REQUEST FOR PROPOSAL (RFP) FOR Design, Financing, Installation,
Commissioning & Operation of a Hybrid Solar Photovoltaic System in New KCC Sotik
plant
NEW KENYA CO-OPERATIVE CREAMERIES LIMITED
NKCC/RFP/083/2019-20
REQUEST FOR PROPOSAL (RFP) FOR DESIGN,
FINANCING, INSTALLATION, COMMISSIONING &
OPERATION OF A HYBRID SOLAR PHOTOVOLTAIC
SYSTEM IN NEW KCC SOTIK FACTORY
New Kenya Co-operative Creameries Ltd.
P.O. Box 30131-00100,
Creamery House, Dakar Road, Ind. Area
Nairobi, Kenya
June 4, 2020.
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 2 of 43
SECTION I
LETTER OF INVITATION
Dear Sir,
New Kenya Cooperative Creameries Limited invites proposals for the provision of
design, financing, installation, commissioning & operation of a hybrid solar photovoltaic
system in New KCC Sotik Factory
The tenderer will be selected under Quality and Cost Based Selection method and the
procedures described in this RFP.
The tenderer shall attach a declaration in the proposal, that you are not debarred from
participating in procurement proceedings and that you will not engage in any corrupt
practice as per the attached declaration form.
The original and one copy of the proposal in plain sealed envelopes clearly marked on
top with the above RFP reference number shall be delivered to:
The Managing Director, New Kenya Co-operative Creameries Ltd.
P.O. Box 30131-00100, Creamery House, Dakar Road, Ind. Area Nairobi, Kenya
On or before 25th June 2020 at 10.00 a.m clearly marked “REQUEST FOR
PROPOSAL FOR DESIGN, FINANCING, INSTALLATION, COMMISSIONING
& OPERATION OF A HYBRID SOLAR PHOTOVOLTAIC SYSTEM IN NEW
KCC SOTIK FACTORY’’
The envelopes MUST be sealed.
Technical Proposals will be opened on 25th June 2020 at 10.00 a.m. in the presence of
the candidate’s representative if they choose to attend at New KCC Creamery House,
Dakar Road, Industrial Area. The Financial Proposals of the technically responsive bids
will be opened in the presence of the candidate’s representative if they choose to attend at
the same venue on a date to be communicated.
HEAD OF PROCUREMENT
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 3 of 43
TENDER NOTICE.
Tenders are invited from interested and eligible firms/suppliers to submit sealed bids for
the following:
Tender number Description Bid Security
(Ksh)
Eligib
ility
Site visit Closing/
opening
Date
NKCC/RFP/083/20
19-2020
Design, Financing,
Installation,
Commissioning &
Operation of a
Hybrid Solar
Photovoltaic System
Not
Applicable
Open 15th to 16th
June 2020 at
10.00 am to
12.00 p.m
and from
14.00 p.m to
16.00 p.m
25th June
2020 at
10.00 a.m
NKCC/T/084/2019
-2020
Supply, Installation
& Commissioning
of Dairy Equipment
at the Proposed
Cooling Plant
1,500,000.00
Open 15th June
2020 at 10.00
am to 12.00
p.m and from
14.00 p.m to
16.00 p.m
25h June
2020 at
10.00 a.m
NKCC/T/085/2019
-2020
Supply, Installation,
Testing &
Commissioning of
internal plumbing,
drainage and
firefighting systems
for cooling plant
400,000.00
Open 16th June
2020 at 10.00
am to 12.00
p.m and from
14.00 p.m to
16.00 p.m
25th June
2020 at
10.00am
NKCC/T/086/2019
-2020
Supply, Installation
& Commissioning
of Electrical Works
for cooling plant 1,000,000.00
Open 17th June
2020 at 10.00
am to 12.00
p.m and from
14.00 p.m to
16.00 p.m
26th June
2020 at
10.00 am.
NKCC/T/087/2019
-2020
Supply, Installation
& Commissioning
of Refrigeration
System at the
Proposed Cooling
Plant
400,000.00
Open 18th June
2020 at 10.00
am to 12.00
p.m and from
14.00 p.m to
16.00 p.m
26th June
2020 at
10.00am
NKCC/T/088/2019
-2020
Supply, Installation
& Commissioning
of Compressed Air
Systems at the
Proposed Cooling
Plant
300,000.00
Open 19th June
2020 at 10.00
am to 12.00
p.m and from
14.00 p.m to
16.00 p.m
26th June
2020 at
10.00am
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 4 of 43
NKCC/T/089/2019
-2020
Supply, Installation
& Commissioning
of Steam
generation/distributi
on s at the Proposed
Cooling Plant
450,000.00
Open 19th June
2020 at 10.00
am to 12.00
p.m and from
14.00 p.m to
16.00 p.m
26th June
2020 at
10.00 a.m
Complete tender/registration documents with detailed information may be obtained from the
office of Head of Procurement, New KCC Ltd, Dakar Road off Enterprise Road
between 9.00 a.m. and 4.00 p.m. upon payment of a non-refundable fee of Kshs. 1,000/-
(Kshs. One Thousand only) per tender document, paid in cash or Bankers Cheque.
Prospective bidders may also download the tender documents from
http://supplier.treasury.go.ke free of charge and New KCC Website (www.newkcc.co.ke).
Interested Bidders are required to send/e-mail their names and contact details to:
Bidders who are interested in site visit can collect their essential service passes from
Head of Procurement office, New KCC Ltd, Dakar Road off Enterprise Road between
9.00 a.m. and 4.00 p.m. for the specific date of visit.
Tenders must be accompanied by a Bid Security as specified above. The bid security should be
valid for 180 days from the tender closing/opening date and in form of either bank
guarantee, cash, Insurance Company Guarantee, a Letter of Credit, or Guarantee by a
Deposit taking Microfinance Institution, Sacco Society, the Youth Enterprise Development
Fund or the Women Enterprise Fund.
Completed tender documents in plain sealed envelope clearly marked with Tender
Number and Description should be addressed to:
The Managing Director
New KCC Ltd
P.O. Box 30131-00100
Nairobi
To be received not later than 10.00 a.m on the closing /opening date shown above.
MANAGING DIRECTOR
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 5 of 43
SECTION II - INFORMATION TO TENDERERS
2.1 Introduction
2.1.1 New KCC will select a tenderer among those invited to submit proposals or those
who respond to the invitation for proposals in accordance with the method of
selection detailed under this section and consistent with the regulations.
2.1.2 The tenderers are invited to submit a technical proposal and a financial proposal
for firms required for the assignment stated in the letter of invitation (Section I)
2.1.3 In the assignment where the New KCC intends to apply standard conditions of
engagement and scales of payments for professional services, which scale of
payments will have been approved by a relevant authority, a technical proposal
only may be invited and submitted by the tenderers. In such a case the highest
ranked individual tenderer in the technical proposals shall be invited to negotiate a
contract on the basis of the set scale of payments. The technical proposals will be
the basis for contract negotiations and ultimately for a signed contract with the
selected individual tenderer.
2.1.4 The tenderers must familiarize themselves with local conditions as regards to the
assignment and take them into account in preparing their proposals. To obtain
adequate information on the assignment and on the local conditions, tenderers are
encouraged to liase with the procuring entity regarding any information that they
may require before submitting a proposal.
2.1.5 The client will provide the inputs and services specified in the special conditions
of contract needed to assist the tenderers to carry out the assignment.
2.1.6 The cost of preparing the proposal and negotiating the contract including any visit
to the procuring entity are not reimbursable as a direct cost of the assignment.
The procuring entity is not bound to accept any of the proposals submitted.
2.1.7 The procuring entity’s employees, committee members, board members and their
relative (spouse and children) are not eligible to participate in the tender.
2.2 Clarification and amendment to the RFP documents
2.2.1 Tenderers may request clarification of any of the RFP documents not later than
Seven (7) days before the deadline for the submission of the proposals. Any
request for clarification must be sent in writing by post, fax or email to the New
KCC address indicated in the special conditions of contract. New KCC will
respond by post, fax or email to such requests and will send written copies of the
response (including an explanation of the query but without identifying the source
of inquiry) to all tenderers invited to submit proposals.
