Upload
others
View
100
Download
5
Embed Size (px)
Citation preview
Project: ACT Acorn Feasibility Study
Terms of Use
The ACT Acorn Consortium partners reserve all rights in this material and retain full copyright. Any reference to
this material or use of the material must include full acknowledgement of the source of the material, including
the reports full title and its authors. The material contains third party IP, used in accordance with those third
party’s terms and credited as such where appropriate. Any subsequent reference to this third party material
must also reference its original source. The material is made available in the interest of progressing CCS by
sharing this ACT work done on the Acorn project.
Pale Blue Dot Energy reserve all rights over the use of the material in connection with the development of the
Acorn Project. In the event of any questions over the use of this material please contact [email protected].
D07 Acorn CO2 Storage Site Development Plan 10196ACTC-Rep-27-01
August 2018
www.actacorn.eu
Acorn
ACT Acorn, project 271500, has received funding from BEIS (UK), RCN (NO) and RVO (NL), and is co-funded by the European Commission under the ERA-Net instrument of the Horizon 2020 programme. ACT Grant number 691712.
D07 Acorn CO2 Storage Site Development Plan Contents
ACT Acorn Consortium Page 3 of 151
Contents
Document Summary
Client Research Council of Norway & Department of Business, Energy & Industrial Strategy
Project Title Accelerating CCS Technologies: Acorn Project
Title: D07 Acorn CO2 Storage Site Development Plan
Distribution: Client & Public Domain
Date of Issue: 30th August 2018
Prepared by: Dr Juan Alcalde and Dr Clare Bond (both University of Aberdeen), Dr Saeed Ghanbari and Dr Eric Mackay (both Heriot Watt-University), Dr Niklas Heinemann and Dr Stuart Haszeldine (both The University of Edinburgh), Dr Philippa Parmiter and Indira Mann (both SCCS), Hazel Robertson, Alan James, Tim Dumenil, David Pilbeam and Charlie Hartley (all Pale Blue Dot Energy)
Approved by: Steve Murphy, ACT Acorn Project Director
Disclaimer:
While the authors consider that the data and opinions contained in this report are sound, all parties must rely upon their own skill and judgement when using it. The authors do not make any representation or
warranty, expressed or implied, as to the accuracy or completeness of the report. The authors assume no liability for any loss or damage arising from decisions made on the basis of this report. The views and
judgements expressed here are the opinions of the authors and do not reflect those of the client or any of the stakeholders consulted during the course of this project.
The ACT Acorn consortium is led by Pale Blue Dot Energy and includes Bellona Foundation, Heriot-Watt University, Radboud University, Scottish Carbon Capture and Storage (SCCS), University of Aberdeen,
University of Edinburgh and University of Liverpool.
Amendment Record
Rev Date Description Issued By Checked By Approved By
V0.1 09/03/18 First Draft N Heinemann H Robertson P Parmiter
V1.0 30/08/18 First Issue N Heinemann H Robertson P Parmiter
D07 Acorn CO2 Storage Site Development Plan Contents
ACT Acorn Consortium Page 4 of 151
Table of Contents
CONTENTS ................................................................................................................................................................................................................................................... 3
1.0 EXECUTIVE SUMMARY .................................................................................................................................................................................................................. 12
2.0 INTRODUCTION TO ACT ACORN .................................................................................................................................................................................................. 16
3.0 SCOPE AND OBJECTIVES ............................................................................................................................................................................................................. 21
4.0 SITE CHARACTERISATION ........................................................................................................................................................................................................... 23
5.0 APPRAISAL PLANNING ................................................................................................................................................................................................................. 99
6.0 DEVELOPMENT PLANNING ......................................................................................................................................................................................................... 100
7.0 BUDGET & SCHEDULE ................................................................................................................................................................................................................ 122
8.0 CONCLUSIONS & RECOMMENDATIONS ................................................................................................................................................................................... 126
9.0 REFERENCES ............................................................................................................................................................................................................................... 132
10.0 ANNEXES ....................................................................................................................................................................................................................................... 135
D07 Acorn CO2 Storage Site Development Plan Contents
ACT Acorn Consortium Page 5 of 151
CONTENTS ................................................................................................................................................................................................................................................... 3
TABLE OF CONTENTS .................................................................................................................................................................................................................................... 4
FIGURES ...................................................................................................................................................................................................................................................... 7
TABLES ...................................................................................................................................................................................................................................................... 10
1.0 EXECUTIVE SUMMARY .................................................................................................................................................................................................................. 12
2.0 INTRODUCTION TO ACT ACORN .................................................................................................................................................................................................. 16
2.1 ACT ACORN OVERVIEW................................................................................................................................................................................................................... 16
2.2 ACORN DEVELOPMENT CONCEPT ..................................................................................................................................................................................................... 19
3.0 SCOPE AND OBJECTIVES ............................................................................................................................................................................................................. 21
3.1 PURPOSE ........................................................................................................................................................................................................................................ 21
3.2 SCOPE ............................................................................................................................................................................................................................................ 21
4.0 SITE CHARACTERISATION ........................................................................................................................................................................................................... 23
4.1 GEOLOGICAL SETTING ..................................................................................................................................................................................................................... 23
4.2 SITE HISTORY AND DATABASE .......................................................................................................................................................................................................... 24
4.3 STORAGE STRATIGRAPHY ................................................................................................................................................................................................................ 30
4.4 SEISMIC CHARACTERISATION ........................................................................................................................................................................................................... 31
4.5 GEOLOGICAL CHARACTERISATION .................................................................................................................................................................................................... 37
4.6 INJECTION PERFORMANCE CHARACTERISATION ................................................................................................................................................................................ 40
4.7 CONTAINMENT CHARACTERISATION .................................................................................................................................................................................................. 81
5.0 APPRAISAL PLANNING ................................................................................................................................................................................................................. 99
6.0 DEVELOPMENT PLANNING ......................................................................................................................................................................................................... 100
6.1 DESCRIPTION OF DEVELOPMENT .................................................................................................................................................................................................... 100
6.2 CO2 SUPPLY PROFILE ................................................................................................................................................................................................................... 100
6.3 WELL DEVELOPMENT PLAN ............................................................................................................................................................................................................ 101
D07 Acorn CO2 Storage Site Development Plan Contents
ACT Acorn Consortium Page 6 of 151
6.4 OFFSHORE INFRASTRUCTURE DEVELOPMENT PLAN ........................................................................................................................................................................ 106
6.5 OPERATIONS ................................................................................................................................................................................................................................. 116
6.6 DECOMMISSIONING ........................................................................................................................................................................................................................ 116
6.7 POST CLOSURE PLAN .................................................................................................................................................................................................................... 117
6.8 HANDOVER TO AUTHORITY ............................................................................................................................................................................................................. 117
6.9 DEVELOPMENT RISK ASSESSMENT ................................................................................................................................................................................................. 117
7.0 BUDGET & SCHEDULE ................................................................................................................................................................................................................ 122
7.1 COST ESTIMATING BASIS ............................................................................................................................................................................................................... 122
7.2 CAPITAL EXPENDITURE ESTIMATE .................................................................................................................................................................................................. 123
7.3 OPERATING EXPENDITURE ESTIMATE ............................................................................................................................................................................................. 124
7.4 ABANDONMENT EXPENDITURE ESTIMATE ........................................................................................................................................................................................ 124
7.5 UNCERTAINTY OF COST ESTIMATES ............................................................................................................................................................................................... 125
7.6 SCHEDULE .................................................................................................................................................................................................................................... 125
8.0 CONCLUSIONS & RECOMMENDATIONS ................................................................................................................................................................................... 126
8.1 CONCLUSIONS ............................................................................................................................................................................................................................... 126
8.2 RECOMMENDATIONS ...................................................................................................................................................................................................................... 129
9.0 REFERENCES ............................................................................................................................................................................................................................... 132
10.0 ANNEXES ....................................................................................................................................................................................................................................... 135
10.1 ANNEX 1 – DATA INVENTORY .......................................................................................................................................................................................................... 135
10.2 ANNEX 2: RISK REGISTER .............................................................................................................................................................................................................. 141
10.3 ANNEX 3: LEAKAGE WORKSHOP SPIDER DIAGRAMS ........................................................................................................................................................................ 142
D07 Acorn CO2 Storage Site Development Plan Contents
ACT Acorn Consortium Page 7 of 151
Figures
FIGURE 1-1: LOCATION MAP OF ACORN CO2 STORAGE SITE COMPLEX.............................................................................................................................................................. 13
FIGURE 1-2: PRIMARY AND SECONDARY CONTAINMENT OF THE ACORN CO2 STORAGE SITE ............................................................................................................................... 13
FIGURE 1-3: ACORN CCS PROJECT SCHEDULE .............................................................................................................................................................................................. 14
FIGURE 2-1: ACT ACORN CONSORTIUM PARTNERS .......................................................................................................................................................................................... 16
FIGURE 2-2: KEY AREAS OF INNOVATION ......................................................................................................................................................................................................... 17
FIGURE 2-3: ACT ACORN WORK BREAKDOWN STRUCTURE .............................................................................................................................................................................. 17
FIGURE 2-4: A SCALABLE FULL-CHAIN INDUSTRIAL CCS PROJECT ..................................................................................................................................................................... 19
FIGURE 2-5: ACORN BUILD OUT SCENARIO FROM THE 2017 PCI APPLICATION ................................................................................................................................................... 20
FIGURE 3-1: ACORN CCS PROJECT PHASE 1 AND BUILD-OUT OPTIONS ............................................................................................................................................................ 21
FIGURE 4-1: CAPTAIN SANDSTONE FAIRWAY ................................................................................................................................................................................................... 23
FIGURE 4-2: TWO-WAY-TIME MAP SHOWING OUTLINE OF ACORN CO2 STORAGE SITE AND CAPTAIN X AREA ........................................................................................................ 24
FIGURE 4-3: TIME SLICE OF THE PGS MEGASURVEY SHOWING SEISMIC COVERAGE AND EXTENT OF THE INTERPRETATIONS IN THE ACORN CO2 STORAGE SITE AREA ................... 27
FIGURE 4-4: MAP OF WELLS AVAILABLE IN THE CAPTAIN FAIRWAY, INCLUDING THESE USED IN THE INTERPRETATION (IN RED, BLUE AND YELLOW) ................................................. 29
FIGURE 4-5: STRATIGRAPHIC COLUMN ............................................................................................................................................................................................................ 30
FIGURE 4-6: SYNTHETIC SEISMOGRAM FROM THE WELL 13/24A- 6 .................................................................................................................................................................... 32
FIGURE 4-7: TOP CAPTAIN SANDSTONE TWO-WAY TIME MAP AND FAULTING ...................................................................................................................................................... 34
FIGURE 4-8: DEPTH CONVERSION SUMMARY.................................................................................................................................................................................................... 36
FIGURE 4-9: PETROPHYSICAL WORKFLOW ....................................................................................................................................................................................................... 37
FIGURE 4-10: EFFECT OF IMPURITIES ON THE PHASE ENVELOPE ....................................................................................................................................................................... 42
FIGURE 4-11: RATES ACHIEVABLE BY CASE FOR MINIMUM AND MAXIMUM TUBING HEAD PRESSURE ..................................................................................................................... 47
FIGURE 4-12: PRESSURE / TEMPERATURE PROFILES – 4½’’ TUBING – MIN/MAX TUBING HEAD PRESSURE ............................................................................................................ 47
FIGURE 4-13: PRESSURE / TEMPERATURE PROFILES – 27/8’’ TUBING – MIN/MAX TUBING HEAD PRESSURE ........................................................................................................... 47
FIGURE 4-14: PRESSURE / TEMPERATURE PROFILES – DUAL 27/8’’’TUBING – MIN/MAX TUBING HEAD PRESSURE ................................................................................................... 48
FIGURE 4-15: CASE 11B (MAXIMUM THP) – PRESSURE AND TEMPERATURE V DEPTH PLOT ................................................................................................................................ 48
FIGURE 4-16: PERFORMANCE ENVELOPE - 27/8’’ SINGLE TUBING STRING ........................................................................................................................................................... 50
FIGURE 4-17: PERFORMANCE ENVELOPE - 4½’’ SINGLE TUBING STRINGINJECTIVITY AND NEAR WELLBORE ISSUES ............................................................................................. 50
D07 Acorn CO2 Storage Site Development Plan Contents
ACT Acorn Consortium Page 8 of 151
FIGURE 4-18: PROFILE OF TEMPERATURE AND PRESSURE AWAY FROM INJECTION WELL, 100 DAYS AFTER THE START OF CO2 INJECTION. ........................................................... 53
FIGURE 4-19: DIFFERENT REGIONS USED IN THE ETI SSAP WORK. LOCATION OF MODEL FRACTURING PRESSURE THRESHOLD SHOWN AS RED POINT ......................................... 57
FIGURE 4-20: GAS SATURATION (TOP) AND CO2 MOLE FRACTION IN THE GAS PHASE (BOTTOM); BOTH IMMEDIATELY AFTER CO2 INJECTION STOPS (2042) .................................... 60
FIGURE 4-21: GAS SATURATION (TOP) AND CO2 MOLE FRACTION IN THE GAS PHASE (BOTTOM) PROFILES 1000 YEARS AFTER CO2 INJECTION IS STOPPED (YEAR 3042) ............... 61
FIGURE 4-22: LIGHT GAS MOLE FRACTION IN THE GAS PHASE PROFILE 1000 YEARS AFTER CO2 INJECTION TERMINATION (YEAR 3042) ................................................................ 61
FIGURE 4-23: CO2 SUPPLY SCENARIOS ........................................................................................................................................................................................................... 62
FIGURE 4-24: CO2 STORAGE ZONES ............................................................................................................................................................................................................... 63
FIGURE 4-25: BHP AND THP PROFILES FOR WELL G02 FOR THE PHASE 1 (4MT) SCENARIO ............................................................................................................................. 64
FIGURE 4-26: PHASE 1 (SUPPLY SCENARIO 1 - 4MT) CO2 SUPPLY SCENARIO GAS SATURATION PROFILE .......................................................................................................... 65
FIGURE 4-27: RETAINED CO2 AND TRAPPING MECHANISM FRACTIONS FOR 4MT CO2 SUPPLY SCENARIO ............................................................................................................ 66
FIGURE 4-28: CO2 PLUME MIGRATION AT THE END OF INJECTION (ABOVE) AND AFTER 1000 YEARS SHUT-IN (BELOW) FOR PHASE 1 (4.2MT) ....................................................... 66
FIGURE 4-29: GAS SATURATION PROFILE AFTER THE END OF CO2 INJECTION (TOP) AND 1000 YEARS LATER (BOTTOM) FOR THE 64MT CO2 SUPPLY SCENARIO ........................... 67
FIGURE 4-30: CO2 MOLE FRACTION IN THE GAS PHASE 1000 YEARS AFTER CO2 INJECTION IS STOPPED FOR THE PHASE 2 (SCENARIO 2 - 64MT) CO2 SUPPLY SCENARIO ............ 68
FIGURE 4-31: BHP AND THP PROFILES FOR WELLS G2 AND G4 FOR PHASE 2 64MT SCENARIO........................................................................................................................ 68
FIGURE 4-32: RETAINED CO2 AND TRAPPING MECHANISM FRACTIONS FOR 64MT CO2 SUPPLY SCENARIO .......................................................................................................... 68
FIGURE 4-33: ACORN CO2 STORAGE SITE STORAGE COMPLEX OUTLINE SHOWING CAPTAIN X AREA AND GOLDENEYE SEGMENT ......................................................................... 69
FIGURE 4-34: GAS SATURATION PROFILE FOR PHASE 3 (SCENARIO 3 - 152MT) CO2 SUPPLY SCENARIO ............................................................................................................ 70
FIGURE 4-35: CO2 MOLE FRACTION IN THE GAS PHASE 1000 YEARS AFTER CO2 INJECTION HAS STOPPED FOR THE THIRD CO2 SUPPLY SCENARIO (SIMULATION RUN SR20) ........ 72
FIGURE 4-36: RETAINED CO2 AND TRAPPING MECHANISM FRACTIONS FOR PHASE 3 CO2 SUPPLY SCENARIO ...................................................................................................... 72
FIGURE 4-37: BHP AND THP PROFILES FOR WELLS G1-4 FOR SR20 ............................................................................................................................................................... 72
FIGURE 4-38: PROFILE OF CO2 DISTRIBUTION IN THE SECOND SIMULATION RUN AFTER 1000 YEARS. WELL G1 IS NOW AT THE BOTTOM OF THE MODEL NEAR THE GOLDENEYE FIELD
.............................................................................................................................................................................................................................................................. 74
FIGURE 4-39: PROFILE OF CO2 DISTRIBUTION IN THE THIRD SIMULATION RUN AFTER 1000 YEARS. BOTH WELLS G1 AND G3 ARE NOW AT THE BOTTOM OF THE MODEL NEAR THE
GOLDENEYE FIELD .................................................................................................................................................................................................................................. 74
FIGURE 4-40: RETAINED CO2 AND TRAPPING MECHANISM FRACTIONS FOR THE PHASE 3 THIRD SIMULATION RUN ................................................................................................ 75
FIGURE 4-41: PIE CHARTS SHOWING FRACTION OF FREE, TRAPPED AND DISSOLVED CO2 FOR DIFFERENT STRATEGIES ....................................................................................... 78
FIGURE 4-42: BAR CHARTS SHOWING FRACTION OF FREE, TRAPPED AND DISSOLVED CO2 FOR DIFFERENT STRATEGIES ...................................................................................... 79
FIGURE 4-43: FRACTION AND DISTRIBUTION OF CO2 FOR DIFFERENT WELL PLACEMENT STRATEGIES ................................................................................................................. 80
D07 Acorn CO2 Storage Site Development Plan Contents
ACT Acorn Consortium Page 9 of 151
FIGURE 4-44: COMPARISON OF FINAL GAS SATURATION PROFILES .................................................................................................................................................................... 81
FIGURE 4-45: ACORN CO2 STORAGE SITE STORAGE COMPLEX OUTLINE ............................................................................................................................................................ 82
FIGURE 4-46: PRIMARY AND SECONDARY CONTAINMENT .................................................................................................................................................................................. 82
FIGURE 4-47: WELL CORRELATION ................................................................................................................................................................................................................. 84
FIGURE 4-48: ADJUSTED BOW-TIE DIAGRAM DISPLAYING THE TWO MAIN STEPS OF THE RISK ASSESSMENT: THE LEAKAGE SCENARIO ANALYSIS AND THE CONSEQUENCE ANALYSIS . 89
FIGURE 4-49: THE 11 LEAKAGE SCENARIOS CONSIDERED AS RELEVANT FOR THE AREA INVESTIGATED ............................................................................................................... 91
FIGURE 4-50: SUMMARY OF THE RISK OF ALL LEAKAGE SCENARIOS; PRIMARY PATHWAYS IN BLACK AND SECONDARY PATHWAYS IN PURPLE ......................................................... 93
FIGURE 4-51: SUMMARY OF CONSEQUENCE IMPACT OF ALL LEAKAGE SCENARIOS ............................................................................................................................................. 94
FIGURE 4-52: LEAKAGE SCENARIO MAPPING TO MMV TECHNOLOGY. THE COLOURS CORRESPOND TO THE RISK MATRIX IN FIGURE 4-50 ............................................................. 97
FIGURE 6-1: KEY ELEMENTS OF OFFSHORE INFRASTRUCTURE ........................................................................................................................................................................ 100
FIGURE 6-2: THREE DIFFERENT CO2 SUPPLY SCENARIOS ENVISAGED FOR THE ACORN PROJECT ..................................................................................................................... 101
FIGURE 6-3: WELL PROFILE TO THE RESERVOIR ............................................................................................................................................................................................. 103
FIGURE 6-4: WELL CONSTRUCTION ILLUSTRATION ......................................................................................................................................................................................... 105
FIGURE 6-5: TRANSPORTATION INFRASTRUCTURE OVERIVEW ......................................................................................................................................................................... 108
FIGURE 6-6: ATLANTIC AND CROMARTY FIELD LAYOUT ................................................................................................................................................................................... 108
FIGURE 6-7: OPERATING CONDITIONS ALONG THE ATLANTIC PIPELINE ............................................................................................................................................................ 113
FIGURE 6-8: PRESSURE/TEMPERATURE PROFILE OBSERVED IN THE ATLANTIC PIPELINE FOR DIFFERENT SUPPLY SCENARIOS. ARROWS SHOW THE DIRECTION OF THE PROFILE FROM
ST FERGUS TO INJECTION SITE ON THE LEFT. THE RED REGION IS THE LIKELY HYDRATE FORMATION REGION ............................................................................................. 115
FIGURE 7-1: DEVELOPMENT SCHEDULE ......................................................................................................................................................................................................... 125
FIGURE 10-1: PGS MEGA SURVEY TIME SLICE SHOWING THE SEISMIC DATA EXTENT AND TILES USED IN THE CAPTAIN AQUIFER EVALUATION ..................................................... 135
FIGURE 10-2: THE 11 LEAKAGE SCENARIOS CONSIDERED AS RELEVANT FOR THE AREA INVESTIGATED ............................................................................................................. 142
FIGURE 10-3: SPIDER DIAGRAM SHOWING THE IMPACT OF CONSEQUENCES .................................................................................................................................................... 143
FIGURE 10-4: SPIDER DIAGRAM SHOWING THE IMPACT OF CONSEQUENCES .................................................................................................................................................... 144
FIGURE 10-5: SPIDER DIAGRAM SHOWING THE IMPACT OF CONSEQUENCES .................................................................................................................................................... 144
FIGURE 10-6: SPIDER DIAGRAM SHOWING THE IMPACT OF CONSEQUENCES .................................................................................................................................................... 145
FIGURE 10-7: SPIDER DIAGRAM SHOWING THE IMPACT OF CONSEQUENCES .................................................................................................................................................... 146
FIGURE 10-8: SPIDER DIAGRAM SHOWING THE IMPACT OF CONSEQUENCES .................................................................................................................................................... 147
FIGURE 10-9: SPIDER DIAGRAM SHOWING THE IMPACT OF CONSEQUENCES .................................................................................................................................................... 148
D07 Acorn CO2 Storage Site Development Plan Contents
ACT Acorn Consortium Page 10 of 151
FIGURE 10-10: SPIDER DIAGRAM SHOWING THE IMPACT OF CONSEQUENCES................................................................................................................................................... 148
FIGURE 10-11: SPIDER DIAGRAM SHOWING THE IMPACT OF CONSEQUENCES................................................................................................................................................... 149
FIGURE 10-12: SPIDER DIAGRAM SHOWING THE IMPACT OF CONSEQUENCES................................................................................................................................................... 150
FIGURE 10-13: SPIDER DIAGRAM SHOWING THE IMPACT OF CONSEQUENCES................................................................................................................................................... 151
Tables
TABLE 1-1: CAPITAL EXPENDITURE ................................................................................................................................................................................................................. 15
TABLE 2-1: ACT ACORN MILESTONES AND DELIVERABLES .............................................................................................................................................................................. 18
TABLE 3-1: SCOPE SUMMARY ......................................................................................................................................................................................................................... 22
TABLE 4-1: FIRST PRODUCTION AND CESSATION OF PRODUCTION DATES FOR CAPTAIN SANDSTONE FIELDS ....................................................................................................... 25
TABLE 4-2: ACORN CO2 STORAGE SITE AVAILABLE WELL DATA ......................................................................................................................................................................... 28
TABLE 4-3: SUMMARY OF SEISMIC HORIZONS INTERPRETED IN THE ETI SSAP WORK ........................................................................................................................................ 33
TABLE 4-4: SUMMARY OF PRIMARY AND SECONDARY STORAGE FORMATIONS .................................................................................................................................................... 38
TABLE 4-5: FAIRWAY MODEL POROSITY AND PERMEABILITY MODELLING RESULTS .............................................................................................................................................. 40
TABLE 4-6: MODELLED FACIES PROPORTIONS ................................................................................................................................................................................................. 40
TABLE 4-7: GROSS ROCK AND PORE VOLUMES FOR THE CAPTAIN FAIRWAY MODEL ........................................................................................................................................... 40
TABLE 4-8: PVT DEFINITION ........................................................................................................................................................................................................................... 41
TABLE 4-9: CAPTAIN RESERVOIR DATA ............................................................................................................................................................................................................ 43
TABLE 4-10: CAPTAIN FIELD AND WELL DATA ................................................................................................................................................................................................... 44
TABLE 4-11: CAPTAIN IPR INPUT DATA............................................................................................................................................................................................................ 44
TABLE 4-12: INJECTION PRESSURE LIMITS ....................................................................................................................................................................................................... 44
TABLE 4-13: RATES ACHIEVABLE BY CASE FOR MINIMUM AND MAXIMUM TUBING HEAD PRESSURE ....................................................................................................................... 46
TABLE 4-14: ETI SSAP RESERVOIR MODEL PROPERTIES ................................................................................................................................................................................. 57
TABLE 4-15: INITIALISATION DEPTHS AND CORRESPONDING PRESSURES AT CONTACT DEPTHS FOR DIFFERENT MODEL REGIONS .......................................................................... 58
TABLE 4-16: PARAMETERS OF THE FLUID MODEL ............................................................................................................................................................................................. 59
TABLE 4-17: TARGET STORAGE ZONES AND TARGET INJECTION WELLS FOR EACH CO2 SUPPLY SCENARIO .......................................................................................................... 63
TABLE 4-18: RESERVOIR ENGINEERING WELL SUMMARY FOR PHASE 1 AND 2 WELLS ......................................................................................................................................... 64
TABLE 4-19: PHASE 2 INJECTION RATES PER WELL .......................................................................................................................................................................................... 67
D07 Acorn CO2 Storage Site Development Plan Contents
ACT Acorn Consortium Page 11 of 151
TABLE 4-20: DIFFERENT SIMULATIONS MODELLED TO ADDRESS THE PHASE 3 CO2 SUPPLY SCENARIO INJECTED INTO THE CAPTAIN X AREA ONLY ................................................ 71
TABLE 4-21: WELL LOCATIONS FOR PHASE 3 152MT SCENARIO ...................................................................................................................................................................... 73
TABLE 4-22: INDIVIDUAL WELL INJECTION PROFILES TO ACHIEVE THE TARGET 152MT CO2 INJECTION ................................................................................................................ 73
TABLE 4-23: SUMMARY OF 8 CAPTAIN X AREA LEGACY WELLS REVIEWED IN DETAIL ........................................................................................................................................... 88
TABLE 4-24: LIKELIHOOD SCALE USED IN LEAKAGE WORKSHOP ....................................................................................................................................................................... 90
TABLE 4-25: SEVERITY SCALE USED IN THE LEAKAGE WORKSHOP .................................................................................................................................................................... 90
TABLE 4-26: SUMMARY OF CATEGORIES AND GRADES OF CONSEQUENCES ....................................................................................................................................................... 92
TABLE 4-27: OUTLINE CORRECTIVE MEASURES PLAN ....................................................................................................................................................................................... 98
TABLE 6-1: PRELIMINARY WELL LOCATION USED IN WELL DESIGN .................................................................................................................................................................... 102
TABLE 6-2: WELL LOCATION AS DETERMINED FROM DYNAMIC MODELLING ....................................................................................................................................................... 102
TABLE 6-3: OUTLINE WELL CONSTRUCTION PROGRAMME ............................................................................................................................................................................... 105
TABLE 6-4: INJECTION PROFILE ..................................................................................................................................................................................................................... 106
TABLE 6-5: ATLANTIC PIPELINE DESIGN PARAMETERS .................................................................................................................................................................................... 110
TABLE 6-6: MAXIMUM OPERATING PRESSURE UNDER DIFFERENT CO2 SUPPLY SCENARIOS .............................................................................................................................. 114
TABLE 7-1: COST ESTIMATE CLASS DEFINITIONS (AACEI 18R-97) ................................................................................................................................................................ 122
TABLE 7-2: CAPEX ESTIMATE ........................................................................................................................................................................................................................ 124
TABLE 7-3: OPEX ESTIMATE .......................................................................................................................................................................................................................... 124
TABLE 7-4: ABEX ESTIMATE .......................................................................................................................................................................................................................... 125
TABLE 10-1: SEG-Y SURVEY DATUM AND MAP PROJECTIONS ......................................................................................................................................................................... 135
TABLE 10-2: SEG-Y TILES FOR CAPTAIN AQUIFER EVALUATION ..................................................................................................................................................................... 135
TABLE 10-3: SUMMARY OF WELL DATA USED IN THE CAPTAIN AQUIFER EVALUATION ........................................................................................................................................ 139
TABLE 10-4: LIST OF CORE DATA USED IN THE CHARACTERISATION OF THE ACORN CO2 STORAGE SITE ........................................................................................................... 140
TABLE 10-5: SUMMARY OF CATEGORIES AND GRADES OF CONSEQUENCES ..................................................................................................................................................... 142
D07 Acorn CO2 Storage Site Development Plan Executive Summary
ACT Acorn Consortium Page 12 of 151
1.0 Executive Summary
The main objectives of this Acorn CO2 Storage Site storage development plan
were: to build upon the results of previous work and update the development
plan to align with the scalable approach for the Acorn CCS Project.
This Storage Development Plan has been built on the existing work of the
Energy Technologies Institute (ETI) Strategic UK Carbon Capture and Storage
Appraisal Project (ETI SSAP), (Pale Blue Dot Energy & Axis Well Technology,
2016), which accelerated the development of strategically important storage
capacity to meet UK needs.
The work undertaken for the ACT research study has confirmed that the Acorn
CO2 storage site offers a low cost, flexible and scalable development plan
solution for the Acorn CCS Project. This opportunity is created by: -
• Pipeline optionality - Two existing and redundant pipelines, Atlantic
and Goldeneye, both run from St Fergus to the Acorn CO2 storage
site. These can be re-used and offer cost savings over a new build
pipeline. The initial re-use of the Atlantic pipeline is the reference
case for the Acorn CCS Project initialisation.
• Low cost flexible well design - A single dual completion subsea
injection well provides lower capital cost than a platform well and is
designed to handle a range of injection rates, from 0.1MT to 2MT/yr,
meaning it can be used in subsequent phases of the project.
• Scalable storage resource - It has been demonstrated through
careful dynamic modelling of the reservoir that up to 152MT can be
securely stored within the Acorn CO2 storage site storage complex,
providing scalability and additional storage resource beyond the
initial Phase 1 (200kT/yr) of the project.
The Acorn CO2 storage site and corresponding
development plan offers a low cost, flexible and
scalable solution for the Acorn CCS Project.
The storage site can safely contain 152MT (5MT/yr
injection rate) within the proposed storage complex
boundary for a minimum of 1000 years after cessation
of injection and is readily scalable.
Phase 1 development consists of 200kT/yr injected
via one dual completion subsea well, starting in 2023.
The base case for transportation is via the existing
redundant 78km 16” Atlantic pipeline, from St Fergus.
An ambitious programme can achieve Final
Investment Decision in 2020 and first injection in
2023.
