Upload
michael-parohinog-gregas
View
217
Download
0
Embed Size (px)
Citation preview
8/2/2019 PD Measurement for HV Cable System
1/7
Proceedings of the 14th International Middle East Power Systems Conference (MEPCON10), Cairo University, Egypt, December 19-21, 2010, Paper ID 128.
112
Investigation of Partial Discharge Measurement for HV
Cable System with Variable FrequencyA.ELFaraskoury *, F.Tahoun, M. Awad O.E.Gouda
Egyptian Electricity Holding Company
Extra High Voltage Research Centre*
Faculty of Engineering,
Cairo UniversityCairo, Egypt Cairo, Egypt
a.elfaraskoury @yahoo.com [email protected]
Abstract The main principle of the insulation co-ordination and HV testing is that the test voltage simulates the
stresses which occur during the operation of the HV apparatus.
High voltage tests should provide the information for decision
whether a defect in the insulation is dangerous or not for the
later operation. That means the failure mechanism (caused by
the kind of internal cavity defect and kind of the voltage stress)
during the HV test and the later operation should follow the
same physical process. To accelerate this process, the test voltage
is usually higher than the corresponding stress during
operation.This paper is an over view covering best practices for
cable testing using variable frequency test system (20-300Hz) and
applying predictive diagnostic programs to aging cable systems.
It contains also the results of many tests carried out on XLPE
cable systems, withstand voltage test is completed with partial
discharge (PD) measurements.
Index Terms - High voltage cables - Variable frequency-
Partial discharge- Cross bonding links- High frequency current
transformers.
I. INTRODUCTION
The variable frequency test system is used to improve
cables performance by using up to date technology for On-site
withstand tests of power cable systems. The tests are mainly
performed to check the quality of the accessories and their
assembling. Damages of the cable during lying can be
detected too by using the frequency tuned resonant test
systems. The withstand test may be combined with PD
measurements check the performance of cable systems
according to IEC standards. High voltage tests should provide
the information for decision whether a defect in the insulationis dangerous or not for the later operation [1-4]. The most
important stress of a XLPE cable in service is the stress with
the operational alternating voltage. If an on-site test is
completed with a partial discharge (PD) measurement, all the
experience of the various tests can be transferred to the
various factory tests to improve the high voltage cable
performance.
II.CHARACTERISTICS OFVARIABLEFREQUENCY
TESTSYSTEMS
The tests are carried by the support of Extra High Voltage
Research Center, Egyptian Electricity Holding Company,
Cairo, Egypt. Resonance is achieved by tuning the frequency
of the converter unit to the natural frequency (f) of the
oscillating circuit formed by the reactor (L) and the cableunder test (C). The test voltage is pure sine-shaped in the case
of series resonant circuit. Its frequency depends on the load
capacitance according to the equation:
( )CLf
=
2
1 (1)
The frequency increases by decreasing the load capacitance,
the test current and the (reactive) test power are given by
L
CVI = (2)
L
CVP = 2 , with V= test voltage (3)
For the constant inductance L, the minimum resonant
frequency fmin is at the maximum load capacitance Cmax.. In
addition to the test voltage V, the maximum load capacitance
Cmax and the acceptable frequency range fmin to fmax is a
decisive design criteria for the fixed HV reactor of variable
frequency test system:
( ) max2
min2
1
CfL
=
(4)
maxminmax 2 CfVI = (5)
8/2/2019 PD Measurement for HV Cable System
2/7
113
maxmin
2
max 2 CfVP = (6)
The maximum reactive test power Pmax decreases with
decreasing fmin [1].
The IEC 60840 /2004 and IEC 62067/2006 [2, 3] recommends
a frequency range from 20 to 300 Hz, corresponding to
15min
max==
f
f (7)
The relation between maximum and minimum load is
according to equation (4)
= (8)
and the characterizes the very wide range of testable cable
lengths.
The quality factor (q) of a resonant test system is the ratio
between test powerPand required feeding power PS
q = p / ps (9)
In this work the withstand voltage tests and PD measurements
are carried out on the cable system by a variable frequency
test system (20Hz-300Hz) with 4.8 F maximum test
capacitance, which corresponds to cable length of 16.4 Km at
a cable capacitance of 0.26 F/Km at 220 kV XLPE cables
and with a cable length of 24.3 Km at a cable capacitance of
0.32 F/Km. The tests are mainly performed to check the
quality of the accessories and their assembling. Damages ofthe cable during lying can be detected too by using the
frequency tuned resonant test systems. The withstand test may
be combined with PD measurements to check the performance
of cable systems according to IEC.