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 6 of 43
2.2.2 At any time before the deadline for submission of the proposals, the New KCC
may for any reason; either at its own initiative or in response to a clarification
requested by an intended tenderer amends the RFP. Any amendment shall be
issued in writing, fax or email to all invited tenderers and will be binding on them.
New KCC may at its discretion extend the deadline for the submission of the
proposals.
2.2.3 Clarification of tenders shall be requested by the tenderer to be received by New
KCC not later than 7 days prior to the deadline for submission of tenders.
2.2.4 New KCC shall reply to and clarifications sought by the tenderer within 3 days of
receiving the request to enable the tenderer to make timely submission of its
tender.
2.3 Preparation of proposals
2.3.1 The tenderer’s proposal shall be written in English language.
2.3.2 In preparing the Technical proposal, the tenderers are expected to examine the
documents constituting the RFP in detail. Material deficiencies in providing the
information requested may result in rejection of a proposal.
2.3.3 While preparing the Technical proposal, the tenderers must give particulars
attention to the following:
(a) If a tenderer considers that it does not have all the expertise required for the
assignment, it may suggest in the proposals other tenderers which will assist
in the assignment but they will not be party to the contract for the purpose of
the performance of the assignment. A tenderer will not propose other
tenderers invited to submit proposals for the assignment. Any tenderers in
contravention of this requirement shall automatically be disqualified.
(b) For all the staff who will be involved in the exercise of the proposals to
tenderer must indicate their responsibility in the assignment and also the staff
time as necessary. It is desirable that the majority of the key professional staff
proposed be permanent employees of the constituent firms forming the
tenderer or have an extended and stable working relationship with them.
(c) The curriculum vitae (CV) of the key staff proposed must be submitted with
the proposal.
2.3.4 The Technical proposal shall provide the following information;
(a) A brief description of the tenderer and an outline of recent experience on
assignments of a similar nature. For each assignment the outline should
indicate inter alia, the profiles of the staff used in the assignment, duration of
the assignment, contract amount and the tenderer/firm’s involvement.
(b) Any comments or suggestions on the Terms of Reference and a list of service
and facilities requested to be provided by New KCC.
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 7 of 43
(c) A description of the methodology and work plan for performing the proposed
assignment.
(d) The list of the proposed staff team by specialty, the tasks that would be
assigned to each staff team member and their timing.
(e) CVs recently signed by the proposed professional staff and the authorized
representative submitting the proposal. Key information should include
number of years working for the firm/entity and degree of responsibility held
in various assignments during the last Ten (10) years for Principle staff and 5
years for assisting staff.
(f) Estimates of the total staff input (professional and support staff staff-time)
needed to carry out the assignment supported by bar chart diagrams showing
the time proposed for each professional staff team member.
(g) Any additional information requested in the Terms of Reference.
2.3.5 The Technical proposal shall be separate from the financial proposal and shall not
include any financial information.
2.4 Financial proposal
2.4.1 The financial proposal will be quoted in payments per kWh as well as any other
cost.
2.4.2 The Financial proposal should include the payable taxes.
2.4.3 The payments shall be expressed in Kenya Shillings.
2.4.4 The Financial proposal must remain valid for 180 days after the submission date.
During this period the individual tenderer is expected to keep available at his own
cost any staff proposed for the assignment. The procuring entity will make best
efforts to complete negotiations within this period. If the procuring entity wishes
to extend the validity period of the proposals, the tenderers who do not agree,
have the right not to extend the validity of their proposals.
2.4.5 The financial proposal must comply with the law governing the profession of the
tenderer.
2.5 Submission, Receipt and opening of proposals
2.5.1 The technical proposal and the financial proposal (if required) shall be prepared in
indelible ink. It shall contain no interlineations or overwriting, except as necessary
to correct errors made by the individual tenderers. Any such corrections must be
initialed by the individual tenderer.
2.5.2 For each proposal the tenderers shall prepare the proposals in the number of
copies indicated in the special conditions of contract. Each Technical proposal
and financial proposal shall be marked “ORIGINAL” or “COPY” as appropriate.
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 8 of 43
If there are any discrepancies between the original and the copies of the proposal,
the original shall govern.
2.5.3 The original and all copies of the Technical proposal shall be placed in a sealed
envelope clearly marked “TECHNICAL PROPOSAL FOR DESIGN,
FINANCING, INSTALLATION, COMMISSIONING & OPERATION OF
A HYBRID SOLAR PHOTOVOLTAIC SYSTEM IN NEW KCC SOTIK
FACTORY’’, and the original and all copies of the financial proposal in a sealed
envelope duly marked “FINANCIAL PROPOSAL FOR DESIGN,
FINANCING, INSTALLATION, COMMISSIONING & OPERATION OF
A HYBRID SOLAR PHOTOVOLTAIC SYSTEM IN NEW KCC SOTIK
FACTORY’’. Both envelopes shall be placed in an outer envelope and sealed.
This outer envelope shall bear the New KCC address and other information
indicated in the appendix to the instructions to tenderers and clearly marked “DO
NOT OPEN BEFORE 25th June 2020 at 10.00 a.m.
2.5.4 The completed Technical and Financial proposals must be delivered at the
submission address on or before the time and date of the submission of the
proposals indicated in the appendix to the instructions to tenderers. Any
proposals received later than the closing date for submission of proposals shall be
rejected and returned to the tenderers unopened. For this purpose, the inner
envelopes containing the technical and financial proposals will bear the address of
the tenderers submitting the proposals.
2.5.5 After the deadline for submission of proposals the outer envelope and the
technical proposals shall be opened immediately by the opening committee. The
financial proposals shall be marked with the tenderers number allocated at the
time of opening the outer envelope and the technical proposals but shall remain
sealed and in the custody of a responsible officer of New KCC up to the time set
for opening them.
2.6 Evaluation of the Proposal (General)
2.6.1 From the time the proposals are opened to the time of the contract award, if any
tenderer wishes to contact the New KCC on any matter relating to its proposal, it
should do so in writing at the address indicated in the appendix to the instructions
to tenderers. Any effort by a tenderer to influence the New KCC staff in the
evaluation of proposals companion proposals or awards of contract may result in
the rejection of the tenderer’s proposal.
2.6.2 The proposal evaluation committee shall have no access to the Financial Proposal,
which in any case will remain sealed, until the technical evaluation is concluded
or finalized.
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 9 of 43
2.7 Evaluation of Technical Proposals
2.7.1 The evaluation committee appointed by the New KCC to evaluate the proposals
shall carry out the evaluation of technical proposals following the criteria set out
in the terms of reference based on the following points criteria.
2.7.2 Detailed Evaluation Criteria
A. Preliminary Evaluation Criteria:
• Valid Business Licence,2020 (local bidders)
• A CR12 Certificate by the Registrar of Companies in Kenya
• Dully filled Confidential Business Questionnaire
• A signed statement declaring that the bidder will not engage in corrupt practices
with regard to this tender
• A signed statement declaring that the bidder is not debarred from participating in
public procurement
• Copy of Registration Certificate/Incorporation (or equivalent for international
bidders)
• Valid TAX Compliance Certificate (local bidders only)
• Valid EPRA Class C1 license, Class V2 license and Class T3 license.
• Submission of an original and one copy of both technical & financial proposals.
• Submission of the technical proposal submission form enclosed with the original
technical proposal.
• Submission of the financial proposal submission form enclosed with the original
financial proposal.
• Sequential pagination of all pages of the bid documents (technical and financial),
i.e. from the beginning to the end of each bid document.
• Site visit certificate signed by New KCC authorized representative.
• Site visit date 15th to 16th June 2020 at 10.00 am to 12.00 p.m. and from 14.00
p.m. to 16.00 p.m.
NB: Failure to comply with any one of the preliminary evaluation criteria shall
lead to outright disqualification. Only those that meet all the preliminary
requirements shall proceed to the Technical Evaluation stage.