A capital investment of £177 million is estimated for
the scalable offshore transport and storage.
D07 Acorn CO2 Storage Site Development Plan Executive Summary
ACT Acorn Consortium Page 13 of 151
The proposed storage complex for the Acorn CO2 storage site covers an area
of 971km2, extending from the west of the Blake oilfield, to the east of the
Goldeneye gas field in the Outer Moray Firth, approximately 80km from St
Fergus. This is illustrated in Figure 1-1 (Pale Blue Dot Energy & Axis Well
Technology, 2016).
Figure 1-1: Location Map of Acorn CO2 storage site complex
The primary storage unit is the Captain Sandstone within the Lower Cretaceous
Cromer Knoll Group. The primary seal is provided by the mudstones within the
Rodby and Carrick Formations, as shown in Figure 1-2 (Pale Blue Dot Energy
& Axis Well Technology, 2016).
Figure 1-2: Primary and secondary containment of the Acorn CO2 storage site
The Captain Sandstone consists of channel dominated turbidite deposits of
generally excellent reservoir quality, with an average porosity of 27% and an
average permeability of 1400mD. The Upper Captain (D) Sandstone is
extensive across the fairway and is separated from the less extensive Lower
Captain (A) Sandstone, by the Mid Captain Shale.
Secure vertical containment is provided by laterally extensive mudstones and
shales of the Rodby and Carrick Formations which are a proven seal for multiple
D07 Acorn CO2 Storage Site Development Plan Executive Summary
ACT Acorn Consortium Page 14 of 151
hydrocarbon fields in the Central North Sea and provides an excellent caprock
for the storage complex.
The seismic interpretation and geological model build work flow that was carried
out in the ETI SSAP study was reviewed, and the dynamic reservoir model
upgraded to account for possible CO2-hydrocarbon behaviour in the depleted
gas fields of Atlantic and Cromary. This “compositional” model was then used
for the ACT Acorn reservoir simulation scenarios. Well injection performance
modelling and well design was carried out specifically for this project.
The dynamic modelling results show that injection into the Captain Sandstone
presents no challenges. However due to high vertical permeability and
connectivity of the Captain Sandstone, the CO2 flow within the reservoir is
expected to be strongly gravity dominated; the lack of permeability baffles to
slow its migration to the top of the Upper Captain Formation suggest that the
CO2 will be highly mobile. This, coupled with the shallow regional dip (1-2o) of
the top of the Captain sandstone means that the ultimate footprint of the plume
is spread out for large injected inventories, which results in low dynamic storage
efficiencies for the site in the order of ~1-2%. Techniques that are common in
the petroleum industry were investigated in an effort to enhance this dynamic
storage efficiency, however the cost effective options proved largely ineffective.
The basis for the development plan for Phase 1 is an assumed CO2 supply of
200kT/yr to be provided from the shore terminal at St. Fergus commencing in
2023. CO2 will be transported offshore in dense-phase via the existing 78km 16”
Atlantic pipeline from St. Fergus, plus an additional flowline to an injection site
in between the Atlantic and Cromarty depleted fields. Phase 1 injection will be
via a single subsea injection well with a dual completion which can provide
injection rates from 0.1kT/yr to 2MT/yr, making it suitable for use during low rate
commissioning and for higher rates during later phases of the project without
further well intervention. Future potential build out scenarios were also modelled,
with rates up to 5MT/yr using additional wells and a storage resource of 152MT
safely contained within the Acorn CO2 storage site storage complex for 1000
years after injection ceases.
Figure 1-3: Acorn CCS Project Schedule
As shown in Figure 1-3, the development schedule has 5 main phases of activity
after this ACT study. Concept, FEED, appraisal and contracting activities will
commence just over 2 years prior to the final investment decision (FID) in 2020.
The capital intensive activities of procurement and construction follow FID (Final
Investment Decision) and take place over a 2.5 year period. First injection is
forecasted to take place in late 2023.
D07 Acorn CO2 Storage Site Development Plan Executive Summary
ACT Acorn Consortium Page 15 of 151
The Phase 1 offshore transportation and injection infrastructure is estimated to
require a capital investment of £177 million. When including the onshore plant
this increases to £276 million. The capital costs are summarised in Table 1-1.
Work area Net
Cost (£M)
Contingency (£M)
Gross Cost (£M)
Offshore
Concept & FEED (including inspection pig)
16.9 1.0 17.9
MMV 9.0 0.1 9.2
Pipeline 16.1 6.0 22.1
Umbilical 60.2 24.1 84.3
Subsea 11.0 4.4 15.4
Well 20.7 6.9 27.6
Total Offshore 133.8 42.5 176.5
Onshore Onshore plant 76.5 23.5 99.9
Full Chain Total Full Chain 210.3 66.0 276.4
Table 1-1: Capital Expenditure
D07 Acorn CO2 Storage Site Development Plan Introduction to ACT Acorn
ACT Acorn Consortium Page 16 of 151
2.0 Introduction to ACT Acorn
2.1 ACT Acorn Overview
ACT Acorn, project 271500, has received funding from BEIS (UK), RCN (NO)
and RVO (NL), and is co-funded by the European Commission under the ERA-
Net instrument of the Horizon 2020 programme. ACT grant number 691712.
ACT Acorn is a collaborative project between seven organisations across
Europe led by Pale Blue Dot Energy in the UK, as shown in Figure 2-1.
Figure 2-1: ACT Acorn consortium partners
The research and innovation study addresses all thematic areas of the ACT Call
including ‘Chain Integration’. The project includes a mix of both technical and
non-technical innovation activities as well as leading edge scientific research.
Together these enable the development of the technical specification for an
ultra-low cost, integrated CCS hub that can be scaled up at marginal cost. It will
move the Acorn development opportunity from proof-of-concept (TRL3) to the
pre-FEED stage (TRL5/6) including iterative engagement with relevant investors
in the private and public sectors.
Specific objectives of the project are to:
Produce a costed technical development plan for a full chain CCS
hub that will capture CO2 emissions from the St Fergus Gas
Terminal in north east Scotland and store the CO2 at an offshore
storage site under the North Sea
Identify technical options to increase the storage efficiency of the
selected storage site based on scientific evidence from
geomechanical experiments and dynamic CO2 flow modelling and
through this drive scientific advancement and innovation in these
areas.
Explore build-out options including interconnections to the nearby
Peterhead Port, other large sources of CO2 emissions in the UK
region and CO2 utilisation plants
Identify other potential locations for CCS hubs around the North Sea
regions and develop policy recommendations to protect relevant
D07 Acorn CO2 Storage Site Development Plan Introduction to ACT Acorn
ACT Acorn Consortium Page 17 of 151
infrastructure from premature decommissioning and for the future
ownership of potential CO2 stores.
Engage with CCS and low carbon economy stakeholders in Europe
and worldwide to disseminate the lessons from the project and
encourage deployment of key learnings.
CCS is an emerging industry. Maturity improvements are required in the
application of technology, the commercial structure of projects, the scope of
each development and the policy framework.
The key areas of innovation in which the project will seek insights are
summarised in Figure 2-2.
Figure 2-2: Key areas of innovation
The project activity has been organised into 6 work packages as illustrated in
Figure 2-3. Specific areas being addressed include; regional CO2 emissions; St
Fergus capture plant concept; CO2 storage site assessments and development
plans; reservoir CO2 flow modelling, geomechanics; CCS policy development;
infrastructure re-use; lifecycle analysis; environmental impact; economic
modelling; FEED and development plans; and build out growth assessment.
The project will be delivered over a 19-month period, concluding on the 28th
February 2019. During that time, it will create and publish 21 items known as
Deliverables. Collectively these will provide a platform for industry, local
partnerships and government to move the project forward in subsequent
phases. It will be driven by business case logic and inform the development of
UK and European policy around infrastructure preservation. The deliverables
are listed in Table 2-1.
Figure 2-3: ACT Acorn work breakdown structure
D07 Acorn CO2 Storage Site Development Plan Introduction to ACT Acorn
ACT Acorn Consortium Page 18 of 151
Milestone Deliverable
1) St Fergus Hub Design
D01 Kick-off Meeting Report
D02 CO2 Supply Options
D17 Feeder 10 Business Case
2) Site Screening & Selection
D03 Basis of Design for St Fergus Facilities
D04 Site Screening Methodology
D05 Site Selection Report
D13 Plan and Budget for FEED
3) Expansion Options D18 Expansion Options
4) Full Chain Business Case
D10 Policy Options Report
D11 Infrastructure Reuse Report
D14 Outline Environmental Impact Assessment
D15 Economic Model and Documentation
D16 Full Chain Development Plan and Budget
5) Geomechanics D06 Geomechanics Report
D07 Acorn Storage Site Storage Development Plan and Budget
6) Storage Development Plans D08 East Mey Storage Site Storage Development Plan and Budget
D09 Eclipse Model Files
7) Lifecycle Assessment D12 Carbon Lifecycle Analysis
8) Project Completion
D21 Societal Acceptance Report
D19 Material for Knowledge Dissemination Events
D20 Publishable Final Summary Report
Table 2-1: ACT Acorn Milestones and Deliverables
D07 Acorn CO2 Storage Site Development Plan Introduction to ACT Acorn
ACT Acorn Consortium Page 19 of 151
The Consortium includes a mix of industrial, scientific and CCS policy experts in
keeping with the multidisciplinary nature of the project. The project is led by Pale
Blue Dot Energy along with University of Aberdeen, University of Edinburgh,
University of Liverpool, Heriot Watt University, Scottish Carbon Capture &
Storage (SCCS), Radboud University and The Bellona Foundation. Pale Blue
Dot Energy affiliate CO2DeepStore are providing certain input material.
2.2 Acorn Development Concept
Many CCS projects have been burdened with achieving “economies of scale”
immediately to be deemed cost effective. This inevitably increases the initial cost
hurdle to achieve a lower lifecycle unit cost (be that £/MWh or £/T) which raises
the bar from the perspectives of initial capital requirement and overall project
risk.
The Acorn development concept uses a Minimum Viable Development (MVD)
approach. This takes the view of designing a full-chain CCS development of
industrial scale (which minimises or eliminates the scale up risk) but at the
lowest capital cost possible, accepting that the unit cost for the initial project may
be high for the first small tranche of sequestered emissions.
Acorn will use the unique combination of legacy circumstances in North East
Scotland to engineer a scalable full-chain carbon capture, transport and offshore
storage project to initiate CCS in the UK. The project is illustrated in Figure 2-4
and seeks to re-purpose an existing gas sweetening plant (or build a new
capture facility if required) with existing offshore pipeline infrastructure
connected to a well understood offshore basin, rich in storage opportunities. All
the components are in place to create an industrial CCS development in North
East Scotland, leading to offshore CO2 storage by the early 2020s.
Figure 2-4: A scalable full-chain industrial CCS project
D07 Acorn CO2 Storage Site Development Plan Introduction to ACT Acorn
ACT Acorn Consortium Page 20 of 151
A successful project will provide the platform and improve confidence for further
low-cost growth and incremental development. This will accelerate CCS
deployment on a commercial basis and will provide a cost effective practical
stepping stone from which to grow a regional cluster and an international CO2
hub.
The seed infrastructure can be developed by adding further CO2 capture points
such as from hydrogen manufacture for transport and heat, future CO2 shipping
through Peterhead Port to and from Europe and connection to UK national
onshore transport infrastructure such as the Feeder 10 pipeline which can bring
additional CO2 from emissions sites in the industrial central belt of Scotland
including the proposed Caledonia Clean Energy Project, CCEP. A build out
scenario for Acorn used in the 2017 Projects of Common Interest (PCI)
application is included as Figure 2-5.
Pale Blue Dot Energy is exploring various ways and partners to develop the
Acorn project.
Figure 2-5: Acorn build out scenario from the 2017 PCI application
D07 Acorn CO2 Storage Site Development Plan Scope and Objectives
ACT Acorn Consortium Page 21 of 151
3.0 Scope and Objectives
3.1 Purpose
The purpose of the ACT Acorn Project Deliverable D07 Acorn CO2 Storage Site
Development Plan (D07) is to document a coherent storage development plan
for the site.
3.2 Scope
The scope of D07 draws heavily on the work from the Strategic UK CO2 Storage
Appraisal Project (ETI SSAP), which accelerated development of strategic
storage resource in UK Continental Shelf and produced Storage Development
Plans (SDPs) for five sites.
One of these five sites was the “Captain X” storage area (Pale Blue Dot Energy
& Axis Well Technology, 2016), which was investigated as a candidate for CO2
storage in the UK Continental Shelf operating alongside the Goldeneye storage
project which, at the time of the ETI project, was being considered in the UK
Government CCS Commercialisation programme.
The Acorn CO2 storage site (see Figure 4-2) is the area considered for the Acorn
CCS Project and this Storage Development Plan. The Captain X storage area
is a sub-area of the Acorn CO2 Storage Site, which extends further east to
include the depleted Goldeneye gas field. The initial stages of development are
focussed near the Atlantic and Cromarty depleted gas fields. Subsequent
phases, to incorporate CO2 from build-out options (Figure 3-1), will likely
incorporate additional injection sites in the broader Acorn CO2 storage site.
Figure 3-1: Acorn CCS Project Phase 1 and build-out options
Whilst the publicly released ETI SSAP work has provided a foundation for the
Acorn CCS Project, additional development plan refinement, option evaluation,
fundamental work and research has been carried out for this ACT Study.
Table 3-1 summarises which parts of the scope include a review of the ETI
SSAP work and which are new. It also highlights which area of the Acorn CO2
storage site the work has been carried out over, e.g. the whole area, or the
smaller Captain X area.
Any assumptions made during this scope of work have been explicitly stated
throughout the text.
D07 Acorn CO2 Storage Site Development Plan Scope and Objectives
ACT Acorn Consortium Page 22 of 151
Scope Item
Geographical Area of Scope Work for Scope Comments
(if applicable) Acorn CO2 Storage Site
Captain X area (initial Phase 1 injection site)
From ETI SSAP
Revised for ACT
Geological setting, reservoir properties, exploration history ✓ ✓ Review of ETI SSAP work
Geophysical interpretation ✓ ✓ Review of ETI SSAP work
Petrophysical interpretation ✓ ✓ Review of ETI SSAP work
Geological model build ✓ ✓ Review of ETI SSAP work
Dynamic model build ✓ ✓ Review of ETI SSAP work – used ETI SSAP Black Oil Eclipse model as
starting point
Dynamic modelling scenarios and storage capacity assessment
✓ ✓ Conversion of black oil Eclipse model to fully compositional model; range of modelling runs from 200kT/yr up to 5MT/yr
Storage complex definition ✓ ✓ Storage complex lateral extent extended from ETI SSAP from west of Blake to east of Goldeneye.
Injectivity performance and well design ✓ ✓ Well design for initial injection well covering range of injection rates
High level review of abandoned wells ✓ ✓ ETI SSAP work used
Leakage scenario workshop ✓ ✓ Workshop held focussing on initial Phase 1 injection site area (Acorn)
Monitoring, measurement & verification plan
✓ ✓ ETI SSAP MMV plan used as basis and modified slightly for Phase 1
Infrastructure requirements, decommissioning
✓ ✓ Revised – subsea injection well plus reuse of existing Atlantic pipeline
Cost estimate, schedule, risk register ✓ ✓ Revised – based on Phase 1
Outline development plan and budget ✓ ✓ Revised – based on Phase 1
Table 3-1: Scope summary
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 23 of 151
4.0 Site Characterisation
4.1 Geological Setting
The pan shaped Captain fairway is an open aquifer system in the UK Central
North Sea (CNS) that stretches for almost 200km from its shallowest part in the
north west, where it has its widest extent and is found to sub-crop at the seabed,
to its deepest extent in the far south east where it exceeds depths of 3660m
(12,000ft). To the east the fairway is a confined corridor representing the “pan
handle”. The fairway has been the subject of significant petroleum activity over
the years and hosts productive fields, Captain, Blake, Cromarty, Atlantic,
Goldeneye and Hannay. The Britannia condensate reservoir in the far east is
also an equivalent of the Captain sandstone. From 2010 to 2015, the Goldeneye
depleted gas field was the location of a proposed CO2 storage development,
initially for the Longannet Power station and then for the Peterhead Power
station (Tucker & Tinios, 2017).
The primary storage unit for the Acorn CO2 storage site is the Captain
Sandstone Member of the Lower Cretaceous Cromer Knoll Group. The Captain
Sandstone Member is an extensive sandy turbidite system, with mass flow
sediments deposited in a long, confined north west to south east fairway.
This proposed development area covers over 971km2, including the Blake oil
field in the northwest, the Atlantic and Cromarty depleted gas fields (blocks
14/26 and 13/30 respectively) and stretches beyond the Goldeneye depleted
gas reservoir in the southeast. These fields all have the Captain Sandstone as
their primary reservoir.
The distribution of the Captain Sandstone in the UK sector of the CNS, and the
fairway model outline is shown in Figure 4-1 (Pale Blue Dot Energy & Axis Well
Technology, 2016).
Figure 4-1: Captain Sandstone fairway
An area referred to as “Captain X” (to avoid confusion with other Captain
sandstone CO2 studies or the Chevron operated Captain oilfield) was studied in
the Energy Technologies Institute’s Strategic UK CO2 Storage Appraisal Project
(ETI SSAP). The Captain X area sits within the broader Acorn CO2 storage site,
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 24 of 151
as shown in Figure 4-2 (modified from ETI SSAP (Pale Blue Dot Energy & Axis
Well Technology, 2016)).
Figure 4-2: Two-way-time map showing outline of Acorn CO2 storage site and Captain X area
4.2 Site History and Database
4.2.1 Geological History
The Acorn CO2 storage site development area comprises an open saline aquifer
system with associated depleted gas fields. The Captain sandstone dips
regionally to the south east at approximately 1 to 2 degrees, with a steep ramp
of up to 20 degrees close to the West Halibut fault at the north western end.
During the Jurassic and Lower Cretaceous, the main structural element in the
area was the east-west trending Halibut Horst. Parts of this remained above sea
level through most of the Jurassic and Lower Cretaceous, contributing
significantly to the deposition of sandy turbidites during the Lower Cretaceous.
The Captain Sand fairway is a 5-10km wide ribbon of sand deposited along the
long southern edge of the Halibut Horst and South Halibut Shelf extending east
across the South Halibut Basin towards the Britannia Field. The sands were
deposited as deep water marine turbidites, controlled by the existing basin
topography, and were triggered in response to a major fall in sea level.
4.2.2 Hydrocarbon Exploration
Within the Central North Sea (CNS) the Captain Sandstone is a prolific
hydrocarbon reservoir with many hydrocarbon fields such as Captain, Blake,
Cromarty, Atlantic, Goldeneye and Hannay. The effective top seal for these is
provided by mudstones of the Carrack (Sola) and Rodby Formations (Pinnock
& Clitheroe, 2003).
The underlying Lower Cretaceous sands of the Punt and Coracle are also
prospective for hydrocarbons, with Punt Sandstone an oil bearing reservoir in
Golden Eagle, Peregrine, Hobby and Solitaire fields nearby.
The deeper Burns and Piper Sandstones of the Upper Jurassic (deeper than the
Lower Cretaceous) are also well documented hydrocarbon reservoirs within the
CNS.
Solitaire is a single well (14/26-8) oilfield in an Upper Jurassic Burns Sandstone
reservoir which lies at 464ft below the top of the Captain Sandstone (235ft below
the Base Captain Sandstone) underneath the Atlantic gas condensate field. First
oil from Solitaire was in 2015, with end of production forecast in 2028 coinciding
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 25 of 151
with the cessation of production (CoP) of the Golden Eagle development to
which it is tied back. Further west, the Upper Jurassic Ross oil field also partially
lies below the Captain Sand fairway. Neither are considered to be hydraulically
connected to the Captain sandstone. In the case of Ross, none of the wells
targeting this deeper interval penetrate the Captain Sandstone as mapped.
The reservoirs of the Cromarty (gas), Blake (oil) and Atlantic (condensate) fields
are part of the Captain Sandstone fairway itself. Both Atlantic and Cromarty are
undergoing decommissioning. First production and expected Cessation of
Production dates are shown in Table 4-1 below.
Field First Production
End of Production
Cessation of Production (CoP)
Blake 2001 (oil) Estimated 2026
Cromarty 2006 (gas) 2009 2011
Atlantic 2006 (oil) 2009 2011
Table 4-1: First production and cessation of production dates for Captain Sandstone fields
The late Jurassic Kimmeridge Clay Formation provides the source rock for the
hydrocarbons, which have migrated into the Cretaceous Captain reservoir from
the West Halibut Basin and Smith Bank Graben, (Pinnock & Clitheroe, 2003).
4.2.3 Previous Studies
Several previous studies have considered the Captain sandstone as a potential
CO2 storage site. This includes the 2015 CO2Multistore joint industry project led
by SCCS which concluded that “stakeholders can have increased confidence
that at least 360 million tonnes of CO2 captured over the coming 35 years could
be permanently injected, at a rate of between 6 and 12 million tonnes per year,
using two injection sites.”, (Shell, The Crown Estate, Scottish Government,
Scottish Enterprise and Vattenfall, 2015).
Whilst it would be possible to engineer a CO2 storage development plan in many
parts of the Captain fairway it was decided to focus upon that part of the “pan
handle” between Blake and Goldeneye, which has pipeline access via existing
redundant pipelines that can be repurposed for CO2 transportation. Whilst the
western “pan” area north of Blake and Captain oil fields represents a large
potential target, it is very shallow, often less than 800m, which is the average
depth below which the CO2 remains in supercritical state. This area also
contains the Captain oilfield which is estimated to continue operations until at
least 2030. Furthermore, the 3D seismic coverage available to this project was
incomplete over the area of the “pan” itself. For these reasons the western “pan”
area was not selected as a potential storage site target.
There have been several CO2 storage studies completed on different aspects of
the Captain Sandstone. These include:
2016 - Strategic UK CO2 Storage Appraisal Project (ETI SSAP). This
project was commissioned and funded by the Energy Technologies
Institute (ETI). ETI SSAP resulted in a portfolio of five storage sites
(which included the Captain X area that sits within the broader Acorn
CO2 storage site) that had potential to mobilise commercial scale CCS
projects in the UK (for power and industry), and prepared storage
development plans and budgets for each of the selected sites (Pale Blue
Dot Energy & Axis Well Technology, 2016).
2015 - Goldeneye FEED with injection planned at Goldeneye via the
Goldeneye platform using CO2 from Peterhead Power station. This
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 26 of 151
project was part of the UK Government’s CCS Commercialisation
Programme (Shell, 2015).
2015 - CO2 Multistore JIP with injection at Sites “A” and “B” (Shell, The
Crown Estate, Scottish Government, Scottish Enterprise and Vattenfall,
2015)/
2012 - Jin, Mackay, Quinn et al with injection sites 1 through 12 (Jin,
Mackay, Quinn, Hitchen, & Akhurst, 2012).
2011 - Goldeneye FEED with injection planned at Goldeneye via the
Goldeneye platform using CO2 from Longannet Power Station. This
project was part of the UK Government’s first CCS Competition
(ScottishPower CCS Consortium, 2010).
4.2.4 Site Database
4.2.4.1 Seismic data
The seismic data used for this study is the PGS Central North Sea MegaSurvey,
(PGS, 2015). Seismic coverage over the Captain Sandstone fairway is nearly
complete apart from data gaps to the south west of Cromarty Field and to the
north west of the Blake Field. The seismic volume is made up of several different
surveys that were merged post stack, (Figure 4-3, adapted from (Pale Blue Dot
Energy & Axis Well Technology, 2016)). The seismic data does not cover the
entire target area, but the interpreted surfaces were interpolated across areas
with no seismic data coverage.
The wavelet extraction identified the seismic data to be SEG normal polarity (i.e.
peak for positive, trough for negative acoustic impedances) and close to zero-
phase.
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 27 of 151
Figure 4-3: Time slice of the PGS MegaSurvey showing seismic coverage and extent of the interpretations in the Acorn CO2 storage site area
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 28 of 151
4.2.4.2 Well data
The well log data used in this project was obtained from the publicly available
CDA database, (www.ukoilandgasdata.com). This database contains data for
the 57 wells crossing the Captain fairway. Of these, 16 wells have the most
suitable data for the geological modelling (i.e. wireline data, Measurement While
Drilling (MWD), and core data) and were used in the Acorn site characterisation,
(Table 4-2). The location of these wells is shown in Figure 4-4 (from (Pale Blue
Dot Energy & Axis Well Technology, 2016)), along with those that were used in
the seismic interpretation. Seven of these wells were cored and their coverage
is extensive for all the Captain sands in these wells. The quality of the data was
good in general and has been reported in detail in the ETI SSAP.
An inventory of well data accessed is included in Annex 1 – Data inventory.
4.2.4.3 Core Data
The core data used in the geomechanical rock strength analysis was carried out
on wells: 14/26-1; 14/26a-6; 14/26a-7, 7A; and 14/26a-8, near the proposed
primary CO2 injection site. The depth intervals chosen for sampling for each
respective well were chosen according to number of parameters, including:
availability of core, depth, occurrence in the oil/water-leg; porosity; and general
lithological variation, as determined from hand specimen observations, gamma
ray and density wireline logs.
Well ID Wireline MWD Core
13/23b- 5 Yes Yes Yes
13/24a- 4 Yes Yes Yes
13/24a- 5 Yes Yes Yes
13/24a- 6 Yes Yes Yes
13/24b- 3 Yes No Yes
13/29b- 6 Yes Yes Yes
13/30 - 3 Yes No Yes
13/30a- 4 Yes Yes Yes
14/26a- 6 Yes Yes Yes
14/26a- 7 Yes Yes Yes
14/26a- 8 Yes Yes Yes
14/28b- 2 No Yes Yes
14/29a- 3 Yes Yes Yes
14/29a- 5 Yes Yes Yes
20/04b- 6 Yes Yes Yes
20/04b- 7 Yes Yes Yes
Table 4-2: Acorn CO2 storage site available well data
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 29 of 151
Figure 4-4: Map of wells available in the Captain fairway, including these used in the interpretation (in red, blue and yellow)
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 30 of 151
4.3 Storage Stratigraphy
A stratigraphic column is shown in Figure 4-5 (Pale Blue Dot Energy & Axis Well
Technology, 2016) and a short description of the key stratigraphy is provided
below.
Upper Jurassic
The Kimmeridge Clay Formation is at the top of the Upper Jurassic, comprising
of marine hemipelagic claystones and shales, which makes it a source rock for
many hydrocarbon fields in the region. Within the Kimmeridge Clay Formation
are local deep water mass flows of the Ettrick and Burns Sand Members
Lower Cretaceous - Cromer Knoll Group
During the Early Cretaceous, deep-water turbidite sands were deposited into a
background of hemipelagic shales and marls that made up the Valhall Formation
(Copestake, et al., 2003). Some of the turbiditic sand units include the Punt,
Coracle and Captain sandstones, and the hemipelagic shales form the top, base
and lateral seal for many of these sand units.
Captain Sandstone Member - The Captain Sandstone is the primary storage
target, consisting of a sand fairway with a north west to south east orientation
and the Halibut Horst to the north. The Captain Sandstone is split into Upper
and Lower Captain Sandstones separated by the mid-Captain shale, with the
Lower Captain Sandstone having a more local deposition than the Upper
Captain Sandstone, which is a thick sand deposited along the length of the
fairway.
The thickness of the full Captain Sandstone unit can be up to 143 m (470 ft)
thick in the centre of the fairway and pinches out to the north and the south. On
average, the thickness of the full unit is 54m (180ft) and the thickness of the mid-
Captain shale (between the upper and lower sands) averages 15m (50ft) thick.
Overlying the Captain Sandstone, but immediately below the Rodby Formation
are the Carrack Formation shales, which provide an additional seal interval.
Figure 4-5: Stratigraphic Column
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 31 of 151
Rodby Formation - The Rodby Formation consists of mudstones, marls and
occasional thin argillaceous limestone beds and is a proven hydrocarbon seal
for many fields in the area, including within the Captain fairway. Across the
Acorn CO2 storage site area, the Top Rodby to Top Captain shale interval has
an average thickness of 90m (300ft) and in the ETI SSAP work it was stated as
being confidently mapped across the Captain Sandstone fairway.
Upper Cretaceous - Chalk Group
Plenus Marl and Hidra Formations – Directly overlying the Rodby Formation and
at the base of the Chalk Group are the Plenus Marl Formation (black anoxic
calcareous mudstones) and Hidra Formation (argillaceous limestones, marls
and mudstones), which are both impermeable. Across the Acorn CO2 storage
site area, the Top Plenus Marl to Top Rodby interval has an average thickness
of 70m (230ft).
Ekofisk, Tor, Hod and Herring Formations – Sitting above the Hidra is a thick
sequence (450-600m; 1500-2000ft) of limestone, which has been deposited as
pelagic chalks and is interbedded with the occasional claystone and marl bed.
Tertiary
Maureen Formation (Montrose Group) - The Maureen Formation is found
regionally within the Central Graben and usually sits above the Chalk Group. It
is comprised predominantly of amalgamated gravity flow sands interbedded with
siltstones and reworked basinal carbonates (chalk).
Lista Formation (Montrose Group) – The Lista Formation and overlying Lista
shale forms the secondary containment for the Acorn CO2 storage site. In this
area, the Lista Formation is made up of grey mudstone deposited in a marine
basin or outer shelf environment, interbedded with sandstones which have been
deposited as submarine gravity flows. In the Outer Moray Firth and Central
Graben these sandstones are assigned to the Mey Sandstone Member, with
local names as the Andrew and Balmoral sandstones.
The Lista Shale is a proven caprock for several Palaeocene fields, the closest
being the Rubie and MacCulloch Fields, (Shell, 2015).
Quaternary - Nordland Group
The thickness of the Nordland Group within the area is over 640m (2100ft) and
is formed of a thick accumulation of undifferentiated mudstones, claystones and
occasionally marls.
4.4 Seismic Characterisation
To validate the static geological model generated for ETI SSAP, (Pale Blue Dot
Energy & Axis Well Technology, 2016), the documentation of the model building
process for the Petrel project generated for the ETI SSAP project was reviewed.
This included a review of the following aspects of seismic characterisation:
• Seismic interpretation of horizons across full storage complex for the
Acorn CO2 storage site.
• Mapping of faults and structures.
• Depth conversion and geological correlation.
The depth conversion for the ETI SSAP project was carried out using the time-
depth relationships found in 12 of the wells. Of these 12, nine (13/24a-4, 13/24a-
6, 13/29b-8, 14/26a-8, 14/26a-9, 14/26b-5, 14-29a-2, 14/29a-5, 20/04b-6) also
contained sonic-logs used in the synthetic seismic trace calibration. The
synthetic seismograms allowed matching the position of different reflections to
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 32 of 151
the main surfaces interpreted in the well log data. An example of this process is
shown in Figure 4-6, (Pale Blue Dot Energy & Axis Well Technology, 2016).