The test system can also be designed in advance for use as two
independently running systems with single reactor which also
can be operated in series or parallel. Such system is available
in Extra High Voltage Research Centre Laboratory.
The on-site testing of cables has to check the insulation
condition after-laying and assembly of cable system, as well
as ageing of cables and accessories, since the performance ofthe cables and accessories was tested during the type and
routine tests in the factory. The after laying test of new cables
fills the quality assurance gap between the type and routine
tests of the cable at the manufactures site and the
commissioning of the complete cable system on-site. During
the assembly or repair of a cable system, defects of the cable
sheath and misassembled of joints and terminations can occur
[4].
The test system block diagram in parallel operation mode is
given in Figure (1).
Fig.1 Block diagram of test system in parallel operation
mode of HV reactors.
The resonant circuit must have both capacitance and
inductance when the resonance occurs, the energy absorbed at
any instant by one reactive element within the system. The
control of test system searches for the resonant frequency
automatically and the HV test is carried out at this frequency
as shown in Figure (2). The voltage applied for 1 h, either
with a voltage according the Table I, depending on practical
operational conditions.
8/2/2019 PD Measurement for HV Cable System
3/7
114
Fig.2 withstand voltage of 220 kV XLPE cable after resonant
frequency automatically.
TABLE I
STANDARDS AC VOLTAGE TESTS FOR AFTER
INSTALLATION OF EXTRUDED HV CABLES
III.TEST ARRANGEMENT
A.WITHSTAND VOLTAGE TESTS
The tests have been carried out on-site according to IEC
for HV cables according to Table I, the test cable have
different lengths to determine the faulty joints and cable
defects sample of these are defects shown in Figures (3, 4, and
5). The results of the on-site withstand testing of 66/220 kV
XLPE cables by the use frequency tuned resonant test system
(20- 300 Hz) are in use since early 2007. To date more than
16 circuits and about 113 km long can be tested by withstand
voltage test with duration of 1 hour and eight faults during test
, three joints , one termination as shown in Figure (6). Sources
of partial discharges in extruded cables include breakdowns in
voids, cavities, along an interface between an energizedelectrode and floating conductor, in an electrical tree etc. It is
known, that HV power cables failure can occur as a result of
the normally applied operational voltage or during a transient
voltage lightning or switching surges. The failure can occur if
localized electrical stresses are greater than the dielectric
materials in the area of localized stress or the bulk dielectric
material degrades to the point where it cannot withstand the
applied voltage.
Fig.3 Breakdown during withstand voltage for 66 kV cable
after 00:31:55 with 27.05 Hz
Fig.4 Breakdown during withstand voltage for 66 kV cable
after 00:47:40 with 26.94 Hz
Fig.5 Breakdown during withstand voltage for 220 kV cable
after 8 second with 42.8 Hz
8/2/2019 PD Measurement for HV Cable System
4/7
115
Fig.6 220kV cable termination failures during
withstand voltage test.
B.
PD MEASUREMENTS
Partial discharges measuring at Cross-Bonding (CB)
links by using inductive sensors are especially designed as an
inductive sensor, such installation is even possible under on-
line conditions, as the sensor is a clamp-on type high
frequency current transformer sensor (HFCT) that can be
opened and clamped around a cross-bonding link cable.
Figure (7) shows the installed HFCT inside a cross-bonding
links, also used PD gating unit MPD540 for gating purposes
in order to provide the possibility to filter certain external
background noise. Also HFCT sensor will be connected
around the core of each phase of the cable as shown in the
Figure (8) to measure both phase-to-phase and phase-to-earthPD activity in the cable and termination. The calibrated HFCT
sensor uses inductive coupling to detect PD pulses flowing
between phases and earth, converter the high frequency
current pulses from the discharges into high frequency voltage
pulses on the PD test unit. The PD sensitivity using HFCT the
central measuring frequency is recommended to lie between 2
MHz and 10 MHz in a flat zone of the frequency spectrum.
The spectrum is obtained from FFT of calibration PD pulses.
Furthermore, the measuring frequency must be set in order to
obtain the greatest possible PD signal/noise ratio. In addition,
an ''on-site performance check" must be carried for the
selected measuring frequency before the PD measurement
starts [5].
PD sensors work based on detection of high frequency current
pulses that occur during PD in the cable system. The PD
pulses occur in very short time, the width and rise time of the
pulses are in the nanosecond region. Consequently, PD pulses
with energy frequency up to hundred MHZ are generated [6].