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 10 of 43
B. Technical Evaluation Criteria
NO. CRITERIA POINTS
i. Experience of the Tenderer in similar Works or services. Confirmation and
verification of evidence of similar services having been fully completed for
5 clients in the last 5 years in large solar system (300KVA minimum) of
which 2 must be of hybrid type power projects. This shall be evidenced by
award documents (purchase orders, contracts or completion certificates).
6 marks per award document per client.
30
ii. - Detailed description of proposed power plant describing operating
principles, single line diagram and schematic of plant layout. (10)
This will include proposed solar module mounting location and
space requirements, inverter location, DC & AC cable routing and
power tie-in point. The bidder must indicate suitability of selected
roofs to carry the weight of the solar modules or the ground
suitability for the module, 10 points.
- The solar plant should be capable of operating in parallel to the grid
or diesel generator, 5 points.
- Operation and maintenance plan to ensure minimal plant
downtime, 5 points.
- Demonstrable renewable energy fraction computed through
industry leading software such as PVSyst or Homer, or equivalent
10 points.
Marks shall be awarded based on accuracy and relevance of the description.
40
iii. Demonstrate financial capability to fund the project either through latest
audited accounts not older than 2018 which shows capacity to avail capital
requirements of up to KES 100 million,
OR
a letter of undertaking from a reputable financing entity, 20 points
Evidence of prior financing arrangements for successfully funded projects
in the last five years, 10 points
30
TOTAL 100
Note: The pass mark shall be 70%. The formulae and procedures below shall apply to
bidders who qualify by the pass mark.
2.7.3 Any proposal which will be examined and found not to comply with all the
requirements for submission of the proposals will be declared non responsive. All
the proposals found to have complied with all the requirements for submission of
proposal shall be declared responsive by the evaluation committee
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 11 of 43
2.7.4 Each responsive proposal will be given a technical score (ST). Any technical
proposal which fails to achieve the total minimum score indicated in the
evaluation criteria shall be rejected at this stage and will not proceed to the next
stage of evaluation. The respective financial proposal will be returned to the
individual tenderer unopened.
2.8 Opening and Evaluation of Financial Proposals
2.8.1 After completion of the evaluation of Technical proposals the procuring entity
shall notify the individual tenderers whose proposal did not meet the minimum
technical score or were declared non responsive to the RFP and terms of
reference. The notification will indicate that their financial proposals shall not be
opened and will be returned to them unopened after the completion of the
selection process and contract award. At the same time, New KCC shall
simultaneously notify the tenderers who have secured the minimum technical
score that they have passed the technical qualifications and inform them the date
and time set by the procuring entity for opening their financial proposal. They
will also be invited to attend the opening ceremony if they wish to do so.
2.8.2 The financial proposals shall be opened by the procuring entity in the presence of
the tenderers who choose to attend the opening. The name of the tenderer, the
technical score and the proposed payments shall be read out aloud and recorded.
The evaluation committee shall prepare minutes of the opening of the financial
proposals.
2.8.3 NB: THE TENDER SHOULD BE AWARDED TO THE BIDDER WHO
SHALL SELL POWER AT THE LOWEST PRICE AND MEETS ALL THE
TECHNICAL REQUIREMENTS (PASS MARK)
2.9 Negotiations
2.9.1 Negotiations will be held at the same address indicated in the appendix to the
information to tenderers. The purpose of the negotiations is for New KCC and
the tenderers to reach agreements on all points regarding the assignment and sign
a contract.
2.9.2 The negotiations will include a discussion on the technical proposals, the
proposed methodology and work plan, staff and any suggestions made by the
tenderer to improve the Terms of Reference. The agreed work plan and Terms of
Reference will be incorporated in the description of the service or assignment and
form part of the contract.
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 12 of 43
2.9.3 The negotiations will be concluded with a review of the draft contract. If
negotiations fail, New KCC will invite the tenderer whose proposal achieved the
second highest score to negotiate a contract.
2.10 Award of Contract
2.10.1 The contract will be awarded before commencement of negotiations. After
negotiations are completed New KCC will promptly notify the other tenderers
that they were unsuccessful and return the financial proposals of the tenderers
which did not pass technical evaluation.
2.10.2 The selected tenderer is expected to commence the assignment on the date
indicated in the appendix to the information to tenderers or any other date agreed
with New KCC.
2.11 Confidentiality
2.11.1 Information relating to evaluation of proposals and recommendations of contract
award shall not be disclosed to the tenderers who submitted the proposal or to
other persons not officially concerned with the process, until the winning tenderer
has been notified that it has been awarded the contract.
Appendix to Information to Tenderers
The following information for procurement of consultancy services and selection of
tenderers shall complement or amend the provisions of the information to tenderers,
wherever there is a conflict between the provisions of the information and to tenderers
and the provisions of the appendix, the provisions of the appendix herein shall prevail
over those of the information to tenderers.
Clause Reference
2.1 The name of the Client is: New Kenya Co-operative Creameries Ltd
2.1.1 The method of selection is: Quality and Cost Based Selection method
2.1.2 Technical and Financial Proposals are requested: Yes
The name, objectives, and description of the assignment are:
Selection of a tenderers for the design, financing, installation, commissioning
& operation of a hybrid solar photovoltaic system in New KCC Sotik
factory
2.1.3 A pre-proposal conference will be held: No
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 13 of 43
The name(s), address (es) and telephone numbers of the Client’s official(s) are:
The Managing Director
New Kenya Co-operative Creameries Ltd.
P.O. Box 30131-00100,
Nairobi, Kenya
Tel: 254 20 3980 200
Email: [email protected]
2.1.4 The Client will provide the following inputs: technical staff to provide relevant
information to the tenderers on need basis.
2.1.5 (ii) The estimated number of professional staff months Required for the
assignment is: N/A
(iv) The minimum required experience of proposed professional staff is:
As per evaluation Technical Staff Requirements under SECTION III
2.1.6 (vii) Training is a specific component of this assignment: Yes
(viii) Additional information in the Technical Proposal includes: N/A.
2.1.7 This RFP document is free of charge.
2.4.2.1 Taxes
a) "Taxes" means all present and future taxes, levies, duties, charges,
assessments, deductions or withholdings whatsoever, including any interest
thereon, and any penalties and fines with respect thereto, wherever
imposed, levied, collected, or withheld pursuant to any regulation having
the force of law and "Taxation" shall be construed accordingly.
b) Local Taxation
i). Nothing in the Contract shall relieve the Contractor and/or his Sub-
Contractors from their responsibility to pay any taxes, statutory
contributions and levies that may be levied on them in Kenya in respect of
the Contract. The Contract Price shall include all applicable taxes and
shall not be adjusted for any of these taxes.
ii). The Contractor shall be deemed to be familiar with the tax laws in the
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 14 of 43
Employer's Country and satisfied themselves with the requirements for all
taxes, statutory contributions and duties to which they may be subjected
during the term of the Contract.
iii.) In instances where discussions are held between the Employer and the
Contractor regarding tax matters, this shall not be deemed to constitute
competent advice and hence does not absolve the Contractor of their
responsibility in relation to due diligence on the tax issue as per 3 .21 .2
above.
c) Tax Deduction
i). If the Employer is required to make a tax deduction by Law, then the
deduction shall be made from payments due to the Contractor and
paid directly to the Kenya Revenue Authority. The Employer shall upon
remitting the tax to Kenya Revenue Authority furnish the Contractor with
the relevant tax deduction certificates.
ii). Where the Contractor is paid directly by the Financiers and the Employer
is not able to deduct tax, then the Contractor will be required to pay the
tax deduction to Kenya Revenue Authority in the name of the Employer
and furnish the Employer with an original receipt thereof as evidence of
such payment. In absence of the said evidence, the Employer will not
process any subsequent payments to the Contractor.
d) Tax Indemnity
i). The Contractor shall indemnify and hold the Employer harmless from and
against any and all liabilities, which the Employer may incur for any
reason of failure by the Contractor to comply with any tax laws arising
from the execution of the Contract whether during the term of the
Contract or after its expiry.
ii) The Contractor warrants to pay the Employer (within fourteen (14) days of
demand by the Employer), an amount equal to the loss, liability or cost
which the Employer determines has been (directly or indirectly) suffered by
the Employer for or on account of the Contractor’s Tax liability arising
from the Contract.
iii). Where the amount in 3.21.8 above remains unpaid after the end of the
fourteen (14) days moratorium, the Employer shall be entitled to
compensation for financing charges.
