PERANCANGAN SEQUENCE BACKFILL DI LOKASI PENAMBANGAN dengan tema “Perancangan Sequence Backfill Di

  • View
    0

  • Download
    0

Embed Size (px)

Text of PERANCANGAN SEQUENCE BACKFILL DI LOKASI PENAMBANGAN dengan tema “Perancangan Sequence Backfill...

  • PERANCANGAN SEQUENCE BACKFILL DI LOKASI

    PENAMBANGAN BUKIT 7A BARU

    Studi Kasus PT. ANTAM, Tbk UBP Bauksit Tayan, Kabupaten Sanggau,

    Kalimantan Barat

    SKRIPSI

    Diajukan sebagai persyaratan memperoleh gelar Sarjana Teknik

    Pertambangan (S.T)

    Oleh :

    AHMAD FATHURROHMAN

    NIM: 11160980000048

    PROGAM STUDI TEKNIK PERTAMBANGAN

    FAKULTAS SAINS DAN TEKNOLOGI

    UNIVERSITAS ISLAM NEGERI SYARIF HIDAYATULLAH

    JAKARTA

    1440 H / 2019

  • i

    PERANCANGAN SEQUENCE BACKFILL DI LOKASI

    PENAMBANGAN BUKIT 7A BARU

    Studi Kasus PT. ANTAM, Tbk UBP Bauksit Tayan, Kabupaten Sanggau,

    Kalimantan Barat

    SKRIPSI

    Diajukan sebagai persyaratan memperoleh gelar Sarjana Teknik

    Pertambangan (S.T)

    Oleh :

    AHMAD FATHURROHMAN

    NIM: 11160980000048

    PROGAM STUDI TEKNIK PERTAMBANGAN

    FAKULTAS SAINS DAN TEKNOLOGI

    UNIVERSITAS ISLAM NEGERI SYARIF HIDAYATULLAH

    JAKARTA

    1440 H / 2019

  • ii

  • iii

  • vi

    KATA PENGANTAR

    Puji syukur penulis panjatkan kehadirat Tuhan Yang Maha Esa atas segala

    rahmat dan hidayah-Nya sehingga penulis dapat menyelesaikan laporan Tugas Akhir

    dengan tema “Perancangan Sequence Backfill Di Lokasi Penambangan Bukit 7A Baru

    Studi Kasus PT. ANTAM Tbk UBP Bauksit, Tayan, Kabupaten Sanggau, Provinsi

    Kalimantan Barat”. Penulisan Laporan Tugas akhir ini merupakan syarat untuk

    memenuhi mata kuliah pada Program Studi Teknik Pertambangan, Universitas Islam

    Negeri Syarif Hidayatullah, Jakarta.

    Dalam penyusunan laporan tugas akhir, banyak pihak yang telah membantu,

    memberikan dukungan dan mempermudah kegiatan penyusunan laporan ini, baik

    secara langsung maupun tidak langsung. Dalam kesempatan ini, penulis mengucapkan

    terima kasih kepada :

    1. Bapak A. Silvan Erusani, S.T., M.Sc selaku Dosen Pembimbing I.

    2. Bapak Ahmad Fauzan Haryono, S.T., M.T. selaku Dosen Pembimbing II

    3. Bapak Ir. Agus Sulaiman Djamil, M.Sc. selaku Dosen Penguji I.

    4. Ibu Nurmaya Arofah, M. Eng. selaku Dosen Penguji II.

    5. Bapak Dr. Ambran Hartono, M.Sc, Ketua Jurusan Teknik Pertambangan UIN

    Syarif Hidayatullah Jakarta.

    6. Bapak Hendra Bayu Suseno, M.Kom. selaku Sekretaris Jurusan Teknik

    Pertambangan UIN Syarif Hidayatullah Jakarta.

    7. Ibu Prof. Dr. Lily Surraya Eka Putri, M.Env.Stud. selaku Dekan Fakultas Sains dan

    Teknologi UIN Syarif Hidayatullah Jakarta.

    8. Bapak Taufik Kadar Nurdaya, ST. (Engineer Mine Production Departement)

    selaku pembimbing lapangan yang telah banyak memberikan masukan, dan arahan

    pada penulis dalam melakukan penulisan laporan tugas akhir ini.

