PD Measurement for HV Cable System

Embed Size (px)

Citation preview

  • 8/2/2019 PD Measurement for HV Cable System

    1/7

    Proceedings of the 14th International Middle East Power Systems Conference (MEPCON10), Cairo University, Egypt, December 19-21, 2010, Paper ID 128.

    112

    Investigation of Partial Discharge Measurement for HV

    Cable System with Variable FrequencyA.ELFaraskoury *, F.Tahoun, M. Awad O.E.Gouda

    Egyptian Electricity Holding Company

    Extra High Voltage Research Centre*

    Faculty of Engineering,

    Cairo UniversityCairo, Egypt Cairo, Egypt

    a.elfaraskoury @yahoo.com [email protected]

    Abstract The main principle of the insulation co-ordination and HV testing is that the test voltage simulates the

    stresses which occur during the operation of the HV apparatus.

    High voltage tests should provide the information for decision

    whether a defect in the insulation is dangerous or not for the

    later operation. That means the failure mechanism (caused by

    the kind of internal cavity defect and kind of the voltage stress)

    during the HV test and the later operation should follow the

    same physical process. To accelerate this process, the test voltage

    is usually higher than the corresponding stress during

    operation.This paper is an over view covering best practices for

    cable testing using variable frequency test system (20-300Hz) and

    applying predictive diagnostic programs to aging cable systems.

    It contains also the results of many tests carried out on XLPE

    cable systems, withstand voltage test is completed with partial

    discharge (PD) measurements.

    Index Terms - High voltage cables - Variable frequency-

    Partial discharge- Cross bonding links- High frequency current

    transformers.

    I. INTRODUCTION

    The variable frequency test system is used to improve

    cables performance by using up to date technology for On-site

    withstand tests of power cable systems. The tests are mainly

    performed to check the quality of the accessories and their

    assembling. Damages of the cable during lying can be

    detected too by using the frequency tuned resonant test

    systems. The withstand test may be combined with PD

    measurements check the performance of cable systems

    according to IEC standards. High voltage tests should provide

    the information for decision whether a defect in the insulationis dangerous or not for the later operation [1-4]. The most

    important stress of a XLPE cable in service is the stress with

    the operational alternating voltage. If an on-site test is

    completed with a partial discharge (PD) measurement, all the

    experience of the various tests can be transferred to the

    various factory tests to improve the high voltage cable

    performance.

    II.CHARACTERISTICS OFVARIABLEFREQUENCY

    TESTSYSTEMS

    The tests are carried by the support of Extra High Voltage

    Research Center, Egyptian Electricity Holding Company,

    Cairo, Egypt. Resonance is achieved by tuning the frequency

    of the converter unit to the natural frequency (f) of the

    oscillating circuit formed by the reactor (L) and the cableunder test (C). The test voltage is pure sine-shaped in the case

    of series resonant circuit. Its frequency depends on the load

    capacitance according to the equation:

    ( )CLf

    =

    2

    1 (1)

    The frequency increases by decreasing the load capacitance,

    the test current and the (reactive) test power are given by

    L

    CVI = (2)

    L

    CVP = 2 , with V= test voltage (3)

    For the constant inductance L, the minimum resonant

    frequency fmin is at the maximum load capacitance Cmax.. In

    addition to the test voltage V, the maximum load capacitance

    Cmax and the acceptable frequency range fmin to fmax is a

    decisive design criteria for the fixed HV reactor of variable

    frequency test system:

    ( ) max2

    min2

    1

    CfL

    =

    (4)

    maxminmax 2 CfVI = (5)

  • 8/2/2019 PD Measurement for HV Cable System

    2/7

    113

    maxmin

    2

    max 2 CfVP = (6)

    The maximum reactive test power Pmax decreases with

    decreasing fmin [1].

    The IEC 60840 /2004 and IEC 62067/2006 [2, 3] recommends

    a frequency range from 20 to 300 Hz, corresponding to

    15min

    max==

    f

    f (7)

    The relation between maximum and minimum load is

    according to equation (4)

    = (8)

    and the characterizes the very wide range of testable cable

    lengths.

    The quality factor (q) of a resonant test system is the ratio

    between test powerPand required feeding power PS

    q = p / ps (9)

    In this work the withstand voltage tests and PD measurements

    are carried out on the cable system by a variable frequency

    test system (20Hz-300Hz) with 4.8 F maximum test

    capacitance, which corresponds to cable length of 16.4 Km at

    a cable capacitance of 0.26 F/Km at 220 kV XLPE cables

    and with a cable length of 24.3 Km at a cable capacitance of

    0.32 F/Km. The tests are mainly performed to check the

    quality of the accessories and their assembling. Damages ofthe cable during lying can be detected too by using the

    frequency tuned resonant test systems. The withstand test may

    be combined with PD measurements to check the performance

    of cable systems according to IEC.

