On Gc x Midterm Appraisal

Embed Size (px)

Citation preview

  • 7/26/2019 On Gc x Midterm Appraisal

    1/34

    ONGCs Mid Term Appraisal of 10thPlan

    OIL AND NATURAL GAS CORPORATION LIMITED

    Mid Term Appraisal Of 10thPlan (Domestic Exploration and Production Activities)

    1.Introduction

    1.1 The 10thFive Year Plan Programme of ONGC was submitted to MOPNG and Planning Commissionin November 2001 along-with the Annual Plan 2002-03. The 10 th Plan exploration and exploitationprogramme of ONGC reflects the ability and resolve of the company to pursue the E&P objectives in thechanging environment and in tune with its long-term business goal to maximise contribution towards the

    national energy requirement. The 10th Plan Outlay is Rs. 33419 Crore for domestic E&P activities ofONGC also Rs.13550 Crore for overseas ventures of OVL.

    1.2 The 10thPlan program encompasses the oil and gas field development strategy of ONGC during Planperiod considering the status of different fields and schedule of implementing of additional developmentinputs. The formula1ion of the exploration programme for the 10th Plan period was based on thefollowing considerations:

    ! The prospectivity perception of the domestic acreages and their potential levels! Acreage specific exploration programme under various dispensations due to the changed

    scenario on account of the Govt. of India's policy initiatives under NELP regime as against theearlier practice of sector-wise/basin-wise exploration programme formulation.

    The hydrocarbon demand scenario in the country necessitated acceleration of the reserves accretion fromthe producing basins, extension of the exploratory activities to the poorly explored, logistically difficultand frontier areas.

    Key sectors were identified in different basins of the country for enhancing the pace of accretion by fasttrack appraisal of leads obtained, exploring the large prospects and opening up of frontier areasincluding deep waters.

    1.3 The projections of crude oil and natural gas production for the 10thPlan period were based on themajor identified initiatives like Redevelopment of Mumbai High, integrated development of Heera field,additional development of Neelam field, implementation of 15 IOR schemes, finalisation of EOR pilots,commercialisation of successful EOR pilots, development of marginal fields, integrated development ofTripura gas field and initiation of production from KG Offshore.

    1.3.1Redevelopment of Mumbai High:

    Mumbai High field has been on production for more than 25 years and produced around 310 MMt ofcrude oil. During its peak production phase, the field has produced around 18-20 MMt of oil per year.The field production has declined since 1990-91. The plan for redevelopment of Mumbai High North &Mumbai High South has been approved for implementation at a cost of Rs 2929 40 Crore and Rs 5255 97

  • 7/26/2019 On Gc x Midterm Appraisal

    2/34

    ONGCs Mid Term Appraisal of 10thPlan

    1.3.2Improved Oil Recovery Programme & EOR:

    In addition to the two EOR Projects in Balol and Santhal fields approved by Government, Improved OilRecovery Programme was approved by ONGC Board for 12 other major fields viz. Heera, Neelam,Gandhar, North Kadi-Phase-I, Jotana, Sobhasan, Santhal Infill, Kalol, Sanand Extended Polymer, Lakwa -Lakhmani, Geleki and Rudrasagar. This programme will increase the Global Recovery Factor by anaverage of 4%. The Balol and Santhal projects have been completed in 2001-02. Two other projects SanandExtended Polymer and Santhal Infill completed in 2002-03 whereas Additional Development Heera Pt-1completed in November 2003. The details of major projects and the current status is appended asAppendix-I and II.

    The Redevelopment of Mumbai High and the IOR/EOR Programme has successfully arrested thedeclining trend in the crude oil production faced during the 9thPlan period. The crude production wentup from the level of 24.71 MMT in the terminal year of 9thPlan to 26.06 MMT in the second year of the10thPlan (2003-04).

    Besides the Redevelopment and IOR/EOR programme envisaged at the time of formulation of 10thPlan,during the first two year of plan period, three major development schemes viz., Development of D-1Prospects, Development of Bassein (Vasai) East Field and Integrated Development of G-1 & GS-15 fields,one value addition project i.e., C2-C3 Recovery from LNG Petronet, Dahej and one replacement projectof Mumbai-Uran Trunk Pipeline (MUT) to maintain the steady & non-interrupted flow of crude fromMumbai offshore to Uran- onshore terminal is also approved by ONGC Board. These developmentprojects will also start contributing to production from 2005-2006.

    1.4Initiatives for Upgradation & Modernisation:

    In the 10th Plan, an outlay of Rs. 2285 Crore has been kept for upgradation, refurbishment andreplacement of plant and equipment including rigs, upgradation of production & exploration technology.

    Token amounts are provided for Infocom and diversification.

    ONGC Initiated in a focused manner for acquiring the state of art technology and equipment,refurbishment and overhauling of existing aged equipments & facilities and implementation of Infocomprojects. ONGC has also acquired advanced interactive workstation to create full-fledged 3-D dataprocessing centre and Virtual Reality Centres. Other innovative measures undertaken include usages ofExtended Reach and horizontal drilling, 4-D seismic, cross well tomography and using gels and polymersfor water shut off jobs. In order to enhance drilling capabilities, two own rigs Sagar Vijay & Sagar Bhusanhave been upgraded

    Out of 12 onland drilling rigs planned to be re-furbished through BHEL in phase-I, 5 rigs have beencompleted and 1 rig is in progress. 12 rigs will be re-furbished during 2004-05 in phase-II. 20 drilling rigs(10 rigs each In 2005-06 & 2006-07) have been planned to be re-furbished in phase-III. Out of 19 w/o rigsplanned for refurbishment during 2003-05, 5 w/o rigs have been refurbished and 1 rig is under progress.

    The corporation has taken up company wise ERP solution on SAP /R3 Platform for Optimization and

  • 7/26/2019 On Gc x Midterm Appraisal

    3/34

    ONGCs Mid Term Appraisal of 10thPlan

    Revenue streams in the upstream business are highly volatile, and no company, for that matter, nocountry can control the geo-political situation in oil & gas section. The fortunes of sectoral companies are

    unpredictable; all major world-scale Oil & Gas companies are, therefore, vertically integrated.Competitive pressures have maximum impact on costs, and therefore, mergers and acquisitions havebecome the name of the game in all businesses, world-wide.

    Towards the first step for integration, marketing Rights for transportation fuels was obtained from GoI inMay 2002; the rights are subject to organizing assured sourcing of products.

    In mid-June 2002, ONGC was asked to go ahead with rehabilitation of Mangalore Refinery &Petrochemical Ltd (MRPL), a joint venture company on the verge of being referred to the BIFR.

    Negotiations for (i) acquisition of one partner's entire stake (@ Rs 2 per share of face value of Rs 10), and(ii) restructuring of debt with 22 lenders (debt- equity improved from 9.15% to 2.5%) were completed insix weeks, an unprecedented feat in a transparent process. Now MRPL is ONGC's subsidiary (71.4 %equity).

    ONGC has also acquired 23% equity in Mangalore-Hasan-Bangalore Pipeline (MHBPL), designed tocarry MRPL's products to the heart of the Karnataka market.

    The C2-C3 & LPG Recovery project from LNG was approved by ONGC Board on 29thDecember 2003 at acost of Rs.900.92 Crore. The project envisages setting up a unit to recover 566574 TPA of C2-C3 and347065 TPA of LPG from LNG at Dahej. The scheduled completion of the project is June'2006.

    Projects initiated for creating new value-added products (Aviation Turbine Fuel) from the fractionators isprogressing well, along with projects for enhancing current productions.

    2.BACKGROUND OF 10thEXPLORATION PROGRAMME- DOMESTIC ACREAGES:

    The broad policy guidelines and milestones for the E&P upstream sector, as brought out in the 'IndiaHydrocarbon vision-2025' provided the broad framework for formulating the Tenth five-year plan. Themain issues as brought out in the document are:

    ! Maximizing exploration and exploitation efforts in the producing basins,! Spreading exploration into non producing/frontier basins,! Appraising all the sedimentary basins within a time frame,

    2.1COMPONENTS OF 10thPLAN EXPLORATION PROGRAMME:

    In the backdrop of the emerging NELP regime and the need for evolving an acreage specific explorationprogramme, detailed micro-planning was carried out for each acreage i.e. PEIs and MLs as well as NELP-II blocks applied and the open acreages, taking into account the prospectivity analysis and attendant riskperception to deduce the exploration input requirement during 10th plan.

  • 7/26/2019 On Gc x Midterm Appraisal

    4/34

    ONGCs Mid Term Appraisal of 10thPlan

    ! NELP-II blocks.

    The programme within these areas was considered as firm, as the availability of these acreages withONGC during the plan period was ensured, as per the existing licensing policy of the government.

    ! The upside programme was worked out by adding 50% of the indicative inputs in the PELacreages held by ONGC beyond their current cycle and the open acreages in the various basins,to the firm programme in order to account for a most likely acreage availability scenario forONGC during the course of the 10thplan period (pending the announcement of RelinquishmentPolicy by GOI during that time).

    3.RATIONALE AND STRATEGY FOR 10th PLAN EXPLORATION PROGRAMME:

    3.1Producing basins:

    ! Consolidating on the known play systems- field growth and lead perusal.! Establishment of new plays in the known sectors and! Extension of exploratory activities to less explored/new sectors.

    3.2Enhancing tempo of Deep-water Exploration:

    ! Deep water sector was accorded priority, to receive a quantum jump in exploration programme,in view of higher degree of expectations, with twin objectives:

    ! To intensify the exploration in the sectors with successful outcome arising out of short- termstrategy.

