NSTX-U NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade Team Princeton Plasma Physics Laboratory NSTX Upgrade Project Office of Science Review LSB B318 February 4, 2014 NSTX-U NSTX-U Supported by Culham Sci Ctr York U Chubu U Fukui U Hiroshima U Hyogo U Kyoto U Kyushu U Kyushu Tokai U NIFS Niigata U U Tokyo JAEA Inst for Nucl Res, Kiev Ioffe Inst TRINITI Chonbuk Natl U NFRI KAIST POSTECH Seoul Natl U ASIPP CIEMAT FOM Inst DIFFER ENEA, Frascati CEA, Cadarache IPP, Jülich IPP, Garching ASCR, Czech Rep Coll of Wm & Mary Columbia U CompX General Atomics FIU INL Johns Hopkins U LANL LLNL Lodestar MIT Lehigh U Nova Photonics Old Dominion ORNL PPPL Princeton U Purdue U SNL Think Tank, Inc. UC Davis UC Irvine UCLA UCSD U Colorado U Illinois U Maryland U Rochester U Tennessee U Tulsa U Washington U Wisconsin X Science LLC

NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

Embed Size (px)

Citation preview

Page 1: NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1

NSTX Centerstack Fabrication StatusNSTX Centerstack Fabrication Status

James H. Chrzanowskiand the NSTX Upgrade Team

Princeton Plasma Physics LaboratoryNSTX Upgrade Project

Office of Science ReviewLSB B318

February 4, 2014

NSTX-UNSTX-U Supported by

Culham Sci CtrYork U

Chubu UFukui U

Hiroshima UHyogo UKyoto U

Kyushu UKyushu Tokai U

NIFSNiigata UU Tokyo

JAEAInst for Nucl Res, Kiev

Ioffe InstTRINITI

Chonbuk Natl UNFRI

KAISTPOSTECH

Seoul Natl UASIPP

CIEMATFOM Inst DIFFER

ENEA, FrascatiCEA, Cadarache

IPP, JülichIPP, Garching

ASCR, Czech Rep

Coll of Wm & MaryColumbia UCompXGeneral AtomicsFIUINLJohns Hopkins ULANLLLNLLodestarMITLehigh UNova PhotonicsOld DominionORNLPPPLPrinceton UPurdue USNLThink Tank, Inc.UC DavisUC IrvineUCLAUCSDU ColoradoU IllinoisU MarylandU RochesterU TennesseeU TulsaU WashingtonU WisconsinX Science LLC

Page 2: NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 2

General Arrangement

TF Flex Bus and Support Structure

Centerstack Assembly

Outer TF CoilsMajor Centerstack Components

Umbrella Structure

Vacuum Vessel

Page 3: NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 3

Upgraded Centerstack Components

Inner TF Bundle

Ohmic Heating Coil

Inner PF1c

Inner PF1b

Inner PF1a

Plasma Facing Components

CS Casing

Ceramic break assembly

Page 4: NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 4

Topics

•Progress of the Centerstack since last review

•Remaining risks and mitigation plans, Plans forward

•Address charge question #1 Critical Path Construction Efforts:

– Does the Project team have a realistic, executable schedule for Center Stack (CS) remaining construction efforts?

– Does the project have adequate resources and the appropriate skills mix to execute the remainder of the project per the plan?

Page 5: NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 5

Center Stack Status Since Last Review

• Inner TF Bundle– Complete

• Centerstack Casing– Delivered and studs have been installed

• OH Solenoid– Major tooling for OH solenoid has been

delivered & commissioned

– Aquapour and epoxy/glass base has been installed over TF bundle

– First layer of OH solenoid has been wound

– Completing layer transition 1 to 2 and resume winding layer 2

• Inner PF coils– PF1b coils have been completed

Page 6: NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 6

Involvement of ES&H Safety Department

• The fabrication & assembly of the Centerstack is being performed by PPPL personnel at the laboratory.

• Safety is an important part of the PPPL culture • Safety is incorporated in all aspects of the development program-

carryover to production• Industrial Hygiene (IH) & Construction Safety have participated in the

planning and setup of the coil area• Job Hazard Analysis (JHA’s) are being developed for each procedure• Procedures: Clearly identify safety precautions for specific operations• Personnel protective equipment (PPE’s) being used• “Tool Box” Safety meeting held monthly with Technicians

• Involvement with all safety groups

Page 7: NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 7

Progress- Raising the Full TF Bundle

• Completed testing of TF Bundle• Raised TF Bundle to the vertical position

in preparation for the application of the Aquapour. √ complete

Page 8: NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 8

Progress- Installation of Aquapour Layer

• Installation of Aquapour layer was successfully completed“Aquapour” is used as a temporary spacer that will be used to maintain 0.100 inch gap between the TF OD and OH ID surfaces. It is removed post VPI of OH coil √ complete

