Perseus 1B North Rankin Drilling Rig ReinstatementPerseus 1B North Rankin Drilling Rig ReinstatementTitle: Perseus 1B Drillsafe
Presentation
Author: Doug Hodson
Drims: 2275628
Perseus 1B North Rankin Perseus 1B North Rankin Drilling Rig Reinstatement Drilling Rig Reinstatement
PresentationPresentation
Doug Hodson8th December 2005
Perseus 1B North Rankin Drilling Rig ReinstatementPerseus 1B North Rankin Drilling Rig ReinstatementTitle: Perseus 1B Drillsafe
Presentation
Author: Doug Hodson
Drims: 2275628
Site Integration Test
Continue Routine Maintnce Activities
Rig Up All Rental & New Equipment
Maintenance To Return Facility Functionality
Transfer & Rig Up Equipment Shared
With GWA
Crew Competence And Inductions
Sap Implementation
Rig Down & Preserve NRA
Risk Mitigation Maintenance
Star Racker Efficiency
Improvements
RIG MOBILISATIONRIG MOBILISATION
HSE Improvements
Perseus 1B North Rankin Drilling Rig ReinstatementPerseus 1B North Rankin Drilling Rig ReinstatementTitle: Perseus 1B Drillsafe
Presentation
Author: Doug Hodson
Drims: 2275628
Perseus 1b Rig Mob ScopePerseus 1b Rig Mob ScopeNew Equipment: HSE/Performance1. Cuttings Driers2. Stab-master3. Dedicated Man-Riding Winches4. Upgrade Pipe Racker
Functionality Maintenance• Mud tank valve actuators ~1500 hrs work• Star Racker - replacement of umbilicals
and upper arm• API RP8B inspections• Tugger maintenance• Overhaul of Drilling Air Compressors
Risk Mitigation Maintenance• Rebuild Draw works• Rebuild Mud Pump Power and Fluid End• Replaced bulk valves• Overhaul Generators• Cement System Major Service
Transferred Equipment1. Top Drive2. Shale Shakers3. BOP4. Iron Roughneck5. All Transferred Equipment
Operational/Hot Stacked Equipment1. Major Services:• Drawworks• Drilling Generators• Skidding System• Mud Pumps
2. API RP8B Inspections• Travelling Block• Crown Block• Deadline Anchor• All load path equipment
Perseus 1B North Rankin Drilling Rig ReinstatementPerseus 1B North Rankin Drilling Rig ReinstatementTitle: Perseus 1B Drillsafe
Presentation
Author: Doug Hodson
Drims: 2275628
North Rankin Life Extension Project North Rankin Life Extension Project Drilling Rig Scope Drilling Rig Scope
• Derrick Wind-wall Crane Clash Modifications • Cuttings Caisson Renewal of Corroded System • Shale Shaker Auto Divert System • Upgrade of V-ICIS [Drillers’ Controls] • Mud Tank Corrosion Repairs• Choke Control Panel Replacement • Drilling MCC Remedial Works• Harmonic Filter Installation [Power Factor Correction] • New Air Drier• Miscellaneous Simple Technical Changes (STC)
Perseus 1B North Rankin Drilling Rig ReinstatementPerseus 1B North Rankin Drilling Rig ReinstatementTitle: Perseus 1B Drillsafe
Presentation
Author: Doug Hodson
Drims: 2275628
Perseus 1B North Rankin Drilling Rig ReinstatementPerseus 1B North Rankin Drilling Rig ReinstatementTitle: Perseus 1B Drillsafe
Presentation
Author: Doug Hodson
Drims: 2275628
Perseus 1B North Rankin Drilling Rig ReinstatementPerseus 1B North Rankin Drilling Rig ReinstatementTitle: Perseus 1B Drillsafe
Presentation
Author: Doug Hodson
Drims: 2275628
Perseus 1B North Rankin Drilling Rig ReinstatementPerseus 1B North Rankin Drilling Rig ReinstatementTitle: Perseus 1B Drillsafe
Presentation
Author: Doug Hodson
Drims: 2275628
.