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 15 of 43
2.5.2 Tenderers must submit one original and one copy to New KCC bound in a
standard way. The tenderer will also submit soft copies in a CDROM, a flash disk
or any other soft format.
2.5.3 The proposal submission address is:
The Managing Director,
New Kenya Co-operative Creameries Ltd.
P.O. Box 30131-00100,
Nairobi, Kenya
Information on the outer envelope should also include the tender description and
number.
2.5.4 Proposals must be submitted no later than the following date and time: 25th June
2020 at 10.00 a.m.
2.6.1 The address to send information to the Client is:
The Managing Director,
New Kenya Co-operative Creameries Ltd.
P.O. Box 30131-00100,
Nairobi, Kenya
2.8.7.1 A variation request must be approved by the Employer
2.9.2 The assignment is expected to commence immediately after signing of the contract
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 16 of 43
SECTION III
TERMS OF REFERENCE (TOR) FOR DESIGN, FINANCING, INSTALLATION,
COMMISSIONING & OPERATION OF A HYBRID SOLAR PHOTOVOLTAIC
SYSTEM IN NEW KCC SOTIK FACTORY
BACKGROUND
General
New Kenya Co-operative Creameries Limited Sotik Factory is a milk processing plant
with installed handling capacity of 250,000 litres per day. The site is fed by a 500kVA
dedicated transformer and billed under the CI1 category. Average consumption from the
grid was 1,428,016 kWh in 2017 and 945,206 kWh in 2018. This translated to KES
27,809,511 and KES 21,081,245 respectively. Updated operations and energy
consumption data will be provided during the site visit. Sotik is one of New KCC UHT
factories with 25% revenue contribution meaning that it has to operate efficiently for the
organization to be sustainable.
Solar Photovoltaic power switch at Sotik can take up to 40% of the power bill cost used
during the day. Under the current set up, Sotik factory uses 69 % imported power from
KPLC and 31% is generated internally using stand by 500 KVA generator.
The facility has roof and ground space available for consideration to mount the solar
modules. Bidders are required to verify dimensions and suitability during site visit.
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 17 of 43
CLIENT will require the Tenderer to render all technical support services which may be
deemed relevant to the above work. The detailed description of the work to be performed
is described in these Terms of Reference (TOR).
Selection Criteria
The Tenderer selected to undertake the work shall have had extensive experience in the
Design, installation, commissioning, maintenance and lease of solar PV power which will
be adequate for the proposed assignment.
Project Description/Project Location
The site of the proposed project is New KCC Sotik Factory in Sotik town.
OBJECTIVES
Contractor/supplier shall provide a total turnkey project including all necessary
equipment, materials, design, manufacturing, and installation services for the installation
of a Rooftop Hybrid/ground mounted Solar PV Power Plant with optional storage.
Contractors will be required to carry out individual analysis of the client’s consumption
and load demand profile, and from this, propose the most optimum system size.
The employer will review the proposed project financing and ownership structure. The
contractor/supplier should prepare a system summary detailing each section, applicable
equipment/size, and predicted system energy production (kWh). The project shall meet
all requirements of this statement of work and other specifications included that apply.
The overall objective of the project is to reduce the overall cost of electricity, stabilize
power supply and switch to environmentally clean energy. This should be lower than
prevailing KPLC rates at any given time.
SCOPE OF SERVICES
The client intents to enter into financing arrangement with a successful bidder where the
vendor will design, finance, install and operate the system while the client pays for the
energy produced.
The Assignment is expected to cover the following items within condensed timelines to
be proposed by the Tenderer. The Tenderer is required to provide the condensed program
in the relevant part of the proposal, clearly indicating the activities, the start date and the
period each activity will take to complete.
The contractor/supplier shall perform all professional services as necessary to provide
NKCC with a complete design package, including the requirements outlined in this
statement of work. The contractor shall install the project such that it is operational and
compliant with all applicable standards, building codes, KPLC interconnection
requirements, and EPRA requirements. The contractor shall include specifications,
calculations, and drawings in the design package and submit it to the employer for review
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 18 of 43
and approval. After approval of the final design package, the contractor/supplier shall
provide all necessary construction services to successfully implement the Solar PV Power
Plant and system installation. The tenderer shall in the end lease to the client metered
electricity from the Solar PV installation.
Location and Extent of Contract
The site of the proposed factory is New KCC Sotik Factory.
Specific activities
The responsibilities delegated to the Tenderer will call for the services listed below,
without, however, being necessarily and strictly restricted to the items identified:
Contractor’s Activities
• Conceptual Design Drawings
• Construction documents and engineering calculations that are signed and
sealed by a licensed surveyor or professional engineer in the appropriate
discipline of the subject design drawings (ie geotechnical, electrical, structural)
• Submittals for materials and products
• Construction materials, equipment, and labour
• Design and construction supervision/contract management
• A quality control plan (QCP)
• A safety plan
• Inspections and tests (per QCP)
• Manuals (e.g., design calculations, operation/maintenance, a shop drawing,
etc.)
• Commissioning of the project
• Mentoring and training of NKCC staff for operation and maintenance
• Operation and maintenance during the lifetime of the PPA agreement and a
service plan for the lifetime of the project
• A web-based performance and status monitoring system for the Solar PV Plant
for a period 25 years
• Establish the optimal project financing model.
Client’s Activities
• Provide information and facilitate site visits per the contractor’s request
• Review for approval design submittals and QCP
• Witness inspections to verify attainment of performance requirements.
• Facilitate project permits with appropriate authorities as necessary.
DETAILED DESCRIPTION OF THE SERVICES
CONCEPT DRAWINGS
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 19 of 43
Concept Drawings
The contractor/Supplier shall provide the employer with conceptual design drawings with
the proposal. The conceptual design drawings must indicate the proposed location of the
PV array(s) and access points along with a single-line electrical diagram showing inverters,
transformers, meters, and interconnection locations.
Conceptual Design Information
The proposal shall include major equipment information, proposed
installation/interconnection information and performance characteristics of the system. The
proposal shall identify an appropriate location for the solar PV inverter equipment and its
related components and environmental control systems that will meet the following criteria:
• Ease of maintenance and monitoring
• Efficient operation
• Low operating losses
• Secured location and hardware
• Compatibility with existing facilities
• All products shall comply with the technical requirements in this document.
• At a minimum, the proposed concept information shall include:
Equipment Information
• System description
• Layout of installation
• Selection of key equipment and layout of equipment
• Performance of equipment components and subsystems
• Specifications for equipment procurement and installation
• All engineering associated with structural and mounting details
• Controls, monitors, and instrumentation
• Operation and maintenance service plan
Installation Interconnection Information
• Solar electric array orientation/ azimuth (degrees)
• Solar electric module tilt (degrees)
• Electrical grid interconnection requirements
• Integration of solar PV system with other power sources
• System type and mode of operation
Performance Characteristics
• Shading calculation documentation
• Total system output (kWh/year)
• Estimated kWh/month per array (shown over a 12-month period)
• Warranties and guarantees
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 20 of 43
Interconnection Agreement
Provide confirmation that the PV systems will be designed to comply with
applicable KPLC and EPRA interconnection requirements
Cost
A Financial proposal of the PPA price and terms
DESIGN SERVICES
The solar PV system shall be designed and engineered to maximize the solar energy
resources, taking into consideration the electrical demand and load patterns, proposed
installation sites, available solar resources, existing site conditions, proposed future site
improvements, and other relevant factors.