These PD pulses with travel through the cable earth conductor
and finally can be recorded by the sensors. These types of
sensor mostly used in practice due to the advantage that these
sensor do not disrupt the normal configuration of the
accessories and cable part.
As the total cable line is energised, a PD test must be carried
out simultaneously at all accessories per phase. This
requirement leaded to the development of a new synchronous
multi channel PD measurement system. Selective PD
measurements need a potential free connection from the
accessories to storage and visualisation unit, these achievedusing optical fibres.
Fig.7 Cross-Bonding links with mounted three HFCT
for 220 kV (PD Sensors)
PD sensors work based on detection of high frequency current
pulses that occur during PD in the cable system. The PD
pulses occur in very short time, the width and rise time of the
pulses are in the nanoseconds region. Consequently, PD
pulses with energy frequency up to hundred MHz are
generated These PD pulses will travel through the cable earth
conductor and finally can be recorded by the sensors. For
unconventional PD detection, internal and external capacitive
and inductive sensor can be used. Internal inductive sensorscan be placed in the cable accessories without disturbing the
cable insulation because they placed on the top of earth screen
of cable. However, this type of sensors has to be already
installed in manufacture of the cable accessories [7].
Fig.8 Measurement set-up for PD detection using HFCT
For 66 kV
8/2/2019 PD Measurement for HV Cable System
5/7
116
Fig.9 Block diagram of an acquisition unit MPD 540
The PD signals are filtered, amplified and digitized. Having
an amplitude quantization of 14 bit and a sampling rate of 64
MS/s, the time accuracy of detection of a PD signal is at about
2ns. The quasi-integration is realized by a digital band - pass
filter. The center frequency for digital filter can be chosen in a
frequency range from DC up to 20 MHz, the bandwidth
between 9 KHz and 3 KHz, respectively. Hence an optimal
frequency band can be chosen to avoid disturbances and to
reach a high signal-to-noise ratio (SNR) even under noisy
conditions on site. Furthermore, the test voltage signal is
digitized in acquisition unit to document the test voltage
during the PD measurement as shown in figure (9) [8].
C. TEST SET-UP FOR PD MEASUREMENTS
The test set-up for on-site PD measurements should be
corona free. Therefore, corona protection spheres and
metallic pipes of suited diameter have to be used. Sufficient
clearance from HV connections to any part of the construction
should prevent PD from earthed potential free components.
IV.TEST RESULTS AND EXPERIENCE
The tests have been carried out on-site according to IEC
for 66/220 kV cables at 2 U0 for 66 kV and1.7 U0 for 220 kVhaving different lengths to determine the faulty joints and
cable defects as shown in Table I. Therefore, the XLPE cable
insulation was subjected to AC tests after assembling and at
the same time partial discharge measurements were done on
all accessories simultaneously for three-phase PD
measurement on the relevant joint box would be possible, also
the cross-bonding can be changed to straight-through
connection, to minimize cross-talk between the three phases
and to clearly distinguish between the three joint of one group.
By using a computer which already installed with PD software
connected to the spectrum PD analyser. The amplitude and
number of PD pulses as a function of phase cable performed
and this pattern will be useful to recognize the type of defect
in the cable system. However, calibration on this PD detection
method cannot be applied as in conventional PD detectionwhich described in the IEC 60270 standard [9] due to several
reasons related with high frequency behaviour of the sensors
and the type and routing of the measurement cables [10].
The results of rechecking frequency dependency on damping
and phase to phase cross-talk are shown in Figure (10), led to
choice of 1 MHz mid frequency for PD measurements to have
approximately equal sensitivities for all joints. For higher
measurement frequencies, under or over estimation of PD
level of different phases is probable. Lower measurement
frequencies would cause the disadvantages of lower cable
damping, resulting in higher external interference from both
ends of the cable link.
The results of the on-site PD measurements with the
alternating voltage of variable frequency have been performed
in conjunction with test at cross-bonding links using HFCT
sensors reported the discharge activity ranged from 7 to 500
pC. The variation of noise level which is experienced during
all measurements resulting in higher external interference
from ends of the cable, also corona effect caused by floating
parts close to high voltage at the cables termination.
Fig. 10 PD measurement relation frequency
8/2/2019 PD Measurement for HV Cable System
6/7
117
The on-site PD measuring level for cable system doesnt limit
in the standards but depends primarily on the experience of
those involved in the measurements, and the experience
learned how to the diagnostics of the PD limit. We always ask
this question from the manufacturers and owner customers,
What is the safe level for PD activity in the cable systems?
