Upload
beverly-powell
View
221
Download
4
Tags:
Embed Size (px)
Citation preview
nlr.net© 2004 National LambdaRail, Inc
1
Capacity PlanningAt Layers 1 and 2
Quilt MeetingOct 13, 2006
nlr.net© 2004 National LambdaRail, Inc
2
Capacity Planning - Basic Issues
• At Layer3 • Measure and monitor traffic on the link• Upgrade or add links based on average or peak traffic
utilization• Overprovision when possible
• At Layer1 and Layer2• Traffic utilization
– Part but not all of the planning Layer2– Not an issue at all for Layer1
• Availability and use of resources– What exists– What is planned
nlr.net© 2004 National LambdaRail, Inc
3
Example - NLR Layer1
• Allocation Map• Indicates capacity of each segment along the
backbone• Easy to tell what the busy paths are• But isn’t the whole story when doing capacity
planning
Allocated Waves - Layer1
nlr.net© 2004 National LambdaRail, Inc
5
Layer1 - Adding a new Lambda
• Need to assess what resources are available between Point A and Point B
• For each segment in the path• Can it physically support a new wave ?• Do needed resources (hardware, cables) already exist ?• If additional resources are needed, are they available?
– Equipment– Space– Power
• A “no” for any of the questions can mean• Capacity is not available along that specific path• An alternate path might be available
– But does it meet the original requirements?• Long delay in getting wave implemented
nlr.net© 2004 National LambdaRail, Inc
6
Example - NLR Layer1
• Path between Starlight (STAR) and Los Angeles (LOSA)• One of the most popular NLR routes• At least 5 possible paths
• Two are equivalent– STAR-CHIC-KANS-DENV-ODGE-BOIS-SEAT-
SUNN-LOSA– STAR-CHIC-KANS-DENV-RATO-ALBU-ELPA-
PHOE-LOSA• Others sub-optimal
– More segments– Too long a path
nlr.net© 2004 National LambdaRail, Inc
7
Example - NLR Layer1
• Currently - • Capacity exists along all 5 paths,
• Implement requested lambda along the most efficient route• Resources
• Use spare/quickstart wave where possible– Already installed transponders
» Channel planning already done– Replace ASAP in order to be prepared for next request
• Use spare transponders where spare/quickstart does not exist– 80-channel transponder cards provide most flexibility
» Otherwise may end up with channel conflicts– Replenish stock of cards as necessary
• Order additional transponders if necessary– Typically 8-12 weeks to install if new transponder cards are
needed.
nlr.net© 2004 National LambdaRail, Inc
8
Example - NLR Layer1
• Constant planning at layer1 is needed• Identify congested segments
• STAR-CHIC - already at 80% capacity• Upgrade plan in progress
– Requires both new fiber and new equipment
• Other busy segments• CHIC-KANS (45%), SEAT-PORT (40%), KANS-DENV &
CHIC-CLEV (35%)– Not yet a problem, but consider alternative paths
when possible to best utilize infrastructure
nlr.net© 2004 National LambdaRail, Inc
9
Example - NLR Layer1
• Capacity exists, but need additional equipment• Front Ends for each segment along Northern route are at
75% or greater capacity. – Resources required
» Equipment - new or existing» Additional co-location space» Additional Racks, Power
• Trade off between cost and delivering services in timely manner• Core set of shared spares, cost effective way to reduce
deployment time– Chassis, transponders, cables, amplifiers, etc.
• Other resources more costly to have “on-hand”– Co-location space, racks, power, fiber
» Add as needed, prioritizes resources with known long-lead times.
nlr.net© 2004 National LambdaRail, Inc
10
Capacity Planning at Layer2
• Layer2 Planning has attributes of both Layer1 and Layer3 networks
• Link Utilization - traffic monitoring is important, but not the whole story
• Link Allocation• VLANs with reserved bandwidth
– Need to include in link utilization estimates, even if the bandwidth isn’t actually used
• Link Utilization and Allocation don’t always correspond• Segments with the most VLANs with dedicated bandwidth don’t
necessarily have the most traffic• Dedicated VLANs as backup paths
– Typically no traffic over the path, but bandwidth needs to be available (and un-congested) on demand.
nlr.net© 2004 National LambdaRail, Inc
11
Capacity Planning at Layer1
• VLANs with non-dedicated bandwidth– May be the busiest segments– Viewed as cheap bandwidth, thus may be used more
than a more expensive link– End user should expect congestion (but that’s not
always the case !!)
nlr.net© 2004 National LambdaRail, Inc
12
Layer2 Traffic Map - Traffic over each segment
nlr.net© 2004 National LambdaRail, Inc
13
FrameNet VLAN Allocation
nlr.net© 2004 National LambdaRail, Inc
14
Layer2 Capacity Planning
• Adding Capacity• Dedicated bandwidth - add capacity once
dedicated bandwidth allocation reaches 75%. • Actual Link Utilization -
• Need to add capacity once actual use reaches 75%• Or need to remind those with non-dedicated bandwidth
VLANs that congestion is possible.
• Where a busy Layer2 segment corresponds to a busy Layer1 segment
• Need to reserve Layer1 segment sooner rather than later