    ! To expand the activities to new sectors simultaneously making foray into the super and ultradeep waters

    3.3Yet to establish Basins:

    ! Focus on the acreage where in spite of elusive commercial success, knowledge building needscontinuation for a breakthrough. The basins under this category are Mahanadi, Satpura, SouthRewa, Vindhyan, Kutch (Mesozoic sequence), Kerala-Konkan and Himalayan Foothills.

    ! In the 'teaser' basins of Bengal and Rajasthan, continued intellectual efforts in basin evaluation tobe maintained in order to register a breakthrough.

    The exploration. of non-conventional hydrocarbons is critical not only to supplement the conventional

    hydrocarbons but also to cater to the possible upsurge in energy demand on account of rapidindustrialisation.

    4.REVIEW OF THE EXPLORATION PROGRAMME IMPLEMENTATION DURING 2002-04:

    4.1Acreage holding scenario:

  • 7/26/2019 On Gc x Midterm Appraisal

    5/34

    ONGCs Mid Term Appraisal of 10thPlan

    where ONGC is the operator. Additionally, 7 CBM blocks (2779 sq. km.) have also been awardedto ONGC (sole rick and consortium) during CBM NELP -I & II rounds.

    !

    The comparison of the acreage holding scenario of ONGC as on 1.4.2002 and 1.4.2004,considering nomination and NELP acreages is as under:

    Year Number of blocks Area(Sq .km.)PEL NELP ML CBM PEL NELP ML CBM

    1.4.2002 131 23 205 0 188685 318368 9525 01.4.2004 119 44 239 5* 145743 464788 10688 1562*

    * 2 Additional CBM blocks also awarded for which PEL has been applied.

    4.2Exploration programme Implementation:

    The scenario of exploration programme implementation during 2002-04 reflects over achievement inrespect of 3D seismic data acquisition, as indicated below:

    2D (GLK/LK) 3D (Sq Km) Exploratory Wells Inplace Accretion(Mmtoe)

    BE Actual BE Actual BE Actual BE Actual

    2002-03 15135 21059 6556 8639 153 150 121.7 128.12003-04 14690 5993 14784 19891 172 124 134.55 104.78Total 29825 27052 21340 28530 325 274 256.25 232.88

    During 2002-03 (BE) & 2003-04(BE) it was envisaged to acquire 29825 GLK/LK of 2D and 21340 Sq. Km.of 3D seismic data. Against this 2D data acquired was 27052 GLK/Lk while 3D data acquired was 28530Sq. Km. The cumulative achievement of 2D seismic is 90.7% of BE targets whereas in 3D seismic it was133.7% .

    The planned 2D data acquisition during 2002-03 in the NELP-III blocks in deep water, could not be takenup since the blocks were awarded to ONGC during February 2003. The same has been prioritised during2003-04 and 2004-05.

    In the 10thPlan it was envisaged to drill 561 exploratory wells (Firm Programme). During the first twoyears of the 10th Plan, against BE target of 325 exploratory wells, 274 wells were drilled.

    4.3 Basin wise planned vs. actuals of the physical programme during 2002-03 and 2003-04 are placed at

    Appendix-III (A) and III (8).

    4.4Exploration objective fulfillment:

    4.4.1 Producing Basins:

    I th d i b i d i 2002 04 12417 GLK/LK f 2D 13113 S K f 3D i i d t

  • 7/26/2019 On Gc x Midterm Appraisal

    6/34

    ONGCs Mid Term Appraisal of 10thPlan

    Cambay Basin:

    !

    Assessing Mesozoic prospectivity In Rajpardi area and West of Baola.! Oligo-Mlocene prospectivity in Navasari area, in South Cambay basin.! Exploration spread to Degam area, leading to oil strike in Degam-1 in Oligocene sequence.

    Rajastan Basin:

    ! Tested Goru and Pariwar play in S. Kharatar area, leading to significant gas strike in ChlnnewalaTibba.

    A&AA Basin:

    ! Exploration spread to Eastern Tripura- initiated the seismic data acquisition.! Exploratory drilling taken up in sector-Vc in Northern Cachar.

    K.G. Basin:

    ! Exploration spread to Vizag high area in northern part of K.G. shallow water area to establishGondwana prospectivity.

    Cauvery Basin:

    ! Exploration spread to Gulf of Mannar to establish extension of Nannilam play and test additionalTertiary turbidite plays.

    ! Panruti and Udaiyur in Ariyalur - Pondicherry and Nammeli in Tranquebar sub-basin

    Mumbai Offshore:

    ! Exploration spread to South Ratnagiri, in the form of seismic surveys and exploratory drilling,leading to establishing significant lead in Panna formation and Oligocene carbonates.

    ! Exploratory drilling in Shelf margin depression (SM-86) area.

    New prospects taken up and Hydrocarbon Strikes made:

    During 2002-04, 51 new prospects were drilled in different basins. 12 new hydrocarbon finds were madeduring first two years of the 10th Plan which are mentioned below:

    Sl. No. Basin Well Find

    1. A&AA Banamali Oil

    2. A&AA Laipling Gaon Oil

  • 7/26/2019 On Gc x Midterm Appraisal

    7/34

    ONGCs Mid Term Appraisal of 10thPlan

    7. A&AA East Lakhibari Oil &Gas

    8. Western Offshore NMT (North East of MidTapti) Gas

    9. Krishna Godavari Offshore G-4 Gas

    10. Krishna Gadavari Onshore Sitarampuram Oil &Gas

    11. Western Onshore Degam Oil

    12. A&AA Sonamura Gas

    The details of these hydrocarbon finds made during 2002-04 are placed in Appendix-IV.

    4.5Hydrocarbon leads obtained:

    Cambay Basin:

    ! Gas bearing Mehsana sands were discovered for the first time in Mansa field in the well Mansa-

    25, providing a significant lead in the eastern basin margin.! Two wells drilled in the Nardipur Low adjoining Umbodra field, on the interpreted K-IX channel

    brought out by 3D interpretation, proved oil bearing thus validating the model. This importantlead has given an impetus to hitherto poorly explored K-IX sand in the Nardipur Low area.

    ! Kalol III+IV sand was found oil bearing in three wells drilled in the south-western part ofNawagam field as an additional pay discovered in the field.

    ! Oil find in the well Gandhar -532, drilled on the western rising flank of Tankari Low has openedup a large area for exploration.

    ! Southwest wards extension of oil/gas bearing Jambusar Sands was proved by the well Jambusar-

    26, leading to exploration expansion.

    A&AA Basin:

    ! The well KG-S produced commercial hydrocarbons from LBS-1 and is presently under testing inLBS-2, opening further areas for exploration.

    ! The well PD-4 produced commercial hydrocarbons from Tura and Sylhet, providing impetus forexploration of Pre-Barails in the area.

    ! The well RO-40 produced commercial hydrocarbons from Upper Bhuban sands, thereby openingup the area south of the well for further exploration.

    Mumbai Offshore:

  • 7/26/2019 On Gc x Midterm Appraisal

    8/34

    ONGCs Mid Term Appraisal of 10thPlan

    ! R4N: It was drilled to explore the Eocene carbonates in a structural play and Panna clasticsassociated with inversion within the Vijaydurg graben. The well has indicated oil and gas from

    Panna Fm.! C37-4: Located in the Tapti-Daman sector, flowed gas from Mahuva Fm.

    4.6 New plays tested:

    A&AA Basin:

    ! The Gondwana sandstone was a new play tested in the well East Lakhibari-1 and establishedpresence of oil.

    K.G. Basin:

    ! Syn-rift sediments in the western part of Gudivada graben and Sub-conformity trap below Mio-Pliocene unconformity in Sitarampuram area

    ! Mio-Pilocene channel fan complex in K.G. deep water

    Mumbai Offshore basin:

    ! Lower Bassein play in the Heera-Panna-Bassein sector (Vasai West, B 182A).! Eocene-Oligocene carbonate wedge-out play in the DLS prospect in BH-DCS sector.! Shelf edge carbonates build-up in Ratnagiri sector.! Eocene carbonates as structural play due to Inversions within Vijaydurg graben in Ratnagiri

    sector.

    4.7Lead pursuing efforts

    Cambay and Rajastan Basins:

    ! Efforts have been expended to pursue the leads obtained in the basin with acquisition of 3Dseismic and firming up of exploratory locations in Chinnewala Tibba, Degam, Nawagam-Sadraand Manso.

    ! Integrated interpretation in the Warosan Low and its flanks for Mandhali prospects and locationsfirmed up.

    ! Reinterpretation of 2D and 3D seismic data for delineation of Wadasma new pay.

    A&AA basin:

    ! The lead established by the well BM-4 in the Banamali area, in 2001-2002, was followed up andlocations were released.

    ! In the East Lakhibari, three locations were released, based on the integrated G&G studies.

  • 7/26/2019 On Gc x Midterm Appraisal

    9/34

    ONGCs Mid Term Appraisal of 10thPlan

    Cauvery Basin:

    ! Significant success obtained in Kanjrangudi-3 with establishment of hydrocarbons in Bhubanagiriand Nannilam plays.

    ! Appraisal drilling taken up in Kuthalam, Vijaypuram, Kamalapuram, Tiruvarur.

    Mumbai offshore:

    ! Bassein East: In addition to the known pays in the wells of Bassein East, additional pays wereencountered in the well BSE-6 at deeper levels which flowed gas.

    ! B28-4: Located to the SW of Vasai West in the Heera- Panna- Bassein sector to explorehydrocarbon potential of Mukta, Bassein & Panna Fm, the well flowed oil and proved theextension of the Panna oil bearing trend of B 149 towards south.

    4.8Field growth established.

