Perseus 1B North Rankin Drilling Rig Reinstatement Perseus 1B North Rankin Drilling Rig Reinstatement Title: Perseus 1B Drillsafe Presentation Author: Doug Hodson Drims: 2275628 Perseus 1B North Rankin Perseus 1B North Rankin Drilling Rig Reinstatement Drilling Rig Reinstatement Presentation Presentation Doug Hodson 8 th December 2005

Perseus 1B North Rankin Drilling Rig Reinstatement ... · 2. API RP8B Inspections • Travelling Block ... Perseus 1B North Rankin Drilling Rig Reinstatement Title: Perseus 1B Drillsafe

  • Upload
    vankhue

  • View
    221

  • Download
    4

Embed Size (px)

Citation preview

Perseus 1B North Rankin Drilling Rig ReinstatementPerseus 1B North Rankin Drilling Rig ReinstatementTitle: Perseus 1B Drillsafe

Presentation

Author: Doug Hodson

Drims: 2275628

Perseus 1B North Rankin Perseus 1B North Rankin Drilling Rig Reinstatement Drilling Rig Reinstatement

PresentationPresentation

Doug Hodson8th December 2005

Perseus 1B North Rankin Drilling Rig ReinstatementPerseus 1B North Rankin Drilling Rig ReinstatementTitle: Perseus 1B Drillsafe

Presentation

Author: Doug Hodson

Drims: 2275628

Site Integration Test

Continue Routine Maintnce Activities

Rig Up All Rental & New Equipment

Maintenance To Return Facility Functionality

Transfer & Rig Up Equipment Shared

With GWA

Crew Competence And Inductions

Sap Implementation

Rig Down & Preserve NRA

Risk Mitigation Maintenance

Star Racker Efficiency

Improvements

RIG MOBILISATIONRIG MOBILISATION

HSE Improvements

Perseus 1B North Rankin Drilling Rig ReinstatementPerseus 1B North Rankin Drilling Rig ReinstatementTitle: Perseus 1B Drillsafe

Presentation

Author: Doug Hodson

Drims: 2275628

Perseus 1b Rig Mob ScopePerseus 1b Rig Mob ScopeNew Equipment: HSE/Performance1. Cuttings Driers2. Stab-master3. Dedicated Man-Riding Winches4. Upgrade Pipe Racker

Functionality Maintenance• Mud tank valve actuators ~1500 hrs work• Star Racker - replacement of umbilicals

and upper arm• API RP8B inspections• Tugger maintenance• Overhaul of Drilling Air Compressors

Risk Mitigation Maintenance• Rebuild Draw works• Rebuild Mud Pump Power and Fluid End• Replaced bulk valves• Overhaul Generators• Cement System Major Service

Transferred Equipment1. Top Drive2. Shale Shakers3. BOP4. Iron Roughneck5. All Transferred Equipment

Operational/Hot Stacked Equipment1. Major Services:• Drawworks• Drilling Generators• Skidding System• Mud Pumps

2. API RP8B Inspections• Travelling Block• Crown Block• Deadline Anchor• All load path equipment

Perseus 1B North Rankin Drilling Rig ReinstatementPerseus 1B North Rankin Drilling Rig ReinstatementTitle: Perseus 1B Drillsafe

Presentation

Author: Doug Hodson

Drims: 2275628

North Rankin Life Extension Project North Rankin Life Extension Project Drilling Rig Scope Drilling Rig Scope

• Derrick Wind-wall Crane Clash Modifications • Cuttings Caisson Renewal of Corroded System • Shale Shaker Auto Divert System • Upgrade of V-ICIS [Drillers’ Controls] • Mud Tank Corrosion Repairs• Choke Control Panel Replacement • Drilling MCC Remedial Works• Harmonic Filter Installation [Power Factor Correction] • New Air Drier• Miscellaneous Simple Technical Changes (STC)

Perseus 1B North Rankin Drilling Rig ReinstatementPerseus 1B North Rankin Drilling Rig ReinstatementTitle: Perseus 1B Drillsafe

Presentation

Author: Doug Hodson

Drims: 2275628

Perseus 1B North Rankin Drilling Rig ReinstatementPerseus 1B North Rankin Drilling Rig ReinstatementTitle: Perseus 1B Drillsafe

Presentation

Author: Doug Hodson

Drims: 2275628

Perseus 1B North Rankin Drilling Rig ReinstatementPerseus 1B North Rankin Drilling Rig ReinstatementTitle: Perseus 1B Drillsafe

Presentation

Author: Doug Hodson

Drims: 2275628

Perseus 1B North Rankin Drilling Rig ReinstatementPerseus 1B North Rankin Drilling Rig ReinstatementTitle: Perseus 1B Drillsafe

Presentation

Author: Doug Hodson

Drims: 2275628

.