Page 9: NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 9

OH Solenoid Winding Facility

• The OH Solenoid is being wound onto the Inner TF Bundle• Completed setup & commissioning of OH winding equipment in CS High Bay area

Page 10: NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 10

Tooling- OH Winding Station Pivot Beam

OH Winding station fully commissioned ShopsCopper Spools

Cut-off saw & Braze Station

Hydraulic Tension Unit

Dual Taping Heads

√ complete

Page 11: NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 11

Progress- Winding Preparations

Epoxy/glass layer was applied over the Aquapour surface to provide a solid winding surface

OH support structure was installed

√ complete

Page 12: NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 12

Transfer TF to OH Winding Station

• The TF bundle was transferred to the OH Winding station

√ complete

Page 13: NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 13

OH Solenoid Fabrication- 1

• Wind the OH solenoid using approved drawings and procedure D-NSTX-IP-3385

• Four layers/ 880 turns/ (2) conductors in-hand

• Co-wound turn to turn insulation (Kapton/glass)

• In-line braze joints

• Layer to layer TIG Braze joints

• Tension wound conductor

Page 14: NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1414NSTXNSTX April 29, 2010NSTX Center Stack Upgrade Peer Review

Layer to layer TIG-Braze joint [Typical]

OH Cooling fittings- torch brazed to copper conductors

“TIG-Braze”

TIG-Brazing method minimizes annealing of conductors (use Sil-Fos)

Provides adequate joint strength

Qualified method and procedures used in previous OH solenoids

OH Solenoid Fabrication- 2

- Glass/epoxy laminate fillers between layers supports turns

- S-2 glass between fillers- Perforations in fillers will

enhance epoxy flow during VPI

14

Page 15: NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 15

OH Winding Status and Accomplishments

• Winding operations have started• Winding station is working well• Completed first layer 240 turns• Use of “Aquapour” as winding surface is working well• Outside diameter of layer 1 turns are in spec• Successfully completed and tested 6 in line brazes• Successfully completed and tested 6 cooling fitting brazes• Completed 2- Layer to layer brazes

Page 16: NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 16

Coil Winding Photos

Page 17: NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 17

Coil Winding Photos -continued

• Completed 240 turns including (6) inline brazes

Page 18: NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 18

Taping Stations

• The dual taping stations had initial startup issues w/ controllers

• They are working as planned applying (3) half-lapped layers of insulation at once on two parallel conductors

Page 19: NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 19

Taping and Winding Operations

Page 20: NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 20

Winding Manpower and Shift Coverage

• Manpower:– (2) 4 man teams– Engineering coverage for both shifts

• Started teams on 1 shift until completing 1st half of layer 1• Began 2 shifts for 2nd half of layer 1• Once we reached the half way point, the actual winding and

braze times and are less than anticipated• Winding: 2nd. Half of layer 1

– Estimated- 3 shifts per quarter– Actual- 1.5 shifts per quarter

• Brazing: (2) brazes– Estimated- 3 shifts per quarter– Actual- 2 shifts per quarter

Page 21: NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 21

Winding Manpower and Shift Coverage

• Layer to Layer Transition is being done on 1 shift to understand and teach associated technical issues with all team members for future transitions

• Future Layer to layer will probably be done with 2 shifts• Resume 2 shifts once winding begins• Engineering coverage is provided for 2nd. Shift (Need will be

evaluated after second layer has been completed)

Page 22: NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 22

Completion Dates

• Completion of OH winding should occur by mid to late March• VPI completed by mid April• Complete OH/TF activities: April thru May

– Continue on 2 shift operations thru completion of OH/TF activities

– Removing Aquapour

– Final OH testing

– Fit-up and installation of laminate crowns

– Finalization of TF fittings and bulkheads

– Installation of Belleville washer assembly

• Centerstack assembly activities: May thru June: – Install lower PF1A coil

– Apply ground plane and diagnostics to OH surface

– Install “Micro therm” insulation

• Transport OH/TF to NSTX South bay for final assembly: June 2014

Page 23: NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 23

Crown Assembly

Field fit and drill final pins holes

Final Assembly Tasks

Purpose of Crowns: Lock conductors together & help transfer load from TF bundle through lid structure to umbrella

TF Cooling connections & bulkhead

Install Belleville Washer Assembly

Install upper and lower crowns (custom fit-up required) and TF cooling fittingsInstall Belleville washer assembly

Page 24: NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 24

Laminate Crown

Epoxy/S-2 glass construction circumferentially wound (jelly-roll)

Upper & Lower Crown Assemblies-cont’d

Pinned to Inner TF Conductors 316 SS

Fabricate in house

Page 25: NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 25

Centerstack Casing

• The Centerstack Inconel casing has been manufactured by Martinez & Turek located in California.

