52
Overpressure Scenarios and Required Relief Rates PART I

Overpressure Scenarios Overview_Final

Embed Size (px)

Citation preview

Overpressure Scenariosand

Required Relief RatesPART I

Required Data

• Procure latest PIDs

• Heat and Mass Balance Report

• Rotating Equipment Datasheet (performance curves, etc.)

• Vessel and Heat Exchanger Datasheets (drawings)

• Operating/Emergency procedures

• Review current project specific document-Relief & Blowdown Philosophy

Overpressure Scenario Identification

• Start with PIDs and PFDs

• Analyze on equipment-by-equipment basis

• Typically start at front end of process

• Identify sources of feed & its maximum pressure

• Identify all heat input sources including external fire

• No credit for favorable instrument or operator response

• Include comments to explain rationale

Industry Guidelines

• API RP 521

• API 2000

• Project Specific Guidelines

API RP 521

1. Fire

2. Closed outlets (Vapor BO or Liquid BO)

3. Failure Opening/closing of Control Valve

4. Thermal Expansion

5. Tube rupture

6. Check Valve Leakage

7. Reflux failure

8. Abnormal heat input

9. Power Failure

10. Utility failure (CW+IA+FG+Steam)

External Fire

Causes:

1.Explosion caused by the ignition of a flammable leaking gas

2. Leakage of flammable hydrocarbon inventory

Applicability Guidelines

• Equipment must be located with in a fire zone

• Some portion of the equipment must be located below the maximum fire height (API RP 521 uses 25 feet)

• In some cases, the time required to reach relief pressure may render the scenario not credible

Sizing Equation-

Q=21000*F*A^0.82 (Btu/hr)

Q=34500*F*A^0.82 (Btu/hr)

Wetted Surface Area-

• Liquid full such as Treaters: 100%

• Surge Drums, KO drums, Process vessels: NLL

• Fractionating Columns: NLL + Hold up

• Working storage (MAWP >15 psig): Max level up to 25 ft

• Spheres: Up to max horizontal diameter or 25 ft whichever is greater

Heat Of Vaporization-Latent heats will be based on the heat required to vaporize the first 10% by mass.

Q = m * Hv@ relief

• Individual exchangers often not individually protected for fire

• Often rely on downstream vessels for protection

• If downstream relief is used, check if loads should be additive (e.g., exchanger and vessel are in same fire zone)

• Shell side and tube side may be treated differently (many companies neglect tube side due to small surface area)

Shell and Tube Exchangers

Air Coolers

• Condensing versus liquid cooling services may be treated differently (see API RP 521 Section 3.15.7)

• Many air coolers are located above the maximum fire height

• API has special equations for air coolers

• Exact treatment of fire case for air coolers should be defined in the Project Guidelines

Filters, Strainers, etc.

• Equipment less than 24” OD is exempt from ASME VIII (and typically fire relief requirement)

• Many companies have additional exclusions for small filters

• Equipment fabricated from pipe may be treated differently than ASME stamped equipment

• Often rely on downstream equipment for relief – check Project Guidelines on rules to use

Inlet Control Valve Failure:-

Causes-

Instrumentation failure may occur due to

-Transmission signal failure-Process Measuring element failure

Mechanical failure may occur due to-Stem breakage-Plug jamming-Misoperation

May result in control valve opening or to move in opposite direction of its design failure position.

Determining Applicability

• Trace all inlet lines to vessel to identify inlet control devices

• Trace upstream from any control devices to determine maximum expected upstream pressure

• Upstream pressure will be normal or maximum operating pressure

• Can selected upstream pressure exceed downstream equipment design pressure?

