Upload
nuri
View
25
Download
0
Embed Size (px)
DESCRIPTION
A Case Study of Precooling with Zone Temperature Reset in a Commercial Office Building. Peng Xu, Philip Haves, James Braun, MaryAnn Piette January 23, 2004 Sponsored by the California Energy Commission and the California Institute for Energy Efficiency. Outline. Aim Test site description - PowerPoint PPT Presentation
Citation preview
Page 1
Peng Xu, Philip Haves, James Braun, MaryAnn Piette
January 23, 2004Sponsored by the California Energy Commission and
the California Institute for Energy Efficiency
A Case Study of Precooling with Zone
Temperature Reset in a Commercial Office
Building
Page 2
Outline
• Aim
• Test site description
• Precooling and demand shedding strategies
• Test results
• Utility analysis
• Conclusions and future work
Page 3
Aim
Demonstrate the potential for reducing peak-period electrical demand in a moderate-weight commercial building using building structural mass.
Page 4
Executive Summary
• Precooling and zone temperature reset can shift up to 100% of cooling power from on- to off-peak in a moderate-weight commercial buildings
• Electricity peak demand reduced by as much as 2.3 W/ft2
• Potential for cost savings when combined with Critical Peak Pricing
Page 5
Case Study - Introduction
• Started in August 2003
• Purpose - preliminary study to assess potential and need for further work– Potential demand reduction/load shifting in
moderate-weight buildings– Effectiveness of precooling and zone
temperature reset – Thermal comfort
Page 6
Test Site Description• Medium-sized government building
– Santa Rosa, CA– 80,000 ft2 (40,000 ft2 office + 40,000 ft2 courthouse)– 3 stories
• Relatively low mass building structure– 6 in. concrete floor, 4 in. concrete wall, medium
furniture density, standard commercial carpet
• High window-to-wall ratio – Floor to ceiling glazing on south and north façade
• Typical internal loads • Number of occupants
– ~100 (office side)
Page 7
South Facade
Page 8
North Facade
Page 9
Windows
• Single glazing• Tinted glass• Internal blinds
Page 10
Cooling Plant
• West wing: three 75-ton, 30-year old McQuay air-cooled chillers
• East wing: two 60-ton, 10-year old Carrier air-cooled chillers
• Constant-speed water pumps, one for each chiller
• Two stage compressors
Page 11
HVAC Secondary Systems
Five VAV air handling units (three single duct & two dual duct systems):
• Variable-speed supply and return fans
• 50-60 VAV zones • DDC control (Alerton)• No global rest of zone
temperature
Page 12
Building Operation
• 5 am - 8 am - start up
• 8 am - 5 pm - occupancy
• 2-3 hot/cold calls per month
• No major faults, some modest problems: – One undersized cooling coil– Some air balance problems– Lack of reheat coils in single-duct systems
causes temp control problems
Page 13
Precooling & Zonal Reset Strategies
66
68
70
72
74
76
78
80
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Tem
p (
oF
)
current precooling+zonal reset
extended precooling + zonal reset
unoccupied hours occupied hours unoccupied hours
floating
floating
floatingfloating
floating
zonal reset
precooling
Page 14
Monitoring
• Existing:– Whole building power meters– Chiller power meters– Weather station– HVAC performance data from EMCS
• ~500 data points• 15 minute intervals
• Added:– AHU fans power meters– Operative temperature sensors
Page 15
Operative Temperature & Comfort
Convectiveheat exchange
Radiant heat exchange
RoomRegular temperature sensor
globe
Operative temperature sensor
screen
Page 16
Peak OA Temperature vs. Peak Demand
Whole building power vs Peak OA temp
0
50
100
150
200
250
300
350
400
450
40 50 60 70 80 90 100 110
Outside air peak temperature
wh