    9. Kedua orang tua tercinta yang telah senantiasa selalu mendoakan, memberikan

  • vii

  • viii

    ABSTRAK

    Penimbunan kembali tanah penutup lahan bukaan bekas tambang harus

    dilakukan secara matang dan terencana, perencanaan penimbunan mencakup

    tahapan – tahapan yang sequential dan terukur jumlah volume dan waktunya. Hal

    ini dilakukan agar kegiatan penimbunan dapat meminimalisir dampak terhadap

    lingkungan serta menyesuaikan pada Peraturan Pemerintah (PP) No. 78 Tahun 2010

    tentang Reklamasi dan Pascatambang. Perencanaan sequence backfill perlu

    mengetahui luas area penimbunan, elevasi awal sebelum penimbunan, kinerja alat

    yang digunakan untuk penimbunan, volume material penimbunan yang tersedia

    serta jam bekerja perusahaan yang tersedia. Pengolahan data dilakukan dengan

    menggunakan software Surpac dan AutoCAD. Hasil dari analisis yang dilakukan

    maka produktivitas alat penimbunan berupa 2 excavator adalah 440,77 LCM/Jam

    dan dibuat 3 sequence penimbunan backfill yang total volume penimbunannya

    adalah 143.807 LCM (Loose Cubic Meters) dan total volume topsoil 8.658,16

    LCM. Masing – masing sequence terdiri dari, besar volume sequence I 52.418

    LCM, besar volume sequence II 52.375 LCM, dan besar volume sequence III

    39.014 LCM. Dengan jumlah waktu penimbunan 19,15 hari.

    Kata kunci : backfill, perencanaan sequence, volume backfill

  • ix

    ABSTRACT

    Backfilling on mine-out area must be carried out carefully and well planned,

    backfill planning includes sequential and measurable stages of volume and time.

    This is done so that landfill activities can minimize the impact on the environment

    and based on government regulation No.78 of 2010 concerning on reclamation and

    post-mining. Backfill sequence planning requires landfill area, initial elevation

    before backfill, the performance of the equipment used for backfill, the volume of

    backfill material available and the company's available working hours. Data

    processing is performed using Surpac and AutoCAD software. As a result, the

    productivity of backfill equipment in the form of 2 excavators is 440,77 LCM/Hour

    and backfilling has 3 sequences with the whole Overburden volume is 143.807

    LCM and topsoil volume is 8.658,16 LCM. Each sequence consist of different

    volume, sequence I volume is 52.418 LCM, sequence II volume is 52.375 LCM

    and sequence III volume is 39.014 LCM. These all sequences need 19,15 days.

    Keyword : backfill, sequence planning, backfill volume

  • x

    DAFTAR ISI

    LEMBAR PERSETUJUAN ................................................................................. ii

    LEMBAR PENGESAHAN ................................................................................. iii

    KATA PENGANTAR .......................................................................................... vi

    ABSTRACT .......................................................................................................... ix

    DAFTAR ISI .......................................................................................................... x

    DAFTAR GAMBAR .......................................................................................... xiii

    DAFTAR TABEL................................................................................................ xv

    DAFTAR LAMPIRAN ...................................................................................... xvi

    DAFTAR ISTILAH DAN AKRONIM............................................................ xvii

    BAB I ...................................................................................................................... 1

    PENDAHULUAN .................................................................................................. 1

    1.1 Latar Belakang ......................................................................................................... 1

    1.2 Identifikasi Masalah ............................................................................................... 3

    1.3 Batasan Masalah..................................................................................................... 3

    1.4 Rumusan Masalah ................................................................................................... 4

    1.5 Tujuan Penelitian .................................................................................................... 4

    1.6 Manfaat Penelitian ................................................................................................ 4

    TINJAUAN PUSTAKA ........................................................................................ 6

    2.1 Kajian Teoritik .................................................................................................... 6

    2.2 Metode Open Cast / Open Mine / Open Cut ........................................................ 10

    2.2.1 Dasar Perhitungan Volume Tanah Pucuk Pada Timbunan .............................. 11

    2.3 Perencanaan Reklamasi ......................................................................................... 18

    2.4 Backfill ................................................................................................................... 18

    2.5 Wilayah Penambangan ...................................................................................... 19

  • xi

    2.6 Kondisi Geologi Daerah Penelitian .................................................................. 20

    2.7 Kegiatan Penambangan di PT Antam Tbk UBPB Tayan.................................. 25

    2.8. Kegiatan Penimbunan atau Backfilling di PT Antam Tbk UBPB Tayan .............. 27

    2.9 Revegetasi ............................................................................................................ 29

    2.10 Hasil Penelitian Yang Relevan ............................................................................. 30

    2.11 Kerangka Berpikir ................................................................................................ 31

    BAB III ................................................................................................................. 33

    METODOLOGI PENELITIAN ........................................................................ 33

    3.1 Waktu Penelitian ..........................