Alford Community Campus
Progress Report No 17
March 2015
View from Playing Fields
1.00 Progress Report
External Fabric – Blocks C, B & D
External Fabric
Blocks B& C
• Partitions 2nd side boarding in
progress
• Ames taping in progress
• Wiring / Dado Trunking in progress
• Ceilings in progress
• Floor preparation commenced
Block F
• Library enclosed
• Stonework continues
• Theatre blockwork completed
• Theatre scaffold being stripped
• Metal stair screed completed
Block D
• 2nd side boarding / taping
• Wiring in progress
• Ceilings commenced
Block A
• M&E conduit drops in progress
• Pool high level walls taped / painted
• Pool structure being built
Block E
• Partitions in progress
• Internal blockwork completed
• Boiler positioned
External Works – Topsoil Spreading & Planting Progressed
External Works – Perimeter Fencing Progressed
Marked-up Programme
Marked-up Programme
Target Programme
Target Programme
1.00 Progress Report
1.02 Overall Programme Position:
• Awaiting delivery of remaining rooflights (expected 20th April)
• Render delayed (Muirfield in administration)
• Partitions progressing all areas
• M&E initial fix on programme
• M&E final fix behind programme
• Suspended ceilings in progress
• External works ahead of schedule
Contract Programme CP / 001: One week behind
1.00 Progress Report
1.03 Labour Report:
Trade No Trade No
Roofing / Cladding 11 Stonework 4
Bricklayers 4 Civils 4
M&E 45 SFS 5
Ceilings 1 Barr and Wray 3
Scaffolder 3 SSE 1
Flooring 4 Decorators 7
Joiners 18 Security 2
General Labourers 4 Others 4
Management / Technical 10
Fire Protection 4
Total 134
1.00 Progress Report
1.04 Main Activities Planned Next Month
• Complete stonework / drop scaffold to complete entrance area
• Additional resource to progress partitions
• Continue M&E all areas
• Continue ceilings
• Commence joiner finishes, flooring, FF&E
2.00 Design Report
2.01 Design:
DTMs continue on a fortnightly basis to coordinate design and sub-contractor input. Ironmongery workshop to fine-tune RDD 15 and building control compliance. Revised room Layouts for Wing B, C & D returned to client for final sign-off Meeting with ACC to resolve RDD 7 & 8 Internal and External Lighting light fittings
now ordered (await delivery) ACC confirmed FF&E colours for Wing B, C & D IWB/Teaching wall proposals submitted and ACC responses and clarifications
returned. Technical Meeting with ACC to resolve sanitary ware, hard landscape changes and
acoustic panel spec / colours. Clarifications provided for CDT dust extract and duct route for fume extract
established. ACC response to LCD screen positions returned. Pool timing equipment requirement to be clarified.
2.00 Design Report
2.02 Planning Conditions:
• Condition 02 – Notification of Completion to be issued (final inspection clears
remainder of Condition 03 confirmation of completion of car parking provision &
Condition 12 confirmation of completion of landscaping).
• Condition 05 – Traffic Calming / Cycling Provision on Greystone Road to be
completed prior to occupation (Aberdeenshire Council action)
• Condition 06 – Speed Limits / Signage as TRO’s to be implemented in surrounding
area prior to occupation (Aberdeenshire Council action)
• Planning Application for PV installation has been submitted.
• All other planning conditions have been closed.
3.00 Health and Safety
3.01 Safety Report:
Item Period Total
Reportable Accidents 0 0
HSE Visits 0 0
Near Miss Incident 0 0
• Current focus is on ‘Working at Height’ issues.
• Safety audit planned for 26th March 15.
• Stand down day planned for 31st March 15.
4.00 Community
• We currently have three work experience placements.
• Site participated in UKCG Open Doors event 6th/7th March 15 - Over 350
members of the public attended (including local school pupils and local
MSP Dennis Robertson) .
• Craigievar Primary visited site on 20th March.