Eight main horizons were interpreted from the seismic data: seabed, top Beauly
Coal, top Chalk, top Plenus Marl Formation, top Rodby Formation, top Captain
Sandstone, Base Captain Sandstone and Base Cretaceous Unconformity
(BCU). The variable and poor seismic response of the top and base Captain
made their interpretation very difficult and prevented the reliable use of auto
tracking methods.
Figure 4-6: Synthetic seismogram from the well 13/24a- 6
4.4.1.1 Seismic horizons
Table 4-3 summarises the events interpreted in the ETI SSAP project that fed
into the ACT Acorn Project. For more detail about these events, see the Captain
X Site Storage Development Plan report, (Pale Blue Dot Energy & Axis Well
Technology, 2016). In the table a peak represents an increase in acoustic
impedance and a trough represents a decrease in acoustic impedance (SEG
normal polarity).
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 33 of 151
Seismic Event Pick Amplitude Comments
Seabed Peak High Acquisition footprint seen in southeast of fairway
Top Beauly Coal Trough High Thickness variation (thicker in the east). Northwest to southeast trending channel incisions observed southeast of the Cromarty field. Outcrops at the seabed to northwest of Blake.
Top Chalk (Top Ekofisk)
Peak High Strong reflector continuous across the Captain Sandstone fairway, with the Halibut Fault offsetting the Top Chalk at the northern edge of the fairway. The Chalk has a rugose nature due to some minor faulting and erosion, which causes it to be variable.
Top Plenus Marl Trough Moderately high Continuous across the Captain sandstone fairway, thickening to the southeast and northwest, and was used as a marker to tie the wells in the ETI SSAP work. The West Halibut fault offsets this formation and it is absent in some areas of the Halibut Horst.
Top Rodby Trough Medium to high Follows similar topography as the Plenus Marl. In the ETI SSAP work, this pick was used to constrain the Captain Sandstone interpretation. Limited well control indicates the Rodby is absent on the Halibut Horst, north of the West Halibut fault.
Top Captain Sandstone
Peak, trough, zero crossing
Variable
The seismic imaging of the reservoir is hindered by a lack of acoustic impedance contrast across the interface between the Rodby/Carrack Shale and the Captain Sandstone, plus the existence of a multiple caused by the overlying Chalk.
Due to the variable nature of the Top Captain seismic response, it was interpreted in the ETI SSAP using the Top Rodby Horizon pick, Top Captain Sandstone well picks, seismic character and Shell’s sand pinch out edge polygon to help guide the interpretation.
Base Captain Sandstone
Mainly peak (can also be trough or zero-crossing)
Variable Challenging to interpret and so a Captain Sandstone depth thickness map (isochore) from the wells was converted to time to give a time thickness map (isochron), which was added to the Top Captain time map to give an approximate Base Captain time map to help guide the interpretation.
Base Cretaceous Unconformity
Trough Moderate to high The Base Cretaceous unconformity is the top of the Kimmeridge Clay formation. The West Halibut and Captain Field Boundary Faults offset it.
Table 4-3: Summary of seismic horizons interpreted in the ETI SSAP work
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 34 of 151
Figure 4-7: Top Captain Sandstone two-way time map and faulting
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 35 of 151
4.4.1.2 Faulting
The east-west trending Captain Fault separates the Captain Sandstone fairway
from the Captain oil field to the north of it, (Figure 4-7). The seismic interpretation
for the ETI SSAP project indicates that the West Halibut Fault appears to extend
this limit to the southeast with the Captain Sandstone fairway lying to south of
the fault in the downthrown hanging wall. Uncertainty exists on whether the
Captain Sandstone extends right to the West Halibut Fault or pinches out before.
This is due to the poor seismic of the Top Captain. Most of this section is
summarised from the Captain X SDP (Pale Blue Dot Energy & Axis Well
Technology, 2016).
Between Blake and Goldeneye there are nine wells on the southern side of the
fault with no Captain Sandstone which confirms that the sandstone is absent
and must pinch-out before reaching this fault. At the Blake oil field, the operator
interprets the Captain to extend to the West Halibut Fault and the fault is likely
to be sealing here, due to the presence of trapped oil. West of the small oil
discovery (Tain - northwest of Blake), the amount of offset on the Captain fault
is seen to decrease and it is likely the Captain Sandstone is juxtaposed against
older Triassic and Jurassic units here which contain sandstones, presenting
increased risk of lateral containment.
Guariguata-Rojas and Underhill (2017) interpreted several west southwest to
east northeast striking normal faults cutting through the Captain Sandstone
saline aquifer in the north western area about 100km from the Acorn Phase 1
injection site. The authors state these could present a risk to any potential CO2
storage in the studied region. As noted in Section 4.2.3, CO2 storage in this north
western region of the Captain Aquifer is unlikely due to the shallow nature of the
Captain Sandstone.
The Captain Sandstone fairway contains several 4-way dip closed and 3-way
dip plus stratigraphic pinch out structures which provide the trapping
mechanisms for four significant Captain Sandstone hydrocarbon accumulations,
Blake, Cromarty, Atlantic and Goldeneye. The West Halibut Fault extends
upwards into the shallow Tertiary section but does not reach the seabed.
Between Atlantic and Tain the Lista (secondary cap-rock) is offset by this fault.
Further to the west it is not clear if the Captain Fault extends to the seabed due
to poor shallow seismic data quality.
Captain Sandstone is not present on the Halibut Horst. Due to the poor seismic
imaging of the Captain Sandstone, faulting may be more significant than
currently identified. However, the Top Rodby is a reliable seismic marker and
this is the top of the primary seal. Top Rodby has potential small-scale features,
running in a north west to south east orientation that could be due to seismic
artefacts or to real faults. These are very minor faults that do not breach the
Rodby/Carrack primary seal or suggest the presence of potential barrier to the
flow of CO2 within the Captain Sandstone, and thus they were not included within
the ETI SSAP Static Model.
The Top Chalk features numerous lineaments mainly orientated north west to
south east. Most of these lineaments appear to be erosional in nature although
some are probably due to faulting. This faulting does not extend far into the
overburden and they do not appear to be connected with the small scale deeper
faulting within the Captain Sandstone and Top Rodby shale. The overburden
model includes the West Halibut Fault, but no faults were included in the ETI
SSAP Captain Sandstone Fairway model.
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 36 of 151
4.4.1.3 Depth conversion method
In the ETI SSAP project, the depth conversion of the interpreted events was
reported as challenging because of rapid lateral velocity changes in the
overburden, particularly related to lithology variations within the Tertiary section
and rugosity of the Top Chalk surface (which is the top of a high velocity interval).
In the ETI SSAP study, each surface was depth converted following different
steps, outlined in Figure 4-8, (Pale Blue Dot Energy & Axis Well Technology,
2016). A single layer depth conversion method was used from Mean Sea Level
(MSL) down to Top Rodby using an average velocity map (Step 1). This is similar
to the method Shell used for their Captain Sandstone fairway depth conversion,
(Shell, 2015). The Top Rodby depth surface was then used as a depth reference
surface and the rest of the layers in Figure 4-8. These were depth converted by
multiplying the different isochrons (time difference surfaces between different
layers) by a constant velocity, obtained from well data from the surrounding
areas.
The steps described fully in (Pale Blue Dot Energy & Axis Well Technology,
2016) are:
• Step 1 - MSL to Top Rodby using single layer depth conversion
• Step 2 - Top Rodby to Top Captain
• Step 3 - Top Captain to Base Captain
• Step 4 - Top Rodby to Base Cretaceous Unconformity
• Step 5 - Seabed
• Step 6 - Seabed to Top Beauly Coal
• Step 7 - MSL to Top Chalk
• Step 8 - Top Plenus Marl
The sensitivity of the depth conversion method was tested by manual
modification of the Top Captain depth surface, which was then used as a
sensitivity test within the dynamic reservoir modelling work. Here, whilst
absolute depth control is only significant for well placement, the detailed shape
of the Top Captain Sandstone surface was found to be a key control on the
lateral migration of the injected CO2 plume. An awareness of the seismic
uncertainty in the definition of this surface must be maintained throughout
development planning.
Figure 4-8: Depth conversion summary
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 37 of 151
4.5 Geological Characterisation
To validate the static geological model generated for ETI SSAP (Pale Blue Dot
Energy & Axis Well Technology, 2016), the model-building process was
reviewed. The geological characterisation carried out for the ETI SSAP included:
• Formation evaluation from logs.
• Static model build (geocellular).
The assumptions made during the ETI SSAP project have been reviewed and
considered. Overall the methodology followed is robust, representing good
practice and the results arising from the work are generally applicable and
relevant to the Acorn CCS Project.
4.5.1 Formation Evaluation
The formation evaluation process in the ETI SSAP project involved the use of
wireline logs and core data extracted from the CDA database. The petrophysics
study used as a reference a previous report for the Blake Field (Colley, 1999)
for five wells within the Captain fairway. This information was used to check the
validity of the results of the study by comparing them to the results in the report.
A summary of the petrophysical workflow used is shown in Figure 4-9. The
results were used to build the static model, (Pale Blue Dot Energy & Axis Well
Technology, 2016).
A summary of the primary store, primary caprock, secondary store and
secondary caprock formations is described in Table 4-4.
Figure 4-9: Petrophysical workflow
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 38 of 151
Subsurface Unit Aspect Summary
Primary store: Captain Sandstone Member (Cromer Knoll Group)
Depositional model
Sand rich deep water marine turbidite system deposited as a 5-10km wide ribbon of sand along the southern edge of the Halibut Horst.
Excellent rock quality: net to gross ratio >75%; average porosity of 25% (max 30%); average permeability of 1400mD, often >2000mD.
4 lithostratigraphic zones: A, C, D, E (bottom to top). Captain A: massive medium grained sandstone, present at the site location; Captain C: heterogeneous with mudstone and shale, but not full sealing anticipated at the site; Captain D: main reservoir unit for the hydrocarbon fields in the Captain Sand Fairway; massive sandstone laterally extensive.
Reservoir Connectivity
No significant lateral baffles or barriers along the fairway which might result in compartmentalisation.
Geomechanics No significant issues related to drilling risk, fracturing risk or sand failure risk detected.
Geochemistry Injection of CO2 into the Captain X area is not expected to lead to any significant risk of loss of strength or significant change in reservoir quality.
Primary caprock
(Carrick and Rodby Fms., and Chalk Group)
Depositional model 90m shale from Top Captain to Top Rodby.
Secondary seal from shales and mudstones of the Valhall and Carrack Formations.
Rock and fluid properties
Core data available. Effective seals in nearby hydrocarbon fields.
Geomechanics
No significant issues related to drilling risk, fracturing risk or sand failure risk were found during the ETI SSAP work.
The ACT Acorn rock laboratory testing (Section 4.7.1.4) concluded that the Captain Sandstone is very friable and poorly cemented and so fracturing will likely be accompanied by extensive disaggregation of the wellbore. Disaggregation may hamper injection and so keeping fluid injection pressures below the fracture gradient will be a requirement.
Geochemistry The calcareous, clay rich Rodby Formation and equivalent caprocks are unlikely to be affected in a way that increases permeability. Rodby Formation seal failure is, therefore, unlikely to be induced by mineral reactions with the CO2.
Secondary store (Maureen and Mey Fms.)
Reservoir and seal geology
Palaeocene sandstones have excellent reservoir quality and good regional connectivity; porosities up to 35% and Darcy permeabilities.
Lista Formation provides the secondary seal; 30m thickness.
Rock and fluid properties
Full characterisation required.
Table 4-4: Summary of primary and secondary storage formations
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 39 of 151
4.5.2 Static Modelling
As part of the site characterisation works in the ETI SSAP project, three static
models were generated:
Fairway model - Semi-regional model covering over 800km2 across
the Captain Fairway, used to select the final site and understand the
connectivity to the nearby hydrocarbon fields. It includes from Top
Rodby to Base Captain formations, and the Halibut Horst fault, in a
grid of 16.1 million cells. The upscaled version of this Fairway model
was used in the dynamic reservoir simulations for the Acorn CO2
Storage Site.
Injection Site model - Reduced section from the Fairway model,
used as basis for building the reservoir simulation models in the ETI
SSAP project.
Overburden model - Used to describe the overburden geology up
to the seafloor and determine containment risk issues.
The Fairway model included:
• The static modelling of porosity (using the available interpreted PHIE
log) and permeability (using the available core data and correlated
to the modelled porosity) modelling for the Captain Sandstone zones
(Captain A, C, D & E). Modelling results are summarised in Table 4-5
(Pale Blue Dot Energy & Axis Well Technology, 2016). The average
modelled porosity within the main Captain D sand is 27%, the same
as the average from well logs for the Captain D. The average
modelled within the Captain A is 24%. The assumed porosity of the
caprock is zero. In the core data within the reservoir, permeability
shows strong positive correlation with the porosity. Whilst the vertical
permeability is less than the horizontal, no barriers to vertical flow
are anticipated within the Captain D interval. The deeper Captain A
sand is separated from the Captain D sand by the shaley Captain C
interval. This creates a significant internal pressure baffle, but even
the Captain A sands have been depleted by production in the
Captain D sands to some degree.
• Facies logs were calculated using Vshale, Density and Sonic logs
for the 16 representative wells, plus Vshale calculation in an extra
16 wells. The facies logs from the 32 wells were used to control the
facies modelling. Facies modelling was then performed in all Captain
zones using the Sequential Indicator Simulation (SIS) across the
entire area, and using the sand, shale and cement proportions
resulting from the well data. Net to gross trend maps derived from
well data were used to control the lateral proportion of sand/shales.
The available well data indicate that the edges of the Captain
Sandstone fairway can sometimes have reduced net to gross, but
this has little to no impact in the capacity or containment due to the
small thickness of these areas. Results from the facies modelling are
summarised in Table 4-6, (Pale Blue Dot Energy & Axis Well
Technology, 2016).
• The bulk rock and pore volumes of the different zones were
calculated as part of the static modelling Table 4-7, (Pale Blue Dot
Energy & Axis Well Technology, 2016).
The poor seismic imaging of the Top and Base Captain Sandstone horizons
adds substantial uncertainty to the models, especially in areas with little or
absent well control, but the results are in line with other experiences, in particular
regarding the hydrocarbon activities in the region.
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 40 of 151
Zone Average
porosity (%) Average horizontal permeability (mD)
Average vertical permeability (mD)
E 21.9 274 219
D 26.6 1753 1402
C 21.4 634 507
A 24.1 704 563
Table 4-5: Fairway model porosity and permeability modelling results
Zone Sand (%) Shale (%) Cement (%)
E 52.8 42.8 4.4
D 82.4 15.9 1.7
C 28 68.18 3.83
A 76.8 18.5 4.7
Table 4-6: Modelled facies proportions
Zone Bulk volume (x 106 m3) Pore volume (x 106 m3)
E 2,081 295
D 24,458 5,935
C 12,204 2,527
A 38,743 8,757
Table 4-7: Gross rock and pore volumes for the Captain Fairway model
4.6 Injection Performance Characterisation
Phase 1 of the Acorn CCS Project will inject approximately 200kT of CO2 per
year over 15 years reaching a total amount of injected CO2 of 4.2MT. The rate
of CO2 modelled in the injection performance characterisation is that which is
currently available at the St Fergus site and ramps up from 200kT/yr for the first
three years, to 281kT/yr thereafter. This CO2 will be used to kick-start the project
as a scalable development.
Additionally, the Acorn CCS Project will seek opportunities to store additional
CO2 as part of a broader regional decarbonisation plan. This will increase the
injection rate and the overall scale of the storage project once Phase 1 has
commenced. Additional CO2 storage beyond the 200kT/yr is referred to as
Phase 2 and 3. The three phases and their dynamic modelling cases are
summarised below and discussed in Section 4.6.5:
• Phase 1 – Minimum Viable Development Case (Scenario 1):
~200kT/yr from part of the current St Fergus emissions, injected via
one subsea injection to an injection site in between the Atlantic and
Cromarty depleted fields, starting in 2023.
• Phase 2 – 64MT Case (Scenario 2): Emissions include those in the
Scenario 1, plus those from a potential build-out scenario, including
CO2 captured from hydrogen generation and importation of CO2 via
Peterhead Harbour (from shipping), with a maximum injection of
2.7MT/yr.
• Phase 3 – 152MT Case (Scenario 3): A supply rate capped at
5MT/yr (259mmscfd) via four injection wells at several injection sites,
including one near the Goldeneye depleted gas field, and brine
production for pressure management. Emissions include those in the
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 41 of 151
Base Case, plus those from a potential build-out scenario, including
CO2 captured from hydrogen generation, importation of CO2 via
Peterhead Harbour (from shipping) and importation of Grangemouth
emissions via the Feeder 10 pipeline to St Fergus.
This chapter describes the well performance modelling for Phase 1 (well design
for subsequent phases will be determined later) and the well placement strategy
and dynamic modelling for Phases 1, 2 and 3.
4.6.1 Well Performance Modelling
The purpose of well performance modelling is three-fold:
to select a suitable injection tubing size;
to evaluate some of the factors that may limit injection performance;
and
to compare this performance with injection targets.
The results from well performance modelling feeds in to the reservoir
engineering in the form of “lift curves”, which are then used to define well
performance in the reservoir simulation models.
The well engineering aspects of the Acorn CO2 Storage Site were delivered by
Axis Well Technology, (Axis Well Technology, 2017).
4.6.1.1 Methodology
Well modelling was carried out using Petroleum Experts’ Prosper software. At
this early stage full details of the planned well and its anticipated trajectory were
not yet available and so modelling assumptions were made, which are
summarised in the sections below. They are based on a previous study
conducted on the Captain X area and are subject to change as the Acorn CCS
Project proceeds. Flow rates from 0.1 to 2MT/yr were modelled for a single
subsea injection well.
4.6.1.2 PVT
In line with Petroleum Experts’ recommendations, the Pressure, Volume and
Temperature (PVT) in Prosper was modelled using the Equation of State option
with Peng Robinson as the equation of state. The CO2 density correction
implemented by Petroleum Experts was enabled for modelling CO2 injection.
The injection fluid was modelled as 100% CO2 in compliance with project CO2
composition limits. The PVT description used is shown in Table 4-8 below, (Axis
Well Technology, 2017).
Property Units Value
Critical Temperature °C 30.98
Critical Pressure bara 73.77
Critical Volume m3/kg.mole 0.0939
Acentric Factor (-) 0.239
Molecular Weight (-) 44.01
Specific Gravity (-) 1.53
Boiling Point °C -78.45
Table 4-8: PVT definition
CO2 physical properties that strongly affect tubing flow and hence transport are
density (ρ) and viscosity (μ). To test the validity of the Prosper PVT model,
predicted in-situ CO2 densities and viscosities were compared with pure-
component CO2 properties which were calculated using the thermophysical
properties of Fluid Systems from the National Institute of Standards and
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 42 of 151
Technology ((NIST), 2018). Comparisons were carried out for a range of
temperatures (4-100°C) and pressures (5-450bara) with the following results:
• Density differs from the NIST calculated value by a maximum of
1.1% with an average of 0.3%.
• Viscosity differs from the NIST calculated value by a maximum of
14.3% with an average of 7.3%.
These results were considered adequate for the purposes of this study.
4.6.1.3 CO2 impurity sensitivity
The well and tubing design work assumed that the CO2 will be contaminant free.
In practice, however, a small amount of other gases may be present in the
injection gas. The main effect of this is that the phase envelope, which simplifies
to a line in the case of pure CO2, has a two-phase region and so the minimum
injection pressure required to ensure a single-phase liquid injection has to be
increased (Figure 4-10). For small amounts of impurities this shift is minor, but
in order to simulate the effect of possible contamination a 10% safety region has
been defined around the pure CO2 phase envelope and this region has been
avoided during the well design work.
A further effect of the presence of contaminants is that the fluid viscosity and
density will change, which influences the flow behaviour. However, this should
be minor for insignificant contaminant content.
Figure 4-10: Effect of impurities on the phase envelope
4.6.1.4 Wellhead and downhole equipment
The subsea well head has been assumed to be located on the seabed, with
water depth assumed to be 115m. To evaluate a suitable tubing size for the
subsea well, a set of sensitivity cases on downhole equipment were defined.
4.6.1.5 Wellbore trajectory
The detailed wellbore trajectory plan for the subsea well had not been finalised
at the time of wellbore modelling and so a synthetic trajectory was constructed
as follows:
• The well was assumed to be vertical between the sea bed and 600m
above the top of the Captain Sandstone, assumed to be at 2015m
TVDSS.
• The well was then kicked off to 60 degrees through the reservoir at
a build rate of 3 degrees per 30m.
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 43 of 151
4.6.1.6 Temperature model
The Prosper software offers three heat transfer models: rough approximation,
improved approximation and enthalpy balance.
The rough approximation model estimates heat transfer and hence fluid
temperatures from background temperature information, an overall heat transfer
coefficient and user-supplied values for the average heat capacity (Cp value) for
oil, gas and water. In an application in which accurate temperature prediction is
required, this model is considered too inaccurate, especially since it neglects
Joule-Thomson effects, which can be essential in predicting the behaviour of a
CO2 injector. As such this model was not considered.
The full enthalpy balance model performs more rigorous heat transfer
calculations (including capturing Joule-Thomson effects) and estimates the heat
transfer coefficients as a function of depth from a full specification of drilling
information, completion details and lithology. However, at the current stage in
the design cycle many of the input parameters are still unknown e.g. mud
densities.
For this reason, the improved approximation model was chosen for this work.
The sole difference between this model and the full enthalpy balance model is
that the user supplies reasonable values for the heat transfer coefficient rather
than having them estimated from the completion information and lithology. In
line with Petroleum Experts recommendations, a uniform heat transfer
coefficient of 3BTU/h/ft2/F (17.04W/m2/K) was chosen.
For the modelling, a seabed temperature of 6°C was assumed and the required
background temperature gradient was defined as 6°C at the seabed and
reservoir temperature at top perforation depth.
Since it is anticipated that CO2 is delivered to the wellhead through a long (78km)
delivery pipeline, the temperature of the injection fluid at the wellhead was
assumed to be at the seabed temperature. Little to no seasonal variation is
expected at this water depth and latitude in the North Sea.
4.6.1.7 Reservoir data and Inflow Performance Relationship (IPR)
Reservoir and field parameters were taken from the ETI SSAP study. The inflow
performance relationship (IPR) modelling was based on estimates which are
summarised in Table 4-9 and Table 4-10, (Axis Well Technology, 2017).
Parameter Unit Low Best Estimate High
Formation Top Depth - Datum
mTVDSS (ft TVDSS)
2015 (-6611)
Formation Gross Thickness
m (ft) 18
(60) 21 (70) 26 (85)
Reservoir Pressure at Datum
bara (psia) 206 (2984)
Reservoir Temperature at Datum
°C (°F) 69 (157)
Permeability mD 700 1350 2500
Permeability Anisotropy (Kv/Kh)
- 0.4 0.65 0.9
Formation Water Salinity
ppm 56,600
Table 4-9: Captain reservoir data
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 44 of 151
Parameter Unit Low Best
Estimate High
Water Depth m (ft) 115 (377)
Pressure Gradient bar/m (psi /ft)
0.102
(0.451)
Geothermal Gradient °C/100m (°F/100ft)
3.4 (1.87)
Table 4-10: Captain field and well data
Using these data from the previous tables, three IPR models were defined in
Prosper to represent high, medium and low reservoir performance. These
models are summarised in Table 4-11 below, (Axis Well Technology, 2017).
Parameter Unit Low Medium High
IPR Model n/a Jones
Permeability mD 700 1350 2500
Reservoir Thickness
ft 60 70 85
Drainage Area acres 1213
Dietz Shape Factor (-) 31.6
Perforation Interval ft 60 70 85
Skin (-) 20 10 0
Table 4-11: Captain IPR input data
4.6.1.8 Tubing selection
Injection Limits
Pressure and temperature limits on injection operations have been defined and
have been summarised in Table 4-12 below (Axis Well Technology, 2017).
Parameter Unit Value
Fracture Limit at Top Perforation Depth bara (psia) 283 (4105)
Minimum Fluid Temperature at Perforation Depth °C 0
Maximum Pipeline Delivery Pressure at Wellhead bara (psia) 160 (2321)
Table 4-12: Injection pressure limits
It should be noted that:
• The fracture limit at top perforation depth has been derived using a
fracture gradient of 0.16bar/m (0.69psi/ft) and a top perforation depth
of 2015m (6611ft) TVDSS. An uncertainty factor of 0.9 was applied
to the calculated fracture pressure.
• The minimum fluid temperature at perforation depth exists to prevent
formation water from freezing during injection.
Sensitivity Cases
The sensitivity cases considered are summarised in Table 4-13 below. The
injection temperature at the well head is 6°C for all cases. The high, medium
and low reservoir cases are as described in the section above.
Single and dual completions were considered for the Phase 1 well. Note, that a
95/8‘’ casing was assumed and a dual 4½‘’ completion is incompatible with this
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 45 of 151
choice and was therefore not considered. For dual completions it was assumed
that only a single string was open for the low-pressure injection case; for the
high-pressure injection case both strings were considered open.
The minimum tubing head pressure (THP) (44.5bara) is the minimum pressure
required to ensure single phase liquid injection throughout the tubing. The
maximum tubing head pressure (160bara) represents the maximum pipeline
delivery pressure. Not all tubing choices can achieve injection at the lower
injection pressure. Where this is the case the minimum pressure for injection
has been calculated.
Table 4-13 summarises the rates achievable for the various sensitivity cases
and Figure 4-11 provides a graphical representation of the data in the table.
Prosper uses volumetric flow rates and the conversion to mass flowrate is based
on a density of 1.87kg/m3 at standard conditions. The calculated figure is
highlighted in red where the minimum tubing head pressure needed to be raised
to achieve injection.
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 46 of 151
Case Reservoir Case Completion Tubing Size Max and Min THP (bara) Rate (MMscf/d) Rate (MMte/yr)
1 High Single 4½’’ (12.6 ppf) 44.5 25.9 0.50
160 125.4 2.43
2 Medium Single 4½’’ (12.6 ppf) 44.5 23.1 0.45
160 123 2.38
3 Low Single 4½’’ (12.6 ppf) 44.5 14.2 0.27
160 115.9 2.24
4 High Single 3½’’ (9.2 ppf) 44.5 9.6 0.19
160 60.8 1.18
5 Medium Single 3½’’ (9.2 ppf) 44.5 7.6 0.15
160 60.3 1.17
6 Low Single 3½’’ (9.2 ppf) 45.3 7.5 0.14
160 58.7 1.14
7 High Single 27/8’’ (6.5 ppf) 45.75 4.7 0.09
160 35.6 0.69
8 Medium Single 27/8’’ (6.5 ppf) 45.95 5 0.10
160 35.4 0.69
9 Low Single 27/8’’ (6.5 ppf) 46.5 5 0.10
160 34.8 0.67
10 High Dual 2 * 3½’’ (9.2 ppf) 44.5 9.6 0.19
160 120.8 2.34
11 Medium Dual 2 * 3½’’ (9.2 ppf) 44.5 7.6 0.15
160 118.6 2.30
12 Low Dual 2 * 3½’’ (9.2 ppf) 45.3 7.5 0.14
160 112.3 2.17
13 High Dual 2 * 27/8’’ (6.5 ppf) 45.75 4.7 0.09
160 71.4 1.38
14 Medium Dual 2 * 27/8’’ (6.5 ppf) 45.95 5 0.10
160 70.5 1.36
15 Low Dual 2 * 27/8’’ (6.5 ppf) 46.5 5 0.10
160 68 1.32
Table 4-13: Rates achievable by case for minimum and maximum tubing head pressure
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 47 of 151
Figure 4-11: Rates achievable by case for minimum and maximum tubing head pressure
Figure 4-12 to Figure 4-14 show the pressure and temperature behaviour along
the tubing, plotted as pressure versus temperature for relevant tubing sizes and
well head injection pressures. The graphs also show the phase boundary with
an upper and lower safety limit and the various pressure and temperature limits.
Figure 4-15 shows a pressure and temperature versus depth profile for a typical
injection case.
Figure 4-12: Pressure / temperature profiles – 4½’’ tubing – min/max tubing head pressure
Figure 4-13: Pressure / temperature profiles – 27/8’’ tubing – min/max tubing head pressure
0
0.5
1
1.5
2
2.5
3
Case 1 Case 2 Case 3 Case 4 Case 5 Case 6 Case 7 Case 8 Case 9 Case 10 Case 11 Case 12 Case 13 Case 14 Case 15
Ra
te (
MM
te/y
r)
Injection Rates Achievable
0
50
100
150
200
250
300
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42
Pre
ssu
re (b
ara)
Temperature (deg C)
Pressure / Temperature Gradients
Case 1a
Case 2a
Case 3a
Case 1b
Case 2b
Case 3b
Phase Envelope
Phase Envlope Upper
Phase Envelope Lower
Fracture Pressure Limit
THP Limit
0
50
100
150
200
250
300
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44
Pre
ssu
re (b
ara)
Temperature (deg C)
Pressure / Temperature Gradients
Case 7a
Case 8a
Case 9a
Case 7b
Case 8b
Case 9b
Phase Envelope
Phase Envlope Upper
Phase Envelope Lower
Fracture Pressure Limit
THP Limit
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 48 of 151
Figure 4-14: Pressure / temperature profiles – dual 27/8’’’tubing – min/max tubing head pressure
Figure 4-15: Case 11b (maximum THP) – pressure and temperature v depth plot
The results shown in Table 4-13 and Figure 4-12 to Figure 4-15 can be
summarised as follows:
• Achieving injection rates ranging from 0.1MT/yr to 2.0MT/yr over
injection field life with a single completion design will be challenging.
In the modelling, only the dual 3 ½’’ and the 4 ½’’ tubing can achieve
a target rate of 2MT/yr under initial reservoir conditions. However,
neither provide an option for the low range of 0.1MT/yr.
• Note that it is not currently possible to model dual completions
explicitly in Prosper. A workaround is provided, which relies on the
user specifying a single string and then providing a multiplier for that
string that defines the fraction of total flow going through it. Prosper
then grosses up this flow contribution to total flow for all remaining
calculations, (e.g. the IPR calculations). For a dual completion
consisting of two identical tubing strings the multiplier is easy to
define as 0.5. For mixed dual completions this is more complex and
Petroleum Expert's GAP software, in which dual completions can be
defined and evaluated rigorously, should be used. It is hence
recommended that a full evaluation of a dual completion is
performed in GAP.
• Though not explicitly modelled, a dual completion consisting of a
27/8’’ tubing string and a 4½’’ does appear to achieve the target
injection range. The combined injection rate will be less than the sum
of the two individual strings (3.06MT/yr), but will easily achieve the
target 2MT/yr.
