PMP Study Guide

Chapter 10: Monitoring and Controlling Change

Page 2: PMP Study Guide Chapter 10: Monitoring and Controlling Change

Chapter 10 Monitoring and Controlling Change

• Managing Integrated Change Control

• Managing Cost Changes

• Monitoring and Controlling Schedule Changes

• Monitoring and Controlling Risk

Page 3: PMP Study Guide Chapter 10: Monitoring and Controlling Change

Managing Integrated Change Control

• How change occurs

• Change control concerns

• Change control techniques

• Integrated Change Control outputs

Page 4: PMP Study Guide Chapter 10: Monitoring and Controlling Change

Change Control Concerns

• Influencing the factors that cause change and reaching agreement on change requests

• Determining a change is needed or has happened

• Managing approved changes• Updating requirements that impact

project plan• Documenting requested changes and

their impacts

Page 5: PMP Study Guide Chapter 10: Monitoring and Controlling Change

Integrated Change Control

• Configuration management

• Change control system

• Configuration control board

Page 6: PMP Study Guide Chapter 10: Monitoring and Controlling Change

Chapter 10 Monitoring and Controlling Change

• Managing Integrated Change Control

• Managing Cost Changes

• Monitoring and Controlling Schedule Changes

• Monitoring and Controlling Risk

Page 7: PMP Study Guide Chapter 10: Monitoring and Controlling Change

Managing Cost ChangesPerformance Measurement Analysis

• Earned value technique– Planned Value (PV) = Budgeted Cost

of Work Scheduled (BCWS)– Actual Cost (AC) = Actual Cost of Work

Performed (ACWP)– Earned Value (EV) = Budgeted Cost of

Work Performed (BCWP)

Page 8: PMP Study Guide Chapter 10: Monitoring and Controlling Change

Earned Value

Figure 10.1

Page 9: PMP Study Guide Chapter 10: Monitoring and Controlling Change

Earned Value Formulas

• Cost Variance(CV) = EV – AC

• Schedule Variance(SV) = EV – PV

• Performance Indexes– Cost Performance Index (CPI ) = EV ÷

AC– Cumulative CPIC = EVC ÷ ACC

– Schedule Performance Index (SPI) = EV ÷ PV

– Cumulative SPIC = EVC ÷ PVC

Page 10: PMP Study Guide Chapter 10: Monitoring and Controlling Change

Earned Value Formulas (cont.)

• Estimate to Completion (ETC)– ETC = (BAC – EVC ) ÷ CPIC – ETC = BAC – EVC

• Estimate at Completion– EAC = ACC + ETC– EAC = ACC + ((BAC – EV) ÷ CPIC)– EAC = ACC + BAC – EV

• Variance at Completion– VAC = BAC – EAC

Page 11: PMP Study Guide Chapter 10: Monitoring and Controlling Change

Chapter 10 Monitoring and Controlling Change

• Managing Integrated Change Control

• Managing Cost Changes

• Monitoring and Controlling Schedule Changes

• Monitoring and Controlling Risk

Page 12: PMP Study Guide Chapter 10: Monitoring and Controlling Change

Monitoring and Controlling Schedule Changes

• Schedule control involves determining status of project schedule, if changes have occurred or should occur, and influencing and managing schedule changes

Page 13: PMP Study Guide Chapter 10: Monitoring and Controlling Change

Monitoring and Controlling Schedule Changes

Tools and Techniques

• Progress reporting

• Schedule change control system

• Performance measurement

• Variance analysis

• Project management software

• Schedule comparison charts

Page 14: PMP Study Guide Chapter 10: Monitoring and Controlling Change

Chapter 10 Monitoring and Controlling Change

• Managing Integrated Change Control

• Managing Cost Changes

• Monitoring and Controlling Schedule Changes

• Monitoring and Controlling Risk

Page 15: PMP Study Guide Chapter 10: Monitoring and Controlling Change

Monitoring and Controlling Risk

• Risk Monitoring and Control tools and techniques– Risk reassessment– Risk audits– Variance and trend analysis– Technical performance

measurement– Reserve analysis– Status meetings

Page 16: PMP Study Guide Chapter 10: Monitoring and Controlling Change

Monitoring and Controlling Risk

• Risk Monitoring and Control outputs– Risk register updates– Requested changes– Recommended corrective actions– Recommended preventive actions– Organizational process asset

updates– Project management plan updates