    ! Cambay / basin: Pool extensions were established in Mandhali and Linch sand units in theJotana-Warosan-Unch area, Kalol and Mehsana sands in the Nandasan area, Kalol IX and X sandsin the Ahmedabad-Nandej-Nawagam-Wasna-Sadra area, Kalol IX sand in Nardipur Low

    southwest of Limbodra field, Wadu pay in the northern part of Wadu field, Kalol VII and VIIIsands In Gamij area, S-I pay in southwestern part of Jambusar field

    ! A&AA basin:Pool extensions were established in Nambar, Khoraghat, Changmaigaon, Gojalia,Panidihlng, Rokhia-Konaban

    ! K.G. Basin: Significant field extensions were established at Pasarlapudi, Kesavadasupalem,Gopavaram, Rangapuram, Kavitam, Penumadam, Endamaru, and Kaikalur, in the on land andGS-KW & G-1 in the offshore.

    ! Cauvery basin:New pools were established in Kamalapuram, Vijayapuram and Tiruvarur fields.

    In Vijayapuram, Kamalapuram and kanjirangudi fields significant field extensions wereestablished! Mumbai Offshore:Established extension of Bassein field in the west

    4.9Reserve accretion:

    ! Tenth Plan in-place hydrocarbon Accretion target is of the order of 570 MMToe. During the firsttwo years, the actual accretion is 233 MMTOE, against the target of 256 MMtOE for these twoyears. Target for 2004-05 (BE) has been kept as 148.4 MMToe.

    ! Similarly against the Ultimate ReseNe accretion target of 147.13 MMToe for the total Tenth planperiod, the actual achievement during 2002-04 has been 74.39 MMToe and accretion of 40 MMtoehas been planned during 2004-05.

    Target (BE) AchievementYearIIH UR IIH UR

    2002 03 2 30 0 28 0 0 3

  • 7/26/2019 On Gc x Midterm Appraisal

    10/34

    ONGCs Mid Term Appraisal of 10thPlan

    4.10Deep Water Exploration:

    ! A major thrust was given to deepwater exploration at the time of formulation of 10 thPlan and itwas envisaged to drill 34 exploratory wells (firm programme) in deepwater areas during 10 thPlan period.

    ! ONGC currently holds 29 deepwater PEL acreages, of which 20 have been awarded under thefour rounds of New Exploration Ucensing Policy (NELP).

    ! During first two years (2002-04) of lOthPlan, ONGC has acquired 8485 LK of 20 and 9684 sq. km.of 3D seismic data and 5 wells have been drilled, against the 2002-04 target (BE) of 13365 LK of20, 1573 sq. km. of 30 and 19 exploratory wells.

    ! To give Impetus to deepwater exploration, project Sagar Sammriddhi was launched in August

    2003. This project, the biggest ever-deepwater exploration campaign by a single operatoranywhere in the world is progressing with 3 drill ships, Belford Dolphin, Discoverer Seven Seasand ONGC's own rig Sagar Vljay.

    ! The deep-water exploratory well GD-1-2 (water depth -751 m) on the GD structure wascompleted during 2003-04. In addition, under the campaign 'Sagar Sammriddhi', ONGC hasalready drilled two wells namely G-4 -2 In a water depth of 430 m in the East Coast, through in-house drill ship "Sagar Vijay and GK-DW-A-1 in bathymetry of 1860 m in the Arabian Sea withchartered hire rig Belford Dolphin.

    ! The well G-4-2 proved to be gas bearing and the estimated initial in place volume of gas is about22 BCM. Three more wells namely, DWRO-1-A in the west coast at a water depth of 1090 m byBelford Dolphin and KD-2-1 by Discoverer Seven Seas at a water depth of 1463 m and GD-2-1 byin-house drill ship "Sagar Vijay at a water depth of 650 m in East Coast were under drilling as on1.04.2004.

    ! The current emphasis is on pre-drill risk reduction measure through validation of theinterpretation carried out in house by internationally reputed consultants namely M/s LandmarkM/s Paradigm and M/s Jason. M/s Triton has been engaged as consultant for deepwaterdrilling.

    4.11Exploration focus in Yet-to-establish basins:

    ! During 2002-04, the tempo of exploration in the yet-to -produce basins viz. Kutch offshore,Kerala-Konkan, Mahanadi and Bengal was enhanced, so as to bring out the GME cycle operativeand establish breakthrough.

    ! During these two years, 4966 LK of 2D, 5732 Sq. km. of 3D seismic data were acquired and 2exploratory well was drilled in these basins against the 2002-04 (BE) target of 8700 LK of 2D, 2579Sq. km. of 3D and 13 exploratory wells.

    ! Several interesting hydrocarbon ploys have been identified based on the geoscientific dataacquired and the analysis carried out/under progress, which will form the basis forintensification of exploration in these basins in the remaining period of the plan period.

    4.12Exploration in the Frontier Onland basins:

    D i 2002 04 l i i i i i d i h f i l d b i i G V ll

  • 7/26/2019 On Gc x Midterm Appraisal

    11/34

    ONGCs Mid Term Appraisal of 10thPlan

    4.13Efforts for CBM Exploration:

    ! Following the establishment of CBM gas production for the first time in India from a well inJharia in Parbatpur block during the previous years and introduction of CBM policy byGovernment of India, ONGC has further consolidated the CBM exploration. Production testingof another well Jharia-4 is in progress to assess its production potential.

    ! Out of the two blocks awarded to ONGC-CIL consortium for CBM exploration and exploitationin the previous years, pre drill G & G activities have been completed in Jharia block. Nine pilotwells have been released and eight bore holes and two exploratory locations have been firmed upin Parbatpur area. Pre drill EIA studies have been completed.

    ! Execution of planned work.; is in progress in the two blocks, one each in Bokaro and NorthKaranpura, awarded under CBM policy-1 jointly to ONGC and Indian Oil Corporation Ltd. Inthe both the blocks, G&G studies have been completed. In Bokaro block two exploratory andeight bore hole locations have been released out of which three bore holes have been completedand two are in progress. Two exploratory and nine borehole locations have been released inNorth Karanpura block, out of which drilling of three bore holes has been completed. Work onone bore hole is in progress.

    ! In the second round of bidding for CBM Gol has invited bids on 23rdMay 2003 for nine blocks forCBM exploration and exploitation. After detailed analysis of the Blocks offered, ONGC submitted

    bids for six Blocks and has been awarded five Blocks, four on sole risk basis and one inconsortium with GSPCL.

    ! ONGC presently holds nine CBM Blocks and has established itself as the leading company forCBM exploration in the country, of which 7 blocks have been obtained through CBM-NELP (PELobtained for 5 blocks). The blocks awarded under the CBM NELP rounds are as follows:

    Blocks / AreaAwarded to

    ONGC &Consortium

    Existing Blocks /Area with

    ONGC

    No. Km2 No. Km2

    CBM Policy-I 2 435 2 435CBM Policy-II 5 2344 3 1,127Total for CBMPolicy

    7 2779 5 1562

    5.THRUST AREAS IDENTIFIED FOR ACCELERATION OF EXPLORATION

    Cambay Basin:

    ! Recent leads obtained along the eastern basin margin in Mansa, Limbodra, Gamij etc reaffirm thisas a priority sector.

    ! Success at Degam -1 and Gandhar - 532 puts the flanks of Tankari and Broach depressions in highi it

  • 7/26/2019 On Gc x Midterm Appraisal

    12/34

    ONGCs Mid Term Appraisal of 10thPlan

    ! Considering the series of success in Oligo-Miocene prospects in the CB-OS-2 block, Olpad-Dandi-Kim area has attained a special thrust for probing similar structures in the onland part.Accordingly, 3D seismic data is being acquired in the entire area for a focused exploration.

    Rajasthan Basin:

    ! The hydrocarbon find in Lower Goru and Pariwar play in Chinnewala Tibba in the western partof Jaisalmer-Mari high has only confirmed the thrust assigned to this sector. This sector attainsthe highest priority and is being covered by 3D seismic survey.

    ! Exploration for new plays in Cambrian and Permo-Triassic sequences (though got delayedpending environmental clearance for the site) remains a high priority.

    A&AA basin:

    ! Banamali- Laipling-gaon -Kuargaon for explorationof Barail plays,! Panidihing-Disangmukh area for exploration of Pre-Barail plays! East Lakhibari-Merapani Sectors for Sylhet and Kopili plays! South of Nambar for Bokabil, Kopili and Syhet plays! Manikyanagar-Sonamura and Tichna-Gojalia for Bokabil and Bhubal plays

    K.G. Basin:

    ! Major emphasis on the shallow offshore area (GS-29, GS-15 and GS-KW) to explore Mio-Pliocenesequences.

    ! Amalapuram block identified for focused exploration based on the leads obtained recently inPSD-36, SR-2 and GM-3&4.

    ! Based on the lead obtained in Kesavadaspaplem-6&7, coastal tracks of Island and amalapuramblocks have been identified as a focused area for exploration of Matsyapuri play.

    !

    Tirupati play in Kavitam and Penumadam area.! Northern part of West Godavari sub basin and Kaza-Kaikalur high to chase the leads obtained

    recently.

    Cauvery Basin:

    ! Gulf of Mannar sector: Deliberate thrust in this Frontier sector during last 2 years to realize thepotential including the extension in the deep water areas. Visualized extension of Nannilam andKamalapuram play to this sector.

    ! Tranquebar sector: Significant success achieved in exploration for Andimadam oil & gas play inKuthalam- Kali areas. Play extension being pursued in NW rising flank of Tranquebar sub-basin.