• Inconel studs for supporting the PFC’s have been installed & are being cut to required length (NSTX South Bay)

Page 26: NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 26

Inner PF Coils

• Contract for fabricating the Inner PF coils has been awarded to Everson-Tesla Inc. (Nazareth, Pa)

• Both inner PF1B’s have been wound and VPI’d• The first Inner PF coil has been delivered the second will be

delivered the week of Feb 10th.• Winding of the first PF1A coil will begin week of Feb 10th.• Late delivery has no impact on critical path schedule

PF1B

PF1APF1C

Page 27: NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 27

Centerstack Casing

• The Inner PF1B coils will be mounted to CS casing followed by the PFC tiles and diagnostics. (NSTX South Bay)

PF1B

Plasma Facing Component tiles

Page 28: NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 28

Miscellaneous Procurements

• TF flex buss has been completed by Zenox Corp.• Super nuts and hardware have been delivered• Outer TF Lead extensions are being manufactured by Martinez-

Turek (California) Delivery scheduled for late March

MT Torque-nut™

Flex-Bus (Cu-Cr-Zr)

OTF Lead Extensions

Page 29: NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 29

Exploded View

Assembled View

Complete Ceramic Break Sub-Assembly

- All components except for PF1C coils have been delivered for ceramic break assemblies- Assemble the ceramic break components to the Upper and Lower PF-1C coil structures. Work to be performed by PPPL

• Ceramic rings were fabricated by Kyocera in Japan

• Stainless rings manufactured by Hollis Machine (NH)

• G-11 insulators manufactured by Astro Machine Works (Pa) and Reno Machine (Conn)

• PF1C coil manufactured by Everson-Tesla Inc

Page 30: NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 30

Mount the Center Stack Support Structure to Lower PF-1A Coil

Step 1- Assemble CS Support & Lower PF-1A Together

Install “Micro-therm” insulation around outside surfaces of “Upper PF1” Coil

Page 31: NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 31

Step 2- Assemble Lower PF-1A Assy. To OH/TF Assy.

Position the Lower PF-1A coil assembly over the OH/TF Assembly

Page 32: NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 32

Step 3 – OH Diagnostics & Thermal Blanket

Mount the OH surface diagnostics and the “Micro-Therm” Insulation Blanket around the outer surfaces of the OH Solenoid-Flux loops-Thermocouples-Rogowski Coils

Micro-Therm Insulation

Lower PF-1A Coil Assy.

TRANSPORT OH/TF BUNDLE TO NSTX SOUTH HIGH BAY AREA

Page 33: NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 33

Lower the CS Casing over the OH/TF Assembly

Step 4 – Install CS Casing to CS Assembly

Upper Assembly Lower Assembly

Lower the Upper PF1A coil over the OH/TF Assembly & secure to Upper PF1B coil

Page 34: NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 34

Step 5- Install Flash Shields

Install the Kapton shields and vertical motion instrumentation

Flash Shields

Page 35: NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 35

Pre-position the lower Ceramic Break Assembly and Rotatable Flange prior to lowering CS assembly into the VV

Install the completed Center Stack Assembly into the Vacuum Vessel (July 2014)

Step 6- Install Completed CS Assembly

Page 36: NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 36

Critical Path Schedule

The OH Manufacturing steps are series activities w/ very few parallel activities

Page 37: NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 37

Charge Question

• Address charge question #1 Critical Path Construction Efforts: – Does the Project team have a realistic, executable schedule for

Center Stack (CS) remaining construction efforts? – The project feels that the schedule to complete the center stack

assembly is realistic and achievable. Most of the high risk tasks or operations have been addressed during the performance of the manufacturing.

• OH winding is proceeding well taking fewer days than anticipated

• The layer 1 diameter is being maintained and is in tolerance

• The Aquapour is performing as expected providing a stable base for winding the OH turns

• In-line brazing operations are going well

– The remaining high risks are associated with the final vacuum pressure impregnation of the OH solenoid

Page 38: NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 38

Charge Question

– Does the project have adequate resources and the appropriate skills mix to execute the remainder of the project per the plan?

– The four man teams operating on 2 shifts provide the necessary manpower to complete the winding of the OH solenoid.

– Additional manpower is available to cover illness or vacation– 3 engineers plus project management (RLM) are assigned to the

center stack through completion.

Page 39: NSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 1 NSTX Centerstack Fabrication Status James H. Chrzanowski and the NSTX Upgrade

NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4, 2014 39

Conclusion

• The full TF bundle have been VPI’d and tested (Retired risks)– Five of the 6 required VPI’s have been completed

• The Inconel casing has been delivered & studs installed• Major tooling for the OH solenoid has been completed• The OH coil manufacturing facility has being setup &

commissioned– There was a delay in commissioning the OH winding station (taping stations)

• Production has started with winding of first layer completed• Times for winding and brazing are less than anticipated• Inner PF coils are being fabricated by Everson Tesla with first (2)

coils completed

• Anticipate completion of the Centerstack components and installation into NSTX in July 2014