    The test system can also be designed in advance for use as two

    independently running systems with single reactor which also

    can be operated in series or parallel. Such system is available

    in Extra High Voltage Research Centre Laboratory.

    The on-site testing of cables has to check the insulation

    condition after-laying and assembly of cable system, as well

    as ageing of cables and accessories, since the performance ofthe cables and accessories was tested during the type and

    routine tests in the factory. The after laying test of new cables

    fills the quality assurance gap between the type and routine

    tests of the cable at the manufactures site and the

    commissioning of the complete cable system on-site. During

    the assembly or repair of a cable system, defects of the cable

    sheath and misassembled of joints and terminations can occur

    [4].

    The test system block diagram in parallel operation mode is

    given in Figure (1).

    Fig.1 Block diagram of test system in parallel operation

    mode of HV reactors.

    The resonant circuit must have both capacitance and

    inductance when the resonance occurs, the energy absorbed at

    any instant by one reactive element within the system. The

    control of test system searches for the resonant frequency

    automatically and the HV test is carried out at this frequency

    as shown in Figure (2). The voltage applied for 1 h, either

    with a voltage according the Table I, depending on practical

    operational conditions.

  • 8/2/2019 PD Measurement for HV Cable System

    3/7

    114

    Fig.2 withstand voltage of 220 kV XLPE cable after resonant

    frequency automatically.

    TABLE I

    STANDARDS AC VOLTAGE TESTS FOR AFTER

    INSTALLATION OF EXTRUDED HV CABLES

    III.TEST ARRANGEMENT

    A.WITHSTAND VOLTAGE TESTS

    The tests have been carried out on-site according to IEC

    for HV cables according to Table I, the test cable have

    different lengths to determine the faulty joints and cable

    defects sample of these are defects shown in Figures (3, 4, and

    5). The results of the on-site withstand testing of 66/220 kV

    XLPE cables by the use frequency tuned resonant test system

    (20- 300 Hz) are in use since early 2007. To date more than

    16 circuits and about 113 km long can be tested by withstand

    voltage test with duration of 1 hour and eight faults during test

    , three joints , one termination as shown in Figure (6). Sources

    of partial discharges in extruded cables include breakdowns in

    voids, cavities, along an interface between an energizedelectrode and floating conductor, in an electrical tree etc. It is

    known, that HV power cables failure can occur as a result of

    the normally applied operational voltage or during a transient

    voltage lightning or switching surges. The failure can occur if

    localized electrical stresses are greater than the dielectric

    materials in the area of localized stress or the bulk dielectric

    material degrades to the point where it cannot withstand the

    applied voltage.

    Fig.3 Breakdown during withstand voltage for 66 kV cable

    after 00:31:55 with 27.05 Hz

    Fig.4 Breakdown during withstand voltage for 66 kV cable

    after 00:47:40 with 26.94 Hz

    Fig.5 Breakdown during withstand voltage for 220 kV cable

    after 8 second with 42.8 Hz

  • 8/2/2019 PD Measurement for HV Cable System

    4/7

    115

    Fig.6 220kV cable termination failures during

    withstand voltage test.

    B.

    PD MEASUREMENTS

    Partial discharges measuring at Cross-Bonding (CB)

    links by using inductive sensors are especially designed as an

    inductive sensor, such installation is even possible under on-

    line conditions, as the sensor is a clamp-on type high

    frequency current transformer sensor (HFCT) that can be

    opened and clamped around a cross-bonding link cable.

    Figure (7) shows the installed HFCT inside a cross-bonding

    links, also used PD gating unit MPD540 for gating purposes

    in order to provide the possibility to filter certain external

    background noise. Also HFCT sensor will be connected

    around the core of each phase of the cable as shown in the

    Figure (8) to measure both phase-to-phase and phase-to-earthPD activity in the cable and termination. The calibrated HFCT

    sensor uses inductive coupling to detect PD pulses flowing

    between phases and earth, converter the high frequency

    current pulses from the discharges into high frequency voltage

    pulses on the PD test unit. The PD sensitivity using HFCT the

    central measuring frequency is recommended to lie between 2

    MHz and 10 MHz in a flat zone of the frequency spectrum.

    The spectrum is obtained from FFT of calibration PD pulses.

    Furthermore, the measuring frequency must be set in order to

    obtain the greatest possible PD signal/noise ratio. In addition,

    an ''on-site performance check" must be carried for the

    selected measuring frequency before the PD measurement

    starts [5].

    PD sensors work based on detection of high frequency current

    pulses that occur during PD in the cable system. The PD

    pulses occur in very short time, the width and rise time of the

    pulses are in the nanosecond region. Consequently, PD pulses

    with energy frequency up to hundred MHZ are generated [6].

