Upload
andypats
View
234
Download
0
Embed Size (px)
Citation preview
7/29/2019 PMP Study Notes Formula Guide
1/29
Project Management Professional
(PMP)
PMP Study Notes & Formula Guide
7/29/2019 PMP Study Notes Formula Guide
2/29
Knowledge Areas (9)
ProjectIntegration
Management
Project ScopeManagement
Project TimeManagement
Project CostManagement
Project QualityManagement
Project HumanResource
Management
ProjectCommunications
Management
Project RiskManagement
ProjectProcurementManagement
Leverage Blueprint - PMP Study Notes & Formula Guide 2
7/29/2019 PMP Study Notes Formula Guide
3/29
Processes (5)
Initiation Planning Execution
Monitorand Control Closing
Leverage Blueprint - PMP Study Notes & Formula Guide 3
7/29/2019 PMP Study Notes Formula Guide
4/29
Project Management Processes (42)
P
rojectIntegration
Management
Develop ProjectCharter
Develop ProjectManagement Plan
Direct / ManageProject Execution
Monitor / ControlProject Work
Perform IntegratedChange Control
Close Project orPhase
Leverage Blueprint - PMP Study Notes & Formula Guide 4
7/29/2019 PMP Study Notes Formula Guide
5/29
Project Management Processes (42)
Project
ScopeManagement
CollectRequirements
Define Scope
Create WBS
Verify Scope
Control Scope
Leverage Blueprint - PMP Study Notes & Formula Guide 5
7/29/2019 PMP Study Notes Formula Guide
6/29
Project Management Processes (42)
Projec
tTimeManagement
Define Activities
SequenceActivities
Estimate ActivityResources
Estimate ActivityDurations
Develop Schedule
Control Schedule
Leverage Blueprint - PMP Study Notes & Formula Guide 6
7/29/2019 PMP Study Notes Formula Guide
7/29
Project Management Processes (42)
ProjectCostManagement
Estimate Costs
Determine Budget
Control Costs
Leverage Blueprint - PMP Study Notes & Formula Guide 7
7/29/2019 PMP Study Notes Formula Guide
8/29
Project Management Processes (42)
ProjectQ
ualityManagement
Plan Quality
Perform QualityAssurance
Perform QualityControl
Leverage Blueprint - PMP Study Notes & Formula Guide 8
7/29/2019 PMP Study Notes Formula Guide
9/29
Project Management Processes (42)
ProjectHumanResource
M
anagement
Develop HumanResource Plan
Acquire ProjectTeam
Develop ProjectTeam
Manage ProjectTeam
Leverage Blueprint - PMP Study Notes & Formula Guide 9
7/29/2019 PMP Study Notes Formula Guide
10/29
Project Management Processes (42)
ProjectCommunications
Managemen
t
IdentifyStakeholders
PlanCommunications
DistributeInformation
Manage StakeholderExpectations
Report Performance
Leverage Blueprint - PMP Study Notes & Formula Guide 10
7/29/2019 PMP Study Notes Formula Guide
11/29
Project Management Processes (42)
ProjectRiskManag
ement
Plan RiskManagement
Identify Risks
Perform QualitativeRisk Analysis
Perform QuantitativeRisk Analysis
Plan Risk Responses
Monitor and ControlRisks
Leverage Blueprint - PMP Study Notes & Formula Guide 11
7/29/2019 PMP Study Notes Formula Guide
12/29
Project Management Processes (42)
ProjectProcure
ment
M
anagement
PlanProcurements
ConductProcurements
AdministerProcurements
CloseProcurements
Leverage Blueprint - PMP Study Notes & Formula Guide 12
7/29/2019 PMP Study Notes Formula Guide
13/29
Network Diagram
Activity Duration = EF -ES + 1
orActivity Duration = LF -
LS + 1
Total Float = LS - ES orTotal Float = LF EF
Free Float = ES ofFollowing - ES ofPresent - DUR of
Present
EF = ES + duration - 1ES = EF of predecessor +
1LF = LS of successor - 1
LS = LF - duration + 1
Leverage Blueprint - PMP Study Notes & Formula Guide 13
7/29/2019 PMP Study Notes Formula Guide
14/29
Project Selection
PV = FV / (1+r)^n FV = PV * (1+r)^nNPV = Formula not
required. Select biggestnumber.