• Consider relative vessel volumes when the upstream volume is much less than the downstream volume

Liquid

Vapor

PSV-1@ 750 psig

Wet Gas675 psig

Lean Glycol

Rich Glycol

Dry Gas

Glycol Contactor

LC

LV

HC Vapors200 psig

LC

LV

Glycol Flash Tank

Liquid

Vapor

Liquid

Vapor

PSV-1@ 750 psig

Wet Gas675 psig

Lean Glycol

Rich Glycol

Dry Gas

Glycol Contactor

LC

LV

HC Vapors200 psig

LC

LV

Glycol Flash Tank

Liquid

Vapor

Fails Open

Liquid

Vapor

PSV-1@ 750 psig

Wet Gas675 psig

Lean Glycol

Rich Glycol

Dry Gas

Glycol Contactor

LC

LV

HC Vapors200 psig

LC

LV

Glycol Flash Tank

Liquid

Vapor

Fails Open

API RP 521 Section 3.10.3

“The scenario to consider is that one inlet valve will be in a fully opened position regardless of the control valve failure position…. Therefore, the required relief capacity is the difference between the maximum expected inlet flow and the normal outlet flow adjusted for relieving conditions and considering unit turndown…”

Determining Required Relief Rate

• Use control valve manufacturer’s calculations

• Determine valve flow coefficients

• Consider partially or fully open bypass

• Calculate flow across control valve at downstream relief pressure

• Take credit for normal outflow in volumetric terms

Gas Blowby – Special Considerations

Potential for Two Phase Relief in Downstream Vessel

• Perform relative inventory check to determine how much downstream vessel will fill

• Assume downstream level control remains in normal position

Relief behavior depends on liquid level

- Below inlet nozzle all vapor relief

- Between inlet nozzle and full, perform disengagement calculation vapor or two phase

- Full liquid displacement equal to volume of incoming vapor

Check Downstream Fill Level

NormalLevel

Vapor

LC

LV

All VaporVenting

PotentialTwo Phase

Inlet fromLC Valve

Overfill – LiquidDisplacement

Gas Blowby – Special Considerations

Calculating Flow Across Level Control Valve

• Consider assuming two phase flow across valve to reduce relief requirement

Heat ExchangerTube Rupture

Causes:

- Vibration, corrosion, erosion, thermal shock, differential shell side to tube side expansion (fixed tube sheet exchanger), brittle fracture potential, tube to baffle chafing, degradation of tubes and tube sheets.

Low Pressure

Hig

h P

ress

ure

Corrosion of Tube

Low Pressure

Hig

h P

ress

ure

Corrosion of TubePinhole Leak

Low Pressure

Hig

h P

ress

ure

Corrosion of TubeTube Failure

Low Pressure

Hig

h P

ress

ure

Corrosion of TubeTube Failure

High Pressure

Lo

w P

ress

ure

Low Pressure on Tube Side

Determining Applicability

1. Determine maximum high-pressure side pressure (Phi)

- Design Pressure

- relief device set pressure

- other mechanical limitation

2. Determine low-pressure side test pressure along with associated equipment and piping (Plow)

• Compare the two pressures

- If (Phi) > (Plow) then tube rupture relief is required

Not generally applied to double pipe exchangers or other types of exchangers with schedule pipe for tubes

API 521 Section 3.18.3

The required rate is determined assuming:

• Single tube has been broken down.

• The high-pressure side fluid is assumed to flow through the broken tube.

• This is often simplified by conservatively estimating the flow rate based on two orifices/one orifice.

• If there is flash across the broken tube then two phase flow needs to consider.

• Use Crane’s equations based on maximum pressure on high pressure side and relief pressure on low side.

Additional Considerations

• Relief fluid properties are generally not the same as those upstream of the tube rupture:

- Flashing across tube rupture

- Heating due to contact with hot side fluid

- Displacement of low-pressure side fluid

• For high pressure differentials, dynamic analysis is sometimes applied

Blocked Outlet (Vapor Or Liquid)

Causes-Instrumentation System failure may occur -Transmission signal failure-Process Measuring element failure

Mechanical failure may occur due to-Stem breakage-Plug jamming-Manual valve mal operation

May result in control valve/block valve to move in closed position.