    Mumbai Offshore Basin:

    S / S l f h d h l

  • 7/26/2019 On Gc x Midterm Appraisal

    13/34

    ONGCs Mid Term Appraisal of 10thPlan

    side of Diu fault; Strati-structural play within Panna Formation, specially in the area girdling theBasement Highs

    ! Bombay High-DCS: Wedgeout prospects of Palaeogene carbonate along Bombay pericline;Miocene Reefal plays along shelf margin and along Diu fault; Structural plays of Palaeogene andMiocene carbonates; Clastic play within Panna formation along the rising flanks of southernpalaeo-sink, basement spurs.

    Deep water sector:

    ! Mio-Pliocene play in K.G. deep offshore in G-4, KD, GO and off Yanam (KG-DWN- 98/4 andKG-DWN-98/5 area).

    !

    Oligo-Miocene play in Mahandi deep water.! Mesozoic play in Kerala-Konkan.! Tertiary carbonate play in Kutch sector.

    Yet to establish basins:

    ! Bengal and Mahanadi offshore:! Large turbidite plays.! 3D seismic data acquired in Bengal and Mahanadi shallow offshore indicates significant geo-

    bodies with good potential. 3D seismic under acquisition in Mahanadi deep water.! Potential evaluation in this new sector promises exciting breakthrough in next 2-3 years.! Kutch shallow offshore: Mesozoic play in shallow water! Kerala-Konkan: Eocene carbonate and Mesozoic play

    6.DEVELOPMENT DRILLING:

    During 10th Plan 622 development wells were projected. During the first two years of 10th Plan 387

    development wells were drilled against BE target of 372 wells. During 2004-05 BE 182 development wellsare planned.

    7.PRODUCTION OF CRUDE OIL, NATURAL GAS AND VALUE ADDED PRODUCTS:

    Crude Oil:

    The 10thplan target for crude oil production was 130.026 MMT. The cumulative achievement in respect offirst 1wo years (2002-03 BE & 2003-04 BE) is 52.062 MMT which is 99.6%. There was a shortfall of 0.326

    MMT during 2003-04, the reasons for shortfall are:

    ! Increase in water cut and seizure of wells in Gandhar, Ankleshwar, Jambusar, Sisodra, Motwanand Dabka.

    ! Environment problems in Assam and ASEB power disruptions.! Less contribution from EOR wells of Santhal and Balol fields in Mehsana Asset.

    R i h MUT k i li

  • 7/26/2019 On Gc x Midterm Appraisal

    14/34

    ONGCs Mid Term Appraisal of 10thPlan

    Natural Gas Sales:

    The 10thPlan target for gas sales was 90.136 BCM. The cumulative achievement in respect of first twoyears of 10th plan is 38.51 BCM which is 100.81% 2002-04 (BE) target.

    Value Added Products:

    The 10thPlan target for value added products was 15156 KT. The cumulative achievement in respect offirst two years of the 10thplan is 7422 KT which is 110% of the total 2002-04 (BE) target.

    8. INITIATIVE TAKEN TO ENHANCE PRODUCTION OF OIL & GAS:

    As mentioned earlier Improved Oil Recovery (lOR)/ EOR in 15 major fields are under different stages ofImplementation.

    Further six new IOR schemes have been started in onshore areas namely Linch, Nadasan in MehsanaAsset, Ungala in KG Asset and Narimanam, Kovilkalappal, Nannilam in Karaikal Asset.

    In addition to above, ONGC has taken/is taking various actions for maintaining/augmenting the crudeoil and natural gas production as mentioned below, apart from focusing on optimisation of artificial lift,

    additional perforation/re-perforation, and work-overt stimulation of wells:

    ! In an effort to reduce cost of offshore well servicing work-over with modular rig was conceivedand Rig Sundowner -VI has commenced operations from 8.6.2003 at IK Platform. The work-overoperations by this concept are not only cost effective but also independent of pugmark of jack uprigs and seabed survey. Also no docking constraints envisaged with this concept.

    ! Solid Expandable Tubular (SET) is a new technology being adopted in Mumbai Offshore for costeffective side tracking of wells in L-III middle layer. These wells save time taken todrill/sidetrack in L -III middle layer.

    ! Self Diverting Acid (SDA) like Visco-elastic Diverting Acid (VDA), Insitu Cross-linking AcidDevelopment Agent (ISCADA) etc. jobs are being taken up as a new pilot introductorytechnology in wells of Mumbai High field to improve oil production.

    ! Application of gel/polymer technology to control production of excess water and gas.! Specialized drilling techniques like horizontal drilling, drain hole drilling, side tracking,

    Extended Reach Drilling (ERD) and multilateral drilling are being adopted to improve wellproductivity.

    ! Polymer flooding in Sanand field of Ahmedabad Asset.

    ! Alkali-Surfactant EOR pilot in Kalol field of Ahmedabad Asset.! Alkali-Surfactant-Polymer (ASP) EOR pilot in Jhalora and Viraj field of Ahmedabad asset, Lakwa

    field of Assam asset and in S3-1 and 54-3 of Ankleshwar asset.! Rigless workover jobs through Coil Tubing Unit (CTU).! Workover jobs without killing pay zones (using clean plug).! Laboratory studies for EOR processes like SWAG, WAG, ASP, Air injection, MEOR as pilots have

    b l d f b f fi ld d f ibili di i

  • 7/26/2019 On Gc x Midterm Appraisal

    15/34

    ONGCs Mid Term Appraisal of 10thPlan

    o Alliance with profit sharing with other E&P companies.o Through service contract.

    9.REALISATION OF POTENTIAL FROM SMALL/MARGINAL FIELDS

    In-house Development:

    Three offshore fields viz. G-1, D-1 and Vasai East are considered under in-house development. Thedevelopment scheme for 0-1 is under execution. Schemes for development of Vasai East and integrateddevelopment of G-1 & GS-15 have been approved by ONGC board on 22.04.2003. Revised FR forintegrated development of G-l & GS-15 was approved in PAC meeting held on 25.3.2004.

    Development of marginal fields through outsourcing:

    In the first phase of the offer tenders were invited for 16 onshore marginal fields and eight fields namelyWest Becharaji, Khambel, Hirapur, S. Patan, Kamboi in Cambay basin and Laxmijan, Bihubar and Barsillain Assam were awarded. Final contract for six fields- West Becharaji, Khambel, Hirapur in Cambay basinand Laxmijan, Bihubar and Barsilla in Assam were signed on 28.04.04.

    ONGC board has also approved outsourcing of 19 identified marginal offshore fields of Western Offshore

    on seNice contract for which process is in progress.

    10. STEPS TAKEN TO REDUCE GAS FLARING:

    As per normal production practice, associated gas is produced along with crude oil as a by-product. Theproduced gas is first utilised for meeting internal requirements and the balance gas is offered/supplied toGAIL for further transportation, distribution and marketing. Low pressure associated gas/balanceavailable gas th6t cannot be supplied to consumers or due to adverse techno-economic has to benecessarily flared. This is done as gas cannot be normally stored, neither can it be allowed to escape in the

    atmosphere without being burnt. Flaring of such gas therefore cannot be avoided. There is, however, noflaring of non-associated (free) gas except technical flaring.

    In order to ensure that there is no flaring of gas other than flaring due to technical reasons, various gasflaring reduction schemes were formulated, some of which have already been implemented while othersare at various stages of implementation. On account of various initiatives taken to reduce gas flaring, gasflaring in ONGC has been considerably reduced from a level of 6% of production in 2001-02 to 3.5% ofproduction in 2003-04.

    In order to reduce flaring of gas from isolated/marginal fields, ONGC has been empowered byMOP&NG for direct marketing of gas upto 1.0 LCMD from each of such fields provided GAIL is not ableto identify consumers in these areas within six months time.

    Further gas supply agreement with Assam Gas Company Limited (AGCL) was signed on 23.01.04 forsupply of 30 000 SCMD gas from isolated fields of Khoraghat and Namber in Assam under direct

  • 7/26/2019 On Gc x Midterm Appraisal

    16/34

    ONGCs Mid Term Appraisal of 10thPlan

    It is pertinent to mention here that with the implementation of various gas flaring reduction schemes.ONGC's installation at Uran Terminal and Heera Offshore platform have achieved zero gas flaring status.Special drive has also been undertaken to achieve zero gas flaring at all installation by 2005-06.

    11.PLAN OUTLAY & EXPENDITURE:

    The basis of 10thPlan revolved fundamentally around certain critical assumptions made at the time offormulation e.g. crude price of 18 $/bbl, Exchange rate of 47.5 Rs. /$, successes in ongoing explorationefforts, Intensive upgradation of old installations. Facilities and equipment and all these to primarily befunded through own internal resources.

    Considering the above the Plan outlays for 10th

    Plan were constrained to a base level if the primaryassumptions were followed.

    After the formulation of the 10thPlan several major changes have come into being - Global, sectoral andwithin the company.

    ! On the Global front Oil prices have steadily remained at high levels than historical averages andthan assumed for lOth Plan. Similarly Exchange rate which has seen reversal with the Rupeeappreciating by Rs.2 to 2.5 against the US Dollar i.e. Rs. 47.50 1$ assumed in 10th Plan against Rs.

    45-46/$ prevailing now.! On the sectoral front Government has allowed International parity for crude price, which has

    benefited the company at two levels first by International pricing and secondly by sustained highInternational crude prices resulting in higher cash flows than planned in 10thPlan.

    ! At the company level there has been major reorganization and efforts to have sustained growthby having three Strategic Goals

    ! To double reserve accretion on Initial in-place hydrocarbons from 6 billion tonnes to 12 billiontonnes in next 20 years.

    !

    Improve Global Recovery Factor from 28% to 40% by the year 2020.! 20 MMT per annum Equity Oil & Gas equivalent from overseas by 2020 through OVL.