• Note that a dual completion consisting of a 27/8’’ and a 4½’’ tubing
string is not commonly run and will provide challenges for well design
(potentially requiring an increase in casing size from 95/8’’to 10¾”
0
50
100
150
200
250
300
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44
Pre
ssu
re (b
ara)
Temperature (deg C)
Pressure / Temperature Gradients
Case 13a
Case 14a
Case 15a
Case 13b
Case 14b
Case 15b
Phase Envelope
Phase Envlope Upper
Phase Envelope Lower
Fracture Pressure Limit
THP Limit
0.0 5.0 10.0 15.0 20.0 25.0 30.0 35.0 40.0 45.0 50.0
0
1000
2000
3000
4000
5000
6000
7000
8000
0
1000
2000
3000
4000
5000
6000
7000
8000
0.0 50.0 100.0 150.0 200.0 250.0
Temperature (deg C)
Me
asu
red
De
pth
(ft
)
Pressure (bara)
Case 11b (Rate = 118.6 MMscf/d)
Pressure
Temperature
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 49 of 151
and modifications to existing subsea tree designs) but is considered
technically achievable.
• Beyond the inability to achieve the extended target range of injection
rates in most cases none of the tubing options considered violate
any of the restrictions specified, including:
o Temperature limits: a fluid temperature of 0°C is not reached
by any of the scenarios considered.
o Fracture Limits: this limit is not reached by any of the cases
considered.
o Phase changes to the gas phase are avoided (though the
fluid may be supercritical at the injection point for some low
rate cases, which is not considered an issue).
Based on the results of the modelling, a well with a dual tubing of 27/8’’ and 4½’’,
with a 95/8’’ casing (although noting that this may potentially require an increase
in casing size to 10¾”) has been proposed for Phase 1 of the Acorn CCS Project.
The Phase 1 well design will be based on 95/8’’ casing for the purposes of this
study and investigated further during the next phase of work. Well design for
subsequent phases will be undertaken at the appropriate time and will likely be
for a single bore design.
4.6.1.9 Vertical lift performance curve generation
Vertical lift performance (VLP) curves were generated for three different
completion options:
• 27/8’’ tubing string
• 3½’’ tubing string
• 4½’’ tubing string
A well with a dual tubing of 27/8’’ and 4½’’ has been proposed for Phase 1 of the
Acorn CCS Project. Hence, results of the 3½’’ tubing string modelling are not
presented here. To allow sensitivities to injection pressure limits and other
quantities to be run in Eclipse without extrapolation, the curves were generated
for pressures and rates that were adjusted to Eclipse requirements.
Input parameters were as follows:
For the 27/8’’ single string:
• Tubing Head Pressures: 44.5bara (645psia) to 172.4bara (2500psia)
in 10 steps
• Gas Rates: 2.5MMscf/d to 50MMscf/d in 20 steps
For the 4½’’ single string:
• Tubing Head Pressures: 44.5bara (645psia) to 172.4bara (2500psia)
in 10 steps
• Gas Rates: 2.5MMscf/d to 180MMscf/d in 20 steps
The performance envelopes of the well are shown in Figure 4-16 and Figure
4-17. It was ensured that, for all points shown on the curves, dense phase
injection was maintained throughout the tubing and that the temperature limit of
0°C was not reached.
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 50 of 151
Figure 4-16: Performance envelope - 27/8’’ single tubing string
Figure 4-17: Performance envelope - 4½’’ single tubing stringInjectivity and Near Wellbore Issues
The effects of long term CO2 injection into a sandstone reservoir are not yet fully
defined. Despite some experience of the process gained in the industry, the
reservoir, injection profiles and development scenarios are different for each
CO2 storage site. The reservoir rock is subject to pressure and thermally induced
stresses, applied in sometimes random patterns (cyclic stressing from variations
in supply conditions). These stresses can lead to rock failure or damage to the
rock fabric and therefore permeability changes. Interaction of CO2 with in-place
reservoir rock and fluids may also alter the ability of the rock to conduct fluids.
Some of the more recognised issues are discussed below, along with their effect
on the storage potential of the Acorn CO2 storage site.
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 51 of 151
4.6.1.10 Halite
When CO2 is injected into formations containing saline brine, most of the brine
will be pushed away from the wellbore by the injected CO2. However, some brine
will remain in pores and adhering to rock matrix. As CO2 and water are miscible,
CO2 will absorb the water. However, the salt in the brine is not soluble in CO2,
thus precipitating the salt out of solution as halite. In other words, the near
wellbore is dehydrated (water removed), leaving the salts behind. If all the water
is removed, the total insoluble (in CO2) content of the brine will be deposited.
The volume of solid salt crystals produced depends on brine salinity, residual
brine volume (left after the ‘sweep’’ of CO2), interactions at the CO2 flood front
and the propensity of the brine to re-saturate the near wellbore during shut-in
periods. Capillary pressure also plays a part in re-saturation but is likely to be
masked by CO2 buoyancy effects (CO2 rising in the fluid column, allowing brine
to recharge from below). As the re-saturation will depend on the number and
length of shut-ins, predictions of actual salt precipitation volumes are not
possible at this stage.
However, on the assumption from the ETI SSAP study that the Captain brine is
relatively low salinity (56,600ppm – see Captain X Storage Development Plan
Section 3.6.3.5 for a discussion about this number, (Pale Blue Dot Energy &
Axis Well Technology, 2016), there is a possibility that near wellbore
permeability will remain unchanged by dehydration, or possibly enhanced. With
connate water saturations assumed to be approximately 30% in the Captain,
removal of this water will significantly increase the pore volume of the rock in the
near wellbore region. Even if all halite (salt) was precipitated, less than 2% of
the pore volume would be occupied with halite.
Halite will only become an issue if the halite crystals are mobilised and form
bridges / plugs in the matrix rock pore throats. Given the large injection area
(sand face) planned in the Captain wells, fluid velocity through the matrix will be
low and mobilisation may not occur. Alternatively, if the halite concentration is
small and the crystals are small with respect to pore throat size, salt crystals
may be mobilised away from the wellbore and deposited in low velocity zones.
At a distance from the wellbore they no longer pose a significant risk to injectivity
(diffusion effect).
Considerable uncertainty remains surrounding the actual halite risk to injectivity
in a low saline system such as Captain, although lessons could be learned from
Equinor’s Snøhvit project. Injectivity in Snøhvit was lower than expected, with
pressure building up earlier. Salt precipitation was suspected, and lab tests
appeared to support this. However, the effect was determined to be relatively
minor in horizontal cores, with a conclusion that limited reservoir heterogeneities
and limited volume were the primary culprits, although halite and pore filling fines
may result in some injection efficiency reductions. Salinity at Snøhvit is more
than twice as high as Captain, at ~ 168,000ppm (Pham, Maast, Hellevang, &
Aagaard, 2011), and permeability was an order of magnitude lower.
The effect of halite precipitation can be mitigated by ‘washing’ the near wellbore
with fresh water. The wash water dissolves the salt and carries it away from the
near wellbore region, where the effects of permeability reduction have most
impact. However, as the halite risk for Captain is currently considered to be low,
the addition of wash water facilities for these operations is not considered
practicable for the subsea well. A residual risk therefore remains.
4.6.1.11 Thermal fracturing
The CO2 stream injected into the Captain formation is colder (less than 20oC
depending on input assumptions) than the modelled ambient reservoir
temperature (52 to 87oC, with a best estimate of 62oC). This reduction in
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 52 of 151
temperature is limited to a region close to the wellbore. A drop in temperature
will influence the near wellbore stresses and will make rock more liable to
fracture (tensile failure). The effect this has on the fracture pressure has not
been investigated in this study. However, as the magnitude of temperature drop
is low and restricted in extent, it is not expected to be problematic in the Captain
Sandstone.
The applied safety margin (10%) on fracture pressure and a stand-off from
injection point to cap rock will provide some security with respect to cap rock
fracturing and containment issues. Furthermore, the effect of increasing fracture
pressure with increased pore pressure (pore pressure increases throughout the
injection period) has not been taken into consideration when defining fracture
limits and this is likely to have a countering effect to the potential for thermal
effects on fracture pressure. It is recommended that these issues be reconciled
in the next development stage.
4.6.1.12 Sand failure
As with water injection wells, there is a potential for sand failure in CO2 injection
wells. The principal causes of this are similar:
• Flow back (unlikely to occur in CO2 injection wells without some form
of pre-flow pad);
• Hammer effects during shut-in;
• Downhole crossflow during shut-in (from and to formation zones with
different charging profiles);
• Well to well crossflow during shut-in (if individual wells are charged
to different pressures and surface valves are left open, allowing
cross-flow via the injection manifold).
The effects of sand failure are that near wellbore injectivity can be reduced
(failed sand packs the perforation tunnels or plugs the formation) or that the well
can be filled with sand (reducing injectivity and potentially plugging the well
completely).
The pre-requisite for sand failure is that the effective near wellbore stresses,
because of depletion and drawdown, exceed the strength of the formation. The
in-situ stresses at the wellbore wall, while predominantly a function of the
overburden and tectonic forces, will vary dependent on the trajectory (deviation
and azimuth) of the proposed wellbore. So, while field wide values can be
generalised, the specifics of the well can impact on the required conditions for
failure of the formation.
The ETI SSAP study applied a generic critical drawdown process to selected
well strength logs to provide a guide for the pressure drops required for failure
in a CO2 injector. The study concluded that the Captain sandstone was a
consolidated formation with limited weak zones (due to uncertainty in rock
strength calibration). However, given that the Captain oil field has suffered sand
production (albeit from shallower and weaker sands) and that Goldeneye has
recommended sand control, the base case development recommendation will
be stand-alone sand screens (SAS). To provide some offset from the caprock
penetration point to the first injection point through the sand screens, it is
recommended that the 95/8’’ shoe is set at least 40ft into the top Captain
Sandstone, and that a further joint of blank pipe with annular isolation is set
above the screens.
More detailed work will be carried out during Concept and FEED.
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 53 of 151
4.6.1.13 Near wellbore thermal effects
In this section, the thermal effects due to CO2 expansion near the wellbore are
further discussed. Compared to typical hydrocarbon gases, CO2 is more
compressible and so on injection, there may be a pressure drop around the
injection well as the CO2 is displaced into the formation, which may cause rapid
expansion of CO2, lowering its temperature. If the temperature drop is
significant, micro fractures could be created within the formation.
A thermal 1-D radial simulation scenario, using a broad range of properties taken
from the Captain Sandstone, was undertaken. Figure 4-18 (top) shows the
temperature and pressure profile after 100 days of CO2 injection and
displacement away from the injection well. A temperature front can be identified
within the system in that the temperature sharply increases from the injection
temperature (18°C) to ambient temperature (65°C).
Figure 4-18: Profile of temperature and pressure away from injection well, 100 days after the start of CO2 injection.
Top: Profile of temperature and pressure away from injection well, 100 days after
the start of CO2 injection. Bottom: Enlarged view of the green dashed area shown in
the above image.
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 54 of 151
The minimum temperature occurs just at the edge of the CO2 thermal front,
which is 17.6°C, only 2% (0.4°C) lower than injection temperature, Figure 4-18
(bottom). One reason for this low temperature effect is the relatively lower
degree of CO2 expansion that occurs near the injection as the permeability is
very high in the Captain Sandstone. The pressure drop around the injection well
is small, with the drop between wellbore to formation observed to be 14barg in
the modelling. Note that the further the CO2 front advances, the cooler it
becomes, but again the effect is expected to be very small and can be safely
ignored.
4.6.2 Transient Well Behaviour
In the Captain injection site, CO2 remains in liquid or dense phase in all injection
scenarios, providing minimum rates of injection are achieved. However, if the
wells are shut-in at surface, the tubing head pressure (THP) will drop below
critical pressure and CO2 will boil off into the gas phase. This will generate
significant temperature drops and create a two-phase scenario when the well is
re-started. These effects are transient but have significant impact on well design
(temperature resistance).
With a surface shut-in, the pressure at the top of the well, below the shut-in point,
falls to below the phase boundary, so gas will evolve, leading to significant
cooling (and gas slugging when injection starts up again). When injection starts
again, the pressure will be low at the wellhead at the top of the CO2 column and
there will be a short transitional period of high pressure liquid entering a low-
pressure gas environment, leading to further cooling effects.
The transient pressure effects of a surface shut-in could be modelled using a
simulator such as OLGA, for example. This would give a better prediction of the
maximum and minimum pressures in the wellbore and highlight if the pressure
variations (for example, the ‘water hammer’ effect) cause problems at the sand
face.
If significant issues are identified, a possible solution to transitional effects is to
add a deep-set shut-in valve to the completion. The deep-set valve would act as
the primary shut-in. Note that a combined deep-set shut-in valve / choke valve
could provide the solution to the variable rates (high injection range) required for
this development, and further investigation of this solution is recommended in
the Concept phase.
Shut-in closer to the formation reduces the hydrostatic head of CO2 acting on
the formation and removes the risk of damaging pressure pulses (‘water
hammer’ effect) affecting the sand face integrity. After shut-in the well could be
left with the CO2 supply pressure applied and therefore mitigate cooling effects
at the wellhead on restart. The pressure differential across the downhole valve
will be minimal and cause no problematic transitional effects. Some OLGA
modelling would be required to determine the minimum depth of shut-in and a
suitable valve specified.
For the purposes of this work, it is assumed that a suitable mechanism is
available to perform the downhole shut-in function. Transient effects are
therefore mitigated. However, further work is required in the Concept and FEED
stages to substantiate this approach, or to provide alternate solutions. In all
cases, well design should reflect the potential for very low temperatures should
these mitigations fail.
4.6.3 Safe Operating Envelope Definition
With respect to CO2 injection, safe operating limits are those that allow the
continuous injection of CO2 without compromising the integrity of the well or the
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 55 of 151
geological store. Since wells are designed to cope with the expected injection
pressures and temperatures, the primary risk to integrity is uncontrolled
fracturing of the formation rock, leading to an escape of CO2 through the caprock
(adjacent to the wellbore or at a point anywhere in the storage complex). The
pressure at which fractures can propagate through formation rock is called the
fracture pressure and is usually defined as a gradient, as it varies with true
vertical depth.
To prevent CO2 migrating from the storage site and storage complex, fracturing
the caprock should be avoided. This can be done by limiting the pressure to
which the caprock is exposed, in both the near wellbore and the storage site
complex as a whole. The pressure limit at any one point depends on the caprock
properties, including strength, elasticity and thickness. Given that there is always
uncertainty in rock properties as you move away from ‘control’ wells, and that
caprock properties are generally not measured and documented to the same
degree as permeable formation rock, there is a high degree of uncertainty
surrounding caprock fracture initiation pressures and the vertical extent of any
resulting fracture (fully penetrating or partially penetrating).
For this reason, this study has used the permeable formation fracture pressure
as the pressure limit (which, in most cases considered for CO2 storage, is lower
than the caprock fracture pressure) rather than that of the caprock itself. This
provides a conservative approach and allays concerns over the concentration
of cold CO2 at high pressure that might be delivered to the caprock boundary
through fracture propagation in the target formation. A further safety margin of
10% is taken from the estimated formation fracture pressure to allow for
variations (and unknowns) within the formation rock properties.
A further risk to well integrity and the well injection performance is the poor
understanding of operating a CO2 injection well close to the gas / liquid phase
boundary. Due to the characteristics of CO2, changes in phase can be
accompanied by significant changes in temperature as well as flow performance
(pressure drops due to friction within the wellbore). For example, across the
phase boundary, CO2 is boiling and condensing, making it an extremely complex
system to model, from both a temperature and flow perspective. This complexity
introduces significant uncertainty.
4.6.3.1 Fracture pressures
The fracture and pore pressures have been taken from the ETI SSAP study,
which incorporated a full geomechanical review, (Pale Blue Dot Energy & Axis
Well Technology, 2016). Well data from within the Captain storage site was
used.
An initial reservoir fracture gradient of 0.17bar/m (0.73psi/ft) was determined
and then corrected for reservoir depletion of 27.58bar (400psi) to give a safe
working assumption of 0.16bar/m (0.69psi/ft) for the study. A safety margin of
10% is applied to this figure to account for local variations and uncertainties,
resulting in a limiting injection pressure gradient of 0.14bar/m (0.62psi/ft).
4.6.3.2 Phase envelope
To minimise the risk associated with the uncertainty introduced by operating
wells across a phase boundary, all injection will be limited to single phase. With
the reservoir pressure of Captain (187bara) being above the critical point for
CO2 (74bara), injection will be limited to liquid (below critical temperature) or
dense phase (above critical temperature). CO2 will be delivered to the injection
sites in liquid phase, with assumed pipeline operating pressures of up to
160bara.
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 56 of 151
4.6.4 Dynamic Modelling – Compositional Fluid Flow Model
For the Acorn modelling study, the ETI SSAP Eclipse dynamic Captain Fairway
model was used as a starting point. The “black oil” Fairway model was initially
converted to a “compositional” model for the following reasons:
To provide a comparison with the black oil modelling study
undertaken previously by ETI SSAP.
To correctly represent the mixing effect between CO2 and lighter
residual methane gas, which cannot be represented in a black oil
model. There are several depleted gas fields that still contain light
gas trapped in their structure within the Captain Fairway model.
Mixing of CO2 with these lighter gases causes a more significant
buoyancy effect between water and CO2/HC mixture than that
observed in a black oil modelling study between water and pure
CO2.
To provide better representation of the CO2-water interaction.
4.6.4.1 Model inputs
The Captain Fairway model consists of two major sand bodies, Captain D
(shallower) and Captain A (deeper), which are separated by the mid-Captain (C)
Shale layer. The lower Captain A Sandstone is not laterally extensive and there
is a suggestion that this sandstone is only poorly connected with the more
extensive Captain D, as outlined in the Captain X SDP, (Pale Blue Dot Energy
& Axis Well Technology, 2016).
The Captain D Sandstone has a higher quality reservoir character along with
better connectivity. Almost 65% of the available pore volume in the Captain X
area resides in the Captain D Sandstone, which is why it was considered for
CO2 storage in the previous ETI SSAP study and also now for the Acorn CCS
Project. Table 4-14 shows a summary of the ETI SSAP model parameters, (Pale
Blue Dot Energy & Axis Well Technology, 2016).
The model consists of 766,080 grid blocks of which only 131,000 grid blocks are
active. The model is divided in several regions principally to allocate different:
initialisation conditions, PVT regions for representing the existing hydrocarbon
fields in the model (for the black oil model) and saturation functions regions,
(Figure 4-19).
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 57 of 151
Parameter Value
Initial Pressure @ datum 197bar
Temperature 65°C
Rock Compressibility 3.5×10-7 at 2500psi
CO2 density 673kg/m3
CO2 viscosity 0.054cP
Brine Salinity 56,600ppm
Porosity 0.185
Permeability H 836mD
Permeability V 445mD
Grid Block 228×112×30
Cell size 400m×400m
Cell Thickness 2.1m
Number of (active) Cells 131,000
Table 4-14: ETI SSAP reservoir model properties
Figure 4-19: Different regions used in the ETI SSAP work. Location of model fracturing pressure threshold shown as red point
The model is an isothermal model at 65°C. At these conditions the injected CO2
will be at supercritical conditions, with a density comparable with liquids and a
viscosity like that of a gas. The in-situ brine salinity is 56,600ppm. Brine salinity
affects the degree of CO2 dissolution in the brine phase. The hydrocarbon fields
considered in the initialisation of the ETI SSAP model include the Blake oil field
and Atlantic and Cromarty (A&C) gas fields.
Like the ETI SSAP study, relative permeability data has been supplied from the
Goldeneye field, (Pale Blue Dot Energy & Axis Well Technology, 2016); (Shell,
2011). For this modelling, hysteresis was considered in the gas phase. The
effect was far less significant for the water phase as it was the wetting phase. A
trapped gas saturation of 30% is defined in the model. A rock compressibility
factor of 3.5×107(1/psia) has been used for the ACT Acorn study. Additionally,
the rock fracture gradient has been assumed as 0.14bar/m (0.62psi/ft), which
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 58 of 151
includes a 10% safety margin. CO2 injection is terminated in the model if the
pressure at the shallowest point located at the Blake field reaches the threshold
fracturing pressure at this correspondence depth (198.91bar/2885psi). Figure
4-19 shows the approximate location of this point at the Blake field.
A high-level calibration has been performed in the ETI SSAP model for matching
the observed pressure in the Captain fairway just before CO2 injection initiation,
between 2011 and 2022. The pressure is matched in the northern and southern
regions by adjusting the observed production data from the existing hydrocarbon
fields and also by varying the size of the connected aquifers to either side of the
model. This prepares the model for CO2 injection which begins at the end of
2022 and continues until 2042 injecting a 60MT inventory of CO2, the same as
in the ETI SSAP model.
A number of equilibration regions have been used in the black oil model that sit
next to each other and are hydraulically communicating. They have been used
to initialise pressure at the start of modelling. The fluid contact depths along with
pressure at the contacts have been depicted in Table 4-15, (Pale Blue Dot
Energy & Axis Well Technology, 2016). Figure 4-19 also shows the
corresponding initialisation regions. The same strategy was undertaken here
except that the Blake oil water contact (OWC) has been updated to 1603m
(5260ft) SS (Du, Pai, Brown, Moore, & Simmons, 2000).
Region Pressure (bar) Pressure (psi)
North Boundary 190 2756
Blake Field 190 2756
Cromarty Field 160 2321
Atlantic Field 156 2263
Captain Aquifer 193 2799
South Boundary 156 2263
Table 4-15: Initialisation depths and corresponding pressures at contact depths for different model regions
4.6.4.2 Compositional fluid flow model
The fluid model used for Acorn CO2 storage site modelling study is the
Eclipse300 compositional simulator, which simulates the solubility of CO2 in the
water phase via the “CO2SOL” option (Eclipse 300 Reference Manual, 2016).
The choice of compositional reservoir simulator in this study allowed for more
accurate estimation of water and CO2 properties and also CO2 solubility in water
and gives more flexibility should parameters that affect CO2 solubility vary.
CO2 properties were automatically calculated via the Peng-Robinson Equation
of State (EOS), while care was taken to accurately estimate water properties in
the aquifer at ambient conditions, considering salinity and CO2 solubility in
water. As with the ETI SSAP model, water evaporation in the supercritical CO2
phase was not considered as it is typically very small (less than 1%) and would
only have a negligible effect on water properties, or the inventory of CO2 at the
end of storage simulation.
The fluid model is a three-component model composed of one light, one heavy
and one CO2 component. Water will also be present in the system but is not
accounted for as a hydrocarbon component. The light and heavy components
were used respectively to replicate the remaining hydrocarbon gas in the Atlantic
and Cromarty (A&C) fields and the relatively heavy oil in the Blake field.
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 59 of 151
Component CO2 C1 C2+
Mw 44 40 90
ΩA 0.457 0.457 0.457
ΩB 0.078 0.078 0.078
Pc (psi) 1071 668 666
Tc (°R) 548 343 1012
Vc (ft3/lb-mole) 1.51 1.57 10
Vc (ft3/lb-mole) 1.51 0.30 5.75
Ω 0.225 0.013 0.570
γCO2-i 0.1 0.1 0.032
Table 4-16: Parameters of the fluid model
Table 4-16 shows the details of the fluid model constructed for this modelling
study. Fluid properties will be estimated by Peng-Robinson EOS. Additionally,
the CO2SOL model calculates a relative density increase as CO2 dissolves in
the brine phase.
The light gas in Atlantic & Cromarty (A&C) is represented by 100%C1. A mixture
of 12%C1 and 88%C2+ replicates the heavy oil in the Blake field. At the ambient
condition of the Captain fairway, the light gas has a density and viscosity of
15.8lb/ft3 and 0.02cP respectively. Similarly, the oil defined for the Blake Field
has a density and viscosity of 57.1lb/ft3 (914.7 kg/m3) and 3.38cP respectively.
The CO2SOL model of Eclipse 300 replicates the interaction between water and
CO2, i.e. the quantity of dissolved CO2 and the relative density increase of brine
as a result of CO2 dissolution at different pressures. The CO2 solubility data in
the water phase is generated via the Chang, Coat and Nolen correlation. The
density of CO2 saturated brine is calculated with Ezrokhi’s method considering
the effect of salt and CO2 on the density of pure water, (Schlumberger, 2014).
Water viscosity at ambient temperature and salinity found in the Captain
sandstone fairway was matched with the CO2STORE model, (Schlumberger,
2014), and was also found to be close to the black oil model at 0.5cP. As with
the ETI SSAP study, water evaporation in the supercritical CO2 phase has not
been considered as the impact is minimal.
4.6.4.3 Fluid mixing
CO2 storage in the Captain Sandstone Member is very gravity dominated due to
the following factors:
• a considerable density difference exists between water and CO2 at
ambient aquifer conditions;
• excellent formation characteristics with low heterogeneity; and
• the tilted nature of the aquifer fairway.
To investigate the role of fluid mixing, 60MT of CO2 was modelled, over a 20-
year injection period. The simulation was further extended to 1000 years
thereafter (to year 3042) to investigate how much of the injected CO2 would be
retained within the Captain X storage complex of the ETI SSAP study. Injecting
the same volumes as for the ETI SSAP study and using the same boundary
enabled a direct comparison between the black oil model (used in the ETI SSAP)
and the compositional model (used in this work).
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 60 of 151
The modelling results at cessation of injection (Figure 4-20) show that during
CO2 injection, part of the injected CO2 has entered into the A&C fields and has
mixed with their remaining hydrocarbon gas that is structurally trapped in these
fields (note the colour change that occurs at the edges of the CO2 plume in the
bottom figure). The light gases in the A&C fields are significantly lighter than
pure CO2, and upon mixing, the buoyancy effects between brine and the gas
mixture (CO2 and C1) become even more significant than in the corresponding
black oil model’s prediction.
Figure 4-21 and Figure 4-22 show final profiles 1000 years after cessation of
injection. Now it can be seen that part of the CO2 has migrated into the northwest
of the Captain fairway. The profile of light component mole fraction in the gas
phase after 1000 years, (Figure 4-22), shows that a significant volume of A&C
light gas has been mobilised by the injected CO2 and has also been displaced
into the northwest.
Figure 4-20: Gas saturation (top) and CO2 mole fraction in the gas phase (bottom); both immediately after CO2 injection stops (2042)
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 61 of 151
Figure 4-21: Gas saturation (top) and CO2 mole fraction in the gas phase (bottom) profiles 1000 years after CO2 injection is stopped (year 3042)
The inclusion of the mixing effect can reduce the overall calculated storage
capacity compared to black oil model predictions. To investigate how much CO2
can now be stored within the previous ETI SSAP storage complex boundary and
to thus enable a comparison with the previous modelling work, the CO2 inventory
was reduced successively from 60MT in 3MT steps. It was identified that with
this configuration of well placement and injection profile, between 45MT and
48MT CO2 could be stored within the ETI SSAP storage complex boundaries,
versus the original 60MT using the black oil simulator. This shows the
significance of mixing on the overall CO2 storage capacity and the importance
of compositional simulation in correctly addressing the mixing effect.
Figure 4-22: Light gas mole fraction in the gas phase profile 1000 years after CO2 injection termination (year 3042)
There is a degree of uncertainty regarding the quantity of remaining light gas in
the A&C fields after their abandonment. The A&C fields were under production
from 2005 to 2009, and this may provide additional pore volume for CO2 storage
in Acorn CO2 storage site. Should this depletion be considered, a different result
could be expected.
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 62 of 151
4.6.5 Dynamic Modelling - CO2 Supply Profiles
This section discusses the methodology and results of the dynamic modelling
for the Acorn CO2 storage site. The results of three modelling scenarios are
presented:
• Phase 1 – Minimum Viable Development Case (Scenario 1):
~200kT/yr from part of the current St Fergus emissions, injected via
one subsea well in the injection site in between the Atlantic and
Cromarty depleted fields, starting in 2023.
• Phase 2 – 64MT Case (Scenario 2): Emissions include those in the
Phase 1, plus those from a potential build-out scenario, including
CO2 captured from hydrogen generation and importation of CO2 via
Peterhead Harbour (from shipping), with a maximum injection of
2.7MT/yr.
• Phase 3 – 152MT Case (Scenario 3): A supply rate capped at
5MT/yr (259mmscfd) via four injection wells at different injection
sites, including one near the Goldeneye depleted gas field, and a
brine production well for pressure management. Emissions include
those in the Base Case, plus those from a potential build-out
scenario, including CO2 captured from hydrogen generation,
importation of CO2 via Peterhead Harbour (from shipping) and
importation of Grangemouth emissions via the Feeder 10 pipeline to
St Fergus.
These scenarios are taken from ACT Acorn Deliverable D02 CO2 Supply
Profiles. Figure 4-23 illustrates the three different CO2 supply profiles.
Figure 4-23: CO2 supply scenarios
Three different CO2 supply scenarios envisaged for the Acorn project. The
cumulative CO2 inventory is calculated and shown for each supply scenario
4.6.5.1 Well placement criteria
The strategy for well placement is particularly important for storage security and
to maximise the available storage capacity. For each CO2 supply profile, a
different development strategy was considered, using wells G01, G02, G03 and
G04.
Three distinct storage zones have been identified within the Captain X area,
shown in Figure 4-24:
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 63 of 151
• Zone 1 - Adjacent to the Blake field where only one well was
positioned (G04 well);
• Zone 2 - Between the A&C fields where two wells were positioned
(G01 and G02 wells);
• Zone 3 - on the west side of the Cromarty field where the fourth well
was positioned (well G03).
Figure 4-24 also shows the position of wells G01 to G04 in each storage zone.
Due to the communication between zones, increasing CO2 storage in one could
limit the storage capacity in another.
Figure 4-24: CO2 storage zones
Three distinct storage zones along with the position of injection wells in each storage
zone used for CO2 storage within the storage site area (white circles). Also shown is
well 13/30b-07, an abandoned well (red circle)
Depending on the CO2 injection profiles, one or more storage zones could
become target for CO2 storage. Table 4-17 shows the target storage zones for
each specific CO2 supply. For the first CO2 supply scenarios, zone 2 located
between the A&C fields would be enough, while for the second phase CO2
injection profile, both zones 1 and 2 will be needed. For the Phase 3 CO2
injection profile (152MT cumulative CO2 stored), all the three storage zones in
the Captain X area plus Goldeneye Segment (shown in Figure 4-33) are
targeted for storing CO2.This is discussed further in Section 4.6.5.4.
Acorn Injection Phase
Final Inventory and Maximum CO2 Injection Rate
Target Storage Zones and Target Injection Wells
Phase 1 4.2MT, 281kT/yr Zone 2, well G02
Phase 2 64MT, 2.7MT/yr Zones 1 and 2, wells G02 and G04
Phase 3 152MT, 5MT/yr
Zones 1, 2 and 3 and additional Goldeneye Segment, wells G01, G02, G03 and G04 and brine producer
Table 4-17: Target storage zones and target injection wells for each CO2 supply scenario
Table 4-18 shows a summary of the injection wells used in the reservoir
modelling study. Since the CO2 injection rate of the first well, G02, varies
significantly across the supply scenarios, a dual completion well has been used
for this well as described in Section 4.6.1.8. The maximum allowable THP is
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 64 of 151
130barg, after which injection into each well will be controlled by THP. All the
remaining three wells (G01, G03 and G04) are single bore wells. One brine
producer is used in the Phase 3 case (Section 4.6.5.4).