Design services for this project shall require a schematic design submission, a design
development submission, a check set submission, and a construction document submission.
A final set of as-built drawings shall also be provided to NKCC. These submissions shall
be delivered based on the project schedule submitted and approved by NKCC. The design
package shall include the following details:
Timeline/Project Schedule. The Contractor/Supplier shall provide an estimate of the
project timeline and schedule.
Post-award Conference. The contractor shall hold a post-award conference within 14
calendar days after receipt of the contract award. The meeting will be attended by NKCC
team members and the contractor’s/Supplier’s personnel. At a minimum, the prime
contractor’s project manager and foreman, the primary designer, and a representative of
any subcontractor performing over 25% of the work shall attend. The meeting shall
include a site walk of the project location. The purpose of the meeting will be to discuss
the contractor’s plan for completing the design and construction, including a construction
schedule.
Specifications. A full set of specifications shall be required for this project.
Specifications that express all information and demonstrate sufficient detail so as to direct
the construction work outlined in this statement of work shall be required. The
specifications package shall be coherent enough that any contractor not familiar with the
project would be able to construct the project design. The specifications shall include all
equipment information, proposed installation and interconnection information, and
performance characteristics of the system.
The contract shall take into account a construction plan producing a minimum disruption
of day-to-day activities, utilities, services, etc.
Construction Drawings
Provide drawings for each discipline required (architectural, structural, electrical, etc.),
with separate plans for new work and demolition as well as special types of drawings
where necessary, such as enlarged plans, equipment curbing and flashing details, etc.
Drawings shall clearly distinguish between new and existing work.
Each drawing shall indicate project title, project number, array identification and
location, architect/engineer (A/E) firm, A/E’s address and/or phone number, contract
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 21 of 43
number, drawing title, drawing type, drawing number, and key plan. A cover sheet shall
be provided and shall include a list of the drawings, legend, vicinity map, and location
map in addition to all items required for each drawing. Each A/E submission shall be
clearly dated and labelled. Each drawing sheet submitted shall include a graphic scale in
the lower right-hand portion of the sheet. The final set shall be stamped by a licensed
engineer as per EPRA regulations.
At a minimum, the following drawings are required:
• Site plan including utility locations and connections – showing staging and
phasing requirements
• Electrical plans – including single line diagram and utility interconnection
• Electrical details
• System Layout – showing the full layout of the system and detailing any obstacles
that must be permanently or temporarily removed or relocated
• Array support and mounting details
• Any drawings that may be required to install a complete project
The contract documents shall sufficiently define the statement of work and shall stand on
their own.
Specifically address the means to keep the existing building accessible and operational by
means of relocation and/or phasing.
Calculations. The contractor will provide the following calculations:
System Electrical Calculations. Provide with design development and again with 100%
check set.
• PV Watts calculation
• System energy production calculation showing estimated monthly and yearly
energy output for each array
• Energy value and project cash flow
• Electrical drawings for the entire project
Solar PV Plant performance calculated by a detailed PV analysis program using industry-
recognized PV design software tools using proposed specific PV modules and inverters.
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 22 of 43
SECTION IV
CONTRACT FOR TENDERER’S SERVICES
Between
_______________________
[Name of the Client]
AND
___________________________
[Name of the Tenderer]
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 23 of 43
Dated: _________________[date]
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 24 of 43
FORM OF CONTRACT
This Agreement (hereinafter called the “Contract”) is made the ________)day of the month of
_______________[month], [year], between ___________________________________, [name
of client] of [or whose registered office is situated at
]_________________________________________[location of office] (hereinafter called the
“Client”) of the one part AND
____________________________________________[name of tenderer] of [or whose registered
office is situated at]
________________________________________________________[location of
office](hereinafter called the “Tenderer”) of the other part.
WHEREAS
(a) the Client has requested the Tenderer to provide certain firmsas defined in the
General Conditions of Contract attached to this Contract (hereinafter called the
“Services”);
(b) the Tenderer, having represented to the Client that he has the required
professional skills and personnel and technical resources, have agreed to provide
the Services on the terms and conditions set forth in this Contract;
NOW THEREFORE the Parties hereto hereby agree as follows:
1. The following documents attached hereto shall be deemed to form an integral part of this
Contract:
(a) The General Conditions of Contract;
(b) The Special Conditions of Contract;
(c) The following Appendices: [Note: If any of these Appendices are not used, they
should be deleted from the list]
Appendix A: Letter of Award and Acceptance
Appendix B: Terms of Reference
Appendix C: Comments on Terms of Reference
Appendix D: Description of the Methodology and
Work plan for performing the assignment.
Appendix E: Time schedule for professional Personnel
Appendix F: Team Composition and Task assignments
Appendix G: Curriculum Vitae (CV) for proposed
professional staff
Appendix H: Activity (Workplan) Schedule
Appendix I: Breakdown of Contract price in Kshs
Appendix J: Other submissions
➢ Technical proposal submission form
➢ Firm’s References
➢ Financial proposal submission form N/A
Appendix K: The request for proposals
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 25 of 43
2. The mutual rights and obligations of the Client and the Tenderers shall be as set forth in
the Contract; in particular:
(a) The Tenderer shall carry out the Services in accordance with the provisions of
the Contract; and
(b) the Client shall make payments to the Tenderer in accordance with the provisions
of the Contract.
IN WITNESS WHEREOF, the Parties hereto have caused this Contract to be signed in their
respective names as of the day and year first above written.
For and on behalf of___________________________________________[name of client]
[full name of Client’s
authorisedrepresentative_____________________________________________
[title]________________________________________________
[signature]___________________________________________
[date]________________________________________________
For and on behalf of ______________________________________ [name of tenderer]
[full name of Tenderer’s
authorized representative]___________________________________
[title]______________________________________________
[signature]_________________________________________
[date]_______________________________________________
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 26 of 43
GENERAL CONDITIONS OF CONTRACT
1.0 GENERAL PROVISIONS
1.1 Definitions Unless the context otherwise requires, the
following terms whenever used in this Contract
shall have the following meanings:
(a) “Applicable Law” means the laws and any other
instruments having the force of law in the Republic of
Kenya as they may be issued and in force from time to
time;
(b) “Contract” means the Contract signed by the Parties, to
which these General Conditions of Contract (GC) are
attached together with all the documents listed in Clause
1 of such signed Contract;
(c) “Contract Price” means the price to be paid for the
performance of the Services in accordance with Clause 6
here below;
(d) “Foreign Currency” means any currency other than the
Kenya Shilling;
(e) “GC” means these General Conditions of Contract;
(f) “Government” means the Government of the Republic
of Kenya;
(g) “Local Currency” means the Kenya Shilling;
(h) “Member”, in case the Tenderer consists of a joint
venture of more than one entity, means any of these
entities; “Members” means all these entities, and
“Member in Charge” means the entity specified in the
SC to act on their behalf in exercising all the Tenderer’s
rights and obligations towards the Client under this
Contract;
(i) “Party” means the Client or the Tenderer, as the case
may be and “Parties” means both of them;
(j) “Personnel” means persons hired by the Tenderer or by
any Subtenderer as employees and assigned to the
performance of the Services or any part thereof;
(k) “SC” means the Special Conditions of Contract by
which the GC may be amended or supplemented;
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 27 of 43
(l) “Services” means the work to be performed by the
Tenderer pursuant to this Contract, as described in
Appendix A; and
(m) “Subtenderer” means any entity to which the Tenderer
subcontracts any part of the Services in accordance with
the provisions of Clauses 3 and 4.
1.2 Law Governing This Contract, its meaning and interpretation
the Contract and the relationship between the Parties shall be governed by the
Laws of Kenya.
1.3 Language This Contract has been executed in English language which shall
be the binding and controlling language for all matters relating to
the meaning or interpretation of this Contract.
1.4 Notices Any notice, request, or consent made pursuant to this Contract
shall be in writing and shall be deemed to have been made when
delivered in person to an authorized representative of the Party to
whom the communication is addressed or when sent by
registered mail, telex, telegram or facsimile to such Party at the
address specified in the SC.