    During 2002-03 against an outlay of Rs. 7408 Crore, actual expenditure was Rs. 5089 Crore. Whereas in2003-04 against BE target of Rs. 10265 Crore, the actual utilisation for the year 2003-04 is Rs. 6760.44 Crore(provisional).

    The activity wise expenditure is appended at Annexure-II.

    Reasons for less utilisation of plan outlay during 2002-04 are:

    ! Less utilization due to delays in hiring / mobilization owing to non-availability of charter rigs /deepwater rigs and less expenditure under capital purchases.

    ! Less expenditure under capital projects! Shortfall in drilling for want of environmental and security clearance.

  • 7/26/2019 On Gc x Midterm Appraisal

    17/34

    ONGCs Mid Term Appraisal of 10thPlan

    Appendix-I

    10th

    Plan Major Project's description

    Improved recovery projects:

    i) Mumbai High Redevelopment:

    Mumbai High field is the largest and most prolific field discovered so far in India. The field developmenthas passed many challenges due to very large aerial extent, complex geology and multi-layered reservoir.A comprehensive review of the field was made in consultation with M/s Gaffney Cline & Associates and

    redevelopment strategy was chalked out. The proposed redevelopment programme in Mumbai High is amajor step to arrest the decline and raise the recovery factor by around 5% i.e., from 25-26% to 30-31%.The redevelopment is planned in two projects namely:a) Mumbai High North Redevelopmentb) Mumbai High South Redevelopment

    ii) Mumbai High North Redevelopment:

    ONGC board approved the project at a cost of Rs.2929.40 Crore. The scheme, with scheduled completionby December'2005, envisages incremental gain of 24.8 MMT of oil and 5.85 BCM of gas from 2000-2001 to2029-30. The project envisages installation of 4 well-head platforms- nine slots each, one process platformwith 1.9 MMSCMD gas compression capacity, 2,50,000 BWPD water injection capacity, drilling of 73 newwells 62 producers and 11 injectors) and 10 side track wells with associated pipelines & modifications.The scheme is being planned to be implemented by inviting 5 tenders.

    iii) Mumbai High South Redevelopment:

    The tentative cost of the project is around Rs 5255 Crore. The facilities envisaged drilling of 140 wells (133producers + 7 injectors) including two S1 sand wells, 4 side tracks, 17 new well platform including ZAplatform, 1 new process platform, bridge connected to BHS complex, submarine pielines, 8 clamp-onstructures and modification and augmentation of facilities on various platform. The scheme will result inproduction of 35.95 MMT of additional oil and 9.63 BCM additional gas by year 2029-30. The recoveryfactor at the end of 2029-30 is expected to be 31.5%.

    iv) Heera

    Heera Field is situated 70 kms. South-West of Mumbai City in the Arabian Sea and 140 kms. South East ofMumbai High at an average water depth of about 50 meters. Based on geological data from exploratorywells it was proved to be one of the major hydrocarbon bearing structures in Mumbai Offshore Basin,with a number of reservoirs of commercial oil and gas accumulations in Heera field. Heera wasdiscovered in 1990 and was developed in 1994. In order to improve the oil recovery, IOR scheme wasproposed in Heera & South Heera Field. The incremental oil production is envisaged to be 3.19 MMT of

    il d 0 553 BCM f d i th i d f 2003 04 t 2019 20 Th j t i i t ll ti f

  • 7/26/2019 On Gc x Midterm Appraisal

    18/34

    ONGCs Mid Term Appraisal of 10thPlan

    field was developed in phases and was put on commercial production in March '90. However, the full-fledged production commenced from June'94 through 11 well platforms. As per earlier developmentscheme it was envisaged to achieve the oil production of 29.35 MMT considering recovery factor of26.75% till 2019-2020. A proposal for improved oil recovery in Neelam field at a capital cost of Rs.347.69Crore was approved. The scheme proposed incremental oil & gas production of 2.06 MMT and 1.23 BCMrespectively upto 2020 over and above base case. This shows increment of around 1.88% in recoveryfactor. The project envisages installation of 3 clamp-on structures on NLM-1, 2, 3, & 4 well platforms, up-gradation of process gas compressors, lying of pipelines and associated modifications. The scheduledcompletion of the project is July'2003.

    vi) Gandhar

    The field was discovered in 1984. The field has multi-layered reservoirs having oil and gas in 12 pays.Production from Gandhar fields started through Early Production System (EPS) in May 1986.

    IOR scheme was prepared for improving recovery, from entire Gandhar field covering an area of around800 Sq. Kms at a cost of Rs. 473.23 Crore with an additional of inputs of 55 development wells. The IORscheme envisages a cumulative production of 34.313 MMT of oil and condensate by 2019-20 from entireGandhar field, out of which incremental production of 4.34 MMT of oil has been, envisaged w.e.f. 2000-01till 2019-20 through IOR scheme. Average Recovery with lOR will be 30.13%, which shows improvement

    of 4.24% in recovery factor. The project comprises of drilling of 55 development wells, construction of 2nos. of Group Gathering Stations, facilities for handling MP/LP gas at GGS-VI, up-gradation offeeder/collector pipelines, facilities for gas lift, compression facilities for low pressure gas and up-gradation of ETP.

    vii) North Kadi

    Discovered in late 1968, the North Kadi field is in the northern part of Ahmedabad - Mehsana block ofCambay basin. Hydrocarbon accumulation has been established in seven pays within lower Cambay

    shale. North Kadi is a major oil field in Mehsana area. The field has been developed in stages based onsimulation studies carried out during the years 1981, 1987, 1989 & 1991. Based on the performance ofdrilled wells of earlier schemes, an IOR scheme was proposed which was approved at a cost of 62.86Crore with scheduled completion by March'2003. The scheme envisages drilling of 33 Infill wells,Installation of Sucker Rod Pumps & Gravel Packs in all the wells, associated well fluid lines, constructionof 1 GGS of 1000m3 Capacity. With the implementation of IOR scheme, improved oil recovery of about1.09 MMT (1.7%) of OIIP will be achieved by further improving the recovery of the field from the presentbase case of 20.118 MMT (31.22%) to 21.215 MMT (32.93%).

    viii) Santhal

    Santhal field located in the heavy oil belt of Mehsana in Gujarat State was discovered in 1971. The fieldhas been developed on 300m x 300m spacing, is on primary production since 1974. To augment theproduction rate and produce the bypassed oil, IOR scheme was approved at a cost of Rs.38.85 Crore withscheduled completion by March'2004 With the implementation of IOR scheme by 2013 Improved Oil

  • 7/26/2019 On Gc x Midterm Appraisal

    19/34

    ONGCs Mid Term Appraisal of 10thPlan

    ix) Kalol

    Kalol field was discovered in 1961. Development of the field started in 1964 and consequently wells were

    drilled with 700 m x 700 m spacing. Even though the trial production started in 1964, full fledgeddevelopment activity was undertaken in the late 80s. The improved oil recovery scheme was approved byONGC board at a cost of Rs. 99.67 Crore with scheduled completion by March'2007. The projectenvisages drilling of 38 infill wells, zone transfer in 57 wells, hydrofracturing in 80 wells, change ofartificial lift mode, installation of 2 compressors, power upgradation at 117 wells, installation of oneheater treater at GGS-IX and associated well fluid lines. With the implementation of IOR scheme by 2020,improved oil recovery of about 2.65 MMT will be achieved by further improving the recovery efficiencyof the field by 2.32 % from the present base case of 12.79 MMT (11.19 %) to 15.44 MMT (13.5 %).

    x) Jotana

    Jotana field discovered in 1977 is located 17 kms south west of Mehsana city. The field is on productionsince 1980. The present scheme is for improving oil recovery from Mandhali units, which comprises ofmore than 77% reserves. The scheme was approved by ONGC board at a cost of Rs. 53.24 Crore withscheduled completion by March'2004. The incremental gain envisaged is 0.96 MMT of oil in the period2000-01 to 2019-20. The project comprises of drilling of 25 infill wells, modification of GGS, creating ofwater injection facility and the associated well fluid lines. The scheme was conceptualize to augment oil

    production rate. Additional oil gain envisaged from the scheme is 0.96 MMT.

    xi) Geleki

    Geleki field is situated towards the southern fringe of Upper Assam valley. Trial production began inAugust' 1970 and regular production started from August' 1974. The proposed project envisagesmaximize recovery with optimum inputs viz. drilling of 25 infill wells, 24 zone transfer, installation of 6nos. HLW pumps and hydrofracturing in 10 wells in phased manner and creation of additional surfacefacilities such as ETP expansion with an anticipated cost of Rs. 343.05 Crore. The incremental recovery

    expected to be 3.942 MMT from 2001-02 to 2019-20.

    xii) Lakwa-lakhmani

    Lakwa field is located 32 sq. km east of Sibsagar town with its aerial extent of 70 sq. km. The field isunder production since 1964. The improve recovery plan has been drawn to tap the undrained oil. Theaction plan envisages additional 34 infill locations (includes side tracks well), 44 zone transfer, 47 watershut off job and creation of additional surface facilities at an anticipated cost Rs. 345.10 Crore. Theincremental recovery expected to be 4.941 MMT from 2001-02 to 2019-20.

    xiii) Rudrasagar

    Rudrasagar field is located south of Brahmputra river with its aerial extent of 30 sq. kms. The field is onproduc1ion since 1966. To improve recovery from the field, an action plan has been drawn to maximizethe recovery which invisages drilling of additional 34 infill location (includes side track wells), 10 water

  • 7/26/2019 On Gc x Midterm Appraisal

    20/34

    ONGCs Mid Term Appraisal of 10thPlan

    1. Development of D 1 Prospect

    D-1 oil field is located at a distance of about 200 Km SW of Mumbai city in the western offshore at the

    water depth of 85-90 m. A development plan was approved by ONGC Board on 25th September 2002 at acost of Rs.310.32 Crore. The project envisages production of 4.57 MMT of oil over a period of 10 years(from 2006 to 2015). The work envisages fabrication and installation of one light weight 12 slots well cumwater injection platform, Water injection capacity of 2500 m3/day, Installation of Electrical SubmersiblePumps in all the producers for artificial lift, Sagar Laxmi processing facility with modifications/utilityupgradation, Associated submarine pipelines and Drilling of 12 wells, 3 producers and 3 injectors each inphase-I & II. The scheduled completion of the project is March' 2005 (Phase-1) and March'2009 (Phase-II).