Well Number G01 G02 G03 G04
UTM North (m) 6436090 6440286 6439233 6447894
UTM East (m) 264719 264946 257146 259536
Grid coordinates (X,Y) (83,45) (90,53) (102,37) (113,57)
Single/Dual Single bore
Dual bore Single bore
Single bore
Depth (m) 2020 2005 1930 1976
Fracturing pressure (barg) 283 281 271 277
Table 4-18: Reservoir engineering well summary for Phase 1 and 2 wells
To maximise CO2 contact with the reservoir, enhance dynamic storage
efficiency and thus reduce the risk of early CO2 migration out of the Acorn CO2
storage site storage complex boundaries, injectors were placed deep within the
Captain D Sandstone.
In addition, CO2 placement and accumulation around well 13/30b-7 was avoided
where possible. This is due to uncertainty regarding the security of its state.
4.6.5.2 Phase 1 results (Supply Scenario 1 - 4MT)
The Storage Zone 2 was targeted via injector G02 located between the Atlantic
and Cromarty fields, with the injection rate in this well equal to the supply profile.
Figure 4-26 shows the gas saturation profile after the end of CO2 injection
(above) and 1000 years later (below).
With this small injection volume, the risk of CO2 migration out of the storage
complex is negligible. Figure 4-25 compares the tubing head pressure (THP)
and bottom hole pressure (BHP) for this well; note that the bottom hole pressure
(BHP) is significantly lower than the fracturing pressure at this well depth.
Similarly, THP is considerably lower than the threshold of 130barg.
Figure 4-25: BHP and THP profiles for well G02 for the Phase 1 (4MT) scenario
Figure 4-27 shows the fraction of stored CO2 within the different geographic
locations of the Acorn CO2 storage site (left) and the fraction of stored CO2 by
the different storage mechanisms (right). The geographic locations are: Captain
X (the original storage complex for the ETI SSAP project), NW (to the northwest
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 65 of 151
of Captain X, including Blake) and SE (to the southeast of Captain X, including
Goldeneye).
In this Phase 1 scenario, all the injected CO2 has been stored within the Captain
X area and no CO2 is within either the northwest or southeast neighbouring
structures.
Figure 4-26: Phase 1 (Supply Scenario 1 - 4MT) CO2 supply scenario gas saturation profile
Top: at the end of CO2 injection and bottom: 1000 years later
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 66 of 151
Figure 4-27: Retained CO2 and trapping mechanism fractions for 4MT CO2 supply scenario
Left, fraction of CO2 retained at Captain X area, SE and NW structures. Right,
fraction of CO2 stored by different trapping mechanisms.
The dynamic modelling confirms that the limited inventory of 4.2MT of CO2 can
be injected safely into the Acorn CO2 storage site (Captain X area) with one well.
The CO2 plume migration is shown in Figure 4-28. For the Acorn CO2 storage
site to be a viable storage site the CO2 must be contained within the storage
complex boundary, 1000 years after injection ceases.
The results of the modelling show that the risk of any of this small inventory of
CO2 migrating out of the storage complex is negligible. The injection profile is
highlighted in Table 6-4. As CO2 is less dense than the brine within the saline
aquifer, the CO2 movement is primarily gravity driven. Post injection, the CO2 is
mainly present in the Atlantic and the Cromarty structural highs to the south west
pinch-out edge of the model. After 1000 years the CO2 plume is still in that
position.
Figure 4-28: CO2 Plume migration at the end of injection (above) and after 1000 years shut-in (below) for Phase 1 (4.2MT)
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 67 of 151
4.6.5.3 Phase 2 results (Scenario 2 - 64MT)
For the Phase 2 CO2 supply profile, two storage zones (1 and 2) were targeted
via two wells, G02 and G04. Injection into the G02 well ran from 2022 to 2057.
The rates injected into each well are summarised in Table 4-19 below.
Year G2
(MT/yr)
G4
(MT/yr)
Sum
(MT/yr)
2022 0.70 0 0.70
2023 - 2024 0.90 0 0.90
2025 - 2029 0.98 0 0.98
2030 - 2037 0.56 1.32 1.88
2038 - 2039 1.34 1.34 2.68
2040 - 2057 0.57 1.33 1.90
2058 - 2059 0 0.90 0.90
Sum (MT) 24.86 38.96 63.82
Table 4-19: Phase 2 injection rates per well
For the G04 well, injection started in 2030 and finished in 2059. Note that 61%
of CO2 injection in the Acorn CO2 storage site has been carried out via well G04.
Figure 4-29 shows the gas saturation profile after CO2 injection has ended
(above) and 1000 years later (below).
Figure 4-29: Gas saturation profile after the end of CO2 injection (top) and 1000 years later (bottom) for the 64MT CO2 supply scenario
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 68 of 151
Figure 4-30 shows CO2 mole fraction in the gas phase. Comparing Figure 4-30
with Figure 4-29, it can be seen that the front of the CO2 plume in the Blake area
is slightly different between these two figures. This is because of CO2 dissolution
in the residual oil phase of Blake, which removes CO2 from the gaseous phase.
Additionally and importantly, no free CO2 in the supercritical phase is found
around the well 13/30b-7.
Figure 4-30: CO2 mole fraction in the gas phase 1000 years after CO2 injection is stopped for the Phase 2 (Scenario 2 - 64MT) CO2 supply scenario
Figure 4-31 shows the evolution of the BHP and THP for this scenario; none of
the BHP and THP criteria have been violated.
Figure 4-31: BHP and THP profiles for wells G2 and G4 for Phase 2 64MT scenario
Figure 4-32: Retained CO2 and trapping mechanism fractions for 64MT CO2 supply scenario
Left, fraction of CO2 retained in the Captain X area, southeast and northwest
structures. Right, fraction of CO2 stored by different trapping mechanisms.
Figure 4-32 shows the fraction of stored CO2 by area (left) and the fraction of
stored CO2 by different storage mechanisms (right). Almost 14% of the
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 69 of 151
cumulative injected CO2 has been trapped by dissolution in the remaining oil in
the Blake field. It is important to note that the CO2 does not meet the Blake
residual oil until after 2050, well after the Blake field has ceased production and
been abandoned.
4.6.5.4 Phase 3 results (Supply Scenario 3 – 152MT)
For this scenario, all four wells and the three storage zones discussed previously
become an integral part of the target storage scenario. Using four wells enables
better distribution of the CO2 inventory before reaching the threshold fracturing
pressure at any of the wells. As it is not possible to store all the 152MT CO2 in
the Captain X area, the full Acorn CO2 Storage Site Area was used, which
included the Goldeneye Segment (Figure 4-33 – adapted from (Pale Blue Dot
Energy & Axis Well Technology, 2016)).
The Phase 3 results are split into two sections – Section 4.6.5.4.1 highlights the
results of injecting the 5MT/yr supply profile for Phase 3 into the Captain X
injection area only. Section 4.6.5.4.2 presents the results of injecting the 5MT/yr
supply profile into the full Acorn CO2 Storage Site area.
4.6.5.4.1 Phase 3 - Captain X injection area only
To investigate the likely storage potential under this last CO2 supply profile,
several simulation runs were modelled, (Table 4-20). For each simulation run,
the CO2 injection profile, including timing and rate and CO2 allocation for each
well, were varied until the system was able to safely retain the maximum injected
CO2 for 1000 years. Note that the criterion for CO2 storage modelling for this
scenario is that no CO2 as a free supercritical phase can leave the storage
complex from the northwest boundary. No CO2 could be expected to leave the
Blake structure, unless it is filled up to its spill point, which is not the case for
either of the depicted simulation runs in Table 4-20.
Figure 4-33: Acorn CO2 storage site storage complex outline showing Captain X area and Goldeneye Segment
The maximum CO2 injection rate for this simulation run was capped at 5MT/yr
from 2030 to 2055. In one of the simulations runs (SR3 – full list in Table 4-20),
the CO2 inventory was divided between the four injection wells and injection was
carried out at 5MT/yr injection rate for as long as possible. It was, however,
noted that injecting CO2 at this high rate causes early triggering of the threshold
fracturing pressure within the Blake field. Only 97MT of CO2 could be injected
under this injection strategy, and injection can be sustained only until year 2046,
though more than 4.5% of this injected CO2 breaks through to the nearby
northwest structure within 1000 years. This shows that the system is not able to
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 70 of 151
absorb the rapid pressure response created by CO2 injection at this high
injection rate (5MT/yr) using the assumptions made.
Figure 4-34: Gas saturation profile for Phase 3 (Scenario 3 - 152MT) CO2 supply scenario
Top: after CO2 injection has stopped and bottom: 1000 years later (Simulation Run
SR20)
Lowering the injection rate and better allocation of CO2 inventory across wells
could improve the storage response. This is the strategy that was completed for
the remaining simulation runs in Table 4-20, where the overall injection rate was
limited to 3MT/yr to enable the system to absorb the rapid pressure increase
due to CO2 injection. The use of brine production wells in this area to counteract
this pressure increase would be of little applicability because the storage
response in the Captain formation is limited by buoyancy driven CO2 migration.
Figure 4-34 shows the gas saturation profile after CO2 injection stopped (top)
and 1000 years later (bottom) for the chosen SR20 scenario. Again, the CO2
plume remains clear of the 13/30b-7 well. Figure 4-35 shows CO2 mole fraction
in the gas phase.
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 71 of 151
Scenario G1 (MT) G2 (MT) G3 (MT) G4 (MT) Sum (MT) Retained CO2 after
1000 Years
Proportion of CO2 into
Southeast Structure
Proportion of CO2 into Northwest (Supercritical)
Proportion of CO2 into
Northwest (Dissolved in
Oil)
Proportion of CO2 into
Northwest (Dissolved in
Water)
SR3 24.13 25.38 25.38 22.5 97.4 95.25% 0.42% 3.83% 0.00% 0.50%
SR4 9.13 6.63 45.63 39 100.4 98.74% 0.14% 0.90% 0.14% 0.08%
SR7 11.13 8.63 45.63 39 104.4 98.53% 0.24% 0.98% 0.16% 0.09%
SR11 11.13 8.63 40.43 44.2 104.4 98.83% 0.23% 0.56% 0.32% 0.06%
SR14 14.13 11.63 40.43 44.2 110.4 98.68% 0.29% 0.64% 0.33% 0.07%
SR15 7 13.63 45.63 48.13 114.4 98.05% 0.09% 1.10% 0.63% 0.13%
SR16 14.13 11.63 32.63 44.2 102.6 99.02% 0.26% 0.31% 0.36% 0.05%
SR17 14.13 11.63 24.83 44.2 94.8 99.37% 0.25% 0.02% 0.33% 0.03%
SR18 14.13 11.63 17.03 44.2 87 99.44% 0.24% 0.00% 0.29% 0.02%
SR19 14.13 11.63 20.93 44.2 90.9 99.42% 0.25% 0.00% 0.31% 0.02%
SR20 14.13 11.63 22.23 44.2 92.2 99.41% 0.25% 0.00% 0.32% 0.02%
Table 4-20: Different simulations modelled to address the Phase 3 CO2 supply scenario injected into the Captain X area only
The chosen simulation run (SR20) has been highlighted
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 72 of 151
Figure 4-35: CO2 mole fraction in the gas phase 1000 years after CO2 injection has stopped for the third CO2 supply scenario (Simulation Run SR20)
Figure 4-36 shows the fraction of CO2 stored at different regions within the Acorn
CO2 storage site structure (left). The fraction of stored CO2 as dissolved, mobile
and trapped can be observed in this figure (right).
Figure 4-36: Retained CO2 and trapping mechanism fractions for Phase 3 CO2 supply scenario
Left: fraction of CO2 retained at Captain X, southeast and northwest structures.
Right: fraction of CO2 trapped by different trapping mechanisms. Both figures are
simulation run SR20
Figure 4-37: BHP and THP profiles for wells G1-4 for SR20
Figure 4-37 shows the evolution of the BHP and the THP for all four wells used
in SR20. The BHPs for wells G01, G02 and G03 are below their limiting
threshold, although for well G04 only, the injection rate becomes limited by BHP
only when this well starts injecting in around 2030, and for only 30 days, after
which its BHP decreases below the fracturing pressure as the gas saturation in
the near wellbore region increases. The THP is also below the threshold
pressure, except again for well G04; this occurs just as the well starts injection;
THP almost reaches the 130barg limit after which it declines. Ignoring these
short-term spikes, which are manageable by gradual ramping up the injection
rates, the chosen THP or BHP limits are not violated in any wells at any time.
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 73 of 151
4.6.5.4.2 Full Acorn CO2 Storage Site Area
Given the storage resource potential using the Captain X injection area only is
still lower than potential CO2 available for injection in Scenario 3 (92.2MT
compared to 152MT), possible injection locations were explored further
southeast.
The well locations for this scenario are in Table 4-21.
Well Latitude Longitude
G1 58°00'18.8918"N 6°29'57.2750"W
G2 58°02'30.0516"N 6°58'57.5443"W
G3 57°59'23.5607"N 6°33'37.7828"W
G4 58°06'25.0057"N 7°04'54.5989"W
Brine Producer 58°00'14.7837"N 6°43'31.5730"W
Table 4-21: Well locations for Phase 3 152MT scenario
Individual well injection profiles are depicted in Table 4-22.
Year G1
(MT/yr)
G2
(MT/yr)
G3
(MT/yr)
G4
(MT/yr)
Sum
(MT/yr)
2022 0.7 0 0 0 0.7
2023-2024 0.9 0 0 0 0.9
2025-2029 1.6 1.2 1.2 0 4.0
2030-2055 1.7 0.8 0.8 1.7 5.0
Sum (MT) 54.7 26.8 26.8 44.2 152.4
Table 4-22: Individual well injection profiles to achieve the target 152MT CO2 injection
First simulation run
In the first run, the location of well G1 was brought down-dip into the Goldeneye
Segment near the Goldeneye field and its BHP was corrected for the
corresponding depth at which it is now located. However, injection was stopped
after only 112MT of CO2 due to pressure increase beyond the threshold
fracturing pressure limit observed adjacent to the Blake field. This showed that,
unlike the previous simulations, to inject the 152MT CO2 inventory, the storage
performance could become limited by pressure build up and that offset brine
production wells may need to be deployed.
Second simulation run
In the second run, one offset brine production well was added in the model
between the new well G01 position and the southeast boundary of the Acorn
CO2 storage site (well WP in Figure 4-38). The offset brine producer produces
brine at a fixed rate of 3180m3/day with a minimum BHP of 203barg to avoid
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 74 of 151
excessive adverse drawdown. Additionally, as soon as its CO2 production rate
increased above 28.3x103m3/day (1000Mscf/day), it is automatically shut-in to
avoid CO2 back production. Figure 4-38 shows final CO2 plume under this CO2
injection strategy. Results show that the storage performance after 1000 years
is not now limited by the pressure response, instead it is limited by the vertical
migration of CO2 plume toward the northwest structure.
Third simulation run
In the third run, well G03 was also brought down-dip close to well G01, and its
maximum injection BHP was corrected for its new depth (Figure 4-39). Now two
wells are located down-dip near the Goldeneye field. The injection profiles are
still as previously identified in Table 4-22. Figure 4-39 shows the final CO2 profile
1000 years after CO2 injection termination. No breakthrough of supercritical CO2
to the northwest structure was identified, but it was observed that only 149MT
of CO2 (97.6% of the 152MT target) had been injected. The reason for this is
less than defined CO2 injection from well G1; it was observed that injection from
well G1 now becomes limited by its BHP, given another high rate injection well
is now located in its vicinity.
Figure 4-38: Profile of CO2 distribution in the second simulation run after 1000 years. Well G1 is now at the bottom of the model near the Goldeneye field
Figure 4-39: Profile of CO2 distribution in the third simulation run after 1000 years. Both wells G1 and G3 are now at the bottom of the model near the Goldeneye field
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 75 of 151
Figure 4-40 compares the CO2 storage at the end of the simulations described
in this section for the second (Figure 4-38) and third (Figure 4-39) simulation
runs. More CO2 has been stored in the southeast structure for the third
simulation run than for the second.
Figure 4-40: Retained CO2 and trapping mechanism fractions for the Phase 3 third simulation run
Top row: second simulation run. Bottom row: third simulation run. Left: fraction of
CO2 retained at the Captain X area, southeast and northwest structures when
expanding the storage boundary to southeast. Right: fraction of CO2 trapped by
different trapping mechanisms
4.6.5.5 Uncertainty analysis
Sensitivity analysis has been carried out for the maximum CO2 storage inventory
in the Captain X area, i.e. SR20 injecting 92.2MT CO2 (Table 4-20). Results are
expected to be less sensitive to variation of model parameters for the first two
CO2 injection profiles (Phase 1 and 2), since the cumulative CO2 inventories for
these three CO2 injection profiles are small.
Compressibility factor: Results show that an order of magnitude reduction of
the compressibility factor increases the maximum pressure experienced in this
block by 1.4barg, which is still smaller than the limiting criterion of 199barg at
this depth. However, increasing the compressibility factor can relax the
maximum pressure by almost 8.3barg. This shows that a relatively small rock
compressibility has been allocated for the Captain Sandstone.
Transmissibility across the Shale Layer: In this sensitivity analysis, the
vertical permeability of the Captain shale layer was varied by an order of
magnitude higher and lower compared to its base case value (0.001md). It was
observed that increasing or decreasing the Captain shale vertical permeability
within this range does not affect the pressure response of the system at all.
Nevertheless, a very small quantity of CO2 migrates to underneath the Captain
shale layer; increasing/decreasing the vertical shale layer transmissibility could
only increase/decrease this migration.
The Degree of Depletion of the A&C Fields: An uncertainty exists regarding
the remaining quantity of light gas at the beginning of CO2 injection that could
affect the storage results. Results show that if depletion from the A&C fields is
considered, the ultimate storage capacity of the system could increase from
45MT-48MT to almost 60MT, a 12MT-15MT increase. Similarly, a sensitivity
scenario was investigated here in that if the contact depths of the A&C fields
were modified for SR20 to account for the cumulative gas production from these
fields, which occurred between 2005 and 2009. Results show that the leading
edge of the CO2 plume is now distant from the northwest storage boundary. The
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 76 of 151
storage potential of the system (under SR20) could now be increased by almost
10-15MT because of this adjustment, and thus the final stored CO2 inventory
could be increased from 92MT to 102-107MT. This may need alternate well
injection profiles than those used for SR20.
Uncertainty in the Top Structure Map: There is a degree of uncertainty in the
interpretation of the top structure map along the Captain fairway, (Pale Blue Dot
Energy & Axis Well Technology, 2016), related to challenges with the
overburden velocity and therefore the seismic depth conversion process and the
lack of acoustic impedance contrast at the top reservoir event. Different
realisations of the Top Captain structure map were modelled in the ETI SSAP
study, which had a direct impact on plume migration. This uncertainty still exists.
Impact of CO2 injection in Captain Sandstone on the Solitaire field: Solitaire
is a single well oilfield in an Upper Jurassic Burns Sandstone reservoir which
lies at 464ft below the top of the Captain Sandstone (235ft below the Base
Captain Sandstone) in the 14/26-8 well underneath the Atlantic gas condensate
field, and the geography of the main Captain Sandstone fairway. First oil from
Solitaire was in 2015, with end of production forecast in 2028 coinciding with the
cessation of production (CoP) of the Golden Eagle development to which it is
tied back. The Captain Sandstone and deeper Burns sandstone are
hydraulically isolated, and it would take a large pressure gradient between the
Captain Sandstone and the depleted Burns Sandstone and a well penetrating
both formations for any CO2 from the Captain Sandstone to reach the Burns
Sandstone. This is highly unlikely and no impact to Solitaire operations is
anticipated.
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 77 of 151
4.6.6 Strategies to Increase CO2 Storage Efficiency
Both the previous ETI SSAP study and the work conducted in the ACT Acorn
study have concluded that the CO2 storage efficiency in the Captain Formation
is low, in the order of 3% pore volume (PV) or less. Given the low storage
efficiency observed, a range of strategies were explored to investigate if it could
be improved. Improving the storage efficiency can potentially directly reduce the
cost of development as the pore space is used more efficiently and less wells
may be required.
In this work, storage efficiency is defined as:
Storage efficiency = Pore volume of full injected and contained CO2 inventory
Pore volume within the footprint of the plume
It can be concluded from the ACT Acorn modelling work that irrespective of the
degree of heterogeneity, the CO2 storage (displacement) process is strongly
gravity dominated; permeability is excellent, the Captain Formation is tilted, and
considerable density difference exists between brine and CO2, all of which make
the displacement gravity dominated.
This causes injected CO2 to rapidly segregate and travel underneath the cap
rock with resultant minimum contact between brine and CO2 during and post
CO2 injection periods producing low macroscopic storage (sweep) efficiency.
4.6.6.1 Overview of strategies
Several alternative strategies to improve the CO2 storage efficiency in the
Captain Formation are listed below, with an indication as to whether or not they
were modelled in this study. All strategies are used in the petroleum industry to
improve recovery efficiency which is a similar process:
• Altering the perforation strategy - studied
• Using water-alternating-gas (WAG) instead of continuous CO2
injection - studied
• Use of horizontal/deviated wells - studied
• Varying the CO2 injection rate - studied
• Use of offset brine production wells (up-dip and down-dip)- studied
• Altering the brine chemistry- studied
• Carbonated water injection - not studied
• Use of polymers- not studied
4.6.6.2 Methodology and results
To enable a direct comparison between strategies, the overall injected CO2
volume was limited to 60MT for all the strategies listed above. The fraction of
retained CO2 within the Captain X area and storage efficiency could then be
compared between different strategies.
Figure 4-41 summarises the results of applying the different strategies and
shows the fraction of CO2 stored by different trapping mechanisms right after
CO2 injection termination and 1,000 years later, with the corresponding storage
efficiency shown in red. Stacked bar charts show the same data in a different
way in Figure 4-42.
Comparison of the results for each strategy with the base case model storage
performance shows that none of the strategies investigated so far are potentially
useful for improving the CO2 storage efficiency in the Captain Formation. This is
primarily because of the exceedingly gravity dominated nature of the storage
process that lets the plume migrate to shallower depths whilst restricting
interaction between brine and CO2 post CO2 injection.
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 78 of 151
Figure 4-41: Pie charts showing fraction of free, trapped and dissolved CO2 for different strategies
The charts are for both after CO2 injection termination and 1,000 years later.
Numbers below each injection strategy respectively illustrate fraction of retained CO2
and corresponding storage efficiency (in red)
4.6.6.3 Enhancing the retention of CO2 within any proposed lease area
Enhancing the retention of CO2 within any proposed lease area was also
investigated (although no direct storage efficiency calculation was carried out).
To do this, additional pore volume that had not previously had contact with CO2
was targeted. Two options were looked at: positioning wells in new areas of the
model and by further depleting the potential trapping structures within the
storage area (i.e. Atlantic and Cromarty fields) to create additional pore volume
for CO2 storage.
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 79 of 151
Figure 4-42: Bar charts showing fraction of free, trapped and dissolved CO2 for different strategies
Well placement alteration
Regions into which CO2 has not been able to propagate can be regarded as
additional targets for CO2 storage in Acorn CO2 storage site and this can be
achieved with appropriate well placement. To investigate this strategy, the two
injection wells present in the model used to investigate storage efficiency were
relocated to several different injection locations and the impact of their relocation
was analysed.
Ten different well placement scenarios were constructed and simulated.
Additionally, the final CO2 inventory was increased from 60MT in the base case
storage efficiency model to 90MT, i.e. each well now injects 45MT of CO2 for 30
years at 1.5MT/year each. Figure 4-43 show the final results in terms of ultimate
retained CO2 in the Captain X area (based on the ETI work), north west and
south east structures (top rows images), and the distribution of stored CO2 due
to different trapping mechanisms (bottom row of Figure 4-43 ).
Overall, the results show that altering well placement may improving retention
of the CO2 within a proposed lease area (in this case, the same Captain X area
as was used in the ETI SSAP work).
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 80 of 151
Figure 4-43: Fraction and distribution of CO2 for different well placement strategies
Top rows: Fraction of retained CO2 in different regions of the model. Bottom rows:
Distribution of CO2 due to different trapping mechanisms 1,000 years after cessation
of CO2 injection
Deliberate depletion of Atlantic and Cromarty Fields
Another strategy for enhancing the retention of CO2 within any proposed lease
area was investigated. This strategy involved producing the remaining gas in the
Atlantic and Cromarty fields to release additional pore volume for CO2 storage
and to reduce the impact of CO2 mixing with the remaining gas in these gas
fields, which may have undesired effects as discussed earlier (Section 4.6.4.3).
This strategy may also resemble an Enhanced Gas Recovery process where
the remaining hydrocarbon gas is produced via CO2 injection, although its
application depends on the availability of infrastructure.
Modelling results show that the Atlantic and Cromarty producers are shut-in,
respectively, after 4 and 7 years of production due to excessive CO2
breakthrough, although by that time they would have produced 86 and 76 BCF
respectively. Only 0.24MT of the injected CO2 is back produced, although it is
expected and thus controlled. Figure 4-44 compares the gas saturation profile
after 1,000 years of CO2 injection between the base case model and Atlantic
and Cromarty depleted versions. The extent of the gas plume in the case where
the Atlantic and Cromarty fields are depleted is much smaller than in the base
case model. This illustrates that the ultimate storage capacity could likely
increase considerably beyond the 60MT because of additional pore volume that
becomes available because of further depleting these fields. Whilst interesting,
this option is practically and economically challenging due to the costs
associated with producing, treating and exporting this gas.
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 81 of 151
Figure 4-44: Comparison of final gas saturation profiles
Comparison between the base case (above) and Atlantic and Cromarty (A&C)
depleted alternatives (below), 1,000 years after cessation of injection (60MT CO2
injected).
4.7 Containment Characterisation
4.7.1 Storage Complex Definition
The Acorn storage complex includes a large proportion of the Captain
panhandle and extends from the Blake oil field in the northwest, down beyond
the Goldeneye depleted gas condensate field in the southeast, as shown in
Figure 4-45.
The vertical limits of the complex are bound by the Base Cretaceous depth
surface below and the Top Lista Shale Formation above. The Top Lista Shale
is the secondary caprock of the storage system, providing an additional barrier
between the storage reservoir and the seabed.
Laterally, the limits of the complex were defined based on the geological and
dynamic modelling. Due to poor seismic imaging, uncertainty exists in the pinch-
out of the Captain Sandstone and the exact location of the West Halibut Fault.
To take this into account, the storage complex boundary has been extended by
~2km. There is no Captain Sandstone present on the Halibut Horst.
The dynamic modelling indicates that the Phase 1 base case CO2 volumes of
4.2MT can be safely stored within this area. Subsequent build out phases can
also be safely stored, including Phase 3 (volumes of 152MT of CO2). For Phase
3, some of this CO2 will eventually reach the Blake oil field, but not until many
years after its anticipated cessation of production.
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 82 of 151
Figure 4-45: Acorn CO2 storage site storage complex outline
4.7.1.1 Top, base and lateral seal
Immediately overlying the Top Captain Sandstone is a thick interval of Carrick
and Rodby Formation mudstone and shales which have been chosen as the
primary caprock interval (Figure 4-46 and Figure 4-47 – both from Pale Blue Dot
& Axis Well Technology (2016)). The thickness varies across the storage site
from approximately 30m to over 120m (circa 90 to >400 ft). These are a proven
effective seal for many hydrocarbon fields within the main Captain Fairway.
There is some evidence of seismically visible small-scale faulting within the
Captain Sandstone. These faults are limited in vertical extent and do not offset
the overlying Rodby/Carrack formation. Within the Captain Sandstone fault
throws appear to be small and due to sand on sand contact on either side of the
faults it is not expected that they will provide a significant barrier or baffle to the
flow of CO2. The calcareous marls of the overlying Hidra Formation provide
additional primary store containment.
Figure 4-46: Primary and secondary containment
Where the Captain Sandstone pinches/ shales out on the southern and northern
margins of the fairway, the lateral seal is also provided by the mudstones of the
Valhall Formation as proven by the Goldeneye Field. Due to poor seismic
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 83 of 151
quality, there is uncertainty associated with the exact location of this pinch out
edge, however there is good well control in places which demonstrate that this
pinch out can be very rapid. An example of this is the 20/01-11 well which
contained no Captain Sand, whilst the side-track less than 1km to the North
contained over 20m (60ft) of net sand.
The Captain fairway is open at both ends, to the north west the sands open out
into the pan handle, and to the south east the sand fairway continues towards
the Hannay oilfield. The base seal is provided by the underlying mudstones of
the Valhall Formation.
4.7.1.2 Hydraulic communication
As can be seen in Figure 4-47, the Upper Captain D Sandstone is laterally
extensive across the full fairway. Lateral connectivity across the fairway within
this zone is expected to be good due to evidence of pressure communication
between producing hydrocarbon fields in this interval. The lower Captain A sand
is more restricted in distribution and has poorer lateral connectivity. Injection will
be in the Captain D Sandstone.
Below the Captain Sandstone, the base seal is provided by mudstones of the
Valhall Formation, which has some thin sand interbeds which are not expected
to be laterally extensive and are at least 25m (80ft) deeper than the Captain,
separated by mudstone.
Below the base Captain Sand are reservoir quality sands of the Coracle and
Punt, which do not appear to be in hydraulic communication with the Captain
Sand. The deeper Upper Jurassic Burns sand intervals (e.g. those of the single
well (14/26-8) Solitaire development below the southern part of the Atlantic field,
where they sit 464ft below the top of the Captain Sandstone and 235ft below the
Base Captain Sandstone) appear to be hydraulically isolated from the Captain
sands, (Pale Blue Dot Energy & Axis Well Technology, 2016). During future
work, the continued isolation of this sand should be carefully considered.
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 84 of 151
Figure 4-47: Well correlation
4.7.1.3 Overburden model
In the ETI SSAP study, an overburden model was built over the same area as
the static model. For more information, please see the ETI SSAP Captain X
Development Plan, (Pale Blue Dot Energy & Axis Well Technology, 2016).
4.7.1.4 Geomechanical analysis and results
4.7.1.4.1 Previous Work
Geomechanical modelling of the primary store was carried out in the ETI SSAP
study to confirm the strength of the storage formation and its ability to withstand
injection operations without suffering mechanical failure at any point during
those operations. No significant issues of drill ability, fracturing risk or sand
failure risk were identified. Further details are included in Section 3.6.6 of the
ETI SSAP Captain X Development Plan.