1.5 Location The Services shall be performed at such locations as are
specified in Appendix A and, where the location of a particular
task is not so specified, at such locations, whether in the
Republic of Kenya or elsewhere, as the Client may approve.
1.6 Authorized Any action required or permitted to be taken and
Representatives any document required or permitted to be executed under this
Contract by the Client or the Tenderer may be taken or executed
by the officials specified in the SC.
1.7 Taxes and The Tenderer, Subtenderer[s] and their
Duties personnel shall pay such taxes, duties, payments and other
impositions as may be levied under the Laws of Kenya, the
amount of which is deemed to have been included in the
Contract Price.
2. COMMENCEMENT, COMPLETION, MODIFICATION AND TERMINATION OF
CONTRACT
2.1 Effectiveness of This Contract shall come into effect on the date
Contract the Contract is signed by either Parties or such other later date as
may be stated in the SC.
2.2 Commencement The Tenderer shall begin carrying out the
of Services Services thirty (30) days after the date the Contract becomes
effective or at such other date as may be specified in the SC.
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 28 of 43
2.3 Expiration of Unless terminated earlier pursuant to Clause
Contract 2.6, this Contract shall terminate at the end of
such time period, after the Effective Date, as is
specified in the SC.
2.4 Modification Modification of the terms and Conditions of this Contract,
including any modification of the scope of the Services or the
Contract Price, may only be made by written agreement between
the Parties.
2.5 Force Majeure
2.5.1 Definition For the purposes of this Contract, “Force
Majeure” means an event which is beyond the reasonable
control of a Party and which makes a Party’s performance of its
obligations under the Contract impossible or so impractical as to
be considered impossible under the circumstances.
2.5.2 No Breach The failure of a Party to fulfil any of its
of Contract obligations under theContract shall not be
considered to be a breach of, or default under,
this Contract insofar as such inability arises
from an event of Force Majeure, provided that
the Party affected by such an event (a) has taken
all reasonable precautions, due care and
reasonable alternative measures in order to
carry out the terms and conditions of this
Contract, and (b) has informed the other Party
as soon as possible about the occurrence of
such an event.
2.5.3 Extension Any period within which a Party shall, pursuant
Of Time to this Contract complete any action or task shall be extended for
a period equal to the time during which such Party was unable to
perform such action as a result of Force Majeure.
2.5.4 Payments During the period of his inability to perform the
Services as a result of an event of Force Majeure, the Tenderer
shall be entitled to continue to be paid under the terms of this
Contract, as well as to be reimbursed for additional costs
reasonably and necessarily incurred by him during such period
for the purposes of the Services and in reactivating the Service
after the end of such period.
2.6 Termination
2.6.1 By the The Client may terminate this Contract by not
Client less than thirty (30) days’ written notice of termination to the
Tenderer, to be given after the occurrence of any of the events
specified in this Clause;
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 29 of 43
(a) if the Tenderer does not remedy a failure in the
performance of his obligations under the Contract within
thirty (30) days after being notified or within any further
period as the Client may have subsequently approved in
writing;
(b) if the Tenderer becomes insolvent or bankrupt;
(c) if, as a result of Force Majeure, the Tenderer is unable to
perform a material portion of the Services for a period of
not less than sixty (60) days; or
(d) if the Tenderer, in the judgement of the Client, has
engaged in corrupt or fraudulent practices in competing
for or in executing the Contract.
(e) For the purpose of this clause;
“corrupt practice” means the offering, giving, receiving
or soliciting of anything of value to influence the action
of a public official in the selection process or in Contract
execution.
“fraudulent practice” means a misrepresentation of facts
in order to influence a selection process or the execution
of Contract to the detriment of the Client, and includes
collusive practice among tenderers (prior to or after
submission of proposals) designed to establish prices at
artificial non-competitive levels and to deprive the
Client of the benefits of free and open competition.
(f) if the Client in his sole discretion decides to terminate
this Contract.
2.6.2 By the The Tenderer may terminate this Contract by
Tenderer not less than thirty (30) days’ written notice to the Client, such notice
to be given after the occurrence of any of the following
events;
(a) if the Client fails to pay any monies due to the Tenderer
pursuant to this Contract and not subject to dispute
pursuant to Clause 7 within sixty (60) days after
receiving written notice from the Tenderer that such
payment is overdue; or
(b) if, as a result of Force Majeure, the Tenderer is unable to
perform a material portion of the Services for a period of
not less than sixty (60) days.
2.6.3 Payment Upon termination of this Contract pursuant to
upon Clauses 2.6.1 or 2.6.2, the Client shall make
Termination the following payments to the Tenderer:
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 30 of 43
(a) remuneration pursuant to Clause 6 for Services
satisfactorily performed prior to the effective date of
termination;
(b) except in the case of termination pursuant to paragraphs
(a) and (b) of Clause 2.6.1, reimbursement of any
reasonable costs incident to the prompt and orderly
termination of the Contract, including the cost of the
return travel of the Personnel and their eligible
dependents.
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 31 of 43
OBLIGATIONS OF THE TENDERER
3.1 General The Tenderer shall perform the Services and carry
out his obligations with all due diligence, efficiency and economy in
accordance with generally accepted professional techniques and practices
and shall observe sound management practices, and employ appropriate
advanced technology and safe methods. The Tenderer shall always act,
in respect of any matter relating to this Contract or to the Services, as
faithful adviser to the Client and shall at all times support and safeguard
the Client’s legitimate interests in any dealing with third parties.
3.2 Conflict of Interests
3.2.1 Tenderer (i) The remuneration of the Tenderer
Not to pursuant to Clause 6 shall constitute the
Benefit from Tenderer’s sole remuneration in
Commissions, connection with this Contract or the
Discounts, Services and the Tenderer shall not
Etc. accept for his own benefit any trade
commission, discount or similar payment
in connection with activities pursuant to this Contract or
to the Services or in the discharge of his obligations
under the Contract and the Tenderer shall use his best
efforts to ensure that his personnel, any subtenderer[s]
and agents of either of them similarly shall not receive
any such additional remuneration.
(ii) For a period of two years after the expiration of this
Contract, the Tenderer shall not engage and shall cause
his personnel as well as his subtenderer[s] and his/their
personnel not to engage in the activity of a purchaser
(directly or indirectly) of the assets on which he advised
the Client on this Contract nor shall he engage in the
activity of an adviser (directly or indirectly) of potential
purchasers of such assets.
(iii) Where the Tenderer as part of the Services has the
responsibility of advising the Client on the procurement
of goods, works or services, the Tenderer will comply
with any applicable procurement guidelines and shall at
all times exercise such responsibility in the best interest
of the Client. Any discounts or commissions obtained
by the Tenderer in the exercise of such procurement
shall be for the account of the Client.
3.2.2 Tenderer The Tenderer agrees that, during the
and term of this Contract and after its
Affiliates termination, the Tenderer and his
Not to be affiliates, as well as any Subtenderer
Otherwise and any of his affiliates, shall be
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 32 of 43
Interested in disqualified from providing goods, works
Project or services (other than the Services and any continuation
thereof) for any project resulting from or closely related
to the
Services.
3.2.3 Prohibition Neither the Tenderer nor his
of Conflicting subtenderer[s] nor their personnel shall
Activities engage, either directly or
indirectly in any of the following activities:
(a) during the term of this Contract, any business or
professional activities in the Republic of Kenya
which would conflict with the activities assigned
to them under this Contract; or
(b) after the termination of this Contract, such other
activities as
may be specified in the SC.
3.3 Confidentiality The Tenderer, his subtenderer[s] and the personnel of
either of them shall not, either during the term of this
Contract or within two (2) years after the expiration of
this Contract, disclose any proprietary or confidential
information relating to the Project, the Services, this
Contract or the Client’s business or operations without
the prior written consent of the Client.