    These PD pulses with travel through the cable earth conductor

    and finally can be recorded by the sensors. These types of

    sensor mostly used in practice due to the advantage that these

    sensor do not disrupt the normal configuration of the

    accessories and cable part.

    As the total cable line is energised, a PD test must be carried

    out simultaneously at all accessories per phase. This

    requirement leaded to the development of a new synchronous

    multi channel PD measurement system. Selective PD

    measurements need a potential free connection from the

    accessories to storage and visualisation unit, these achievedusing optical fibres.

    Fig.7 Cross-Bonding links with mounted three HFCT

    for 220 kV (PD Sensors)

    PD sensors work based on detection of high frequency current

    pulses that occur during PD in the cable system. The PD

    pulses occur in very short time, the width and rise time of the

    pulses are in the nanoseconds region. Consequently, PD

    pulses with energy frequency up to hundred MHz are

    generated These PD pulses will travel through the cable earth

    conductor and finally can be recorded by the sensors. For

    unconventional PD detection, internal and external capacitive

    and inductive sensor can be used. Internal inductive sensorscan be placed in the cable accessories without disturbing the

    cable insulation because they placed on the top of earth screen

    of cable. However, this type of sensors has to be already

    installed in manufacture of the cable accessories [7].

    Fig.8 Measurement set-up for PD detection using HFCT

    For 66 kV

  • 8/2/2019 PD Measurement for HV Cable System

    5/7

    116

    Fig.9 Block diagram of an acquisition unit MPD 540

    The PD signals are filtered, amplified and digitized. Having

    an amplitude quantization of 14 bit and a sampling rate of 64

    MS/s, the time accuracy of detection of a PD signal is at about

    2ns. The quasi-integration is realized by a digital band - pass

    filter. The center frequency for digital filter can be chosen in a

    frequency range from DC up to 20 MHz, the bandwidth

    between 9 KHz and 3 KHz, respectively. Hence an optimal

    frequency band can be chosen to avoid disturbances and to

    reach a high signal-to-noise ratio (SNR) even under noisy

    conditions on site. Furthermore, the test voltage signal is

    digitized in acquisition unit to document the test voltage

    during the PD measurement as shown in figure (9) [8].

    C. TEST SET-UP FOR PD MEASUREMENTS

    The test set-up for on-site PD measurements should be

    corona free. Therefore, corona protection spheres and

    metallic pipes of suited diameter have to be used. Sufficient

    clearance from HV connections to any part of the construction

    should prevent PD from earthed potential free components.

    IV.TEST RESULTS AND EXPERIENCE

    The tests have been carried out on-site according to IEC

    for 66/220 kV cables at 2 U0 for 66 kV and1.7 U0 for 220 kVhaving different lengths to determine the faulty joints and

    cable defects as shown in Table I. Therefore, the XLPE cable

    insulation was subjected to AC tests after assembling and at

    the same time partial discharge measurements were done on

    all accessories simultaneously for three-phase PD

    measurement on the relevant joint box would be possible, also

    the cross-bonding can be changed to straight-through

    connection, to minimize cross-talk between the three phases

    and to clearly distinguish between the three joint of one group.

    By using a computer which already installed with PD software

    connected to the spectrum PD analyser. The amplitude and

    number of PD pulses as a function of phase cable performed

    and this pattern will be useful to recognize the type of defect

    in the cable system. However, calibration on this PD detection

    method cannot be applied as in conventional PD detectionwhich described in the IEC 60270 standard [9] due to several

    reasons related with high frequency behaviour of the sensors

    and the type and routing of the measurement cables [10].

    The results of rechecking frequency dependency on damping

    and phase to phase cross-talk are shown in Figure (10), led to

    choice of 1 MHz mid frequency for PD measurements to have

    approximately equal sensitivities for all joints. For higher

    measurement frequencies, under or over estimation of PD

    level of different phases is probable. Lower measurement

    frequencies would cause the disadvantages of lower cable

    damping, resulting in higher external interference from both

    ends of the cable link.

    The results of the on-site PD measurements with the

    alternating voltage of variable frequency have been performed

    in conjunction with test at cross-bonding links using HFCT

    sensors reported the discharge activity ranged from 7 to 500

    pC. The variation of noise level which is experienced during

    all measurements resulting in higher external interference

    from ends of the cable, also corona effect caused by floating

    parts close to high voltage at the cables termination.

    Fig. 10 PD measurement relation frequency

  • 8/2/2019 PD Measurement for HV Cable System

    6/7

    117

    The on-site PD measuring level for cable system doesnt limit

    in the standards but depends primarily on the experience of

    those involved in the measurements, and the experience

    learned how to the diagnostics of the PD limit. We always ask

    this question from the manufacturers and owner customers,

    What is the safe level for PD activity in the cable systems?