ROI = Formula notrequired. Select biggest
number.
IRR = Formula notrequired. Select biggest
number.
Payback Period = Addup the projected cashinflow minus expenses
until you reach theinitial investment.
BCR = Benefit / Cost CBR = Cost / BenefitOpportunity Cost = Thevalue of the project not
chosen.
Leverage Blueprint - PMP Study Notes & Formula Guide 14
7/29/2019 PMP Study Notes Formula Guide
15/29
Earned Value Management
BAC = Budget AtCompletion
EV = Actual % *BAC
PV = Planned % *BAC
AC = Sum of allincurred costs
CV = EV - AC SV = EV - PV
CPI = EV / AC
< 1 = Over Budget > 1 = Under Budget
SPI = EV / PV
< 1 = Behind Schedule > 1 = Ahead of
Schedule
EAC = BAC / CPI EAC = AC + ETCEAC = AC + (BAC +
EV) / CPIETC = EAC - AC
VAC = BAC - EAC BCWS = PV BCWP = EV ACWP = AC
Leverage Blueprint - PMP Study Notes & Formula Guide 15
7/29/2019 PMP Study Notes Formula Guide
16/29
TIPS: Earned Value Management
Negative isbad
Positive isgood
If Variance: EV- Something
If Index: EV /Something
If Cost relateduse AC
If Time relateduse PV
Most formulasstart with EV
Leverage Blueprint - PMP Study Notes & Formula Guide 16
7/29/2019 PMP Study Notes Formula Guide
17/29
PERT
PERT 3-point =(Pessimistic+(4*MostLikely)+Optimistic)/6
PERT = (Pessimistic -Optimistic) / 6
PERT Activity
Variance =((Pessimistic -
Optimistic) / 6)^2
PERT Variance all
activities =sum((Pessimistic -Optimistic) / 6)^2
Leverage Blueprint - PMP Study Notes & Formula Guide 17
7/29/2019 PMP Study Notes Formula Guide
18/29
Values
1 sigma = 68.26% 2 sigma = 95.46% 3 sigma = 99.73%
6 sigma = 99.99%Control Limits = 3sigma from mean
Control Specifications= Defined by
customer; looser thanthe control limits
Order of Magnitudeestimate = -25% to
+75%
Preliminary estimate =-15% to + 50%
Leverage Blueprint - PMP Study Notes & Formula Guide 18
7/29/2019 PMP Study Notes Formula Guide
19/29
Values
Budget estimate =-10% to +25%
Definitive estimate= -5% to +10%
Final estimate = 0%
Float on the criticalpath = 0 days
Pareto Diagram =80/20
Time a PM spendscommunicating =
90%
Crashing a project= Crash least
expensive tasks oncritical path.
JIT inventory = 0%(or very close to
0%.)
Minus 100 = (100)or -100
Leverage Blueprint - PMP Study Notes & Formula Guide 19
7/29/2019 PMP Study Notes Formula Guide
20/29
Procurement
PTA = ((Ceiling Price
- Target Price) /Buyer's Share Ratio)
+ TargetCost
Leverage Blueprint - PMP Study Notes & Formula Guide 20
7/29/2019 PMP Study Notes Formula Guide
21/29
Depreciation
Straight-line Depreciation:Depr. Expense = Asset Cost / Useful
LifeDepr. Rate = 100% / Useful Life
Double Declining Balance Method:Depr. Rate = 2 * (100% / Useful Life)
Depr. Expense = Depreciation Rate *Book Value at Beginning of Year
Book Value = Book Value at beginningof year - Depreciation Expense
Sum-of-Years' Digits Method:Sum of digits = Useful Life + (Useful
Life - 1) + (Useful Life - 2) + etc.