4.7.1.4.2 ACT Geomechanical Analysis
As part of the ACT work programme, the tensile strength of the Captain
Sandstone was investigated in a rock laboratory using core samples. This is
described and discussed in more detail in ACT Acorn Deliverable D06
Geomechanics, (Pale Blue Dot Energy and University of Liverpool, 2018), with
a short summary presented in this section.
The failure of a wellbore surface by tensile fracturing can be induced when fluid
pressures overcome the rock tensile strength and/or the local least principal
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 85 of 151
stress. This process is known as hydraulic fracturing and can be purposely
performed to increase the transmissibility of rock, when used with proppants, for
hydrocarbon extraction (shale gas) and geothermal fluids. However, these
tensile fractures can result in an unstable wellbore which may hamper long term
fluid injection and borehole integrity. To sustain prolonged injection operations
and preserve borehole integrity such as is required for CO2 storage, which would
operate over several decades, fluid pressures must be maintained at conditions
below the tensile failure strength of the reservoir rock.
The geomechanical study carried out investigated the tensile strength of the
Captain Sandstone.
The geographic location of the sampled wells, 14/26-1; 14/26a-6; 14/26a-7, 7A;
and 14/26a-8, correspond to the proposed primary CO2 injection site. The depth
intervals chosen for sampling for each respective well were chosen according
to number of parameters, including: availability of core, depth, occurrence in the
oil/water-leg; porosity; and general lithological variation, as determined from
hand specimen observations, gamma ray and density wireline logs.
4.7.1.4.3 Geomechanical Testing Methods
The indirect (also known as Brazilian) tensile testing of rock cores is
accomplished by applying diametric compressive stresses on two opposing
curved surfaces of a rock disc. This generates a uniform tensile stress on the
plane containing the axis of the disc and the loaded surfaces, producing Mode
I- tensile fractures through the test specimen, replicating the stress conditions
of hydraulic fracturing.
The tests detailed in this study were conducted using a uniaxial press in a
Brazilian test jig. The specimen (within the test jig) is compressed unconfined
(σ2 = σ3 = 0) between a fixed plate and hydraulic piston at a constant loading
rate and at room temperature. The applied load is measured using a load cell
(Tedea-Huntleigh compression load cell, model 220, grade C4), the load signal
is fed through a National Instruments USB-6210 (analogue to digital convertor)
to a computer were the load signal is recorded using LabVIEW software. These
tests were undertaken according to ASTM D3967-08 (2008) standards.
The Brazilian Test Jig is comprised of two blocks of mild steel that house curved
bearing platens (D2 steel, hardened to HRC 60), this curvature reduces contact
stresses on the specimen. The top block contains a hemispherical seat that
houses a chrome ball upon which sits a bearing block, this configuration
prevents asymmetric loading once in contact with the uniaxial press’ upper fixed
plate. Test specimens were comprised of 18-38 mm diameter discs with
thickness-to-diameter ratios between 0.5- 0.75, sampled from half cores rounds
of the Captain Sandstone.
Larger diameter specimens were used for the most friable material to increase
the accuracy of measurement of failure on the load cell, with smaller specimen
diameters failure occasionally occurred close to the maximum resolution of the
load cell (± 20 N). The tensile strengths of these larger diameter specimens had
a close correspondence to that of the smaller specimen diameters, once
calculated using Equation 1, and served to validate the measurements
performed on smaller diameter specimens.
The calculation of the splitting tensile strength of the test specimen is achieved
through the following equation:
σt = 2P/πLD (1)
where σt is the splitting tensile strength (STS) in MPa, P is the maximum force
applied indicated by the load cell in N, L is the length of the specimen in mm and
D is the diameter of the specimen in mm (D3967-08, 2008).
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 86 of 151
4.7.1.4.4 Results
Due to the variability in the experimentally derived splitting tensile strength
values several repeat tests for some depth intervals has been repeated. The
original conventional core analysis (CCA) porosity measurements, helium
porosity at ambient conditions, were included in this data set as porosity
indicates the degree of cementation and thus tensile strength. To check CCA
porosity analyses several porosities were measured on the test specimens using
a helium pycnometer in the University of Liverpool (UoL)-Rock Deformation
Laboratory. These porosity values matched well with the closest corresponding
CCA porosity data, which were measured approximately every foot.
Overall the tensile strength for the Captain Sandstone is low, specimens from
the gas/water-legs in the sampled wells range between <1-7.4bara, oil-saturated
specimens range between 2.7-7.4bara, and calcite-cemented specimens 32.8-
44.9bara. The specimens sampled from the gas/water-legs represent the
majority of the Captain Sandstone with core analyses showing porosities of
15.7-34.4% (average 27.45%). More cemented horizons occur throughout this
high porosity sandstone, <1.5 ft thick in the cored material, composed of calcite-
cemented sandstone with porosities ranging between 2.7-13.9% (average
5.89%).
4.7.1.4.5 Discussion
As evidenced previously, porosity and thus the degree of cementation appears
to control the tensile strength of the Captain Sandstone member. The majority
of the Captain X Sandstone is of high porosity (average 27.45%) sandstones
with low tensile strength. In a histogram of the high porosity Captain Sandstone
splitting tensile strengths (STS <7.4bara), the mean is 2 ± 0.19bara and
standard deviation is 1.6bara. Calcite-cemented doggers occur throughout the
sandstone but are of limited thickness, <1.5ft, and likely laterally discontinuous,
as such they are unlikely to influence CO2 injection operations greatly.
If, during injection, the fluid pressures exceed the least principal stress and/or
the tensile strength of the rock, tensile fracturing (hydraulic fracturing) may occur
(Zoback, 2007). This pressure/stress threshold for fracture is known as the
formation fraction pressure and may be overcome if the rate of fluid flow into the
formation away from the injection site is exceeded by the fluid supply. Such a
situation would allow pore fluid pressure to build, resulting in stresses that may
deform the rock.
The fracture gradient is the pressure/stress gradient required to fracture the rock
at a given depth, this increases with depth due to increasing overburden
pressure, (Schlumberger, 2018). There is currently no consensus in the
petroleum industry on the calculation of the fracture gradient, some use the least
principal stress gradient, and others the maximum leak-off pressure gradient
(fracture breakdown pressure gradient) or the fracture initiation pressure
gradient, (Zhang & Yin, 2017). Knowledge of the tensile strength of the rock in
a formation gives us a further constraint on the fracture gradient when used in
conjunction with the least principal stress and leak off test results.
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 87 of 151
As the Captain Sandstone is very friable and poorly cemented fracturing will
likely be accompanied by extensive disaggregation of the wellbore. This
disaggregation may hamper injection as porosity and thus permeability is lost
around the injection depth interval as loose material accumulates. Therefore,
keeping fluid injection pressures below this threshold, i.e. the fracture gradient,
is required.
4.7.1.4.6 Conclusions
The Captain Sandstone, within the formation gas and water-legs, is composed
predominantly of high porosity sandstone with low tensile strength, mean of 2 ±
0.19bara.
These tensile strengths correlate well with the porosity of the sandstone, high
porosities (average 27.45%), and thus low degrees of cementation, result in low
tensile strengths.
Stronger horizons exist throughout the sandstone, including calcite-cemented
doggers, <1.5ft thick with average porosities of ~5.89%, and oil-saturated
sandstones.
4.7.1.5 Geochemical degradation analysis and results
Geochemical modelling of the potential degradation of the cap rock lithologies
when exposed to CO2 for long periods of time is presented in Section 3.5.2.5 of
the ETI SSAP Captain X development plan, (Pale Blue Dot Energy & Axis Well
Technology, 2016). The conclusion of this work suggests that Rodby Formation
seal failure is unlikely to be induced by mineral reactions with the CO2.
4.7.2 Engineering Containment
For CO2 to be safely contained in the Captain sandstone, caprock integrity is
key. Engineering containment risks primarily include the risk of any caprock
damage through the application of excessive pressure (fracturing) or the failure
to maintain an effective seal in the wells that penetrate the caprock. A summary
of the engineering containment assessment of the Captain X area is provided in
this section. For a full description, please refer to Section 3.7.2.2 in the Strategic
UK CO2 Storage Appraisal Project Captain X development plan, (Pale Blue Dot
Energy & Axis Well Technology, 2016).
In general, abandonment practices for wells have become more rigorous over
time, and so older wells (especially pre-1984) pose a greater potential leakage
risk. Wells drilled for hydrocarbon production in the same formation as the
storage site will generally have higher abandonment practices, to ensure no
hydrocarbon movement to the seabed. Where wells are drilled for a deeper
target than the storage formation, or have found no hydrocarbons, there is a
greater chance that these will have poorer abandonment practices and
potentially less barriers between the storage reservoir and seabed.
4.7.2.1 Engineering containment assessment
For the Captain X injection area, a total of 59 wells were plugged and
abandoned. A detailed risk assessment was performed in the ETI SSAP work
using the historical well data in the CDA data base. These data include the Final
Well Reports or Abandonment Reports for the legacy wells.
A selection of 8 representative legacy wells was chosen for this review, some
from within the plume areas and some from the wider complex area. The review
is summarised in Table 4-23, extracted directly from the Captain X Storage
Development Plan (Pale Blue Dot Energy; Axis Well Technology, 2015). The
abandonment year for the 8 legacy wells ranges from 1979 to 2007 (over 25
years) and cover a range of abandonment specifications. A detailed review of
every legacy well will be undertaken prior to final investment decision.
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 88 of 151
Well UKOOA or API
Target Above/Below/In Primary Store
Specification Comments
13/24b-3 1997
Issue 0 - 1994
In store depth Meets
Cased hole well with 3 cement plugs. Lower plug across perforations in 95/8’’ casing. Second plug immediately above and lapped with annulus cement. 95/8’’ casing cut at 1369ft and shallow set cement T-plug set inside both 95/8’’ casing and 133/8’’casing. Shallow set plug lapped with annulus cement. Plugs supported with either viscous pill or bridge plug. Store depth at reservoir target and isolated 2 cement plugs. Meets spec – with 2 cement plugs above store.
13/30-1 1981
API RP 57
Below Fails
Openhole well with 3 cement plugs. Lower plug in openhole section across reservoir. Two cement plugs in 95/8’’ casing but not lapped with annulus cement. Both casing cement plugs not supported with bridge plugs. Hydrocarbon sands. Store depth above reservoir target and isolated with plugs #2, #3. Does not meet spec – no annulus cement.
13/30-2 1984
API RP 57
Below Fails
Cased hole well with 3 cement plugs. Lower plug filled bottom of well and across perforations, Middle plug supported with bridge plug and lapped annulus cement. Cement plug #3 not supported with bridge plug and no annular cement. Hydrocarbon sands. Store depth above reservoir target and isolated with 2 cement plugs. Does not meet spec – shallow set cement plug not lapped with annulus cement.
13/30a-4 1998
Issue 0 - 1994
Below Meets
Openhole well with 4 cement plugs; 3 plugs in openhole section and one cement plug at 13 3/8” casing shoe. Casing cement plug lapped with annulus cement. All plugs supported with viscous pill. Water wet sands. Store depth above reservoir target and isolated with plugs #3, #4. Meets spec with two permanent barriers above store depth.
13/30b-7 2007
Issue 2 - 2005
Below Meets Openhole well with one cement plug placed across 13 3/8” shoe and lapped with annulus cement. Water wet sands. Store depth above reservoir target and isolated with one cement plug. Meets spec with one barrier for isolation of water zone.
14/26-1 1979
API RP 57
Below Meets
Openhole well with 3 cement plugs and additional bridge plug. Shallow set cement plug lapped with annulus cement. Oil and water bearing zones. Store depth above reservoir target and isolated with cement plugs #2, #3. Meets spec with 2 cement plugs above store depth.
14/26a-6 1997
Issue 0 - 1994
In store depth Meets
Cased hole well with 3 cement plugs. Lower plug set across perforation in 7” liner and to 800ft above. Second plug in 95/8’’ casing and lapped with annulus cement. Shallow set cement plug in 95/8’’ casing and lapped with annulus cement. Meets spec with 2 cement plugs above store depth.
14/26a-7A 1999
Issue 0 - 1994
Below Meets
Openhole well with 4 cement plugs. Lower 2 cement plugs in open hole section. 3rd cement plug at 13 3/8” casing shoe. 13 3/8” casing cut at 676ft and shallow set cement T-plug set in 20” casing. Store depth above reservoir target and isolated with 2 cement plugs both lapped with annulus cement. Meets spec with 2 cement plugs above store depth.
Table 4-23: Summary of 8 Captain X area legacy wells reviewed in detail
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 89 of 151
In Table 4-23, well 13/24b-3 (1997) is an example of an abandoned well that
meets the specification. The target sands are the same as the store depth at
4,987ft MDBRT in the 95/8” casing and are isolated with 3 cement plugs. The
first plug is across the perforation and supported with viscous pill. The second
cement plug is in the 95/8” casing immediately above the first plug. The 95/8”
casing is cut at 1369ft and the shallow set cement T-plug is set inside both the
13 3/8” and 95/8” casings and supported with a bridge plug. All cement plugs are
lapped with annular cement. The second and third cement plugs have been
tagged and tested.
However, well 13/30-1 failed to meet the specification and is reliant on only one
barrier as the shallow set cement plug is not lapped with annulus cement. Well
13/30b-7 was found to be water wet and meet the spec at that time. However,
for a CO2 storage site, it is reliant on only one barrier, which presents a risk to
containment. The recent dynamic modelling results for ACT Acorn indicated that
by moving the injection site CO2 plume contact with well 13/30b-7 can be
avoided completely.
4.7.3 Containment Risk Assessment
A workshop on the containment risk assessment for the subsurface and wells
was carried out and the results are discussed in this section. The risk analysis
on CO2 leakage was conducted using a methodology which allows a fast yet
precise identification and assessment of relevant leakage scenarios. For this
workshop, the term “leakage” was used to define any undesired vertical or
horizontal flow of CO2 out of the primary reservoir (also referred to as “loss of
containment”). The storage site life span is defined as 10,000 years with an
operating life of approximately 30 years.
4.7.3.1 Methodology
The risk assessment is based on the “bow-tie” method, defining threats that may
trigger a top event occurring, which can subsequently lead to other
consequences, (Figure 4-48). Instead of threats, 11 leakage scenarios were
defined. As the top event, the loss of containment, or leakage, was chosen.
Threat barriers and methodologies to reduce the threat, and hence make the top
event less likely to occur, were also discussed. Subsequently, potential
consequences, dependent on both the pre-defined leakage scenario and on the
severity of the loss of containment, were discussed during the consequence
analysis.
Figure 4-48: Adjusted bow-tie diagram displaying the two main steps of the risk assessment: the leakage scenario analysis and the consequence analysis
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 90 of 151
The leakage scenario analysis consisted of three steps:
Definition of leakage scenarios: here, all relevant leakage
scenarios specific to the Captain X area were identified and defined.
Every identified leakage scenario can lead to a theoretical “loss of
containment”.
Identification and assessment of Features, Events and
Processes (FEPs), which relate to the possible ways in which the
system could evolve: Every leakage scenario has generic and
specific FEPs, which will either enhance or reduce both the
likelihood and the severity of the “loss of containment” to occur. A
detailed discussion of the FEPs and how they influence the risk of
leakage scenarios is the core of the leakage scenario analysis.
Identification of threat barriers: Threat barriers are active
procedures to reduce the risk of the loss of containment happening.
They are often specific to the leakage scenario. A quantitative
analysis of how much a threat barrier will reduce the risk of a
leakage scenario occurring has not been performed. Instead,
various threat barriers have been recommended.
The results of the leakage scenario analysis are displayed on a risk matrix to
quantify the likelihood and the severity of the leakage scenario occurring.
The likelihoods are in Table 4-24:
Score Likelihood Frequency
1 Very Low about once in 10,000 years
2 Low about once in 1,000 years
3 Medium about once in 100 years
4 Likely about once in 10 years
5 Very Likely about once per year or more
Table 4-24: Likelihood scale used in Leakage Workshop
The severity of the loss of containment has been defined as the volume of
leakage over the storage life span of 10,000 years relative to the CO2 present in
the storage site according to the storage plan and the scale is shown in Table
4-25. The product of the likelihood and the severity is defined as the risk.
Score Severity CO2
1 Very Low negligible
2 Low >2%
3 Medium 2.1-5%
4 High 5.1-10%
5 Very High >10%
Table 4-25: Severity scale used in the Leakage Workshop
4.7.3.2 Leakage scenario definition
Eleven relevant leakage scenarios were pre-defined for the Captain X area,
(Figure 4-49). They are subdivided into primary pathways (leakage out of the
primary reservoir into the adjacent storage unit) and secondary pathways
(leakage beyond primary pathways).
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 91 of 151
Figure 4-49: The 11 leakage scenarios considered as relevant for the area investigated
Primary Pathways:
CO2 migrating through overlying primary seal, the Rodby and the
Carrick Shale, into secondary reservoir, one of the Palaeocene
sandstone formations.
CO2 enters abandoned well and leaks to the seabed. An abandoned
well is defined as one drilled and completed before the CO2 storage
operation started, and the CO2 then leaks vertically to the seafloor.
CO2 enters a modern well, one drilled for this CO2 storage project
(injection well, monitoring well, pressure relief well, etc) or one that
has been drilled through a CO2 storage site (e.g. for future
petroleum activity) and the CO2 then leaks vertically to the seafloor.
As 2, but CO2 leaks into the secondary reservoir (Palaeocene
sandstone formations).
As 3, but CO2 leaks into the secondary reservoir (Palaeocene
sandstone formations).
CO2 leaks by migrating along the primary reservoir formation, the
Captain sandstone, out of the storage complex in a north-westerly
direction into shallower areas. Migration towards the deeper south-
east is excluded because CO2 will not migrate down-dip.
CO2 leaks by migrating into depleted, underlying Jurassic
formations under production via leakage pathways, such as wells.
Secondary Pathways:
As 1, 4 and 5 but, additionally, CO2 migrates along secondary
reservoirs (Palaeocene sandstones) out of the storage complex.
As 1, 4 and 5 but, additionally, CO2 leaks across the secondary seal
into the overburden.
As 6 and 8 but, additionally, CO2 reaches the seafloor either via a
fault cross-cutting the primary and secondary reservoir or by
migrating all the way along the primary and secondary reservoirs
until they reach the seafloor.
As 9 but, additionally, the CO2 keeps migrating through the
overburden to the seafloor.
4.7.3.3 Consequence analysis
Consequences are traditionally displayed on the right-hand side of the bow-tie
diagram. In the presented method, they are not necessarily directly related to
the severity of the top event but are strongly influenced by the definition of the
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 92 of 151
leakage scenario. Consequences are sometimes, but not always, subject to and
hence dependent on the interpretation of the outcome of a leakage scenario.
Impact Low Medium High
Storage Security
CO2 migrates inside the storage complex or does not reach shallower formations.
CO2 reaches the shallow overburden.
CO2 reaches to the seabed.
Social Acceptance
Not present in the public discussion and no coverage in the media. Covered in the scientific community.
Present in the local news; policy and industry are aware
Nationwide coverage, headline news and broad debate in the public
Environment Minor damage, no threat to the environment.
Local damage, certain threat to flora and fauna and, if any, minor restitution required.
Widespread damage with major risk for the environment; major restitution required.
Hydrocarbon Industry
Negligible impact, strategy plans of hydrocarbon industry do not need adjustment.
Small to medium adjustments may be required.
Major change of industry operations, including long delays and significant costs.
Costs Negligible costs < £10 million > £10 million
Table 4-26: Summary of categories and grades of consequences
Consequences deriving from a leakage scenario with a very low likelihood must
still be regarded as occurring within a reasonable timeframe. The impact of a
consequence is not connected to the likelihood of the leakage scenario
occurring. Consequences considered for the workshop are summarised in Table
4-26.
The impacts of consequences were displayed on a spider diagram (Annex 3:
Leakage Workshop Spider Diagrams) and have three grades: low, medium
and high, (Govindan et al., 2018).
• Impact on storage security: this consequence is pre-defined in the
leakage scenario. It defines where the CO2 leaks to.
• Impact on social acceptance: this is estimated by the assumed
media coverage, such as in print, broadcast or online news outlets,
and intensity of the debate after loss of containment has occurred.
Social uproar due to the loss of containment can be one of the main
consequences, which not only compromises ongoing projects but
also future projects.
• Impact on environment: this summarises the expected
environmental damage on flora and fauna, including the seafloor.
• Impact on hydrocarbon industry: here, the impact on all aspects of
the hydrocarbon industry, such as the production of fields nearby, is
assessed.
• Costs: costs directly related to the loss of containment, such as
remediation-actions, loss of storage licence, etc.
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 93 of 151
4.7.3.4 Results and conclusions
Risk Analysis
Figure 4-50: Summary of the risk of all leakage scenarios; primary pathways in black and secondary pathways in purple
Figure 4-50 shows the results of the risk analysis. In summary:
• No high or very high severity or high or very high likelihood events
were identified.
• 10 of the 11 scenarios have a severity less than three (medium)
which corresponds to low volumes of CO2 relative to the injected
inventory.
• Leakage scenarios with a likelihood of three (medium) or higher
include potential leakage along abandoned wells.
• Loss of containment into the Palaeocene is due to a combination of
abandoned wells and the chalk lithology.
• If the CO2 were to reach the shallower Palaeocene sandstones, it is
likely that it would migrate west and reach 800m depth. The
timescale for this is uncertain.
• Loss of containment of CO2 across geological formations (Leakage
Scenarios 1 and 6), is generally less likely than loss of containment
along wells (Leakage Scenarios 2, 3, 4, 5 and 7).
• Leakage Scenario 6 (lateral loss of containment out of the storage
complex) has the greatest potential CO2 inventory associated with
this loss of containment and hence the greatest severity.
• All leakage scenarios using secondary pathways are expected to
show rather sporadic, negligible volumes of leakage relative to the
injected volume and hence a lower severity.
Consequence Analysis
Figure 4-51 provides a summary of the consequences of all leakage scenarios.
The impact of a consequence is not necessarily connected to the severity
(defined as the volume of leakage over the storage life span of 10,000 years
relative to the CO2 present in the storage site according to the storage plan) of
a leakage scenario, but rather to the leakage scenario itself. For example, small
amounts of CO2 (low severity) to the seafloor will have higher impact on public
acceptance than moderate amounts of CO2 (moderate severity) deep in the
subsurface.
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 94 of 151
Figure 4-51: Summary of consequence impact of all leakage scenarios
The following observations can be drawn about the consequences:
• The scenarios with the greatest consequence relate to CO2 reaching
the seabed (scenarios 2, 3, 10 and 11). Some of these
consequences might involve penalties, loss of EUAs, environmental
damage and remediation costs.
• The scenarios with the lowest consequences are when CO2 remains
within the storage complex, does not impact other subsurface users
and does not require expensive remediation. Scenario 7 has the
lowest overall consequences for these reasons.
• The greatest cost relates mainly to any remediation that would be
required and any fines for loss of containment that may be incurred.
• Impact on public acceptance is directly linked to the location of the
CO2 – if it is within the subsurface but out with the storage complex,
there is still some impact. A leak of CO2 to seabed would have the
greatest impact on public acceptance.
• The consequence of environmental damage only occurs when CO2
reaches the seafloor.
• The impact of a loss of containment of CO2 on the hydrocarbon
industry is generally low. Appropriate care should be given to any
future hydrocarbon development wells penetrating a CO2 storage
site e.g. drilling a deeper target.
Some examples of mitigations include:
• Monitoring of the storage site prior, during and after injection (see
Section 4.7.4) to detect any irregularities early on.
• Limit injection to 90% of the estimated fracture pressure of the
caprock.
• Inject deeper within the reservoir to reduce plume footprint.
• High standards of drilling and completion and quality control to
ensure these standards are in place.
• Future work / research:
o A range of “worst case” modelling studies to consider known
uncertainties and knowledge gaps.
o Detailed modelling of CO2 flow along shallower secondary
containment (Palaeocene) formations.
o Fault seal analysis to assess the likelihood of fault
reactivation and faults as leakage pathways.
o Numerical modelling of sensitivities around CO2 flow along
an open well to surface.
Storage
integrity
Public
acceptanceEnvironment Cost
Hydrocarbon
industry
Scenario 1 Low Medium Low Medium Low
Scenario 2 High High Medium High Low
Scenario 3 High High Medium High High
Scenario 4 Low Medium Low High Low
Scenario 5 Low Medium Low High High
Scenario 6 Low Low Low High Low
Scenario 7 Low Low Low Low Medium
Scenario 8 Low Medium Low High Low
Scenario 9 Medium Medium Low Medium Low
Scenario 10 High High Medium High Low
Scenario 11 High High Medium High Low
Consequence
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 95 of 151
4.7.4 MMV Plan
Monitoring, measurement and verification (MMV) of any CO2 storage site in the
United Kingdom Continental Shelf (UKCS) is required under the EU CCS
Directive (The European Parliament And The Council Of The European Union,
2009) and its transposition into UK Law through amendments to the Energy Act
2008 (Energy Act, Chapter 32, 2008) in 2010 and 2011. A comprehensive
monitoring plan is an essential part of the CO2 Storage Permit.
A list and description of the offshore technologies is in the ETI SSAP Captain X
Storage Development Plan Annex 5 - MMV Technologies, (Pale Blue Dot
Energy & Axis Well Technology, 2016), which has been pulled together from two
reports, (National Energy Technology Laboratory, US Department of Energy,
2012) and (IEAGHG, 2015). Many technologies which can be used for offshore
CO2 storage monitoring are well established in the oil and gas industry.
An MMV Plan was designed for the Captain X storage site in the ETI SSAP
study and has been revised for Phase 1 of the Acorn CCS Project. The outline
corrective measures plan (CMP) discussed in Section 4.7.4.2 has been kept
consistent with previous work. For more detail, including about the purposes of
monitoring and the different monitoring phases and domains, please refer to the
ETI SSAP Captain X Storage Development Plan, (Pale Blue Dot Energy & Axis
Well Technology, 2016).
Additional work will be carried out in the Concept and FEED phases to further
refine and update the MMV plan.
4.7.4.1 Outline Base Case monitoring plan
The outline monitoring plan has been modified from the plan developed for the
ETI SSAP project. The main change is related to the frequency of the 3D seismic
surveys. Since the volumes injected in Acorn Phase 1, which start at 200kT/yr,
are small, the current plan is for 1 x baseline 3D seismic survey to be carried out
prior to injection and 1 x 4D seismic survey to be carried out once injection has
ceased. If subsequent project development phases are sanctioned, with greater
injection rates, the MMV plan will be updated during development planning.
1 x well intervention is planned for Phase 1 and a wireline logging suite will be
run at this time to provide additional data for monitoring.
A distributed temperature sensor (DTS) and pressure and temperature (P/T)
gauges are planned for the injection well. These will provide continuous data
throughout injection.
The frequency and spatial distribution of side scan sonar and sampling of both
seabed and water column will be decided during FEED.
Before the site can be handed over to the Regulator, confidence that the plume
has stabilised must be demonstrated. Due to the uncertainties that exist over
plume migration, (please see Section 4.6 for a discussion on CO2 plume
migration), it may be that the post closure injection phase is extended beyond
20 years, with more extensive monitoring during this time. The post closure
monitoring period has been kept at 20 years but noting that this could be
extended. Annual MMV reporting to the Oil and Gas Authority (OGA) will include
information about site performance and may include commentary around any
site-specific monitoring challenges that have occurred, which could include
uncertainties over plume stabilisation. An on-going dialogue with the Regulator
will be key to managing this uncertainty.
Figure 4-52 maps the selected technologies to the leakage scenarios discussed
in Section 4.7.3. The colours correspond to those in the risk matrix in Figure
4-50.
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 96 of 151
4.7.4.2 Outline corrective measures plan
The corrective measures plan will be deployed if either leakage or significant
irregularities are detected from the MMV plan data. Examples of significant
irregularities and their implications are shown in Table 3-32.
Once a significant irregularity has been detected, additional monitoring may be
carried out to gather data which can be used to more fully understand the
irregularity. A risk assessment should then be carried out to decide on the
appropriate corrective measures to deploy, if any. It may be that only further
monitoring is required.
For the leakage scenarios discussed in Section 4.7.3 and mapped to MMV
technologies in Figure 4-52, some examples of control actions and remediation
options are shown in Table 4-27.
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 97 of 151
Figure 4-52: Leakage scenario mapping to MMV technology. The colours correspond to the risk matrix in Figure 4-50
D07 Acorn CO2 Storage Site Development Plan Site Characterisation
ACT Acorn Consortium Page 98 of 151
Outline Corrective Measures
Control/ Mitigation Actions Potential Remediation Options
Leak
age
Sce
nar
io
Overburden 1 Primary reservoir to secondary reservoir
Investigate irregularity, assess risk, update models if required, increased monitoring to ensure under control
Increased monitoring to ensure under control (CO2 should be trapped by additional geological barriers in the overburden)
4 Primary reservoir to secondary reservoir via abandoned well
Investigate irregularity, assess risk, update models if required, increased monitoring to ensure under control
Increased monitoring to ensure under control. Consider adjusting injection pattern if can limit plume interaction with pre-existing wellbore. Worst case scenario would require a relief well (re-entry into an abandoned well is complex, difficult and has a very low chance of success)
5 Primary reservoir to secondary reservoir via modern well
Stop injection, investigate irregularity, acquire additional shut-in reservoir data, update models
Replacement of damaged well parts (e.g. tubing or packer) by workover. Worst case scenario would be to abandon the injection well.
8 Lateral movement out of secondary reservoir after 1/4/5
Investigate irregularity, assess risk, update models if required, increased monitoring to ensure under control
Increased monitoring to ensure under control (CO2 should be trapped by additional geological barriers in the overburden)
9 Primary reservoir to overburden after 1/4/5
Investigate irregularity, assess risk, update models if required, increased monitoring to ensure under control
Increased monitoring to ensure under control (CO2 should be trapped by additional geological barriers in the overburden)
Seabed 2 Primary reservoir to seafloor via abandoned well
Stop injection, investigate irregularity via additional monitoring at seabed and acquisition of shut-in reservoir data, assess risk, update models
Re-entry into an abandoned well is complex, difficult and has a very low chance of success. A relief well would likely be required.
10 Vertical movement to seafloor after 6 and 8
Stop injection, investigate irregularity via additional monitoring at seabed and acquisition of shut-in reservoir data, assess risk, update models
If injection well - replacement of damaged well parts (e.g. tubing or packer) by workover. Worst case scenario would be to abandon the injection well. If P&A well - a relief well may be required.
3 Primary reservoir to seafloor via modern well
Stop injection, shut in the well and initiate well control procedures, investigate irregularity via additional monitoring at seabed and acquisition of shut-in reservoir data, assess risk, update models
Replacement of damaged well parts (e.g. tubing or packer) by workover. Worst case scenario would be to abandon the injection well.
11 Vertical movement from overburden to seafloor after 9
Stop injection, investigate irregularity via additional monitoring at seabed, assess risk
If injection well - replacement of damaged well parts (e.g. tubing or packer) by workover. Worst case scenario would be to abandon the injection well. If P&A well - a relief well may be required.
