document.xlsx OTD Page 1 of 1 04/19/2023 15:22:11
File: issued on September 27, 2013
On Time Deliver (OTD) metricContext: Mechanical spare parts
Month: August 2013
Shipping window (calendar days) = 15
Order line Qty % August 2013 Perfromance
1 6/15/2013 0 84 84 100% Past Due 02 7/31/2013 0 9 8 89% Past Due 0 Total Order lines due 183 8/1/2013 0 55 54 98% Past Due 04 8/3/2013 8/3/2013 53 52 98% On Time 15 8/5/2013 8/5/2013 31 31 100% On Time 1 Total order lines shipped on time 116 8/7/2013 8/7/2013 87 87 100% On Time 17 8/9/2013 8/9/2013 10 9 90% On Time 18 8/11/2013 8/11/2013 21 15 71% On Time 0 OTD 61%9 8/13/2013 8/13/2013 19 19 100% On Time 1
10 8/15/2013 8/15/2013 35 35 100% On Time 111 8/17/2013 8/17/2013 59 59 100% On Time 1 Performance calculation rules12 8/19/2013 8/19/2013 45 45 100% On Time 113 8/21/2013 8/21/2013 59 59 100% On Time 1 To be considered on time, the quantity shipped of an order line must:14 8/23/2013 8/23/2013 81 81 100% On Time 1 1) Be shipped within the shipping window: 15 8/25/2013 8/20/2013 77 77 100% On Time 1 performance =1 if the ship date is until 15 days before the due date, and % q.ty. >=90%, so 16 8/27/2013 8/10/2013 30 30 100% Not on time 0 anticipated shipping is allowed. Performance=0 if the ship date is after the due date.17 8/29/2013 8/31/2013 5 4 80% Not on time 0 2) Be at least 90% of the order quantity18 8/31/2013 8/29/2013 9 8 89% On Time 0 3) performance =0 if the ship date is later than due date
NoteOrder line 16In line 16, the ship date is 17 days (and not max 15) before the order date, so performance =0 Rationale of two days before: need to free up space in the warehouse.
Order line 18There was a rush order customer side and the same time a shortage in suppy for a long period..
Order date= Due date
(dd/mm/yy)
Ship date (dd/mm/yy)
Order q.ty
Shipped qty
On time check
Considered in Performance