Click here to load reader
Upload
salman-hussain
View
107
Download
1
Embed Size (px)
DESCRIPTION
dd
Citation preview
PMP® Formula Cheat Sheet
Project Management Professional Formula Cheat Sheet
Initiation Process Group
Present Value PV= FV
(1+r)n
FV= future value
R= interest rate
n = number of time periods
Net Present Value The higher the better
Internal Rate of Return The higher the better
Benefit to cost Ration The higher the better
Pay Back Period The lower the better
Benefit to Cost Ratio The lower the better
Planning Process Group
Three Point Estimate Optimistic + Pessimistic + 4 * Most Likely
6
Standard Deviation Pessimistic - Optimistic
6
Activity Variance Pessimistic - Optimistic 2
6
Free Float or Free Slack Free Float ( A) = Early Start (B) – Earl y Finish (A)
Total Float or Total Slack Total Float (A) = Late Start ( A) – Early Start (A)
Total Float (A) = Late Finish (A) – Early Finish (A)
Cost Estimation Rough Order Magnitude (ROM) Estimate + or – 50%
Budget Estimate -10 to +25%
Definitive Estimates (2 options) + or -10% | -5 to 10%
Expected Monitory Value (EMV) Probability * Impact
Communication Channels N (N-1) /2
PMP® Formula Cheat Sheet
Project Management Professional Formula Cheat Sheet
Monitoring & Controlling Process Group
Cost Variance (CV) Earned Value – Actual Cost | EV-AC
Schedule Variance (SV) Earned Value – Planned Value | EV-PV
Cost Performance Index (CPI) Earned Value / Actual Cost | EV/AC
Schedule Performance Index (SPI) Earned Value / Planned Value | EV/PV
Estimate at Completion (EAC)
At Present CPI
Budget at Completion / Cost Performance Index
EAC = BAC/CPI
Estimate at Completion (EAC)
At Budgeted Rate
Actual Cost +( Budget at Completion – Earned Value)
AC + (BAC-EV)
Estimate at Completion (EAC)
Considering both CPI and SPI
AC + ( BAC – EV_)
CPI * SPI
Estimate to Complete (ETC)
When original estimates are flawed
Estimate at Completion – Actual Cost | EAC - AC
Estimate to Complete (ETC)
When variances are typical
Budget at Completion – Earned Value | BAC- EV
Cost Performance Index CPI
To-Complete Performance Index
Based on Budget at completion
Budget at Completion – Earned Value | BAC - EV
Budget at Completion – Actual Cost BAC- AC
To Complete Performance Index
Based on EAC
Budget at Completion – Earned Value | BAC - EV
Estimate at Completion – Actual Cost EAC- AC
Variance At Completion (VAC) Budget at Completion – Estimate at Completion |
BAC - EAC