The answer to this can only be, there is no safe level for
internal PD in the cable systems, all internal discharges will
be damaging.
The PD Guide line level given below for the on-line PD
testing condition assessment of polymeric-insulated XLPE
cables, cable accessories and cable sealing ends of operation
voltages from 66 kV up to 400 kV as shown in Table II [11].
Table II
PD LEVEL FOR ON-LINE MEASUREMENTS FOR
OPERATION VOLTAGE FROM 66 kV UP TO 400 kV
Most polymer based insulation now has standards which set
by IEC guidelines (at least in the factory/type test) to have a
PD level of better than 10pC. It is difficult to see that properly
installed plant which is discharging less than this level is
going to fail by insulation failure. All other failure modes can
be sorted with maintenance programs and hence the aim
should be to run any new system discharge-free (this can be
tested at commissioning stage to provide a base-line, at
installation PD level).
The results of on-site PD measurements on this paper compare between two 220 kV XLPE cable system have 8Km length
and 14 cross bonding box as shown in Figures (11, 12), the
PD magnitudes in pico-Coulombs versus the cable length. PD
activity of up to pC can be observed at the discharging joint. It
can also noted from Figures (13, 14) that there are some PD
event originating in the termination at the remote end of the
cable, in this way, PD pattern allows a view of the PD
activity on the cable in a non-destructive.
Fig.11 PD measurements results on circuit 1
Fig.12 PD measurements results on circuit 2
8/2/2019 PD Measurement for HV Cable System
7/7
118
Fig.13 Example of PD measurement pattern some noise and
corona
Fig.14 Example of PD measurement pattern with same corona
due to floating electrode
V. CONCLUSION
The experience of testing with variable frequency, and several
other laboratory tests on aged cables show the advantage of
testing cable with frequencies in the range of 20-300Hz. on-
site withstand test of 66/220 kV XLPE cables with variable
frequency test systems combined with un-conventional PDdetection is performed by using HFCT sensors after
installation of HV cable system reduces the risk from the
service, also after repair the joint reassembling was done
exactly in the same place given good results. Nevertheless,
besides all routine and type tests before installation and the
use of prefabricated and pretested accessories with
conventional PD detection.
ACKNOWLEDGMENT
The authors would like to express his great thanks to the
staff of the Extra High Voltage Research Centre for providing
their facilities during this work.
REFERENCES
[1] S. Schierig, D. Russwurm, HV On-site Testing on Cable by AlternatingVoltage of Variable Frequency, IEEE Insulated Conductors Committee
(ICC), October 2000.
[2] IEC Publ. 60840, 3rd ed., Power Cables with Extruded Insulation andtheir Accessories for Rated Voltages above 30 kV (Um =36 kV) up to 150
kV (Um=170 kV) Test Methods and requirements, 2004-4.
[3] IEC Publ.62067 Power cables with extruded insulation and theiraccessories for rated voltages above 150 kV (Um = 170 kV) up to 500 kV
(Um =550 kV) - Test methods and requirements, 2006-1.
[4] M. Awad, F.Tahoun, A.ELFaraskoury and O.Gouda On-siteCommissioning Test and Diagnostics of 220kV XLPE Cable System,
CIGRE, B1.304, 2010.
[5] F.Garnacho, I.Trasmonte et al., On-site measurements experiences ininsulation condition for medium and high voltage cables, CIGRE, D1-
201, 2008.[6] S. M.eijer, R.A.Jongen, et al, On-site VHF Partial Discharge Detection
on Power Cable Accessories,Proceedings Jicable, 2007.
[7] Jarot Setyawan Investigation of Partial Discharge Occurrence ANDDetectability in High Voltage Power Cable Accessories TU DELFT-
NOV.2009.
[8] K.Rethmeier, P.Mohaupt, et al, New Studies on PD Measurements onMV Cable Systems at 50Hz and Sinusoidal 0.1 Hz (VLF) Test Voltage
CIRED- May 2007.
[9] IEC Publ. 60270 High voltage test techniques- partial dischargemeasurements 2000-12.
[10]S. M.eijer, R.C.Ladde, R.A.Jongen, et al, Sensitivity VerificationProcedure of VHF PD Detection Systems,Proceedings Jicable, 2007.
[11]HVPD Technical Guide for PD Levels in MV and HV Cables and Joints-Manchester, UK- May2009.