    2. Development of Bassein East

    Bassein East field is located in the Heera-Panna-Bassein block, which is one of the highly explored andprospective areas of Mumbai offshore basin. The water depth over Bassein East field ranges from 40-Som.A development plan has been approved by ONGC Board on 22th April 2003 at a cost of Rs.985.17 Crore.The project envisages production of 6.185 MMT of oil and 3.175 BCM of gas over a period of 15 years.The facilities planned are 8 legged production, processing cum water injection platform bridgeconnected to BPA, 2 well platforms (BSEA-12 slots and BSEB-9 slots), Oil Handling Capacity 20000BOPD, Water Handling -63000 BWPD, Submarine pipelines- 6 segments (38 Kms.). The project is

    scheduled for completion by March 2006.

    3. Integrated Development of G-l & GS-15 Fields

    G- 1 structure is located in Bay of Bengal, off Amalapuram coast in Andhra Pradesh in the water depth of267-300 m south east of existing G-15/23 offshore field. Discovery of hydrocarbon made in 1980 in thisstructure. GS-15 prospects are small oil & gas pools with marginal potential located in KG Offshore verynear to the coast in the water depth ranging from 8 -15 m. A development plan has been approved byONGC Board on 22th April 2003 at a cost of Rs.429.82 Crore. The project envisages production of 0.704

    MMT of oil and 4.135 BCM of gas over a period of 10 years (from 2005-06 to 2014-15).

    The following facilities are proposed for development of the field:

    G-l Field:

    ! Drilling of 2 new sub-sea wells, Regaining of G-1-9 well! Sub Sea Manifolds and control system!

    14 H x 30 kms common sub sea pipeline! Additional oil and gas processing and oil pumping facilities at onshore terminal! Pipeline to S. Yanam for transporting crude

    GS-15 Structure:

    ! One monopod platform at GS 15 1 with two well slots

  • 7/26/2019 On Gc x Midterm Appraisal

    21/34

    ONGCs Mid Term Appraisal of 10thPlan

    4. C2-C3 & LPG Recovery from LNG, Dahej

    The project was approved by ONGC Board on 29th December 2003 at a cost of Rs.900.92 Crore. The

    project envisages setting up a unit to recover 566574 TPA of C2- C3 and 347065 TPA of LPG from LNG atDahej. The scheduled completion of the project is June'2006.

    5. Mumbai High Uran Trunk Pipeline

    The project was approved by ONGC Board on 29th December 2003 at a cost of Rs.2792.50 Crore as areplacement of earlier laid Mumbai-Uran Trunk line. The project envisages laying, burying, testing &commissioning of 30N Sub-marine Oil Trunk Line from MNW to Uran Shore Terminal, Laying, burying,testing & commissioning of 28" Sub-marine Gas Trunk Line from MNW to Uran Shore Terminal, Laying,testing & commissioning of Associated Feeder Lines to both Oil and Gas Trunk Lines, Hook-Up &Modification on Platform complexes and at Uran Shore Terminal, Instrumentation, Elect. System etc. andprovision of 3 new MOL Pumps on NQ Complex.

  • 7/26/2019 On Gc x Midterm Appraisal

    22/34

    ONGCs Mid Term Appraisal of 10thPlan

    Appendix-II

    Progress of the Major Projects as end of March 2004:

    Brief status of implementation is as under:

    Sl.No.

    Project Approvedon

    ApprovedCost Rs.Crore

    Status of Implementation

    1. Mumbai HighNorth

    Redevelopment

    16.12.2000 2929.40 Project is under implementation. Scheduled completionDec. 2005. Out of 4 packages two packages MNCO &

    N11/N12 Platform completed. Work in progress in resttwo packages. One more package is added as 3 Pipelineproject and is under execution. No cost or time overrunfor the project anticipated at this stage.

    2. Mumbai HighSouthRedevelopment

    16.10.2001 5255.97 Project is under implementation. Scheduled completionJuly 2007. Out of 7 packages, two packages i.e. ZAPlatform and MSCO completed. MSP process platformwork is under execution with schedule completion byApril 2005. After the review of the recently drilledwells, proposed platforms requirement reviewed andsome platforms merged into 9 well platforms andpipeline & platform modification project. The work forthe same awarded on 20.02.2004. 9 Clamp-on projectadded in scope of work and awarded on 14.11.2003. Nocost or time overrun for the project anticipated at thisstage.

    3. IOR Neelam 11.01.2001 347.69 Project is under implementation. Scheduled completion

    July 2003. Out of 3 packages, two packages. Clamp-onsand PM&PL completed ahead of schedule on 04-05-01and 3-11-02 respectively. Thira package Upgradation ofPGC-part work i.e, overhauling & upgradation of 3turbines completed and upgradation of D&Rcompressors is underway. There is no cost over run butthe completion is likely to delay by 12 months as it tooklong time to negotiate with OEM of installedcompressors.

    4. IOR Gandhar 16.12.2000 473.23 Project is under implementation. Scheduled completionDecember 2004. Work planned in seven packages, outof which one package. Expansion of GGS-VI has beencompleted and process unit commissioned for package-II Construction of GGS-VII. Work on other fourpackages in progress. The seventh package i.e. ETP

  • 7/26/2019 On Gc x Midterm Appraisal

    23/34

    ONGCs Mid Term Appraisal of 10thPlan

    for post monsoon 2006-07 and subject to review. Nocost of time overrun for the project anticipated at thisstage.

    6. IOR Geleki 26.09.2001 390.90 Project is under implementation. Scheduledcompletion March 2007. Pre-award activities forEffluent Treatment Plant in progress. No cost or timeoverrun for the project anticipated at this stage.

    7. IOR-Rudrasagar 15.09.2001 113.90 Project is under implementation. Scheduledcompletion March 2006. Work on Gas LiftCompressor Plant is in progress. Package II-Installation of ETP- completed as per schedule in Dec.'

    2003. No cost overrun for the project anticipated atthis stage.8. D-l Prospect Dev 29.9.2002 310.32 Work awarded to M/s EIL at quoted price. Due to

    change in scope of work the cost has gone up.9. G1/G15

    Development22.04.2003 429.82 Geotechnical investigation is in progress. For

    consultancy work awarded to M/s Intec AsiaPacific . Malaysia. NIT for onland export pipelineissued on 15.01.2004. EIA & RA studies are in progressat M/s NEERI. Nagpur.

    10. Dev. of BasseinEast

    22.04.2003 985.17 NIT issued on 04.11.2003. The NOA date is06.04.2004 with scheduled complet ion by 31.03. 2005 (RFD).

    11. Mumbai UranTrunk Pipeline

    29.12.2003 2792.50 NOA placed to M/s HHI on 9.1.2004. Pre-Enggsurvey for top side modifications and jacket facecompleted. Design Engineering is in progress.

    12. C2-C3 RecoveryProjects

    29.12.2003 900.92 Recently approved.

  • 7/26/2019 On Gc x Midterm Appraisal

    24/34

    ONGCs Mid Term Appraisal of 10thPlan

    Appendix-III-A

    Exploration Programme Implementation-Basin Wise( 2002-03)

    2D (GLK/LK) 3D (Sq. km) Exploratory Wells

    BE Actual BE Actual BE Actual

    CAMBAY 440 1497 360 472 49 54

    RAJASTHAN 300 1 1

    UPPER ASSAM 100 47 280 344 21 22

    ASS. ARA (CACHAR) 75 196 17 1 2

    K-GODAVAR1 900 856 138 248 18 27

    CAUVERY 300 416 130 289 18 19

    BENGAL 100 1

    TRIPURA 200 155 5 5

    HF &G V 715 534

    VINDH. & GOND. 14

    TOTAL ONLAND 3130 3715 908 1370 114 130

    MUMBAI OFFSHORE 1540 7301 1098 1098 22 15

    KUTCH & SAURASH. 4000 2857 3KERALA-KONKAN 32 1

    IK-GODAVARI 192 192 3 3

    CAUVERY 1035 1035 3

    MAHANADI

    BENGAL SW 600 1119 1447 1447 1

    EAST COAST DEEPWATER 842 842 3 2

    WEST COAST DEEPWATER 5865 6035 2655 2655 3

    TOT AL OFFSHORE 12005 17344 7269 7269 39 20

    TOTAL ONGC 15135 21059 8177 8639 153 150

    Accretion: Targets & Actuals

    In-Place Hydrocarbon Accretion (O+OEG), MMt

    2002-03Basin X-Five Year Plan(2002-07) STP

    BE Actual

    Western Onshore 71.1 21.5 24.09

    h

  • 7/26/2019 On Gc x Midterm Appraisal

    25/34

    ONGCs Mid Term Appraisal of 10thPlan

    Appendix-III-B

    Exploration Programme Implementation-Basin Wise (2003-04)

