 Tugas I I Hitung EST, EFT, LST, LFT dan Slack Time pada tabel di bawah. Kegiatan Durasi (Hari) Awal Akhir A 4 - B C D B 4 A E C 4 A F D 6 A G E 10 B - F 6 C - G 6 D - Jawab: Membuat Critical Path Method (CPM) Bar Chart Jadwal Kerja

PENGELOLAAN DAN PERENCANAAN PROYEK

Embed Size (px)

Citation preview

Page 1: PENGELOLAAN DAN PERENCANAAN PROYEK

7/21/2019 PENGELOLAAN DAN PERENCANAAN PROYEK

http://slidepdf.com/reader/full/pengelolaan-dan-perencanaan-proyek 1/3

Tugas I I

Hitung EST, EFT, LST, LFT dan Slack Time pada tabel di bawah.

Kegiatan Durasi (Hari) Awal Akhir

A 4 - B C D

B 4 A E

C 4 A F

D 6 A G

E 10 B -

F 6 C -

G 6 D -

Jawab:

Membuat Critical Path Method (CPM)

Bar Chart Jadwal Kerja

Page 2: PENGELOLAAN DAN PERENCANAAN PROYEK

7/21/2019 PENGELOLAAN DAN PERENCANAAN PROYEK

http://slidepdf.com/reader/full/pengelolaan-dan-perencanaan-proyek 2/3

Perhitungan EST, EFT, LST, LFT dan Slack Time

  Kegiatan A

 

Kegiatan B

  Kegiatan C

EST = EFT –  durasi

= 4 –  4

= 0

EFT = EST + durasi

= 0 + 4

= 4

Slack Time = LFT –  EFT

= 4 –  4

= 0

LST = LFT –  durasi

= 4 –  4

= 0

LFT = LST + durasi

= 0 + 4

= 4

EST = EFT –  durasi

= 8 –  4

= 4

EFT = EST + durasi

= 4 + 4

= 8

Slack Time = LFT –  EFT

= 8 –  8

= 0

LST = LFT –  durasi

= 8 –  4

= 4

LFT = LST + durasi

= 4 + 4

EST = EFT –  durasi

= 8 –  4

= 4

EFT = EST + durasi= 4 + 4

= 8

Slack Time = LFT –  EFT

= 12  –  8

= 4

LST = LFT –  durasi

= 12 –  4

= 8

LFT = LST + durasi

= 8 + 4

Page 3: PENGELOLAAN DAN PERENCANAAN PROYEK

7/21/2019 PENGELOLAAN DAN PERENCANAAN PROYEK

http://slidepdf.com/reader/full/pengelolaan-dan-perencanaan-proyek 3/3

  Kegiatan D

  Kegiatan E

  Kegiatan F

  Kegiatan G

EST = EFT –  durasi

= 10  –  6

= 4

EFT = EST + durasi

= 4 + 6

= 10

Slack Time = LFT  –  EFT

= 12  –  10

= 2

LST = LFT –  durasi

= 12  –  6

= 6

LFT = LST + durasi

= 6 + 6

EST = EFT –  durasi

= 18 –  10

= 8

EFT = EST + durasi

= 8 + 10

= 18

Slack Time = LFT –  EFT

= 18  –  18

= 0

LST = LFT – 

 durasi

= 18 –  10

= 8

LFT = LST + durasi

= 8 + 10

EST = EFT –  durasi

= 14 –  6

= 8

EFT = EST + durasi

= 8 + 6

= 14

Slack Time = LFT –  EFT

= 18  –  14

= 4

LST = LFT –  durasi

= 18 –  6

= 12

LFT = LST + durasi

= 12 + 6

LST = LFT –  durasi

= 18 –  6

= 12

LFT = LST + durasi

EST = EFT –  durasi

= 16  –  6

= 10

EFT = EST + durasi

= 10 + 6

= 16

Slack Time = LFT  –  EFT

= 18  –  16

= 2