• Current CCS score 42 (next visit scheduled for 16th April).
5.00 Quality
• Temperatures being monitored / work rescheduled if required
• Underfloor heating loop pressure tests being checked
• Technical Services inspections ongoing
• F&G (M&E) inspections commenced
• AC Clerk of Works visits ongoing / comments being addressed
• Preliminary discussions held relating to contract completion inspections /
snagging process
6.00 Utilities
Item Current Progress Target Installation Date Critical ‘live’ date
Electricity Substation now live
Cables from substation to switch room installed awaiting main panel
Main panel due on site by 9th April – aim to build by 17th April
Target date for meter 20th April (awaiting confirmation from AC)
Substation live.
Supply to building – aiming for
wc 20th April.
8th May 15
(required earlier for temp
supplies)
Water Track inspection (BW) – date requested from SW by 6th April
FES will install external mains commencing 30th March
Aim for water supply live by 8th
May
8th May 15
(required earlier for temp
supplies)
Gas AC has confirmed tanks will be available from April 15 – MC will schedule a
date for installation during May 15.
May 15 May 15
Telecom Additional BT works undertaken as instructed.
MC now have the order number from AC so MC will make direct with our
contact in BT to agree the installation date (provisionally 2nd April)
2nd April 15 8th May 15
7.00 Procurement
Package Contractor
Mass cut and fill / Stabilisation Ground Developments Limited
Ground works / Concrete / Drainage Carey
Structural Steelwork / Decking BSB
Roofing & Cladding Curtis Moore
SFS Veitchi
Precast Concrete Bison (supply only)
Glulam Beams Glulam Solutions
Swimming Pool Barr and Wray
Lifts Kone
Windows & Curtain Walling Glassolutions
Mechanical & Electrical CHES
Louvres Colt
Package Contractor
Fire Protection Orr FP
Brickwork Fairways
Stonework Stirling Stone
Natural Ventilation JRF Chimney Specialists
Landscaping Ground Control
Chemical Hoist Stannah Lift Services
Kitchens James Scott & Sons
Rooflights Lareine Engineering
Sports Pitches Malcolm Construction
Metalwork Miller Fabrications
Kalwall SD Systems 96
Package Contractor
IPS Inscape
Siphonic drainage West Siphonics
Roller doors Fortress
FFE ESA
Retractable seating Audience systems
Ceiling mounted hoists Hill-Rom (Liko)
Render Muirfield (replacement required)*
Folding partitions Movawall
Revolving door Geze
Pool sports equipment Alpha Sports
Partitions Morrison
Package Contractor
Decoration and Ames Taping Angus Decorators
Suspended Ceilings Hi-Tech Acoustic Services
Flooring Harndec
Signage
Fencing Alpine
Joinerwork Morrison
Bespoke furniture Thomas Johnstone
Tiling De Cecco
Blinds & Curtains Kaydee
Timber sports flooring MacKay
Hygienic partitions Morrison
8.00 Key Risks
Item Measures Risk
Inclement Weather Conditions improving. Low
Works being undertaken adjacent to site, housing
development, etc
Ongoing dialogue with other parties Low
Electrical connection Work was on hold pending resolution of wayleave issues –
dates now agreed.
Medium
Water connection Connection approved – dialogue with SW to agree dates. Medium
Interface between MCUK activity and work by
others incl. Gas and Telecomm connection
Dependency schedule issued to Hubco Medium
Completion of external Road works to enable
interfaces and comply with Planning Conditions
Price requested from MC – meeting required to agree
scope of works
High
Availability of joiners Ongoing issue – addition resource being arranged by
Morrison.
Medium
Resolution of list of changes requiring formal
instruction.
General instruction issued 19/2/15 - ongoing dialogue to
formalise changes / instructions / costs.
Medium
PV Installation PV instruction issued 19/2/15 – programme being
assessed
High
Render works Appointed Subcontractor Muirfield in administration –
alternative options being reviewed
High