Depr. rate = fraction of years left andsum of the digits (i.e. 4/15th)
Leverage Blueprint - PMP Study Notes & Formula Guide 21
7/29/2019 PMP Study Notes Formula Guide
22/29
Human Resource Management
Organizational Structures:
Functional, Matrix (weak,balanced, strong) , Projectized,Composite
Maslows Hierarchy ofNeeds:
Physiological, Safety, Social, Self-esteem, Self-actualization.
McGregor:
Theory X, Theory Y.
Ouchi:
Theory Z. Motivated bycommitment, opportunityadvancement.
Herzbergs Theory ofMotivation:
Hygiene factors, MotivatingAgents.
Leadership Styles:
Directing, Facilitating, Coaching,Supporting, Autocratic,Consultative, Consensus.
Project Manager Powers:
Formal (legitimate,) Reward,Penalty (coercive), Expert,Referent.
Conflict Management:
Withdraw (avoid), Smooth(accommodate), Compromise,Force, Collaborate, Confront(problem solving.)
Leverage Blueprint - PMP Study Notes & Formula Guide 22
7/29/2019 PMP Study Notes Formula Guide
23/29
Quality Management
Ishikawa = FishboneDiagram: cause and
effect.
Pareto Diagram:Identify problems andfrequency. 80/20 Rule.
Flow Charts; ControlCharts.
Just in Time: Reducesinventory; requiresadditional quality
control.
Quality Theories: Kaizen(continuous
improvement,) SixSigma, TQM (total
quality management.)
Kaizen: Smallimprovements toreduce costs and
improve consistency.
Deming Cycle: Plan, DoCheck, Act
Leverage Blueprint - PMP Study Notes & Formula Guide 23
7/29/2019 PMP Study Notes Formula Guide
24/29
Risk Management
Risk Strategies (threats):
Avoid
Transfer
Mitigate
Accept
Risk Strategies(opportunities):
Exploit
Share
Enhance
Accept
Qualitative Risk Analysis:Chance and impact of risk
occurrence Results in
prioritized list of risks; riskranking.
Quantitative Risk Analysis:
Numerical analysis ofprobability and impact.
Tools:
Interviews
Sensitivity Analysis
Decision Tree Analysis Simulation
Monte Carlo Analysis
Leverage Blueprint - PMP Study Notes & Formula Guide 24
7/29/2019 PMP Study Notes Formula Guide
25/29
Communications
Communication
Channels=
n * (n-1) / 2
Leverage Blueprint - PMP Study Notes & Formula Guide 25
7/29/2019 PMP Study Notes Formula Guide
26/29
Probability
EMV = Probability *Impact in currency
Leverage Blueprint - PMP Study Notes & Formula Guide 26
7/29/2019 PMP Study Notes Formula Guide
27/29
Rules Based on Numbers
80 Hour Rule = Max sizeof work packages
80/20 Rule = ParetosLaw
20% of causes responsible for
80% of problems
0/50/100 = Workpackage completion
No credit until 50% complete
No additional credit until100% complete
Leverage Blueprint - PMP Study Notes & Formula Guide 27
7/29/2019 PMP Study Notes Formula Guide
28/29
Contact Details
Leverage Blueprint - PMP Study Notes &Formula Guide
28
7/29/2019 PMP Study Notes Formula Guide
29/29
Contact Detail
Postal P.O. Box CT 6440, Cantonments Accra, Ghana
Telephone 233 (0) 200 116 119
Email [email protected]
Website
www.leverage-blueprint.com
Skype
leverage.blueprint
Facebook www.facebook.com/leverage.blueprint.com
Twitter www.twitter.com/levBlueprint
Leverage Blueprint - PMP Study Notes & Formula Guide 29