0%
20%
40%
60%
80%
100%14
-Feb
-05
28-F
eb-0
5
14-M
ar-0
5
28-M
ar-0
5
11-A
pr-0
5
25-A
pr-0
5
9M
AY
200
5
23-M
ay-0
5
6JU
N 2
005
20-J
un-0
5
4JU
L 20
05
18-J
ul-0
5
1A
UG
200
5
15-A
ug-0
5
29-A
ug-0
5
12-S
ep-0
5
26-S
ep-0
5
10-O
ct-0
5
24-O
ct-0
5
7N
OV
200
5
21-N
ov-0
5
5D
EC
200
5
19-D
ec-0
5
2JA
N 2
006
16-J
an-0
6
30-J
an-0
6
13-F
eb-0
6
27-F
eb-0
6
13-M
ar-0
6
27-M
ar-0
6
10-A
pr-0
6
24-A
pr-0
6
Pro
gres
s %
Com
plet
e
0
1000
2000
3000
4000
5000
6000
7000
Hours
Forecast HrsActual HrsEarnedForecastActual Target Rebaseline EarnedRebaseline ActualRebaseline Target
821573 P1B Rig MobilisationOverall SCurve and Histogram
Planned: 78.5%Earned: 67.5%Actual: 75.7 %
Based on Hours (Does Not Include Procurement)
Rebaseline
Feb-
05
Mar
-05
Apr
-05
May
-05
Jun-
05
Jul-0
5
Aug
-05
Sep
-05
Oct
-05
Nov
-05
Dec
-05
Jan-
06
Feb-
06
Mar
-06
Apr
-06
0%
20%
40%
60%
80%
100%
120%
SCurve Based on Hours (Does Not Include Procurement)
Hoisting Equipment
PERSEUS 1B RIG MOBILISATIONDESIGN S-CURVE & BARCHART
Well Control Equipment
Cement System
Low Pressure Mud
Skidding
150 kg Manriding Tuggers
Utilities
Materials Handling
` Rotary Equipment
Structures
Site Integration Test
High Pressure Mud
Mud Treatment
Pipe Handling
Planned: 92.3%Earned: 85.8% Actual: 92.4%
Stabmaster
Cutting Drier
CLOSE-OUT
Design progress has maintained increased growth in actuals and earned hours, with additional scope/budget requirements, percentages are only approx. 7% behind the target plan.
Schedule expected to align with targeted progress over the next fortnight, and actuals to exceed the planned budget.
Forecast target completion 24th November for all Worleyparsons, Perth TW design works.
Based on Hours (Does Not Include Procurement)
0%
20%
40%
60%
80%
100%
14-F
eb-0
5
28-F
eb-0
5
14-M
ar-0
5
28-M
ar-0
5
11-A
pr-0
5
25-A
pr-0
5
9M
AY
200
5
23-M
ay-0
5
6JU
N 2
005
20-J
un-0
5
4JU
L 20
05
18-J
ul-0
5
1A
UG
200
5
15-A
ug-0
5
29-A
ug-0
5
12-S
ep-0
5
26-S
ep-0
5
10-O
ct-0
5
24-O
ct-0
5
7N
OV
200
5
21-N
ov-0
5
5D
EC
200
5
19-D
ec-0
5
2JA
N 2
006
16-J
an-0
6
30-J
an-0
6
13-F
eb-0
6
27-F
eb-0
6
13-M
ar-0
6
27-M
ar-0
6
10-A
pr-0
6
24-A
pr-0
6
Pro
gre
ss %
Co
mp
lete
0
20
40
60
80
100
No
. of P
eop
le
Actual HoursForecast: TW/Other SupportForecast: Drill/HS CrewRebaseline ActualRebaseline EarnedRebaseline TargetTarget Actual ForecastEarned
821573 P1B Rig MobilisationOffshore SCurve and Histogram
Availability: AOA (includes hot stacking) 9 people to end May 13 people to end June 17 people to shutdown 35 people post-shutdownTW - As Required (10 Currently)
Planned: 73.3%Earned: 67.4% Actual: 75.1%
NRA Shutdown
Assist Well Services
Competency Based Training / Site Integration Test
Rig Mob S CurvesRig Mob S Curves
Perseus 1B North Rankin Drilling Rig ReinstatementPerseus 1B North Rankin Drilling Rig ReinstatementTitle: Perseus 1B Drillsafe
Presentation
Author: Doug Hodson
Drims: 2275628
Perseus 1B North Rankin Drilling Rig ReinstatementPerseus 1B North Rankin Drilling Rig ReinstatementTitle: Perseus 1B Drillsafe