3.4 Insurance to be The Tenderer (a) shall take out and
Taken Out by the maintain and shall cause any
Tenderer subtenderer[s] to take out and maintain, at his (or the
subtenderers’, as the case may be) own cost but on terms
and conditions approved by the Client, insurance against
the risks and for the coverage, as shall be specified in the
SC; and (b) at the Client’s request, shall provide
evidence to the Client showing that such insurance has
been taken out and maintained and that the current
premiums have been paid.
3.5 Tenderer’s The Tenderer shall obtain the Client’s
Actions Requiring prior approval in writing before taking
Client’s Prior any of the following actions;
Approval
a) entering into a subcontract for the performance of
any part of the Services,
b) appointing such members of the personnel not listed
by name in Appendix C (“Key Personnel and Sub
tenderers”).
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 33 of 43
3.6 Reporting The Tenderers shall submit to the Client
Obligations the reports and documents specified in Appendix
A in the form, in the numbers, and within the
periods set forth in the said Appendix.
3.7 Documents All plans, drawings, specifications,
Prepared by the designs, reports and other documents and
Tenderer to software submitted by the
Be the Property Tenderer in accordance with Clause 3.6
of the Client shall become and remain the property of
the Client and Tenderer shall, not later than
upontermination or expiration of this Contract, deliver
all such documents and software to the Client together
with a detailed inventory thereof. The Tenderer may
retain a copy of such documents and software. Neither
Party shall use these documents for purposes unrelated
to this Contract without the prior approval of the other
Party.
3. TENDERER’S PERSONNEL
4.1 Description The titles, agreed job descriptions,
of Personnel minimum qualifications and estimated periods of
engagement in the carrying out of the Services of the
Tenderer’s Key Personnel are described in Appendix C.
The Key Personnel and Sub tenderers listed by title as
well as by name in Appendix C are hereby approved by
the Client.
4.2 Removal (a) Except as the Client may otherwise and/or
agree, no changes shall be made in
the Key Personnel. If for
Replacement any reason beyond the reasonable control
Of Personnel of the Tenderer, it becomes necessary to replace any of
the Key Personnel; the Tenderer shall provide as a
replacement a person of equivalent or better
qualifications.
(b) If the Client finds that any of the Personnel have
(i) committed serious misconduct or have been
charged with having committed a criminal
action, or
(ii) the Client has reasonable cause to be
dissatisfied with the performance of any of the
Personnel, then the Tenderer shall, at the
Client’s written request specifying the grounds
thereof, provide as a replacement a person with
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 34 of 43
qualifications and experience acceptable to the
Client.
(c) The Tenderer shall have no claim for additional
costs arising out of or incidental to any removal
and/or replacement of Personnel.
5. OBLIGATIONS OF THE CLIENT
5.1 Assistance and The Client shall use his best efforts to Exemptions
ensure that he provides the Tenderer
such assistance and exemptions as may be necessary for
due performance of this Contract.
5.2 Change in the If after the date of this Contract, there is
Applicable Law any change in the Laws of Kenya with respect to taxes
and duties which increases or decreases the cost of the
Services rendered by the Tenderer, then the
remuneration and reimbursable expenses otherwise
payable to the Tenderer under this Contract shall be
increased or decreased accordingly by agreement
between the Parties and corresponding adjustments shall
be made to the amounts referred to in Clause 6.2 (a) or
(b), as the case may be.
5.3 Services and Facilities The Client shall make available to the Tenderer the
Services and Facilities listed under Appendix E.
6. PAYMENTS TO THE TENDERER
6.1 Monthly The Tenderer’s total remuneration shall
Remuneration not exceed the payments calculated by from the agreed
statutory guidelines for the services. Except as provided
in Clause 5.2, the Contract Price may only be increased
above the amounts stated in Clause 6.2 if the Parties
have agreed to additional payments in accordance with
Clause 2.4.
6.2 Contract Price The price payable is set forth in the Special Conditions.
6.3 Payment for For the purposes of determining the
Additional
Services remuneration due for additional services
as may be agreed under Clause 2.4. A
breakdown of the Contract price is
provided in Appendices D. (N/A)
6.4 Terms and Payments will be made to the account of
Conditions of the Tenderer and according to the
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 35 of 43
Payment payment schedule stated in the “Special Conditions of
Contract” or governed by the statutory rules governing
the various professions.
6.5 Interest on Payment shall be made within thirty (30)
Delayed days of receipt of invoice and the relevant
Payment documents specified in Clause 6.4. If the Client has
delayed payments beyond ninety (90) days after the due
date hereof, simple interest shall be paid to the Tenderer
for each day of delay at a rate three percentage points
above the prevailing Central Bank of Kenya’s average
rate for base lending.
7. SETTLEMENT OF DISPUTES
7.1 Amicable Settlement: The Parties shall use their best efforts to
settle amicably all disputes arising out of
or in connection with this Contract or its
interpretation.
7.2 Dispute Settlement: Any dispute between the Parties as to
matters arising pursuant to this Contract
that cannot be settled amicably within
thirty (30) days after receipt by one Party of
the other Party’s request for such amicable
settlement may be referred by either Party
to the arbitration and final decision of a
person to be agreed between the Parties.
Failing agreement to concur in the
appointment of an Arbitrator, the
Arbitrator shall be appointed by the
Chairman of the Chartered Institute of
Arbitrators, Kenya Branch, on the request
of the applying party.
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 36 of 43
SPECIAL CONDITIONS OF CONTRACT
Number of GC Amendments of and Supplements to Clauses in the
Clause General Conditions of Contract
1.1(i) The Member in Chargeis__________________________ [name of
Member]
1.4 The addresses are:
Client: _____________________________________________
Attention:
_____________________________________________
Telephone: _____________________________________________
Telex;
_____________________________________________
Facsimile:
_____________________________________________
Tenderer:
_____________________________________________
Attention:
_____________________________________________
Telephone;
_____________________________________________
Telex:
_____________________________________________
Facsimile:
_____________________________________________
1.6 The Authorized Representatives are:
For the Client:
_____________________________________________
For the Tenderer
__________________________________________
2.1 The date on which this Contract shall come into effect
is (_________________) [date].
Note: The date may be specified by reference to conditions of
effectiveness of the Contract, such as receipt by Tenderers of advance
payment and by Client of bank guarantee
2.2 The date for the commencement of Services is________[date]
2.3 The period shall be ______________________ [length of time].
Note: Fill in the period, e.g., forty eight (48) months or such other
period as the Parties may agree in writing.
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 37 of 43
3.4 The risks and coverage shall be:
(i) Professional Liability: Full amount of this contract excluding
taxes and contingency amount.
(ii) Loss of or damage to equipment and property:
Kshs 5,000,000
(iii) Third party Liability: Kshs 3,000,000
(iv) Employer’s Liability and workers compensation:
Kshs 2,000,000
6.2(a) The amount in local Currency is________N/A___________ [Insert
amount]
6.4 Payments shall be made on monthly basis. N/A
Payments in Kshs shall be made to the following Account
Account Number: ___________________
Account Name: ___________________
Bank: ________________________________
Address: ___________________________
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 38 of 43
MANDATORY CONFIDENTIAL BUSINESS QUESTIONNAIRE
(Must be filled by all applicants or Tenderers’ who choose to participate in this tender)
Name of Applicant(s)..........................................................................................
You are requested to give the particulars in Part 1 and either Part 2 (a), 2 (b) or 2 (c), whichever
applies to your type of business. Part 2 (d) to part 2 (i / j) must be filled. You are advised that giving
wrong or false information on this Form will lead to automatic disqualification of your tender or
termination of your contract or debarment of your firm at your cost.
Part 1 – General
Business Name:……………………………………………………………Certificate of Incorporation /
Registration No. ………………………………………..…Location of business premises:
Country …………………………………..…Physical address …………………….……………….
Town ………………………………….……………………….Building………………………………
Floor…………………………………………………………….Plot No. ……..……………………….