    The answer to this can only be, there is no safe level for

    internal PD in the cable systems, all internal discharges will

    be damaging.

    The PD Guide line level given below for the on-line PD

    testing condition assessment of polymeric-insulated XLPE

    cables, cable accessories and cable sealing ends of operation

    voltages from 66 kV up to 400 kV as shown in Table II [11].

    Table II

    PD LEVEL FOR ON-LINE MEASUREMENTS FOR

    OPERATION VOLTAGE FROM 66 kV UP TO 400 kV

    Most polymer based insulation now has standards which set

    by IEC guidelines (at least in the factory/type test) to have a

    PD level of better than 10pC. It is difficult to see that properly

    installed plant which is discharging less than this level is

    going to fail by insulation failure. All other failure modes can

    be sorted with maintenance programs and hence the aim

    should be to run any new system discharge-free (this can be

    tested at commissioning stage to provide a base-line, at

    installation PD level).

    The results of on-site PD measurements on this paper compare between two 220 kV XLPE cable system have 8Km length

    and 14 cross bonding box as shown in Figures (11, 12), the

    PD magnitudes in pico-Coulombs versus the cable length. PD

    activity of up to pC can be observed at the discharging joint. It

    can also noted from Figures (13, 14) that there are some PD

    event originating in the termination at the remote end of the

    cable, in this way, PD pattern allows a view of the PD

    activity on the cable in a non-destructive.

    Fig.11 PD measurements results on circuit 1

    Fig.12 PD measurements results on circuit 2

  • 8/2/2019 PD Measurement for HV Cable System

    7/7

    118

    Fig.13 Example of PD measurement pattern some noise and

    corona

    Fig.14 Example of PD measurement pattern with same corona

    due to floating electrode

    V. CONCLUSION

    The experience of testing with variable frequency, and several

    other laboratory tests on aged cables show the advantage of

    testing cable with frequencies in the range of 20-300Hz. on-

    site withstand test of 66/220 kV XLPE cables with variable

    frequency test systems combined with un-conventional PDdetection is performed by using HFCT sensors after

    installation of HV cable system reduces the risk from the

    service, also after repair the joint reassembling was done

    exactly in the same place given good results. Nevertheless,

    besides all routine and type tests before installation and the

    use of prefabricated and pretested accessories with

    conventional PD detection.

    ACKNOWLEDGMENT

    The authors would like to express his great thanks to the

    staff of the Extra High Voltage Research Centre for providing

    their facilities during this work.

    REFERENCES

    [1] S. Schierig, D. Russwurm, HV On-site Testing on Cable by AlternatingVoltage of Variable Frequency, IEEE Insulated Conductors Committee

    (ICC), October 2000.

    [2] IEC Publ. 60840, 3rd ed., Power Cables with Extruded Insulation andtheir Accessories for Rated Voltages above 30 kV (Um =36 kV) up to 150

    kV (Um=170 kV) Test Methods and requirements, 2004-4.

    [3] IEC Publ.62067 Power cables with extruded insulation and theiraccessories for rated voltages above 150 kV (Um = 170 kV) up to 500 kV

    (Um =550 kV) - Test methods and requirements, 2006-1.

    [4] M. Awad, F.Tahoun, A.ELFaraskoury and O.Gouda On-siteCommissioning Test and Diagnostics of 220kV XLPE Cable System,

    CIGRE, B1.304, 2010.

    [5] F.Garnacho, I.Trasmonte et al., On-site measurements experiences ininsulation condition for medium and high voltage cables, CIGRE, D1-

    201, 2008.[6] S. M.eijer, R.A.Jongen, et al, On-site VHF Partial Discharge Detection

    on Power Cable Accessories,Proceedings Jicable, 2007.

    [7] Jarot Setyawan Investigation of Partial Discharge Occurrence ANDDetectability in High Voltage Power Cable Accessories TU DELFT-

    NOV.2009.

    [8] K.Rethmeier, P.Mohaupt, et al, New Studies on PD Measurements onMV Cable Systems at 50Hz and Sinusoidal 0.1 Hz (VLF) Test Voltage

    CIRED- May 2007.

    [9] IEC Publ. 60270 High voltage test techniques- partial dischargemeasurements 2000-12.

    [10]S. M.eijer, R.C.Ladde, R.A.Jongen, et al, Sensitivity VerificationProcedure of VHF PD Detection Systems,Proceedings Jicable, 2007.

    [11]HVPD Technical Guide for PD Levels in MV and HV Cables and Joints-Manchester, UK- May2009.