Presentation
Author: Doug Hodson
Drims: 2275628
Star Racker FingersStar Racker Fingers
Perseus 1B North Rankin Drilling Rig ReinstatementPerseus 1B North Rankin Drilling Rig ReinstatementTitle: Perseus 1B Drillsafe
Presentation
Author: Doug Hodson
Drims: 2275628
Star Star RackerRacker
Perseus 1B North Rankin Drilling Rig ReinstatementPerseus 1B North Rankin Drilling Rig ReinstatementTitle: Perseus 1B Drillsafe
Presentation
Author: Doug Hodson
Drims: 2275628
Drillers ScreenDrillers Screen
Perseus 1B North Rankin Drilling Rig ReinstatementPerseus 1B North Rankin Drilling Rig ReinstatementTitle: Perseus 1B Drillsafe
Presentation
Author: Doug Hodson
Drims: 2275628
Cuttings Dryer SkidCuttings Dryer Skid
Perseus 1B North Rankin Drilling Rig ReinstatementPerseus 1B North Rankin Drilling Rig ReinstatementTitle: Perseus 1B Drillsafe
Presentation
Author: Doug Hodson
Drims: 2275628
Mud Tank HabitatsMud Tank Habitats
Perseus 1B North Rankin Drilling Rig ReinstatementPerseus 1B North Rankin Drilling Rig ReinstatementTitle: Perseus 1B Drillsafe
Presentation
Author: Doug Hodson
Drims: 2275628
Valve Actuators Under Mud TanksValve Actuators Under Mud Tanks
Perseus 1B North Rankin Drilling Rig ReinstatementPerseus 1B North Rankin Drilling Rig ReinstatementTitle: Perseus 1B Drillsafe
Presentation
Author: Doug Hodson
Drims: 2275628
DerrickDerrick
Perseus 1B North Rankin Drilling Rig ReinstatementPerseus 1B North Rankin Drilling Rig ReinstatementTitle: Perseus 1B Drillsafe
Presentation
Author: Doug Hodson
Drims: 2275628
Perseus 1B Rig Mob Main ChallengesPerseus 1B Rig Mob Main Challenges• New crews, access to crews• Access to engineering support• Reinstating rig contractor• Project implementation management• Productivity early on• Procurement turnaround• Brownfield “growth”• Critical path in derrick• Platform requirements:
– Hot work– Concurrent activity– Inductions– Travel booking system
Perseus 1B North Rankin Drilling Rig ReinstatementPerseus 1B North Rankin Drilling Rig ReinstatementTitle: Perseus 1B Drillsafe
Presentation
Author: Doug Hodson
Drims: 2275628
SuccessesSuccesses
• HSE and Teamwork Offshore• Early start strategy• Focus on critical path• Engaging workforce in critical path• Worked estimate in detail at the outset• Engaging stakeholders
Perseus 1B North Rankin Drilling Rig ReinstatementPerseus 1B North Rankin Drilling Rig ReinstatementTitle: Perseus 1B Drillsafe
Presentation
Author: Doug Hodson
Drims: 2275628
Project Project LearningsLearnings
• Cost Engineers more versatile and project focussed than accountants
• Planners spend considerable time manipulating Primavera and need to be focussed on critical path
• Need to understand estimating jargon: “Norms, Productivity, Non-prods, Growth, Contingency, Probabilistic”
• Project quality processes need to be focussed on project objectives
• Project Execution Plan: Very good document• Toll-gate reviews have to be managed carefully