Street / Road ……..………………….……………………Postal Address ………..………………
Postal / Country Code…………………………………….Telephone No’s…...…………………
Fax No’s. ……………………….………………E-mail address ………………….…………………
Website ……………………………………………………………………………………….…………
Contact Person (Full Names) …………………………… Direct / Mobile No’s.…………….…
Title ……………………………………… Power of Attorney (Yes / No)
If yes, attach written document.
Nature of Business (Indicate whether manufacturer, distributor, etc) ………………..……….………..
Part 2 (d) – Debarment
I/We declare that I/We have not been debarred from any procurement process and shall not engage in any
fraudulent, corrupt, coercive and obstructive acts with regard to this or any other tender by the New KCC
and any other public or private institutions.
Full Names
……………………………………………………………………………………………………………
Signature
………………………………………………………………………………………………………….
Dated this …………………………………….……………day of ……………………………2015.
In the capacity of
………………………………………………………………………………………………………
Duly authorized to sign Tender for and on behalf of …………………………………………………
Part 2 (e) – Bankruptcy / Insolvency / receivership.
I/We declare that I/We have not been declared bankrupt or insolvent by the competent Authorities in Kenya
and neither are we under receivership:
Full Names
……………………………………………………………………………………………………………
Signature
………………………………………………………………………………………………………….
Dated this …………………………………….……………day of ……………………………2015.
In the capacity of
………………………………………………………………………………………………………
Duly authorized to sign Tender for and on behalf of …………………………………………………
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 39 of 43
Part 2 (f) – Criminal Offence
I/We, (Name (s) of Director (s)):-
a) ……………………………………………………………………….………..……………
b) …………………………………………………………………………..….……….………
Have not been convicted of any criminal offence relating to professional conduct or the making of false
statements or misrepresentations as to its qualifications to enter into a procurement contract within a period
of three (3) years preceding the commencement of procurement proceedings.
Signed
…………………………………………………………………………………………………………….
For and on behalf of M/s
………………………………………...…………………………………………………………………..
In the capacity of
……………………………………….……………………………………………………………………
Dated this ……………………………………………day of ………………………………….2015.
Suppliers’ / Company’s Official Rubber Stamp
………………………………………………………….
Part 2 (g) – Conflict of Interest
I/We, the undersigned state that I / We have no conflict of interest in relation to this procurement:
a) ………………………………………………………………………………………………
b) ………………………………………………………………………………………………
For and on behalf of M/s …………………………………………………………………………………..
In the capacity of ………………………………………………………………………………………
Dated this ………………………………………day of ……………………………………….2019
Suppliers’ / Company’s Official Rubber Stamp
………………………………………………………
Part 2 (h) – Interest in the Firm:
Is there any person/persons in New KCC or any other public institution who has interest in the Firm?
Yes/No ……………………….. (Delete as necessary) Institution ………………………….
……………………………………. ……………………………… ………………………
(Title) (Signature) (Date)
Part 2(i) - Declaration
I / We, the undersigned state and declare that the above information is correct and that I / We give New
KCC authority to seek any other references concerning my / our company from whatever sources deemed
relevant, e.g. Office of the Registrar of Companies, Bankers, etc.
Full names
…………………………………………………………………………………………………………..
Signature………………………………………………………………………………………………
For and on behalf of M/s
…………………………………………………………………………………………..
In the capacity of
………………………………………………………………………………………………
Dated this ……………………………………………day of ………………………………….2015.
Suppliers’ / Company’s Official Rubber Stamp
…………………………………………………………
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 40 of 43
CERTIFICATE OF TENDERER’S VISIT TO SITE
1. This is to certify that I ___________________________________________________
(Name of bidder or his Representative)
of____________________________________________ (Name of Firm of tendering)
in the company of________________________________________________ (Name
of New Kenya Co-operative Creameries Ltd Representative conducting the visit)
visited the site in connection with the Tender for: - “DESIGN, FINANCING,
INSTALLATION, COMMISSIONING & OPERATION OF A HYBRID
SOLAR PHOTOVOLTAIC SYSTEM IN NEW KCC SOTIK FACTORY”
2. Having previously studied the contract documents, I carefully examined the site.
3. I have made myself familiar with all the local conditions likely to influence the works
and the cost thereof.
4. I further certify that I am satisfied with the description of the work and the
explanations given by the said Representative and that I understand perfectly the
work to be done as specified and implied in the execution of the contract.
Signed by Tenderer
Name of Tenderer:
_________________________________________________________
Name of Representative:
____________________________________________________
Date: ________________________________________________________
Signed by New Kenya Co-operative Creameries Ltd (New KCC)
Name of New KCC’s Representative: ________________________________________
Date:_______________________________________________________
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 41 of 43
FORM SD2
SELF DECLARATION FORMS (r 62)
REPUBLIC OF KENYA
PUBLIC PROCUREMENT REGULATORY AUTHORITY (PPRA) SELF DECLARATION THAT THE PERSON/TENDERER WILL NOT
ENGAGE IN ANY CORRUPT OR FRAUDULENT PRACTICE. I, …………………………………….of P. O. Box ………………………. being a
resident of
………………………………….. in the Republic of ------ do hereby make a statement as
follows:-
1. THAT I am the Chief Executive/Managing Director/Principal Officer/Director of
……….... ……………………………….. (insert name of the Company) who is a Bidder in respect of Tender No. ………………….. for ……………………..(insert tender title/description) for ……………………..( insert name of the Procuring entity) and duly authorized and competent to make this statement. 2. THAT the aforesaid Bidder, its servants and/or agents /subcontractors will not engage in any corrupt or fraudulent practice and has not been requested to pay any inducement to any member of the Board, Management, Staff and/or employees
and/or agents of ……………………..( insert name of the Procuring entity) which is the procuring entity.
3. THAT the aforesaid Bidder, its servants and/or agents /subcontractors have not offered any inducement to any member of the Board, Management, Staff and/or employees and/or agents of ……………………..(name of the procuring entity)
4. THAT the aforesaid Bidder will not engage /has not engaged in any corrosive practice with other bidders participating in the subject tender
5. THAT what is deponed to hereinabove is true to the best of my knowledge information and belief.
………………………………. ………………………… ……………………… (Title) (Signature) (Date)
Bidder’s Official Stamp
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 42 of 43
DECLARATION FORM
Date
To ______________________
_________________
The tenderer i.e. (name and address)
declare the following:
a) Has not been debarred from participating in public
procurement.
b) Has not been involved in and will not be involved in
corrupt and fraudulent practices regarding public
procurement.
_____
Title Signature Date
Request for Proposal for design, financing, installation, commissioning & operation of a hybrid solar
photovoltaic system in New KCC Sotik Factory
Page 43 of 43
FORM OF TENDER Date____________________________
Tender No._______________________
To: New Kenya co-operative Creameries Limited
P.O. Box 30131 – 00100 - Nairobi
Tel: 552965, 652415
For enquiries:Email:[email protected]/[email protected]
Gentlemen and/or Ladies:
Having examined the tender documents including Addenda Nos…………………, the receipt of which is hereby duly acknowledged, we the undersigned, offer to ……………………………………………………………………………………………. [description of services] in conformity with the said tender documents for the sum of ……………………………… …………………………………………………………... [total tender amount in words and figures] or such other sums as may be ascertained in accordance with the Schedule of Prices attached herewith and made part of this Tender.
We undertake, if our Tender is accepted, to provide the services in accordance with the
services schedule specified in the Schedule of Requirements.
If our Tender is accepted, we will obtain the tender guarantee in a sum equivalent to Ten
percent of the Contract Price for the due performance of the Contract, in the form
prescribed by New KCC.
We agree to abide by this Tender for a period of ……….. days from the date fixed for
tender opening of the Instructions to tenderers, and it shall remain binding upon us and
may be accepted at any time before the expiration of that period.
Until a formal Contract is prepared and executed, this Tender, together with your written
acceptance thereof and your notification of award, shall constitute a binding Contract
between us.
Dated this _________________ day of________________2011
................................................................
………………………………………………….
[signature] [in the capacity of]
Duly authorized to sign tender for and on behalf of
...................................................................