is the new construction of the elementary school is place on the demoed Ford Intermediate

EXECUTIVE SUMMARY

PROGRESS: Brook Park Elementary School

Area A:

• CMU Walls — 90% Complete

• Structural Steel — 100% Complete

• Metal Decking — 50% Complete

• Slab on Grade — 40% Complete

• Underground Electrical — 30% Complete

• AHU’s Set

Area B:

• CMU Walls — 100% Complete

• GYM Roofing — 50% Complete

• Structural Steel — 100% Complete

• Slab on Grade — 90% Complete

• Underground Electrical — 100% Complete

• Wall Branch Wiring — 35% Complete

• Brick Veneer — 80% Complete

• AHU’s Set

Area C:

• Brick Veneer — 80% Complete

• Interior Stud Framing — 75% Complete

• Drywall — 50% Complete

• Ceiling Insulation — 45% Complete

• Wall Insulation — 65% Complete

• Ground Sanitary Plumbing — 95% Complete

• Domestic Water Plumbing — 95% Complete

• Heating Water Piping — 90% Complete

• Chilled Water Piping — 90% Complete

• Ductwork — 100% Complete

• MEP Insulation — 60% Complete

• Wall Branch Wiring — 100% Complete

• Overhead Branch Wiring — 95% Complete

• Cable Tray — 1000%Complete

• Fire Suppression Piping — 60% Complete

• Aluminum Windows — 70% Complete

Area D: 1st Floor

• Exterior Stud Framing — 100% Complete

• Exterior Wall Sheathing — 50% Complete

• Interior Stud Framing — 90% Complete

• Sanitary Plumbing — 85% Complete

• Domestic Water Plumbing — 85% Complete

• Chilled Water Piping— 80% Complete

• Heated Water Piping — 800% Complete

• Ductwork — 85% Complete

• Wall Branch Wiring — 90% complete

• Overhead Branch Wiring — 90% Complete

• Cable Tray — 100% Complete

• Fire Suppression Piping — 40% Complete

Area D: 2nd Floor

• Roof Sheathing — 100% Complete

• Exterior Stud Framing — 100% Complete

• Exterior Wall Sheathing — 50% Complete

• Wall Branch Wiring — 10% Complete

• Sanitary Plumbing — 20% Complete

Sitework:

• Site Underdrain — 65% Complete

• House Gas Line — 100% Complete

• Water/Fire Line — 100% Compete

• Rough Grading — 95% Complete

• Curbs — 30% Complete

• Primary Electrical Service—85% Complete

Page 3: New Construction - Berea City School District€¦ · rook Park Elementary School project is the new construction of the elementary school is place on the demoed Ford Intermediate

PROJECT SUMMARY

Brook Park Elementary School project is the new construction of the elementary school is place on the

demoed Ford Intermediate School, while connecting to new school to the existing Auditorium.

• Area A: Administration Area & Existing Auditorium

• Area B: Gymnasium, Kitchen & Mechanical Rooms

• Area C: Single Story Academic Wing

• Area D: Two Story Academic Wing

PROJECT KEY PLAN

Brook Park Elementary

Page 4: New Construction - Berea City School District€¦ · rook Park Elementary School project is the new construction of the elementary school is place on the demoed Ford Intermediate

Brook Park Elementary School: PROGRESS PHOTOS

Slab on Grade (Music/Mech) — Area A

Structural Steel — Area B

Page 5: New Construction - Berea City School District€¦ · rook Park Elementary School project is the new construction of the elementary school is place on the demoed Ford Intermediate

Brook Park Elementary School: PROGRESS PHOTOS

Metal Decking Low Roof — Area B

Structural Steel Main Entrance Canopy — Area B

Page 6: New Construction - Berea City School District€¦ · rook Park Elementary School project is the new construction of the elementary school is place on the demoed Ford Intermediate

Brook Park Elementary School: PROGRESS PHOTOS

T.P.O Roofing — Area B

Roof & Floor Drains — Area B

Page 7: New Construction - Berea City School District€¦ · rook Park Elementary School project is the new construction of the elementary school is place on the demoed Ford Intermediate

Brook Park Elementary School: PROGRESS PHOTOS

Brick Veneer — Area B

Electrical Panels & Emergency Power Room — Area B

Page 8: New Construction - Berea City School District€¦ · rook Park Elementary School project is the new construction of the elementary school is place on the demoed Ford Intermediate

Brook Park Elementary School: PROGRESS PHOTOS

Glass Installed — Area C

Interior Soffit Framing — Area C

Page 9: New Construction - Berea City School District€¦ · rook Park Elementary School project is the new construction of the elementary school is place on the demoed Ford Intermediate

Brook Park Elementary School: PROGRESS PHOTOS

Exterior Walls Sheathing (North) — Area D

Exterior Metal Stud Walls (South) — Area D

Page 10: New Construction - Berea City School District€¦ · rook Park Elementary School project is the new construction of the elementary school is place on the demoed Ford Intermediate

Brook Park Elementary School: PROGRESS PHOTOS

Roof Sheathing (North) — Area D

Electrical Home Runs 2nd Floor — Area D