    2D (GLK/LK) 3D (Sq. km) Exploratory Wells

    BE Actual BE Actual BE Actual

    CAMBAY 670 652 360 553 47 45

    RAJASTHAN 280 79

    UPPER ASSAM 410 5 180 150 24 10

    ASS. ARA (CACHAR) 177 30 20 3

    K-GODAVARI 250 485 138 338 17 15

    CAUVERY 325 405 138 331 22 17BENGAL 1 1

    TRIPURA 515 223 50 5 4

    HF &GV 445 505 1 1

    VINDH. , GOND.& SAT 295 133 1

    TOTAL ONLAND 3190 2586 896 1470 120 94

    MUMBAI OFFSHORE 3862 7798 23 21

    KUTCH & SAURASH. 3000 763 3883 1KERALA-KONKAN 1000 1

    K-GODAVARI 200 150 6 3

    CAUVERY 800 4 2

    MAHANADI 100 402 1

    BENGAL SW 958 1500 4

    EAST COAST DEEP 2450 900 5119 3 2

    WEST COAST DEEP 7500 7263 1068 10 1

    TOTAL OFFSHORE 11500 3407 13888 18421 52 30

    TOTAL ONGC 14690 5993 14784 19891 172 124

    Accretion: Targets & Actuals

    In-Place Hydrocarbon Accretion (O+OEG), MMt

    2003-04Basin X-Five Year Plan

    (2002-07) STP BE Actual

    Western Onshore 71.1 18.75 28.36

    Western Offshore 302 70 27.75

    A&AA 85.3 23 16.49

    Krishna Godavari 64 12 27.48

    th

  • 7/26/2019 On Gc x Midterm Appraisal

    26/34

    ONGCs Mid Term Appraisal of 10thPlan

    Appendix-IV

    NEW FINDS DURING 2002-04

    Year 2002-03:

    1. Vasai West (B-22). Mumbai Offshore

    The discovery well B-22-5 is about 15 km west of Bassein field (water depth: 73 m) & was drilled up to2110 m. The well flowed oil and gas from the Middle Eocene Bassein Formation (Lower & Upper) andgas from the Early Oligocene Mukta Formation. Another well SB-E was drilled to the NE & about16.5 km from B-22-5 which flowed oil & gas from Bassein Fm.

    Flow RatesInterval (m) Payzone Choke SizeInches Oil (BPD) Cond (BPD) Gas (M3/d)

    1972-56 Lr. Bassein 1/2 1774 10760

    1945-43, 1942-37.5 Lr. Bassein 1/2 1050 7955

    1799-87 Bassein Upp. 1/2 312 165503

    1779-69, 1767-55 Mukta 1/2 82 38846

    Testing Results: SB-E

    2213-2201 Bassein 1/2 732 13538

    2. Banamali, Assam Shelf. Assam and Assam-Arakan Basin

    Banamali prospect is located in the Northeast of Lakwa field and North of Safrai field in Sivasagardistrict of Assam. The discovery well Banamali-4, drilled down to a depth of 4200m has establishedhydrocarbons in Barail sands. Two objects in the Oligocene-Barail sands, have been tested of whichone interval, 3990-97 m, has produced oil and gas during testing.

    Testing results

    Bean Size Flow Rate (m3/day) W/CutInterval (m) Pay

    (mm) Oil Gas %6 53 12233 65 47 9890 23997-90 BCS

    4 30 6211 5

    Th l t t f th t t i b t 1 53 S K Thi h d b t ik i i ifi t it h

    ONGC Mid T A i l f 10th Pl

  • 7/26/2019 On Gc x Midterm Appraisal

    27/34

    ONGCs Mid Term Appraisal of 10thPlan

    3. Laipling-Gaon, Assam Shelf, Assam and Assam-Arakan Basin

    Laipling-Gaon prospect is located in the North of Lakwa field in Sivasagar district of Assam and is

    about 20 KM ENE of Sivasagar (Sibsagar Town). The discovery well Laipiling-Gaon-1, drilled downto 3900m with an objective of Barail and Tipam sands, flowed oil and gas from Barail sands. Fourobjects, all in the Oligocene-Barail sands, with a cumulative thickness of 84 m have been tested asoil and gas bearing. The details are as follows:

    Testing results

    Interval (m)Pay Zone

    Bean Size(mm)

    Gas(m3/d)

    Liquidi(m3/d)

    Remarks

    3683-3660. LBS-I 6 17,434 113.6 Water cut 0.6%

    3628-3602 LBS-II 6 40,000 81 Traces of water

    3492-3473 LBS-V 6 30,000 82 -

    3450-3434 LBS-VI 6 66,500 -

    The areal extent of the structure is 6.0 Sq Km. This hydrocarbon strike is significant, as multiplestacked oil pools north of giant Lakwa-Lakhmani field have been established, opening up the entiresector for exploration.

    4. GS-KW: (Krishna-Godavari shallow offshore basin):

    GS-KW is located about 4 km south-east of Kesanapalli-West oil and gas field, off the Amalapuramcoast of Krishna-Godavari Basin, in the logistically difficult land-marine transition zone. The

    discovery well, GS-KW #1, at a water depth of 8.5m, was drilled to explore the hydrocarbon potentialof reservoirs within Matsyapuri Formation and a sand layer in the interval, 2017 - 2019 m ontesting produced 163 m3/d of oil and 17948 m3/d of gas through 8 mm bean.

    The testing result has established the extension of Matsyapuri play in the offshore area further southof Kesanapalli-West onland oil and gas field and also brings out the prospectivity of the land-marine transition zone.

    5. GS-49 (Krishna-Godavari shallow offshore basin):

    GS-49 is located at about 8.5 km south-west of Kesavadasupalem (onland) gas field, in shallowoffshore area of Krishna- Godavari basin off the Amalapuram coast. The discovery wel l, GS -49-2was drilled at a water depth of 7.0 m to explore the hydrocarbon potential of MatsyapuriFormation. On initial testing five intervals, in Matsyapuri Formation produced gas as per thefollowing details:

    ONGCs Mid Term Appraisal of 10th Plan

  • 7/26/2019 On Gc x Midterm Appraisal

    28/34

    ONGC s Mid Term Appraisal of 10 Plan

    1462.5-1460.5 6 56,175 19,82,247

    1362.0-1357.0 6 34,715 12,24,988 Traces

    The testing result of this well has established the extension of multiple stacked gas bearing poolsin Matsyapuri Formation, in onland gas field Kesavadasupalem field, to the offshore area furthersouth-west and also highlights the prospectivity of the land-marine transition zone.

    6. Chinnewala Tibba (Jaisalmer basin):

    The Chinnewala Tibba prospect is located in the western part of Jaisalmer Mari High around 12kmnorth-west of Ghotaru field in Jaisalmer Basin of Rajasthan in the district of Jaisalmer bordering

    Pakistan. Discovery well Chinnewala Tibba-1 is the first well drilled on the prospect on anindependent structural closure. The well was drilled to 2004m upto Pariwar Formation of LowerCretaceous age. Out of four objects tested, two produced hydrocarbons.

    Testing results:

    Flow Rate (m3/day)Interval (m) Formation Bean Size (mm)

    Gas Condensate1901.0-09 Pariwar Fm 8 1,30,622 3.6

    1685.5-89 Lower Goru Fm 6 69,127 2.4 (water: 10%)

    The preliminary analysis of gas produced indicates a better quality of gas accumulation having acalorific value of the order of 7091-7109 Kcal/m3 as compared to the gas in adjoining fields ofGhotaru and Kharatar, where calorific value ranges from 1250 to 3100Kcal/m3.

    Year 2003-04

    1. East Lakhibari, Assam Shelf

    Exploratory well, East Lakhibari-1 was drilled to a depth of 2547 m on a new prospect which is an updip closure, located south west of the Borholla Field and 3.5 km west of the well, Gamariguri-1 in theDhansiri Valley (Assam Shelf) to probe Kopili & Sylhet Formations and Basement,

    The Object-IV in the interval 2042.5-2044.5 m within the Sylhet Formation flowed oil @ 37.5 m3/d with

    little water through 5 mm bean.

    Additionally, gas has also been assessed based on electrolog analysis in the Kopili sand leading to theopening up of a new play in Borholla- Mekrang sector

    This has opened up a new area south west of the Borholla-Mekrang sector for further exploration.

    ONGCs Mid Term Appraisal of 10th Plan

  • 7/26/2019 On Gc x Midterm Appraisal

    29/34

    ONGC s Mid Term Appraisal of 10 Plan

    On initial testing, object-Ill in the interval 1745-1755m within Dadhar Formation flowed oil @ 32 m3/daythru 5 mm bean.

    This testing result has provided an excellent lead for exploration of Dadhar reservoir in the northern partof Broach depression.

    3. NMT. Western Offshore

    NMT-2 (North of Mid Tapti-2) is an exploratory well in Tapti-Daman block targeted to 2880m with theobjective to explore hydrocarbon potential of Daman, Mahuva and Panna Formation. The well wasdrilled down to 2880m (T.D) and terminated within Panna Formation.

    Object-l (2013-2011m ) within Mahuva Formation, on testing, flowed gas @1,53,312 m3/d andcondensate @:201 BPD (API:59.65) through 24/64" choke.

    4. Sitarampurarn, KG Basin

    Sitarampuram-2, an exploratory well in Amalapuram Block, East Godavari sub-basin, KG basin andlocated at about 2.5 km south-west of Sitarampuram-1 and 2.25 km south-east of Pasarlapudi-29, wasdrilled to a depth of 2267 m to explore hydrocarbon potential in Matsyapuri Formation and sands in

    Vadaparru Shale. The well encountered multiple hydrocarbon bearing sands in Matsyapuri Formationand Vadaparru Shale within depth range of 500-2500m.