Determining Applicability For Blocked Vapor

• Identify potential mechanism resulting in blockage

• Identify sources of overpressure include compressors, high-pressure supply headers, and process heat

Liquid

Vapor

PSV-1@ 200 psig

Dry Gas

Flash Drum-Blocked Vapor

LC

LV

HC Liquid250 psig

Fails Close

CV

Determining Applicability For Blocked Liquid

• Identify potential mechanism resulting in blockage

• Identify sources of overpressure include pumps, high-pressure supply headers.

• Adequate indication and response time may render overfilling not credible

- Independent high level alarm

- 20 minutes of retention after alarm prior to overfill

• Often not considered for columns and vessels with no normal liquid inflow (suction scrubbers, etc.)

Liquid

Vapor

PSV-1@ 200 psig

Dry Gas

Flash Drum-Blocked Liquid

LC

LV

Fails Close

HC Liquid250 psig

CV

Required Relief Rates

• Centrifugal pumps and compressors

- Performance curves define flow at relief

• PD pumps

- Use design flow rate

• Reciprocating compressors

- Use reduced volumetric efficiency

• High pressure supply headers

- Normal inlet flow

Thermal Expansion

Causes:

“Hydraulic expansion … can result from several causes, the most common of which are the following:

a. An exchanger is blocked-in on the cold side with flow in the hot side.

b. Piping or vessels are blocked-in while they are filled with cold liquid and are subsequently heated by heat tracing, coils, ambient heat gain, solar radiation or fire.

Hot Side

Co

ld S

ide

90o

F

110o

F220o

F

120o

F

Heat Exchanger Thermal Expansion

Hot Side

Co

ld S

ide

90o

F

110o

F220o

F

120o

F

Cold Side InadvertentlyBlocked Prior to Hot Side

Hot Side

Co

ld S

ide

220o

F

Cold Side Temperature Increases

170o

F

q=(Cubic Expansion Coeff.*Q)/(1000*sp.gravity*specific heat capacity)

Is a relief device required?

• Guidelines on piping from, “Decide Whether to Use Thermal Relief Valves,” CEP 12/93; Bravo and Beatty

- Yes, for lines more than 80 feet long

- No, for lines with an ID less than 1.5”

- No, for lines with high operating temperatures

• API RP 521 on exchangers

- Locking open a block valve and posting signs may be adequate protection

Causes-

-Stuck Open-Broken flapper-Check valve seat leakage

May result in overpressure due to leakage through check valve if the maximum normal operating pressure of the high-pressure system is greater than the design pressure of vessels present upstream of the check valve.

Check Valve Leakage

- Leakage rate can be assumed equal to the 10% of the maximum normal forward flow (vapor or liquid).

-The reverse flow rate through a single check valve can be determined using the normal flow characteristics (i.e., forward-flow Cv) of the check valve. Leakage rate can be assumed to be 10 % forward flow Cv.

Check Valve Leakage

Overhead CondenserFailure, Reflux Failure, Abnormal Heat Input

Or Power FailureCauses-

Utility Failure, Mechanical failure of rotary equipments, Shutting down of utility compressor, Failure opening of control valve, Pumps or fail closure of control valve on supply line may result in complete loss of a utility or the partial loss of a utility, Instrumentation failure or loss of transformer/MCC/Busbar

PC

LC

Feed (F)

Heat in (Q)

Overhead (V)

Bottoms (B)

Reflux (R)

Column

Condenser

Accumulator

Reboiler

LC

PC

LC

Feed (F)

Heat in (Q)

Overhead (V)

Bottoms (B)

Reflux (R)

Column

Condenser

Accumulator

Reboiler

LC

Loss of Coolantto Condenser

PC

PC

LC

Feed (F)

Heat in (Q)

Overhead (V)

Bottoms (B)

Reflux (R)

Column

Condenser

Accumulator

Reboiler

LC

Loss ofReflux

Steam

Process

Determining Applicability

• In general, loss of cooling (from condenser or pump-around exchanger) will result in overpressure for distillation systems

• Loss of reflux can also result in flooding of condenser

In Conclusion…

• Collect information required to perform analysis

• Review relevant guidelines

• Determine all overpressure scenarios that apply to each piece of equipment

• Analyze required relief rates using standard methods

• Be conservative at first

Thank You