Lateral 6 Lateral movement out of primary reservoir
Investigate irregularity, assess risk, update models if required, increased monitoring to ensure under control
Continue to monitor, licence additional area as part of Storage Complex if required.
U'burden 7 Vertical movement into underlying reservoir
Investigate irregularity, assess risk, update models if required, increased monitoring to ensure under control
Continue to monitor, licence additional area as part of Storage Complex if required. Worst case scenario: a relief well may be required to plug 13/7-b (re-entry into an abandoned well is complex, difficult and has a very low chance of success)
Table 4-27: Outline corrective measures plan
D07 Acorn CO2 Storage Site Development Plan Appraisal Planning
ACT Acorn Consortium Page 99 of 151
5.0 Appraisal Planning
Appraisal Drilling: Whilst some uncertainties do remain regarding the
subsurface reservoir and caprock properties, the Geomechanical research
undertaken by the University of Liverpool for the ACT Acorn CCS Project (D06
Geomechanics) has provided additional insights. Any remaining uncertainties
are not considered to currently justify the expense of an additional appraisal well.
In addition, the Captain Sandstone has undergone hydrocarbon exploration and
extraction since the 1970s, with extensive drilling, logging, coring, testing, the
results of which are mostly on the CDA. Hydrocarbon production indicates that
there is hydraulic connectivity across the fairway.
Seismic Acquisition: The PGS MegaSurvey used for the interpretation over
the Acorn CO2 Storage Site does not include “offset or angle stacks” which might
improve the quality of data in some of the more challenging areas of
interpretation. As described in the site characterisation section, the Top and
Base Captain are poor seismic reflectors due to a lack of impedance contrast
over them. This feeds into a depth conversion uncertainty and therefore
uncertainty in the Top Captain structure map and ultimate plume migration.
Other 3D seismic surveys over the Acorn CO2 storage site area have “angle
stacks” which may be a data acquisition option going forward. Another option is
to acquire new (possibly broadband) seismic, which could also provide a
baseline survey for the monitoring, measurement and verification (MMV) plan,
against which all future surveys will be assessed. Broadband seismic retains
more of the lower frequencies which helps in undertaking seismic inversion.
Before making any procurement decision, it is recommended that a modern rock
physics study and seismic acquisition modelling study is completed to confirm
whether the imaging at Top Captain can be improved upon before a decision is
taken to acquire new seismic. This should also be revisited to check the
performance of a new survey in tracking plume migration. The final investment
decision on the project is not currently considered dependent on acquisition of
a new seismic survey.
Other Appraisal Activity: Further modelling work is recommended which is
fully calibrated to well by well production and pressure data from the operators
of Blake, Atlantic, Cromarty and Goldeneye. In addition, complete well
abandonment records should be sought from Operators as not all abandonment
records are on the CDA database. It is also important to work closely with all
petroleum operators in the area to ensure that wells are abandoned to maintain
maximum subsurface integrity in the light of a potential future CO2 storage
development. This is required to eliminate any further degradation of engineered
containment risk introduced through well abandonment operations.
D07 Acorn CO2 Storage Site Development Plan Development Planning
ACT Acorn Consortium Page 100 of 151
6.0 Development Planning
6.1 Description of Development
The Acorn CO2 storage site is in the Captain Sandstone Member, part of the
Captain Fairway in the outer Moray Firth.
The current base case for the Acorn CO2 storage site development is to use the
existing 18”/16” Atlantic pipeline from St Fergus to the Atlantic depleted
condensate field, (via an acquisition from Shell).
The storage site will be developed subsea rather than using a platform, with an
umbilical to shore as the base case for providing power and control to the
wellhead. Remote technology options are currently being explored, which would
eliminate the need for an umbilical to shore.
Only one subsea well will be required with the adoption of the 4” Monoethylene
Glycol (MEG) line from the Atlantic and Cromarty pipeline for start-up and restart
operations. An infield flowline will be required from the end of the Atlantic
pipeline to deliver the CO2 to the injection site.
Figure 6-1: Key elements of offshore infrastructure
6.2 CO2 Supply Profile
As indicated previously in the Storage Development Plan, the assumed initial
supply rate for the reference case, Phase 1, starts at 200kT/yr in 2023 from the
St Fergus terminal, delivered via one injection well. The profile is shown in
Figure 6-2 as Scenario 1, with the reference case resulting in a cumulative
injection of 4.2MT CO2 over 17 years. For the dynamic modelling, the range of
possible injection rates for one well was explored, up to 1.5MT/yr.
The ACT project deliverable D02 CO2 Supply Profile, (Pale Blue Dot Energy,
2017), explored several possible CO2 supply scenarios, based on possible
future build-out of the Acorn CCS Project to include emissions from central
Scotland and importation of CO2 via ship to Peterhead port. These have been
modelled for the Acorn CO2 storage site and are described below and shown in
Figure 6-2:
• Phase 1 – Minimum Viable Development Case (Scenario 1):
~200kT/yr from part of the current St Fergus emissions, injected via
one subsea injection well in the injection site between the Atlantic
and Cromarty depleted fields, starting in 2023.
• Phase 2 – 64MT Case (Scenario 2): Emissions include those in the
Base Case, plus those from a potential build-out scenario, including
CO2 captured from hydrogen generation and importation of CO2 via
Peterhead Harbour (from shipping), with a maximum injection of
2.7MT/yr.
• Phase 3 – 152MT Case (Scenario 3): A supply rate capped at
5MT/yr (259mmscfd) via four injection wells at several injection sites,
D07 Acorn CO2 Storage Site Development Plan Development Planning
ACT Acorn Consortium Page 101 of 151
including one near the Goldeneye depleted gas field, and brine
production for pressure management. Emissions include those in the
Base Case, plus those from a potential build-out scenario, including
CO2 captured from hydrogen generation, importation of CO2 via
Peterhead Harbour (from shipping) and importation of Grangemouth
emissions via the Feeder 10 pipeline to St Fergus.
Figure 6-2: Three different CO2 supply scenarios envisaged for the Acorn project
6.3 Well Development Plan
The well engineering aspects of the Acorn storage site were provided by Axis
Well Technology, (Axis Well Technology, 2017).
For the Acorn CCS Project, the most economical development strategy is a
subsea development. The advantage of a subsea well over a platform well is
that it does not require expensive superstructure and it therefore carries
considerably lower capital costs for single well projects. If no maintenance is
expected on the well during its lifetime, the cost savings can be considerable.
One additional cost carried by a subsea well is that of the control umbilical.
Options for remote control and monitoring or reducing the umbilical length (e.g.
via a nearby platform vs shore) will be explored during Concept.
For a CCS development, the primary risks from a single subsea well
development are filtration and single-well downtime risk.
Filtration - For some injection wells, the removal of fine particulates from the
injection stream can be critical. If this is not done, then it can lead to a rapid
degeneration of injectivity as the rock pore throats are plugged with fines.
Platform wells can incorporate a filter pod on the upstream injection line,
removing any particulates carried from the pipeline. These filters can be
replaced or cleaned out on a regular basis. At present, there is no equivalent
subsea filter system. Particulate debris remains a residual risk for subsea wells
and therefore for the project. A pipeline pigging (cleaning) programme may
reduce the initial particulate loading but is unlikely to prevent long term damage
from continuous corrosion products. It is recommended this is explored more
fully in the Concept work and has been assumed every 5 years at this stage.
Downtime - Should the well suffer any problems, including temporary or
permanent plugging issues, integrity issues or control issues, the well may need
to be shut-in for a period. As a single-well development (no redundancy), this
means that no injection can take place and may require storage in temporary
tankage.
D07 Acorn CO2 Storage Site Development Plan Development Planning
ACT Acorn Consortium Page 102 of 151
With a subsea well, the wellhead will be located close to the reservoir injection
point than for a platform well, meaning that a lower cost vertical well can be
drilled. It is preferred that the well profile through the reservoir is at a moderate
angle of 60° to increase the reservoir contact and to provide some offset of the
point of injection from the caprock penetration point. A modest build rate of 3°
per 30m has been assumed, to achieve a 60° angle through the reservoir. This
results in a kick-off point at around 1,500m and a lateral offset of around 400m
at the bottom of the well. Note that no drilling engineering has been done to
verify the suitability of this kick-off point. However, there is confidence that this
well profile can be delivered as there are several ways in which the same profile
can be achieved.
6.3.1 Well Design
The well design described in this section is for a dual completion single subsea
well, which would be suitable for both Phase 1 of the Acorn CCS storage project
(with a maximum CO2 supply rate of 281kT/year captured at the St Fergus gas
processing plant) and subsequent phases. During subsequent phases,
additional wells will be required to match the CO2 supply profile. These are likely
to be single bore wells and not dual completion wells like the initial one.
The key design criteria for the Phase 1 subsea injection well is that it must be
capable of a large range of injection capacities, starting from a relatively low
injection rate of 0.1MT/yr during start-up, ramping up to 2MT/yr over a period of
time as further injection capacity is required as subsequent CO2 sources come
on-line. Please see Sections 4.6.1 for results of the well performance modelling
and key inputs for the well design.
6.3.2 Well Construction
The following preliminary reservoir target was used for the well design, as the
proposed injector coordinates had not yet been finalised (Table 6-1):
Target Name TVDSS
(m) UTM North
(m) UTM East
(m)
GI-01 Top Captain (preliminary)
2,014 6,440,148 265,001
Table 6-1: Preliminary well location used in well design
The revised well location for the primary injector following the dynamic modelling
work is shown in Table 6-2.
Target Name
TVDSS (m)
UTM North (m)
UTM East (m)
G2 Top Captain
2,005 6,440,286 264,946
Table 6-2: Well location as determined from dynamic modelling
The conceptual directional plan for the CO2 injector has been designed on the
following basis:
• The well will be drilled as a slant well.
• The well will be drilled vertically to around 1,500m TVD.
D07 Acorn CO2 Storage Site Development Plan Development Planning
ACT Acorn Consortium Page 103 of 151
• The well will be kicked off at around 1,500m TVD, with a planned
modest build rate of 3° per 30m, to achieve a 60° angle through the
reservoir.
• A build section will be drilled from the kick-off depth to the depth at
which inclination is sufficient to reach the identified reservoir target.
• The reservoir section will be drilled as a tangent section, holding
inclination at 60° to TD.
A deviation survey plot is provided in Figure 6-3.
Figure 6-3: Well profile to the reservoir
6.3.2.1 Well completion
Lower Completion:
The lower completion would consist of 51/2’’ stand-alone sand screens. Any
shale sections can be isolated by blank pipe (with or without external isolation
packers). This will allow the formation sands to “relax” and form a pack around
the screens. Open hole gravel pack could be considered, but as it is a more
expensive and technically complex installation operation, it is felt that the risk of
D07 Acorn CO2 Storage Site Development Plan Development Planning
ACT Acorn Consortium Page 104 of 151
poor clean-up or inefficient installation outweighs the benefits. Note that reactive
shales are unlikely to be a risk in CO2 injection wells.
The 95/8’’ shoe would be set around 40ft to 80ft into the Captain Sandstone
formation at an angle of 60°, thereby providing some offset from the top injection
point through the screens to the penetration point. This also provides a vertical
stand-off of 20 to 40ft TVD between the top injection depth and the caprock for
thermal and fracture initiation moderation.
Upper Completion:
The upper completion consists of a dual completion 27/8’’ / 41/2’’ tubing string,
anchored at depth by a production packer in the 95/8’’ production casing, just
above the 51/2’’ lower completion hanger. Components include:
• 27/8’’ 13Cr tubing (weight to be confirmed with tubing stress analysis
work)
• 4½’’ 13Cr tubing (weight to be confirmed with tubing stress analysis
work)
• 95/8’’ Production Packer
• ‘Y’ piece connector above packer depth
• Deep Set Surface-controlled Tubing-Retrievable Isolation Barrier
Valve (wireline retrievable, if available), on the 41/2’’ ‘long string’
• Permanent Downhole Gauge (PDHG) for pressure and temperature
above the production packer
• Optional DTS (Distributed Temperature Sensing) installation
• Tubing Retrievable Sub Surface Safety Valve (TRSSSV) x 2
• Dual bore subsea production tree
The DTS installation will give a detailed temperature profile along the injection
tubulars and can enhance integrity monitoring (leak detection) and give some
confidence in injected fluid phase behaviour. The value of this information
should be further assessed, if confidence has been gained in other projects
(tubing leaks can be monitored through annular pressure measurements at
surface, leaks detected by wireline temperature logs and phase behaviour
modelled with appropriate software).
A summary well construction illustration (without DTS) is included in Figure 6-4.
D07 Acorn CO2 Storage Site Development Plan Development Planning
ACT Acorn Consortium Page 105 of 151
Figure 6-4: Well construction illustration
The outline drilling, casing and mud programme for the well, based on the
assumption that the drilling parameters are similar to the ones considered in the
ETI SSAP study, (Pale Blue Dot Energy & Axis Well Technology, 2016), is
provided in Table 6-3. Note that the ETI SSAP study assumed platform (and
therefore dry) wells.
Section Casing Drilling Mud Comment
Surface (driven)
26" Conductor, 60m below mudline
Surface hole (20")
20’’ x 133/8’’ Cemented to the mudline
10.0ppg (seawater and viscous sweep)
Casing should be set directly below the top of the Chalk Formation
Intermediate hole (12¼”)
95/8’’ Cemented to 1000m below the 133/8’’ shoe
11.5ppg (oil-based mud)
Casing should be set 12 to 25m MD below the top of the Captain Sandstone
Production hole (8½”)
51/2‘’ Stand-alone sand screens
9.5ppg (oil-based mud)
Table 6-3: Outline well construction programme
6.3.3 Injection Forecast
For the Acorn CCS Project Phase 1, injection would commence in 2023 and
continue for approximately 17 years. The final year of injection would be 2039.
The injection forecast for the reference case starts at 200kT/yr and builds to
D07 Acorn CO2 Storage Site Development Plan Development Planning
ACT Acorn Consortium Page 106 of 151
281kT/yr. This forecast results in a cumulative injection of 4.2MT of CO2 which
would be delivered by one injection well.
Year Rate
(kT/yr) Total (kT) Year
Rate (kT/yr)
Total (kT)
2022 0 0 2032 281 2647
2023 199 199 2033 281 2929
2024 199 398 2034 281 3210
2025 281 679 2035 281 3491
2026 281 960 2036 281 3772
2027 281 1241 2037 281 4053
2028 281 1523 2038 82 4136
2029 281 1804 2039 82 4218
2030 281 2085 Total 4218
2031 281 2366
Table 6-4: Injection profile
6.4 Offshore Infrastructure Development Plan
This chapter reviews the recommended facility to transport CO2 from St Fergus
for injection into the Acorn CO2 storage site. A review of the current CO2 injection
in offshore applications is also briefly covered.
6.4.1 Offshore CO2 Injection Facilities
The one subsea well required initially to meet the proposed injection rates will
be drilled by a semi-sub drill rig. A subsea manifold will be installed to allow CO2
to be distributed to future injection well(s). The manifold houses the subsea
umbilical termination unit (SUTU) and would also function as the subsea
distribution assembly (SDA). Control and monitoring of the manifold would come
via the subsea control module (SCM) mounted on the injection tree, which would
also control the actuated valves and monitors on the tree itself. The subsea
manifold will have a piled fishing friendly structure (shaped to minimise damage
to and from fishing gear). A subsea well is considered as both the most
economical and technically suited development concept.
The 4” Monoethylene Glycol (MEG) line from the Atlantic and Cromarty fields
may be adopted for start-up and restart operations. A new umbilical to shore is
the base case for providing control and monitoring of the tree. As mentioned
previously, remote technology options are currently being explored.
6.4.2 Overview of Pipeline Facilities
For the Acorn CCS Project, the CO2 supply will come from St Fergus where
gathered CO2 will be transported via existing pipeline to the Acorn CO2 storage
site. Figure 6-5, (BG Group, 2016), shows the target storage site along with the
available transportation facilities in its vicinity. The proposed injection site is
approximately 80km from St Fergus and approximately 8km from the end of the
Atlantic Pipeline.
The development plan will use the Atlantic pipeline and for future build out
scenarios, the Goldeneye pipeline may be required (for Phase 3).
Atlantic Pipeline
The Atlantic Pipeline (also referred to as the A&C pipeline), connected the
Atlantic and the Cromarty (A&C) fields to the St Fergus gas terminal. The
Atlantic pipeline is 78km long and 16” in diameter apart from the initial 1.2km
from the beach at St Fergus which is 18” (BG Group, 2016). The pipeline was
D07 Acorn CO2 Storage Site Development Plan Development Planning
ACT Acorn Consortium Page 107 of 151
designed with the aim that it could serve other potential users well beyond the
CoP of the A&C fields in 2009. The nominal capacity of the Atlantic pipeline was
circa 232mmscfd, (Apache, 2017). During operation, gas and gas condensate
produced from the two Atlantic wells and single Cromarty well were routed to
the Atlantic manifold and then, via the Atlantic pipeline to the Scottish Area Gas
Evacuation (SAGE) terminal at the St Fergus gas processing plant. Section
6.4.2 shows that the pipeline can handle a rate of 5MT/yr of CO2
The statutory and public consultation on the draft decommissioning programme
for the field’s facilities took place in the autumn of 2016 with responses being
explored further pending submission of the final decommissioning programme
in 2017, (UK Government, 2017). Within the decommissioning programme, the
pipeline itself and its associated piggy-backed monoethylene glycol (MEG) lines
will be cut, flooded and remain in the place to corrode away whilst the Atlantic
manifold will be removed and brought onshore for recycling, (BG Group, 2016).
The Goldeneye Pipeline
The Goldeneye Pipeline connected the Goldeneye field to the St Fergus gas
Terminal. The Goldeneye pipeline is a 20” 130km pipeline used to transport
produced fluid from the Goldeneye field located in Block 14/29a of the UK sector
of the North Sea for onshore processing.
Goldeneye ceased production in March 2011 and has been considered for CO2
storage by its owner Shell. However, following cancellation of the Peterhead
CCS project in 2015, Shell is now progressing decommissioning plans, (UK
Government, 2017). The nominal capacity of this pipeline is around
1100mmscfd, (Apache, 2017).
The Atlantic pipeline and its respective facilities have been prioritised over the
Goldeneye pipeline for the following reasons:
• The Goldeneye field is located 30km further west of the Captain X
area which requires additional pipeline construction from Goldeneye
to the Captain X storage area.
• The maximum operating pressure (MOP) of the Goldeneye pipeline
is 132barg (compared to 170barg of the Atlantic pipeline) which is
less than the maximum Acorn CCS Project injection pressure
requirement of 160barg, (Pale Blue Dot Energy & Axis Well
Technology, 2016).
However, both remain potential options at this stage.
It is assumed that a new flowline will be required to connect the end of the
Atlantic Pipeline with the injection manifold.
D07 Acorn CO2 Storage Site Development Plan Development Planning
ACT Acorn Consortium Page 108 of 151
Figure 6-5: transportation Infrastructure overivew
Overview of the available transportation infrastructures near the Captain X area.
Yellow area shows the approximate extent of the Captain X area
Figure 6-6, (BG Group, 2016), shows the A&C facilities.
Atlantic Pipeline Asset Status
Decommissioning plans for the A&C facilities are advanced with the
decommissioning programme submitted by BG (the operator of the A&C fields)
to the Department of Business Energy and Industrial Strategy (BEIS), (UK
Government, 2017). Since the acquisition of BG by Shell, Shell have become
operator of the Atlantic facilities.
Figure 6-6: Atlantic and Cromarty field layout
Several options were investigated by BG for reusing the A&C facilities. These
include gas storage, CO2 storage (2012-13 discussion with DECC) and sale of
facilities and infrastructure to other companies, (BG Group, 2016). According to
BG, none of these discussions have progressed, although there remains interest
by third parties in the possibility of continued preservation of the Atlantic pipeline
for transporting CO2 for offshore storage.
6.4.3 The Atlantic Pipeline
Table 6-5 shows the design parameters of the Atlantic pipeline, (Pale Blue Dot
Energy & Axis Well Technology, 2016). After formal cessation of production
(CoP) (2011), the Atlantic pipeline was cleaned and put into the Interim Pipeline
Regime (IPR) pending investigation of options to extend the useful life of this
D07 Acorn CO2 Storage Site Development Plan Development Planning
ACT Acorn Consortium Page 109 of 151
facility. The export and MEG pipelines are trenched and mostly buried along
their length, apart from a short section at the shore approach, close to the
Atlantic manifold and at crossings which are rock covered, (BG Group, 2016).
Based on the outcome of the comparative assessment of feasible options, the
recommendation for decommissioning the offshore pipelines and umbilicals is
to leave these in place with minimum intervention, i.e. to disconnect them from
the Atlantic manifold and Goldeneye platform, cutting and removing them where
they emerge from burial and applying remedial rock cover to the cut ends to
mitigate against the risk of snagging by other sea users, (UK Government,
2017).
D07 Acorn CO2 Storage Site Development Plan Development Planning
ACT Acorn Consortium Page 110 of 151
Parameter Value
PL ID (BEIS) PL2029
Design life 20 years
Outer diameter 16”
Wall thickness 0.61”
Material X65 Carbon Steel HFW (high frequency welded)
Corrosion allowance 3mm
External coating Concrete weight coating 40-60mm thick
Internal coating 0.075mm internal thin film epoxy coating
Cathodic protection Coating and cathodic protection (CP) anodes
Design pressure 170barg
MOP 170barg
Operating pressure 82barg
Design temperature 60/-10°C
Operating temperature 50°C
Table 6-5: Atlantic pipeline design parameters
The pipeline has been designed for a 20-year service life of which less than 4
years has been used (from 2005 to 2009) which means considerable service life
remains. The pipeline has an internal epoxy layer which further protects it from
corrosion and erosion.
Should the pipeline be reused for CO2 transportation, a full pipeline inspection
to check its integrity will be required to ensure the pipeline is suitable for CO2
transportation. This may include ROV inspection to visually inspect the status of
the pipeline, intelligent pigging, end to end testing, hydrostatic pressure testing
and finally drying. The DNV RP J202 ‘Design and Operation of CO2 Pipelines’
demonstrates the recommended requalification process for using pipelines for
CO2 transportation, (Veritas, Det Norske, 2010).
Onshore experience shows that if a CO2 leakage occur from a pipeline, the CO2
pressure and temperature will rapidly decrease, (IEAGHG, 2017). This may
impose significant thermal stress to the pipeline making it brittle. Since the
Atlantic pipeline is located offshore the situation may be different to onshore
experience, but impact of potential leaks must be thoroughly considered.
Assuming the Atlantic pipeline will be reused for CO2 storage in the Acorn
Storage Site, Section 6.4.4 investigates the expected operating condition along
the Atlantic pipeline.
6.4.4 Expected operating conditions along the Atlantic pipeline
ACT Acorn Deliverable D02 CO2 Supply Options provides a description of the
likely CO2 supply profiles for CO2 injection into the Acorn CO2 storage site. Using
the scenarios, the expected operating conditions along the Atlantic pipeline for
different supply scenarios was calculated.
6.4.4.1 Inputs and assumptions
Some assumptions have been made before estimating the actual profiles along
the Atlantic pipeline. For pipeline trajectory, it was assumed that the whole
pipeline length from St. Fergus to the Captain X area (injection site) of 87.6km
is divided into three main sections, (BG Group, 2016):
D07 Acorn CO2 Storage Site Development Plan Development Planning
ACT Acorn Consortium Page 111 of 151
An onshore first section of 1.6km (18”) from St. Fergus terminal
(+15m elevation) to beach (0m elevation).
An offshore second section of 78km from beach (0m elevation) to
the end of Atlantic pipeline (-115m depth). The pipeline diameter for
this section is 16” except for the first 1.2km of the pipeline where it
is 18”. The pipeline resides on the seabed. Over the first 45km of
pipeline the seabed depth below sea level is assumed to drop
linearly from 0m to -90m. From the 45km mark to the 78km mark
the sea bed flattens out and the depth is assumed to drop linearly -
90m to -115m, the latter being at the end of the Atlantic pipeline.
A final third 8km 16” section of pipeline which delivers CO2 from the
end of the Atlantic pipeline to the Phase 1 injection well G02 is
assumed to lie flat.
The seabed mean temperature was assumed to be 8°C for this modelling work,
(BG Group, 2016). The CO2 temperature at the St Fergus terminal compressor
discharge was assumed to be between 10-30°C with a base case temperature
of 20°C. The Longannet FEED close out report references keeping the CO2
temperature below 29°C to avoid ductile fracture formation, (ScottishPower CCS
Consortium, 2010). Similarly, in their 2016 Basic Design and Engineering
Package report for the Peterhead CCS project, Shell referenced 124barg gas
being cooled to below 25°C to reduce ductile fracture risk, (Shell, 2016).
The pipeline has been assumed to be coated with a heat transfer coefficient of
2BTU/h.deg°F.ft2. Other extremes of heat transfer scenarios were also
investigated; a completely bare pipeline without any insulation with a heat
transfer coefficient of 20Btu/h.deg°F.ft2 and a completely insulated pipeline with
a heat transfer coefficient of 0.2Btu/h.deg°F.ft2. The CO2 stream is assumed to
be completely pure. A delivery pressure of 130barg at the injection manifold has
also been assumed. The Schlumberger software Pipesim has been used to
generate the profiles shown in Figure 6-7.
The modelling investigated the following parameters for all three injection
scenarios (discussed in the dynamic modelling section 4.6.5):
• Bare pipe
• Insulated pipe
• Discharge Temp 10oC
• Discharge Temp 30oC
For each scenario, the following plots are shown in Figure 6-7:
• Pressure vs pipeline length
• Temperature vs pipeline length
• Velocity vs pipeline length
• Pressure vs temperature
6.4.4.2 Results
Figure 6-7 shows profiles for pressure and temperature along the pipeline under
different CO2 supply scenarios. The top row of images illustrates pressure
profiles along the length of the pipeline. Starting from the St Fergus terminal
(furthest left), it can be seen that pressure increases all the way through the
pipeline toward the subsea injection site (where pipeline elevation primarily
decreases i.e. the inlet pressure is less than the outlet pressure) due to different
hydrostatic head between the two ends of the pipeline.
At the lowest injection rate (Phase 1), the frictional pressure drop component is
considerably smaller than the hydrostatic pressure increase through the
pipeline. As the supply rate increases, the extent of this observation becomes
smaller and finally, at 5MT/yr (Phase 3) scenario, the frictional pressure drop
D07 Acorn CO2 Storage Site Development Plan Development Planning
ACT Acorn Consortium Page 112 of 151
component dominates. Now, apart from a small section of the pipeline, it can be
seen that the pressure decreases for the rest of pipeline length, all the way to
the injection site. Nevertheless, all the profiles follow the same footprint in that
no distinction can be made between different sensitivity analysis scenarios that
have been simulated.
The maximum pressure along the pipeline of 145barg was observed for the
5MT/yr scenario just at the location where the pipeline diameter decreases. This
is still well below the maximum operating pressure of 170barg, (Table 6-6).
Inspection of temperature profiles in the second row of images in Figure 6-7
show that unless the pipeline is completely insulated, the CO2 stream
temperature finally reaches the ambient water temperature (8°C). Depending on
the CO2 flow rate, this will happen in between the first 10-60km of the pipeline
length. Note that at lower CO2 supply rates, more time will be available for heat
transfer to occur between CO2 and water at the periphery of the pipeline, thus
temperature drops earlier in the pipeline length.
D07 Acorn CO2 Storage Site Development Plan Development Planning
ACT Acorn Consortium Page 113 of 151
Figure 6-7: Operating conditions along the Atlantic pipeline
Shown for all CO2 supply scenarios. The region to the left of the dashed line in the P/T graphs (last row) show the potential hydrate formation regions
D07 Acorn CO2 Storage Site Development Plan Development Planning
ACT Acorn Consortium Page 114 of 151
Inspection of velocity profiles on the third row of images shows that for all the
scenarios, the maximum velocity occurs at the inlet of the 16” pipeline where the
diameter of the pipeline decreases (from 18” to 16”). Except for the fully
insulated scenario (shown in green), the velocities converge to the same value
depending on the CO2 supply rate. Note that there is correlation between
velocity and temperature profiles in that as soon as temperature drops along the
pipeline, CO2 density increases and velocity decreases. For the fully insulated
scenario, since heat transfer is relatively small, the temperature does not drop
considerably and thus velocity does not decrease notably either. The maximum
observed velocity is for the 5MT/yr CO2 supply scenario which is almost 1.6m/s
(5.8km/h). For the 5MT/yr scenario, it was originally anticipated that CO2 velocity
would increase along the pipeline because of pressure drop and CO2 expansion.
However, since the CO2 temperature effect is more dominant than CO2
expansion, this phenomenon may not be observed.
Finally, the last row of images in Figure 6-7 shows the P/T cross plot along the
pipeline. Except for the fully insulated pipeline scenario, nearly all scenarios
terminate at 130barg and 8°C. The grey dashed vertical line in these figures
show the hydrate formation boundary discussed later. For now, note that the
area to the left of the vertical grey dashed line is the region where hydrate
formation is probable if water content within the CO2 stream increases
significantly.
Table 6-6 shows the inlet pressure and the maximum operating pressure
observed for each CO2 supply scenario under the base case pipeline
parameters described earlier. Note that the inlet pressure is usually the pressure
for which the CO2 compression facilities should be designed.
Overall, these profiles together with the design parameters of the Atlantic
pipeline in Table 6-5 show that all the foreseen CO2 supply scenarios can be
effectively handled by the current 16” Atlantic pipeline.
Scenario
Maximum Injection Quantity (kT/yr)
Inlet Pressure (barg)
Maximum Observed Pressure (barg)
Outlet Pressure (barg)
1 281 118.3 130 130
2 2,682 125.4 131 130
3 5,000 142.2 143.3 130
Table 6-6: Maximum operating pressure under different CO2 supply scenarios
6.4.5 Flow Assurance Considerations
Figure 6-8 shows the Pressure/Temperature (P/T) profile along the Atlantic
pipeline for the base case supply scenarios investigated in the previous section.
The data in this figure can be used to infer the likelihood of several flow
assurance considerations. This includes CO2 hydrate formation and phase
shifting between gaseous and liquid phases. Having a proper understanding of
the potential flow assurance issues helps avoid large and complex expenditures
that could occur in future.
D07 Acorn CO2 Storage Site Development Plan Development Planning
ACT Acorn Consortium Page 115 of 151
Figure 6-8: Pressure/Temperature profile observed in the Atlantic pipeline for different supply scenarios. Arrows show the direction of the profile from St Fergus to injection site on the left. The red region is the likely hydrate formation region
6.4.5.1.1 Hydrate and ice formation
Formation of CO2 hydrate may affect the safe pipeline operation and therefore,
must and can be avoided by ensuring a CO2 quality specification is maintained.