    Out of the five objects tested, four have produced gas as per the details given below:

    OBJ INTERVAL (m) BEAN FLOW RATE OF OIL/GAS

    1 2496.5-2494.5, 2490.5-2489 6 Qg: 87,651 m3/d, Qc: 5.8 m3/d

    II 2247-2444 6 Qg: 81,121 m3/d, Qc: 18 m3/d

    IV 2037-2034 6 Qg: 73,198 m3/d, Qc: 12.11 m3/d

    V 1896-1890 6 Qg: 82,495 m3.d, Qc: 5.10 m3/d

    The testing results in this well have opened up a new fault corridor, to the south of Pasarlapudi -29 blockfor exploration of sands within Vadaparru Shale.

    Exploratory well, Sitaramapuram-3, located SW of the discovery well Sitaramapuram # 2 inAmalapuram block, KG Basin was drilled to a depth of 1653 m to test shallower sands withinMatsyapuri Formation. The testing results of the two objects are given below

    OBJ INTERVAL (m)BEAN(mm)

    FLOW RATE OF OIL/GAS

    I 1600.5-1602.5 6 Qo: 23 m3/d, Qg: 45600 m3/d

    II 499-502, 506.5-509.5 & 515-521 6 Qg: 23067 m3/d

    ONGCs Mid Term Appraisal of 10th Plan

  • 7/26/2019 On Gc x Midterm Appraisal

    30/34

    ONGC s Mid Term Appraisal of 10 Plan

    5. G-4, Krishna Godavari Deepwater.

    The well G-4 # 2 on G-4 prospect, dril led to a depth of 2675 m to explore the hydrocarbon potential

    of Pliocene sequence is located in KG offshore off the coast of Yanam within the ONGC shallow waterPEL block I-G at a water depth of 428 m. The prospect is about 38 km from the land and about 10 km tothe east of GS-29 oil find. Geologically the prospect is a strati-structural feature with multiple stacked sandbodies within a Pliocene channel / fan complex.

    In the well, G-4#2, based on the drilling and log data, 5 para-sequences having 56 m net pay havebeen interpreted to be hydrocarbon bearing in this well within Pliocene sequence. One object wastested and has produced gas as per details given below:

    Object Interval (M) Choke (Inch) Flow Rate Of Gas

    12133.0-2130.0

    2115.5-2114.532/64

    4,12,169m3/day FTHP - 2350 psi

    Traces of sand.

    The hydrocarbon bearing sands identified in the present well has given a major fillip to explorationof Pliocene and Miocene sediments to the north, north-western and eastern part of G-4 structure.

    Based on this exploration lead, the available geoscientific data in the area is under further analysis toassess the upside potential in the area. Additionally, four locations have been released in the similargeological set up to the west of G-4 structure to target the Mio-Pliocene sequence.

    6. Sonamura, A&AA-Tripura

    Sonamura prospect is located about 10 km south of Rokhia-Manikyanagar field and about 5 kmSSE of well Rokhia -35 in Assam Arakan Fold Belt (Tripura) basin. Rokrua-41, an exploratory wellwas spudded on 30.06.03 on this prospect and drilled down tc a depth of 2553 m to explore the

    hydrocarbon potential of Upper and Middle Bhuban Formations. The well has encountered multiplepays as in the Konaban-Manikyanagar fields in the north but found to be thicker in this prospect.

    The details of the testing results are given below:

    Object Interval (m) Bean Size Gasm3 d

    Condensatem3 d

    I 2034-2037 8 1. 1 6.502 1.50

    II 1886-1895 & 1898.5-

    8 1. 35.420 1.68

    I I I - IV 1766.0-1767.0 8 76.896 1.13

    1775.5-1776.5,

    1784 0-1785 5

    ONGCs Mid Term Appraisal of 10thPlan

  • 7/26/2019 On Gc x Midterm Appraisal

    31/34

    pp f

    Annexure-IOil and Natural Gas corporation ltd. Mid term appraisal of 10thplan (2002-07) percentage distribution

    of planwise outlay & expenditure

    SL.

    NO.

    ACTIVITY Tenth Plan 2002-2003 2003-04 2004-05

    Percentage w.r.t.

    Total Outlay

    Target

    (BE)

    Actual

    Expenditure

    Target

    (BE)

    Target

    (RE)

    Target

    (BE)

    A SURVEY * 5.14 8.90 11.30 8.54 8.01 8.55

    B EXPLORATORYDRILLING *

    21.85 21.80 26.58 30.87 22.88 31.34

    C DEVELOPMENTDRILLING

    24.37 23.19 26.00 16.77 17.66 18.66

    D CAPITALACQUISITION

    42.67 38.41 29.78 39.43 25.39 32.27

    E R&D7 INSTITUTES 3.96 3.07 2.37 1.77 2.07 3.07

    F JV PROJECTSDOMESTIC

    2.00 4.64 3.97 2.63 2.34 3.10

    G JV PROJECTS OVERSEAS/DIVERSIFICATION #

    21.65

    H TOTAL OUTLAY 100.00 100.00 100.00 100.00 100.00 100.00

    * Inclusive of CBM, Deepwater & NELP.# Excluding advances

    ONGCs Mid Term Appraisal of 10thPlan

  • 7/26/2019 On Gc x Midterm Appraisal

    32/34

    http://www.infraline.com- Your information Gateway to Indian Energy Sector 32

    Annexure-II

    TenthPlan

    2002-2003 2003-04 2004-05Sl.

    No.Activity

    Approved Outlay

    Target(BE)

    ActualExpenditure

    Variation w.r.t.target(BE)

    Reasonsforshortfallif any,

    Target (BE)

    Target (RE)

    Variationw.r.t.target (BE)

    Reasonsforshortfallif any,

    Target(BE)

    Likely %ExpDuring2002-05(Cols 5+9+12) as%age of(Col 3)

    Balanceavailable forthe last twoyears of the10th Plan(Col. 3minus Cols.

    Suggestedcorrective steps,if any.with

    justification

    1 3 4 5 6 7 8 9 10 I 11 12 13 14 15

    A SURVEY * 1719 14 659 22 575.06 -84 16 876.23 851.51 -24.72 855.30 132.73 -562.73

    B EXPLORATORY

    7301 97 161472 1352.55 -262.17 3168.81 2430.84 -737.97 3134.13 94.73 384 45

    C DEVELOPMENT

    8145.56 1717.62 1323.30 -394.32 172 1.04 1876.44 155.46 1866.43 62.20 3079.39

    D CAPITALPROJECTS

    14260.14 2845.45 1515.62 -1329.83 4047.66 2697.18 -1350.48 322590 52.17 6820.438

    E R&D/INSTITUT

    1323 85 227.63 12053 -107.1 181.29 220.28 38.99 307.05 4894 67599

    F JVPROJECTS

    668.29 343.66 201.90 -141.76 270.09 248.45 -21.64 310.19 113.80 -92.25

    G JVPROJECTS

    2300 00 230000 30000 -2600

    H TOTALOUTLAY

    33418.95 7408.30 5088.96 -2319.34 10265.12 10624.70 359.58 10000.00 76.94 7705.29

    * Inclusive of CBM, Deepwater & NELP# Excluding advancesNote:- RE for 2002-05 not yet prepared

    ONGCs Mid Term Appraisal of 10thPlan

  • 7/26/2019 On Gc x Midterm Appraisal

    33/34

    http://www.infraline.com- Your information Gateway to Indian Energy Sector 33

    Annexure-III

    2002-03 2003-04 2004-05S.No ACTIVITY UNIT Tenth PlanApprovedTarget ' Target

    (BE)Actual Variatio

    n w.r.t.Target

    Reasonsforshortfallifany

    BE Actual Variation w.r.t.Target

    Reasonsforshortfallif any

    BE

    Achievements in 2002-03 and 2003-04 andtargets for2004-05(BE) as%age of 10thPlan Tar ets

    Generalcommentsandsuggestions

    1 CRUDE OILPRODUCTION

    MMT 130.026 25.897 26.005 0.108 26.387 26.057 -0.330 26.174 60

    2 NATURAL GASPRODUCTION

    MMSCM 112105 23700 24244 544 23315 23584 268 22127 62

    3 NATURAL GASSALES

    MMSCM 90136 19240 19436 196 18960 19073 113 17495 62

    4 VALUE ADDED

    PRODUCTS

    KT 15156 3246 3795 549 3228 3627 400 3003 69

    5 (a) DEVELOPMENT METREAGE

    K.M. 1163.96 406.26 425.33 19.07 431.45 412.72 -18.73 413.16 107

    (b) WELLS Nos. 622 184 190 6 188 197 9 182 91

    6 (a) SEISMICSURVEYS 2D

    GLK 35286 15135 21059 5924 14690 5991 -8699 5178 91

    (b) 3D SKM 34834 6556 8639 2083 14784 19891 5107 15956 128

    7 (a) EXPLORATORYMETREAGE

    K.M. 1575.53 41881 348.19 -70.62 491.86 324.79 -16707 499.91 74

    (b) WELLS Nos 561 153 150 -3 172 124 -48 178 81

    8 (a) RESERVESACCRETIONIIH

    MMToe 538-553 121.7 128.1 6.4 134.55 104.78 -29.77 148.4 70

    ONGCs Mid Term Appraisal of 10thPlan

  • 7/26/2019 On Gc x Midterm Appraisal

    34/34

    http://www.infraline.com- Your information Gateway to Indian Energy Sector 34

    (b) UR MMToe 147.13 30.01 4073 10.72 30.9 33.67 2.77 40 78

    Note: Reasons for shortfall are given in the write-up.* Firm Programme only