2
 ID Task Name Duration Start Finish 1 P14-04027 76 days Fri 5-9-14 Fri 19-12-14 2 3 Receipt of Purchase Order 0 days Fri 5-9-14 Fri 5-9-14 4 5 Engineering & Documentati on 31 days Fri 19-9-14 Fri 31-10-14 6 Initial Project Documentation 5 days Fri 19-9-14 Thu 25-9-14 7 Submittal of Documents 13 days Fri 26-9-14 Tue 14-10-14 8 Process Design Calculation 1 day Fri 26-9-14 Fri 26-9-14 9 Process General Arrangment Drawing 8 days Fri 26-9-14 Tue 7-10-14 10 Arrangement Drawings 5 days Wed 8-10-14 Tue 14-10-14 11 Submittal I nstallation & Maintenance Manual 1 day Wed 8-10-14 Wed 8-10-14 12 Approval by Client on Drawings and Process Design 10 days Wed 15-10-14 Tue 28-10-14 13 Fabrication Drawings 3 days Wed 29-10-14 Fri 31-10-14 14 15 Procur em ent & Production 35 days Fri 31-10-14 Fri 19-12-14 16 Order to Subsupplier 0 days Fri 31-10-14 Fri 31-10-14 17 Material Receipt 5 days Mon 3-11-14 Fri 7-11-14 18 Production of Internals 22 days Mon 10-11-14 Tue 9-12-14 19 Pickling and Passivating 5 days Wed 10-12-14 Tue 16-12-14 20 Final Inspection 1 day Wed 17-12-14 Wed 17-12-14 21 Packing and Marking 2 days Thu 18-12-14 Fri 19-12-14 22 Del ivery 0 days Fri 19-12-14 Fri 19-12-14 23 Ex works Delivery 0 days Fri 19-12-14 Fri 19-12-14 5-9 31-10 19-12 19-12 30 1 3 5 7 9 1113151719  2123252729 1 3 5 7 9 1113151719212325272931 2 4 6 8 1012141618202224262830 2 4 6 8 101214161820222426  '11 Sep '148 Sep '1415 Sep '1  22 Sep '129 Sep '16 Oct '1413 Oct '1 20 Oct '1 27 Oct '1 3 Nov '1410 Nov '117 Nov '124 Nov '11 Dec '148 Dec '1415 Dec '122 Dec '1  Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Progress Deadline Engineering & Producti on Schedule Project: THAI BINH – HAM RONG GAS DISTRIBUTION Client: SOUTHERN PETROLEUM JS COMPANY Page 1 Project: P14-04027 Date: Fri 26-9-14

P14-04027-EPS rev.1

Embed Size (px)

DESCRIPTION

ffff

Citation preview

  • ID Task Name Duration Start Finish

    1 P14-04027 76 days Fri 5-9-14 Fri 19-12-14

    2

    3 Receipt of Purchase Order 0 days Fri 5-9-14 Fri 5-9-14

    4

    5 Engineering & Documentation 31 days Fri 19-9-14 Fri 31-10-14

    6 Initial Project Documentation 5 days Fri 19-9-14 Thu 25-9-14

    7 Submittal of Documents 13 days Fri 26-9-14 Tue 14-10-14

    8 Process Design Calculation 1 day Fri 26-9-14 Fri 26-9-14

    9 Process General Arrangment Drawing 8 days Fri 26-9-14 Tue 7-10-14

    10 Arrangement Drawings 5 days Wed 8-10-14 Tue 14-10-14

    11 Submittal Installation & Maintenance Manual

    1 day Wed 8-10-14 Wed 8-10-14

    12 Approval by Client on Drawings and Process Design

    10 days Wed 15-10-14 Tue 28-10-14

    13 Fabrication Drawings 3 days Wed 29-10-14 Fri 31-10-14

    14

    15 Procurement & Production 35 days Fri 31-10-14 Fri 19-12-14

    16 Order to Subsupplier 0 days Fri 31-10-14 Fri 31-10-14

    17 Material Receipt 5 days Mon 3-11-14 Fri 7-11-14

    18 Production of Internals 22 days Mon 10-11-14 Tue 9-12-14

    19 Pickling and Passivating 5 days Wed 10-12-14 Tue 16-12-14

    20 Final Inspection 1 day Wed 17-12-14 Wed 17-12-14

    21 Packing and Marking 2 days Thu 18-12-14 Fri 19-12-14

    22 Delivery 0 days Fri 19-12-14 Fri 19-12-14

    23 Ex works Delivery 0 days Fri 19-12-14 Fri 19-12-14

    5-9

    31-10

    19-12

    19-12

    30 1 3 5 7 9 11131517192123252729 1 3 5 7 9 1113151719212325272931 2 4 6 8 1012141618202224262830 2 4 6 8 1012141618202224262g '11 Sep '148 Sep '1415 Sep '122 Sep '129 Sep '16 Oct '14 13 Oct '1420 Oct '1427 Oct '143 Nov '1410 Nov '117 Nov '124 Nov '11 Dec '148 Dec '1415 Dec '122 Dec '1

    Task

    Split

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    Progress

    Deadline

    Engineering & Production ScheduleProject: THAI BINH HAM RONG GAS DISTRIBUTION

    Client: SOUTHERN PETROLEUM JS COMPANY

    Page 1

    Project: P14-04027Date: Fri 26-9-14