PROGRESS: Brook Park Elementary School
Area A:
• CMU Walls — 90% Complete
• Structural Steel — 100% Complete
• Metal Decking — 50% Complete
• Slab on Grade — 40% Complete
• Underground Electrical — 30% Complete
• AHU’s Set
Area B:
• CMU Walls — 100% Complete
• GYM Roofing — 50% Complete
• Structural Steel — 100% Complete
• Slab on Grade — 90% Complete
• Underground Electrical — 100% Complete
• Wall Branch Wiring — 35% Complete
• Brick Veneer — 80% Complete
• AHU’s Set
Area C:
• Brick Veneer — 80% Complete
• Interior Stud Framing — 75% Complete
• Drywall — 50% Complete
• Ceiling Insulation — 45% Complete
• Wall Insulation — 65% Complete
• Ground Sanitary Plumbing — 95% Complete
• Domestic Water Plumbing — 95% Complete
• Heating Water Piping — 90% Complete
• Chilled Water Piping — 90% Complete
• Ductwork — 100% Complete
• MEP Insulation — 60% Complete
• Wall Branch Wiring — 100% Complete
• Overhead Branch Wiring — 95% Complete
• Cable Tray — 1000%Complete
• Fire Suppression Piping — 60% Complete
• Aluminum Windows — 70% Complete
Area D: 1st Floor
• Exterior Stud Framing — 100% Complete
• Exterior Wall Sheathing — 50% Complete
• Interior Stud Framing — 90% Complete
• Sanitary Plumbing — 85% Complete
• Domestic Water Plumbing — 85% Complete
• Chilled Water Piping— 80% Complete
• Heated Water Piping — 800% Complete
• Ductwork — 85% Complete
• Wall Branch Wiring — 90% complete
• Overhead Branch Wiring — 90% Complete
• Cable Tray — 100% Complete
• Fire Suppression Piping — 40% Complete
Area D: 2nd Floor
• Roof Sheathing — 100% Complete
• Exterior Stud Framing — 100% Complete
• Exterior Wall Sheathing — 50% Complete
• Wall Branch Wiring — 10% Complete
• Sanitary Plumbing — 20% Complete
Sitework:
• Site Underdrain — 65% Complete
• House Gas Line — 100% Complete
• Water/Fire Line — 100% Compete
• Rough Grading — 95% Complete
• Curbs — 30% Complete
• Primary Electrical Service—85% Complete
PROJECT SUMMARY
Brook Park Elementary School project is the new construction of the elementary school is place on the
demoed Ford Intermediate School, while connecting to new school to the existing Auditorium.
• Area A: Administration Area & Existing Auditorium
• Area B: Gymnasium, Kitchen & Mechanical Rooms
• Area C: Single Story Academic Wing
• Area D: Two Story Academic Wing
PROJECT KEY PLAN
Brook Park Elementary
Brook Park Elementary School: PROGRESS PHOTOS
Slab on Grade (Music/Mech) — Area A
Structural Steel — Area B
Brook Park Elementary School: PROGRESS PHOTOS
Metal Decking Low Roof — Area B
Structural Steel Main Entrance Canopy — Area B
Brook Park Elementary School: PROGRESS PHOTOS
T.P.O Roofing — Area B
Roof & Floor Drains — Area B
Brook Park Elementary School: PROGRESS PHOTOS
Brick Veneer — Area B
Electrical Panels & Emergency Power Room — Area B
Brook Park Elementary School: PROGRESS PHOTOS
Glass Installed — Area C
Interior Soffit Framing — Area C
Brook Park Elementary School: PROGRESS PHOTOS
Exterior Walls Sheathing (North) — Area D
Exterior Metal Stud Walls (South) — Area D
Brook Park Elementary School: PROGRESS PHOTOS
Roof Sheathing (North) — Area D
Electrical Home Runs 2nd Floor — Area D