0%

20%

40%

60%

80%

100%14

-Feb

-05

28-F

eb-0

5

14-M

ar-0

5

28-M

ar-0

5

11-A

pr-0

5

25-A

pr-0

5

9M

AY

200

5

23-M

ay-0

5

6JU

N 2

005

20-J

un-0

5

4JU

L 20

05

18-J

ul-0

5

1A

UG

200

5

15-A

ug-0

5

29-A

ug-0

5

12-S

ep-0

5

26-S

ep-0

5

10-O

ct-0

5

24-O

ct-0

5

7N

OV

200

5

21-N

ov-0

5

5D

EC

200

5

19-D

ec-0

5

2JA

N 2

006

16-J

an-0

6

30-J

an-0

6

13-F

eb-0

6

27-F

eb-0

6

13-M

ar-0

6

27-M

ar-0

6

10-A

pr-0

6

24-A

pr-0

6

Pro

gres

s %

Com

plet

e

0

1000

2000

3000

4000

5000

6000

7000

Hours

Forecast HrsActual HrsEarnedForecastActual Target Rebaseline EarnedRebaseline ActualRebaseline Target

821573 P1B Rig MobilisationOverall SCurve and Histogram

Planned: 78.5%Earned: 67.5%Actual: 75.7 %

Based on Hours (Does Not Include Procurement)

Rebaseline

Feb-

05

Mar

-05

Apr

-05

May

-05

Jun-

05

Jul-0

5

Aug

-05

Sep

-05

Oct

-05

Nov

-05

Dec

-05

Jan-

06

Feb-

06

Mar

-06

Apr

-06

0%

20%

40%

60%

80%

100%

120%

SCurve Based on Hours (Does Not Include Procurement)

Hoisting Equipment

PERSEUS 1B RIG MOBILISATIONDESIGN S-CURVE & BARCHART

Well Control Equipment

Cement System

Low Pressure Mud

Skidding

150 kg Manriding Tuggers

Utilities

Materials Handling

` Rotary Equipment

Structures

Site Integration Test

High Pressure Mud

Mud Treatment

Pipe Handling

Planned: 92.3%Earned: 85.8% Actual: 92.4%

Stabmaster

Cutting Drier

CLOSE-OUT

Design progress has maintained increased growth in actuals and earned hours, with additional scope/budget requirements, percentages are only approx. 7% behind the target plan.

Schedule expected to align with targeted progress over the next fortnight, and actuals to exceed the planned budget.

Forecast target completion 24th November for all Worleyparsons, Perth TW design works.

Based on Hours (Does Not Include Procurement)

0%

20%

40%

60%

80%

100%

14-F

eb-0

5

28-F

eb-0

5

14-M

ar-0

5

28-M

ar-0

5

11-A

pr-0

5

25-A

pr-0

5

9M

AY

200

5

23-M

ay-0

5

6JU

N 2

005

20-J

un-0

5

4JU

L 20

05

18-J

ul-0

5

1A

UG

200

5

15-A

ug-0

5

29-A

ug-0

5

12-S

ep-0

5

26-S

ep-0

5

10-O

ct-0

5

24-O

ct-0

5

7N

OV

200

5

21-N

ov-0

5

5D

EC

200

5

19-D

ec-0

5

2JA

N 2

006

16-J

an-0

6

30-J

an-0

6

13-F

eb-0

6

27-F

eb-0

6

13-M

ar-0

6

27-M

ar-0

6

10-A

pr-0

6

24-A

pr-0

6

Pro

gre

ss %

Co

mp

lete

0

20

40

60

80

100

No

. of P

eop

le

Actual HoursForecast: TW/Other SupportForecast: Drill/HS CrewRebaseline ActualRebaseline EarnedRebaseline TargetTarget Actual ForecastEarned

821573 P1B Rig MobilisationOffshore SCurve and Histogram

Availability: AOA (includes hot stacking) 9 people to end May 13 people to end June 17 people to shutdown 35 people post-shutdownTW - As Required (10 Currently)