ole
bu
ildin
g p
ow
er
(kW
)
-0.2
0.8
1.8
2.8
3.8
4.8
5.8
wh
ole
bu
ildin
g p
ow
er
(kW
/sf)
weekend/holidays
working days
CPP hours
Page 17
Classification of Weather Conditions
40
60
80
100
120
10/1 10/6 10/11 10/16 10/21 10/26 10/31
Ou
tsid
e ai
r te
mp
(oF
)
Hot daysWarm daysCool days
Page 18
Comparison of Baseline & Test Conditions
40
60
80
100
120
10/7 10/8 10/9 10/10 10/11
Warm daybaseline
Warm dayprecooling
Cool daybaseline
Cool dayprecooling
10/2310/22
Page 19
Tests Performed
Limited Precooling + zonal reset
Extended Precooling + zonal reset
Cool days 3Warm days 5 1Hot days 2
Page 20
Cool Days – Limited Precooling
Limited precooling (Cool days)
00.5
11.5
22.5
33.5
4
0 2 4 6 8 10 12 14 16 18 20 22 24
Time (hour)
Wh
ole
bu
ildin
g p
ow
er
W/s
qft
Limited precooling 1 Limited precooling 2 baseline
1 W/sf shed
Page 21
Warm Day – Limited Precooling
Limited precooling (Warm days)
0
0.5
1
1.5
2
2.5
3
3.5
4
0 2 4 6 8 10 12 14 16 18 20 22 24
Time (hour)
Wh
ole
bu
ildin
g p
ow
er
W/S
qft
baseline Limted precooling
1.4 W/sf shed
Page 22
Extended & Limited Precooling
Limited and Extended Precooling (warm days)
00.5
11.5
22.5
33.5
4
0 2 4 6 8 10 12 14 16 18 20 22 24
Time (hour)
Wh
ole
bu
ildin
g p
ow
er W
/sq
ft
baseline Limited precooling Extended precooling
1.4 W/sf shed
Page 23
Hot days – Extended Precooling
Extended Precooling (Hot days )
0
1
2
3
4
5
0 2 4 6 8 10 12 14 16 18 20 22 24
Time (hour)
Wh
ole
Bu
ildin
g p
ow
er
W/s
qft
Extended precooling 1 Extended precooling 2 baseline
2.3 W/sf shed
Page 24
Chiller Power: Limited Precooling
Chiller power shedding
0
0.2
0.4
0.6
0.8
1
1.2
1.4
0 2 4 6 8 10 12 14 16 18 20 22 24
Time (hour)
Ch
ille
r p
ow
er
(W/f
t)
precooling+DL_10_8 baseline_10_6
0.7 W/sfshed
Page 25
Results – Fan Power
response of one supply fan
0
1
2
3
4
5
6
7
8
9
10
0 2 4 6 8 10 12 14 16 18 20 22 24
Time (hour)
fan
po
wer
(kW
)
fan power
1.5 kW shed
precooling zonal reset
Page 26
Results – Zone Temp
zone air temperatures
68
69
70
71
72
73
74
75
76
4:00 8:00 12:00 16:00 20:00 0:00
zon
e t
em
pe
ratu
re (
oF
)
Precooling_Temp_operative Precooling_Temp_DDCPrecooling_Average zone temp baseline_temp
Page 27
Critical Peak Pricing (1 of 3)
• Operating time– CPP high price: 3:00pm –6pm– CPP moderate price: 12:00pm –3:00pm
• CPP days (12 days: 5/1 – 10/31)– Average of maximum outside air
temperatures in San Francisco, San Jose, Sacramento and Fresno > 98 oF
Page 28
Critical Peak Pricing (2 of 3)
• Current tariff: A-10S
• Non CPP Day Rate– On-peak credit, $0.0559/kWh, (12 pm- 6 pm)– Part-peak credit, $0.0050/kWh, (8:30 am-12 pm)
• CPP Day Rate– Moderate price, $0.24/kWh (12 pm – 3 pm)– High price, $0.82/kWh, (3 pm-6 pm)
Page 29
Critical Peak Pricing (3 of 3)
$-
$2,000.00
$4,000.00
$6,000.00
$8,000.00
$10,000.00
$12,000.00
$14,000.00
$16,000.00
$18,000.00
non-CPP dayssavings
CPP days extracost withprecooling
CPP days extracost w/o
precooling
Page 30
Market Potential – Cooling in Office Buildings
• State-wide peak demand ~50GW• Commercial cooling - largest contributor: 15%, ~7.5 GW
Cooling Electricity Breakdown*
Large office (>30,000 sf)
Small office (<30,000 sf)
RetailsCollegeRestraurant
School
Health
Hotel
Others
*CEC 1994 electricity consumption
Page 31
Conclusions• Precooling & zone temp reset can shed up to 80 –100% of
the cooling peak load, without comfort complaints, even in relatively high outside temperature conditions (90 oF)
• Benefits of nocturnal precooling are unclear• Economic savings can be made if combined with CPP or
similar DR programs Extended Precooling + DL Hot days
0
1
2
3
4
5
0 2 4 6 8 10 12 14 16 18 20 22 24
Time (hour)
Wh
ole
Bu
ild
ing
po
wer
W/s
qft
Extended precooling 1 baseline
2.3 W/sf shed