Planned: 73.3%Earned: 67.4% Actual: 75.1%

NRA Shutdown

Assist Well Services

Competency Based Training / Site Integration Test

Rig Mob S CurvesRig Mob S Curves

Perseus 1B North Rankin Drilling Rig ReinstatementPerseus 1B North Rankin Drilling Rig ReinstatementTitle: Perseus 1B Drillsafe

Presentation

Author: Doug Hodson

Drims: 2275628

Perseus 1B North Rankin Drilling Rig ReinstatementPerseus 1B North Rankin Drilling Rig ReinstatementTitle: Perseus 1B Drillsafe

Presentation

Author: Doug Hodson

Drims: 2275628

Star Racker FingersStar Racker Fingers

Perseus 1B North Rankin Drilling Rig ReinstatementPerseus 1B North Rankin Drilling Rig ReinstatementTitle: Perseus 1B Drillsafe

Presentation

Author: Doug Hodson

Drims: 2275628

Star Star RackerRacker

Perseus 1B North Rankin Drilling Rig ReinstatementPerseus 1B North Rankin Drilling Rig ReinstatementTitle: Perseus 1B Drillsafe

Presentation

Author: Doug Hodson

Drims: 2275628

Drillers ScreenDrillers Screen

Perseus 1B North Rankin Drilling Rig ReinstatementPerseus 1B North Rankin Drilling Rig ReinstatementTitle: Perseus 1B Drillsafe

Presentation

Author: Doug Hodson

Drims: 2275628

Cuttings Dryer SkidCuttings Dryer Skid

Perseus 1B North Rankin Drilling Rig ReinstatementPerseus 1B North Rankin Drilling Rig ReinstatementTitle: Perseus 1B Drillsafe

Presentation

Author: Doug Hodson

Drims: 2275628

Mud Tank HabitatsMud Tank Habitats

Perseus 1B North Rankin Drilling Rig ReinstatementPerseus 1B North Rankin Drilling Rig ReinstatementTitle: Perseus 1B Drillsafe

Presentation

Author: Doug Hodson

Drims: 2275628

Valve Actuators Under Mud TanksValve Actuators Under Mud Tanks

Perseus 1B North Rankin Drilling Rig ReinstatementPerseus 1B North Rankin Drilling Rig ReinstatementTitle: Perseus 1B Drillsafe

Presentation

Author: Doug Hodson

Drims: 2275628

DerrickDerrick

Perseus 1B North Rankin Drilling Rig ReinstatementPerseus 1B North Rankin Drilling Rig ReinstatementTitle: Perseus 1B Drillsafe

Presentation

Author: Doug Hodson

Drims: 2275628

Perseus 1B Rig Mob Main ChallengesPerseus 1B Rig Mob Main Challenges• New crews, access to crews• Access to engineering support• Reinstating rig contractor• Project implementation management• Productivity early on• Procurement turnaround• Brownfield “growth”• Critical path in derrick• Platform requirements:

– Hot work– Concurrent activity– Inductions– Travel booking system

Perseus 1B North Rankin Drilling Rig ReinstatementPerseus 1B North Rankin Drilling Rig ReinstatementTitle: Perseus 1B Drillsafe

Presentation

Author: Doug Hodson

Drims: 2275628

SuccessesSuccesses

• HSE and Teamwork Offshore• Early start strategy• Focus on critical path• Engaging workforce in critical path• Worked estimate in detail at the outset• Engaging stakeholders

Perseus 1B North Rankin Drilling Rig ReinstatementPerseus 1B North Rankin Drilling Rig ReinstatementTitle: Perseus 1B Drillsafe

Presentation

Author: Doug Hodson

Drims: 2275628

Project Project LearningsLearnings

• Cost Engineers more versatile and project focussed than accountants

• Planners spend considerable time manipulating Primavera and need to be focussed on critical path

• Need to understand estimating jargon: “Norms, Productivity, Non-prods, Growth, Contingency, Probabilistic”

• Project quality processes need to be focussed on project objectives

• Project Execution Plan: Very good document• Toll-gate reviews have to be managed carefully

Perseus 1B North Rankin Drilling Rig ReinstatementPerseus 1B North Rankin Drilling Rig ReinstatementTitle: Perseus 1B Drillsafe

Presentation

Author: Doug Hodson

Drims: 2275628

Concept Concept LearningsLearnings

• Platform drilling rig concepts• Incentivising rig labour contracts