The formation of hydrate is described and controlled by the hydrate phase
boundary.
Figure 6-8 shows the hydrate phase boundary generated for a pure CO2 stream.
The data depicted in Figure 6-8 may be used to assess the probability of hydrate
formation along the Atlantic pipeline under different CO2 supply scenarios. For
this, the red area in Figure 6-8 shows the hydrate formation phase envelope.
Although it appears that only a small portion of the P/T regions may fall in the
hydrate formation region, it must be considered that this small P/T region
corresponds to a large physical distance along the pipeline where CO2
temperature has fallen to ambient sea water. The profile shown in Figure 6-8
illustrates the worst likely scenario that could occur if free phase water for
whatever reason appears in the pipeline along the CO2 stream. Given the extent
of hydrate formation depends on the water content of the CO2 stream, the risk
of hydrate formation can be effectively managed by ensuring appropriate drying
of the CO2 prior to the CO2 entering the pipeline, e.g. to below 200ppm water
content.
6.4.5.1.2 Corrosion and erosion
Cooling and drying the CO2 stream before injecting into the pipeline also protects
the pipeline from corrosion, particularly at the pipeline inlet where CO2
temperature may be at its highest. During evaluation of the Peterhead CCS
project, Shell concluded that the pipeline inlet temperature should be maintained
below 29°C, (Shell, 2016). Injecting MEG could be a possible mitigation strategy,
however, since the direction of the flow is now reversed (i.e. is from shore to
sea), this may require MEG gathering facilities at the injection site, otherwise,
the CO2 stream mixed with MEG may be injected directly and provide further
corrosion inhibition for the wellbore and the injection facilities.
As with the corrosion, erosion is expected to be particularly important in the first
few kilometres of the pipeline since CO2 density is lower which means that CO2
velocity is higher.
6.4.5.1.3 CO2 shifting between gaseous and liquid phases
CO2 phase shifting between gaseous and liquid conditions may cause significant
sudden volume change; this is not safe and should be avoided. To minimise the
chance of phase change occurring in the pipeline, the CO2 discharge
temperature will be kept below 30°C which is less than the CO2 critical
D07 Acorn CO2 Storage Site Development Plan Development Planning
ACT Acorn Consortium Page 116 of 151
temperature (31°C). Temperature further decreases along the pipeline due to
heat transfer between CO2 and the periphery seawater and this coupled with the
CO2 pressure remaining above the CO2 critical pressure (74bar; Figure 6-8)
means that the CO2 will always remain at dense phase throughout the pipeline
and thus the risk of phase change is minimal.
6.4.6 Conclusions on Pipeline Reuse
Several redundant hydrocarbon pipelines exist within the vicinity of the Acorn
CO2 storage site. The preferred option is to transport CO2 through the Atlantic
pipeline due to the shallower depth of the reservoir at its seaward location and
its higher anticipated throughput afforded by a higher operating pressure.
Furthermore, the line is buried for over 90% of its length and therefore protected
from scour and free span development.
The Atlantic pipeline is expected to effectively handle the anticipated CO2 profile
under all supply scenarios.
The likelihood of erosion and corrosion of the pipeline is expected to be highest
near the inlet of the Atlantic pipeline (at the shore and near shore zone) where
gas temperature is still high. This can be managed by ensuring CO2 post
compression is cooled to below 29°C prior to the pipeline inlet to avoid running
ductile fracture (RDF). No issue regarding phase change between CO2 gaseous
state and CO2 liquid is expected as the operating pressure along the pipeline is
always higher than the CO2 critical pressure.
6.4.7 A&C Manifold
The Atlantic manifold, the largest item of subsea equipment which connects the
A&C wells to the export pipeline and to the control umbilicals, is still in place, but
does not form part of this development plan and is expected to be removed as
part of the BG decommissioning programme.
The A&C manifold is a production manifold and consequently there is little
opportunity for reusing the A&C manifold unless it is recovered onshore and
converted into an injection manifold which would be costly and difficult to justify
versus the construction of a new purpose-built injection manifold.
6.4.8 A&C Umbilical
Re-use of the original umbilical does not form part of this development plan.
6.5 Operations
The Acorn CCS Project development will inject CO2 at an initial rate of 200kT/yr
in phase 1, with potentially up to 5MT/yr in subsequent phases. The number of
injection wells will vary depending on the phase of the project, ranging from one
well to four wells in later phases.
The pipeline and any infield flowlines will require regular inspection, including
surveys by remotely operated vehicles (ROV) to confirm integrity and ensure no
spans have formed.
6.6 Decommissioning
The decommissioning philosophy for Acorn will be confirmed by comparative
assessment but for the Acorn CO2 storage site is assumed to be:
• Well(s) plugged and abandoned
• Subsea infrastructure recovered and taken ashore for recycling
(manifold, Xmas tree)
D07 Acorn CO2 Storage Site Development Plan Development Planning
ACT Acorn Consortium Page 117 of 151
• Pipeline cleaned and left in place, part end recovery and ends
protected by burial
• Pipeline spools and flowlines recovered
• Umbilical and jumpers recovered
Note that decommissioning will be in line with legal requirements at the time.
6.7 Post Closure Plan
The aim of post-injection/closure monitoring is to show that all available
evidence indicates that the stored CO2 will be completely and permanently
contained. Once this has been shown the site can be transferred to the UK
Competent Authority.
In the Captain aquifer, this translates into the following performance criteria:
1. The CO2 has not migrated laterally or vertically from the storage
complex
2. The CO2 within the structural containment storage site has reached
a gravity stable equilibrium. Any CO2 in an aquifer storage
containment site is conforming to dynamic modelling assumptions
– i.e. its size and rate of motion match the modelling results.
3. The above is proven by a post closure survey.
The post closure period is assumed to last for a minimum of 20 years after the
cessation of injection. During this time monitoring will be required.
6.8 Handover to Authority
Immediately following the completion of the post closure period, the
responsibility for the Acorn CO2 storage site will be handed over to the UK
Competent Authority. It is anticipated that a fee, estimated at ten times the
annual cost of post closure monitoring will accompany the handover.
6.9 Development Risk Assessment
This chapter will summarise new and open research questions that are of
importance for the development of the Acorn CO2 storage site. These questions
have evolved during the technical work on the Acorn CO2 storage site and are
therefore seen as recommendations for future work.
6.9.1 Key Uncertainties Regarding CO2 storage in the Acorn CO2
storage site
Abandoned wells: As is the case with many CO2 storage projects, the main risk
is related to abandoned wells. Well 13/30b-7 poses a greater risk than other
abandoned wells due to uncertainty over its abandonment state. The modelling
work has indicated that direct CO2 contact with well 13/30b-7 can be avoided
with careful injection well placement and this should be investigated further
during FEED.
Uncertainty regarding top structure map: A major source of uncertainty is
related to the seismic resolution of the top of the Captain Sandstone. The lack
of acoustic impedance contrast between the Rodby/Carrack Shale and the
Captain Sandstone results in a variable seismic response and poor seismic
resolution, which in turn results in imprecise picking of the reservoir-seal
boundary. The high acoustic impedance of the overlying Chalk can also induce
frequent multiple reflections, which adds difficulty to the interpretation of the top
reservoir. The resulting uncertainty in the top reservoir pick has a significant
impact on the accuracy of the CO2 flow modelling and plume migration.
D07 Acorn CO2 Storage Site Development Plan Development Planning
ACT Acorn Consortium Page 118 of 151
Remaining light gas volume in the A&C fields and its saturation
distribution: Uncertainty exists with regards to the accurate saturation (i.e.
remaining volume) and distribution of remaining light gas within the gas fields
present in the Captain X area. This remaining gas may occupy a fraction of pore
volume, which could otherwise be used for CO2 storage.
6.9.2 Uncertainties Regarding CO2 Injection and Migration within
the Reservoir
6.9.2.1 Uncertainty with regards to the pressure response of the system
Pressure response is mostly important during the CO2 injection period. After the
CO2 injection terminates, the pressure build-up reduces, and buoyancy-driven
plume migration will dominate. Several uncertainties could affect the pressure
evolution during CO2 injection; the magnitude of fracturing pressure gradient,
rock compressibility and the degree of hydraulic communication between the
storage site and the greater Captain Fairway area. Experimental rock mechanics
studies, being conducted by the University of Liverpool for D06 ACT Acorn
Geomechanics, (Pale Blue Dot Energy and University of Liverpool, 2018), could
reduce this uncertainty by updating the rock compressibility and fracture
pressure in the Acorn CO2 Storage Site dynamic model. This should be explored
in the next development phase. The uncertainty related to pressure response
within the system during CO2 injection can be addressed by investigating the
effect using offset brine production wells to reduce injection-related pressure
increase. This will be of particular importance during future phases of the project,
with possible injection to the east of the Grampian Arch.
6.9.2.2 Uncertainty with regards to geological data
The storage performance post CO2 injection is mostly controlled by buoyancy-
driven CO2 migration towards the boundaries of the storage complex coupled
with the effectiveness of trapping mechanisms i.e. residual and solubility
trapping. The important parameters affecting any gravity dominated
displacement are fluid properties (i.e. density contrast between CO2 and other
phases), formation characteristics, formation tilt and, lastly, the effectiveness of
trapping mechanisms at larger time scales. CO2 trapping mechanisms may
compete with CO2 plume migration and make the plume migration slightly
slower. A list of major uncertainties in this regard, which could affect the results,
is also presented below.
Brine properties: A certain degree of uncertainty regarding true brine properties
exists in this modelling study. There is no experimental measurement of brine
in-situ properties i.e. brine density and viscosity, either in the ETI SSAP study or
the current modelling study. They have been estimated using correlations with
no supporting experimental evidence.
Formation characteristics: The Acorn CO2 storage site in general and Captain
Sandstone in particular are significantly large storage complexes. There is a
degree of uncertainty with regards to the heterogeneity of the formation
properties away from wells, which may affect the extent of plume migration post
CO2 injection.
Relative permeability data: There are elements of uncertainty regarding
relative permeability data; the base set of relative permeability data taken from
the Goldeneye field may not be representative for the entire Acorn CO2 storage
site. Additionally, core flood experiments are usually conducted in viscous-
dominated conditions. However, the CO2 flow pattern in the Captain Formation
is gravity dominated. Therefore, there is added uncertainty related to the validity
of these curves for Acorn CO2 storage site displacement conditions.
D07 Acorn CO2 Storage Site Development Plan Development Planning
ACT Acorn Consortium Page 119 of 151
Residual trapping: The derived residual trapping fraction of 0.3 is from a
viscous core flood experiment. The dependence of residual trapping on flow
rates, especially for gravity dominated displacement, is still uncertain.
Experimental measurement of relative permeability and residual trapping under
different flow conditions on Captain Sandstone reservoir samples is required to
improve the accuracy of the modelling results.
Migration along Palaeocene formations: Uncertainty remains about possible
CO2 migration pathways within the secondary store, the Palaeocene
Sandstones. This scenario has not been addressed in detail and requires more
insight into the structure and the lithology of the Palaeocene formations as well
as a numerical analysis to quantify the consequences of this scenario.
6.9.2.3 Uncertainties with regards to modelling CO2 flow
CO2-brine interaction: There is no empirical measurement of CO2-brine
interactions in the ambient conditions of the Captain Formation. Again, CO2-
brine interaction in the Acorn CO2 storage site has been estimated using
correlations from the Eclipse300 CO2SOL model. It can be argued that, if the
simulation is repeated with another CO2 solubility model, then a different set of
results could be expected. Simulations using alternative software packages (e.g.
Tough, CMG) to benchmark the existing results is recommended.
Numerical dispersion: The impact of numerical dispersion in exaggerating the
CO2 plume migration and CO2 dissolution in the brine phase can be significant
for large reservoir models, such as the Acorn CO2 storage site. Identifying an
appropriate gridding strategy for a gravity-dominated process like one observed
in the Captain Formation could decrease the effect of numerical dispersion and
reduce the model run time.
6.9.3 Uncertainties Relating to Hydrocarbon Industry and
Infrastructure
Pipeline: Uncertainty exists over particulates (rust, organics and produced
sand) residing in the Atlantic pipeline, which could be a risk to injection. These
may need to be evaluated by remote camera and pipe condition inspection. A
pipeline pigging (cleaning) programme may reduce the initial particulate loading
but there may still be a risk around long-term damage from continuous corrosive
products. However, the pipeline is lined and so this further reduces the risk.
Additional investigation of solutions should be carried out during FEED,
including options for subsea filtration systems.
Alternative storage plan: For the unlikely scenario that the Acorn CO2 storage
site is either unavailable for CO2 storage at all or is not suitable for Phase 2
injection plans, alternative storage plans should be assessed. A key alternative
option is a more extensive evaluation of the East Mey location being undertaken
for the ACT Acorn study as a potential back-up plan.
Hydrocarbon industry: Uncertainty exists over possible future hydrocarbon
exploration in a region with CO2 storage, however on-going dialogue with OGA
will ensure best practice is carried out to minimise risk.
6.9.4 The Assessment of Leakage Risk and Appropriate
Remediation Strategies
Quantifying leakage rates: The risk analysis involved the quantification of
actual CO2 leakage rates for leakage scenarios based on expert elicitation. This
process can be subjective and suffer bias. To improve the quality of the risk
assessment, the numerical simulation of leakage scenarios is required including
sensitivity studies to assess the impact of uncertain parameters.
D07 Acorn CO2 Storage Site Development Plan Development Planning
ACT Acorn Consortium Page 120 of 151
Mitigation and remediation strategies: Although mitigation strategies to
reduce the threat of potential leakage scenarios have been briefly discussed in
Section 4.7.3, a detailed analysis of the impact of different strategies using
numerical simulations will reduce the risk of leakage scenarios occurring.
Additionally, remediation strategies to reduce the severity and consequence
impact of leakage, such as those touched on in Table 4-27, should be explored
using simulations. A detailed corrective measures plan is an essential part of
any Storage Permit application.
6.9.5 Advanced Selection Criteria
Predicting storage development costs: Storage efficiency can have a major
indirect contribution to the cost of operations of a project: a site that appears
very suitable in principle (e.g. located close to the existing infrastructures, at an
appropriate depth and with a great capacity), but with a very low storage
efficiency, may require extra injection wells and/or water withdrawal operations
in order to reach its full potential, increasing overall costs dramatically. An
accurate assessment of storage efficiency is required to calculate the levelised
cost (i.e. the cost per stored tonne of CO2) from which storage sites maybe
selected or dismissed. However, the way in which storage efficiency is
calculated is currently not standardised. Future research efforts should focus on
determining effective methods for the calculation of storage efficiency factors.
6.9.6 Risk Assessment
The containment risk assessment considered 11 potential leakage scenarios
(Section 4.7.3). Following are the main conclusions and potential further work.
Risk Assessment Conclusions
• No high or very high severity or high or very high likelihood events
were identified.
• 10 of the 11 scenarios have a severity less than three (medium),
corresponding to low volumes of CO2 relative to injected inventory.
• Leakage scenarios with a likelihood of three (medium) or higher
include potential leakage along abandoned wells.
• Loss of containment into the Palaeocene is due to a combination of
abandoned wells and the chalk lithology.
• If the CO2 were to reach the shallower Palaeocene sandstones, it is
likely that it would migrate west and reach 800m depth. The
timescale for this is uncertain.
• Loss of containment of CO2 across geological formations (Leakage
Scenarios 1 and 6), is generally less likely than loss of containment
along wells (Leakage Scenarios 2, 3, 4, 5 and 7).
• Leakage Scenario 6 (lateral loss of containment out of the storage
complex) has the greatest potential CO2 inventory associated with
this loss of containment and hence the greatest severity.
• All leakage scenarios using secondary pathways are expected to
show rather sporadic, negligible volumes of leakage relative to the
injected volume and hence a lower severity.
Further work / research:
• A range of “worst case” modelling studies to consider known
uncertainties and knowledge gaps.
• Detailed modelling of CO2 flow along shallower secondary
containment (Palaeocene) formations.
D07 Acorn CO2 Storage Site Development Plan Development Planning
ACT Acorn Consortium Page 121 of 151
• Fault seal analysis to assess the likelihood of fault reactivation and
faults as leakage pathways.
• Numerical modelling of sensitivities around CO2 flow along an open
well to surface.
D07 Acorn CO2 Storage Site Development Plan Budget & Schedule
ACT Acorn Consortium Page 122 of 151
7.0 Budget & Schedule
7.1 Cost Estimating Basis
7.1.1 Introduction
An overview of the cost estimation process is presented in this section. This
provides context for the project cost estimate information for both capital
expenditure (Capex), operating expenditure (Opex) and abandonment
expenditure (Abex).
7.1.2 Cost Estimate Accuracy
Cost estimates are prepared throughout the various phases of a large project
development process. Estimate types are based on a standard international
approach, (AACE International, 2016), and range from Type 5 (least accurate)
to Type 1 (most accurate) as the definition of each project increases and
matures through the process as summarised in Table 7-1.
As the project moves through phases of maturation, the cost estimate should
mature in line with the project. Typically, the base estimate increases as the risk
mitigations are incorporated in to the design, the contingency becomes less as
the risks are understood and engineered out and the cost accuracy improves.
Class Project Definition (%)
Purpose Estimating Accuracy
Basis
5 0 - 2 Concept Screening
L: -20% to -50%
H: +30% to +100%
Capacity factored, Judgement, parametric models
4 1 - 15 Feasibility L: -15% to -30%
H: +20% to +50%
Equipment factored, parametric models
3 10 - 40 Budget L: -10% to -20%
H: +10% to +30%
Semi-detailed unit costs
Major equipment list
2 30 - 75 Control L: -5% to -15%
H: +5% to +20%
Detailed unit cost and material take-off
1 65 - 100 Check L: -3% to -10%
H: +3% to +15%
Detailed unit cost and material take-off
Table 7-1: Cost Estimate Class Definitions (AACEI 18R-97)
7.1.3 Cost Estimate Components and Terminology
The components of a cost estimate generally include the following items:
• Base scope costs;
• Contingency;
• Market factors; and
• Inflation
D07 Acorn CO2 Storage Site Development Plan Budget & Schedule
ACT Acorn Consortium Page 123 of 151
The same principles are generally applied when defining Capex and Opex
estimates.
Market factors include allowance for market escalation, i.e. experience of a Real
Terms cost increase (or decrease) because of the market volatility, over and
above the impact of Inflation. Each activity within the estimate also needs to be
uplifted to account for inflation and to estimate an equivalent cost at the time of
Project Execution.
7.1.4 Cost Uncertainty
When preparing cost estimates, contingencies are assessed to arrive at a
validity of the estimate with an accepted confidence level. Contingencies are
assigned to raise the estimate to achieve a 50% confidence level, i.e. there is
an equal chance that the 'as built' cost of the project will show an over or under
expenditure. This figure is usually referred to as the P50 estimate and is, in
statistical terms, the median of the range of possible final expenditure outcomes.
The accuracy band for a cost estimate is defined by the range of costs from the
P10 (10% probability that the project will come in on or under budget) to P90
(90% probability that the project will come in on or under budget).
7.1.5 Contingency
Contingency is added to a cost estimate to allow for further scope definition
emerging in subsequent phases, and risks which have not been identified in the
present project phase. It also covers minor design and field changes but does
not include major scope changes, such as increased throughput/concept/layout.
Pale Blue Dot Energy uses commercially available simulation tools for cost risk
analysis which apply an industry standard Monte Carlo simulation approach.
This method generates a full range of possible outcomes and their associated
probability of occurrence and is based on:
• Deterministic cost inputs and ranges;
• Probability distribution curves;
• Risks;
• Opportunities; and
• Levels of effort.
The output from the cost uncertainty modelling process provides an overall
project contingency figure and a cost uncertainty range, bounded by the P10
and P90 cost estimates.
7.2 Capital Expenditure Estimate
7.2.1 Methodology
Capital cost estimates have been taken from existing work wherever applicable
or pro-rated from similar work to give an appropriate estimate at this stage of
development. For additional detail, please see D16 ACT Acorn Full Chain
Development Plan and Budget, (Pale Blue Dot Energy, 2016).
7.2.2 Capex Estimate
The Class 4 estimate of capital required to develop Acorn Phase 1 is
summarised in Table 7-2.
D07 Acorn CO2 Storage Site Development Plan Budget & Schedule
ACT Acorn Consortium Page 124 of 151
Work area Net
Cost (£M)
Contingency (£M)
Gross Cost (£M)
Offshore
Concept & FEED (including inspection pig)
16.9 1.0 17.9
MMV 9.0 0.1 9.2
Pipeline 16.1 6.0 22.1
Umbilical 60.2 24.1 84.3
Subsea 11.0 4.4 15.4
Well 20.7 6.9 27.6
Total Offshore 133.8 42.5 176.5
Onshore Onshore plant 76.5 23.5 99.9
Full Chain Total Full Chain 210.3 66.0 276.4
Table 7-2: Capex estimate
7.3 Operating Expenditure Estimate
7.3.1 Methodology
Opex has been estimated by factoring the relevant Capex estimate. The post
closure and handover costs have been included in the Abex cost estimate.
7.3.2 Opex Estimate
The estimate of operating cost required to run the Acorn project over a 20-year
period is summarised in Table 7-3.
The post closure and handover costs have been included in the Abex cost
estimate.
Work area Net
Cost (£M)
Contingency (£M)
Gross Cost (£M)
Offshore
Subsurface monitoring (MMV) 1.1 0.5 1.6
Transport and subsea 1.9 0.7 2.5
Total (per annum) 3 1.2 4.1
Total over life of the project 60 24 82
Onshore Onshore 11.9 3.6 15.5
Full Chain
Total full chain (per annum) 14.9 4.7 19.6
Total full chain over project life 298.5 94.0 392.5
Table 7-3: Opex estimate
7.4 Abandonment Expenditure Estimate
7.4.1 Methodology
These costs are assumed to be 10% of the incurred capital cost of the project
installed infrastructure and 25% of the capital cost of the well for the well
abandonment.
7.4.2 Post-closure MMV
The post closure and handover costs have been included in the Abex cost
estimate.
Post closure monitoring of the Acorn CO2 storage site is expected to be required
for a minimum of 20 years. The post-closure requirements are assumed to be
D07 Acorn CO2 Storage Site Development Plan Budget & Schedule
ACT Acorn Consortium Page 125 of 151
4D seismic initially after injection has ceased and seabed monitoring and
sidescan sonar every 5 years for the post closure monitoring period.
7.4.3 Handover to authority
Immediately following the completion of the post closure period, the
responsibility for the Acorn CO2 storage site will be handed over to the UK
Competent Authority. It is anticipated that a fee, estimated at ten times the
annual cost of post closure monitoring will accompany the handover.
7.4.4 Abex Estimate
The Abex estimate is shown in Table 7-4. These figures have not been adjusted
for inflation.
Work area Net
Cost (£M)
Contingency (£M)
Gross Cost (£M)
Offshore
Well P&A 5.2 2.1 7.2
Subsea, pipeline, umbilical 8.7 3.5 12.2
Post Closure 10.2 0.3 10.5
Handover 5.2 1.0 6.3
Total Offshore 29.4 6.8 36.2
Onshore Onshore 7.6 3.1 10.7
Full Chain Total Full Chain
37.0 9.9 46.9
Table 7-4: Abex estimate
7.5 Uncertainty of Cost Estimates
The estimating accuracy associated with a Class 4 estimate is -30% / + 40%.
7.6 Schedule
The Acorn CCS Project schedule is shown in Figure 7-1.
Figure 7-1: Development schedule
2019 2020 2023 20242018 2021 2022
Concept
ACT
FEED
Final investment decision (FID)
Appraisal and planning
Start injection
Operations
Commissioning
Well operations
Subsea construction and pre-commissioning
Onshore construction and precommissioning
Engineering and procurement
D07 Acorn CO2 Storage Site Development Plan Conclusions & Recommendations
ACT Acorn Consortium Page 126 of 151
8.0 Conclusions & Recommendations
8.1 Conclusions
The work undertaken for the ACT study shows that the Acorn CO2 storage site
and corresponding development plan offers a low cost, flexible and scalable
solution for the Acorn CCS Project due to:
• Pipeline optionality - Two existing and redundant pipelines, Atlantic
and Goldeneye, both run from St Fergus to the Acorn CO2 storage
site storage complex. These can be re-used and offer cost savings
over a new-build pipeline. The re-use of the Atlantic pipeline is the
reference case for the Acorn CCS Project.
• Low cost flexible well design - A single dual completion subsea
injection well provides lower capital cost than a platform well and is
designed to handle a range of injection rates, from 0.1MT to 2MT/yr,
meaning it can be used in subsequent phases of the project.
• Scalable storage resource - Up to 152MT can be securely stored
within the Acorn CO2 storage site storage complex, providing
scalability and additional storage resource beyond the initial
(200kT/yr) Phase 1 of the project.
Data
• The work undertaken for the ETI Strategic UK CO2 Storage Appraisal
Project (ETI SSAP) was drawn heavily from and built on for the ACT
Acorn CCS Project Study.
• The seismic 3D dataset used for the evaluation of Captain Aquifer
was the PGS UK CNS Mega Survey (1990-2003), tiles F04 and F05.
It covers over 95% of the storage complex.
• There is good regional well coverage and good well data available
within the storage complex, including modern logs and core data.
• Data from 78 wells. The well data used (including well-logs,
completion and abandonment reports) were obtained from the UK
Oil & Gas CDA database.
• The core data analysed was obtained from 15 wells, mainly from the
Blake, Cromarty, Atlantic, Solitaire and Goldeneye fields.
• The geomechanical analysis (ACT Acorn D06 Geomechanics, (Pale
Blue Dot Energy and University of Liverpool, 2018)) was conducted
on wells 14/26-1; 14/26a-6; 14/26a-7, 7A; and 14/26a-8, near the
proposed primary CO2 injection site.
• Limited pressure data from operators were also used in the ETI
SSAP work, on which the Acorn reservoir engineering work has been
based.
Containment
• The primary seal is provided by the marls and mudstones of the
Rodby Formation, which is a proven seal for many hydrocarbon
fields in the area. Over the Acorn storage site it is about 90-100m
thick and in the ETI SSAP work it was mapped across the fairway.
• The storage complex has been defined as the subsurface volume
between the Top Lista Formation and Base Cretaceous, and
D07 Acorn CO2 Storage Site Development Plan Conclusions & Recommendations
ACT Acorn Consortium Page 127 of 151
between the east of Goldeneye to the south east and beyond the
Blake oilfield in the north west. This has been extended since the
ETI SSAP study.
• The base seal is provided by the Valhall Formation, which consists
of shales and marls.
• In addition to a high degree of confidence that the Phase 1 reference
case of 4.2MT CO2 can be safely and fully contained within the
storage complex, there is confidence that up to 152MT of CO2 can
be contained within the Captain Sandstone in the Acorn CO2 storage
site complex for subsequent injection phases. This may require a
single pressure relief well.
• The Acorn CO2 storage site complex includes the Atlantic, Cromarty,
Blake and Goldeneye hydrocarbon fields in addition to the saline
aquifer beneath and between them. This may provide a degree of
structural containment.
• 1000 years after the cessation of injection the CO2 plume is still
contained within the Storage Complex.
• The Captain Sandstone reservoir quality is excellent and the CO2
plume is gravity dominated, due to the high vertical permeability and
low heterogeneity.
• The pattern of plume migration has been shown to be sensitive to
the structure depth map of the Top Captain Sandstone in the ETI
SSAP work, due to poor seismic imaging of the Top Captain event
and the complex velocity field in the overburden.
• A containment workshop was carried out, which determined that loss
of containment of CO2 along abandoned wells is the greatest risk for
long term CO2 storage.
• In addition, no high or very high severity or high or very high
likelihood events were identified and 10 of the 11 scenarios have a
severity less than three (medium), corresponding to low volumes of
CO2 relative to injected inventory.
• Dynamic modelling results indicate that by modifying the injection
strategy, CO2 contact with well 13/30b-7 (which has some residual
uncertainty over its abandonment state) can be avoided completely.
Site Characterisation
• The Acorn CO2 storage site complex covers an area of 971km2 of
the Captain aquifer in UKCS quadrants 13, 14 and 20, approximately
100km from Aberdeen.
• The Captain Sandstone of the Acorn storage site is a sand-rich
turbidite fan system deposited along the southern edge of the Halibut
Horst in the Central North Sea. Also known as the Captain sandstone
“pan handle”, it ranges from 5 to 10km wide.
• The rock quality of the Captain Sandstone is assessed to be
excellent. The average modelled porosity within the main Captain D
sand is 27%. The average permeability is over 1400mD and
permeability shows a strong positive correlation with the porosity. A
sand proportion of 82% is estimated in the Captain D sand.
• The vertical permeability is smaller than the horizontal permeability,
but in general no flux barriers are anticipated.
• The net to gross reduces at the edges of the Captain fairway, but this
has little or no impact on the capacity or on containment.
• The seismic characteristics of the reservoir and caprock increase the
difficulty of carrying out the depth conversion and interpretation
processes. The Top Captain Sandstone has a lack of acoustic
D07 Acorn CO2 Storage Site Development Plan Conclusions & Recommendations
ACT Acorn Consortium Page 128 of 151
impedance contrast across it, which makes it challenging to interpret.
This challenge has been one of the primary issues for petroleum
developments in the area and the remaining uncertainty over the top
structure map feeds into an uncertainty in modelling plume
migration. The seismic interpretation challenges experienced on this
project have also been reported by others, (Shell, 2015).
• The depth conversion in the ETI SSAP Project was performed by
generating synthetic seismograms from 12 wells spread across the
storage complex, with eight horizons interpreted, from deeper than
the reservoir up to the seabed.
• There is no evidence of significant faulting in the reservoir or primary
caprock.
• The Top Captain Sandstone dips gently at 1-2o to the southeast, and
up to 15o in the area to the west of the injection site.
• The well density is relatively high within the site and therefore the
degree of confidence about the reservoir quality across the site is
high. Core data is available for the primary caprock, which is studied
in a parallel Geomechanics work package of the ACT Acorn Project.
• The dynamic modelling results indicate the importance of using
compositional simulation (versus black oil simulation) in correctly
addressing the mixing effect between CO2 and hydrocarbons.
Storage Resource
• The main storage unit is the Captain Sandstone of the Lower
Cretaceous Cromer Knoll Group.
• In addition to the Phase 1 reference minimum viable development
case of 4MT CO2 stored, significant volumes (up to 5MT/yr modelled)
of CO2 can be injected into the Acorn CO2 storage site, with 152MT
safely and fully contained within the Storage Complex. To store
152MT would require 4 wells and 1 pressure relief well.
• 1000 years after Phase 1 injection stops, 13% of the injected
inventory is structurally trapped, 35% residually trapped, 33% in
solution and the remaining 20% continues to be mobile, travelling at
less than 10m/year.
• Strategies for increasing storage efficiency were modelled using a
range of techniques regularly deployed in the petroleum industry.
Dynamic storage efficiency in the ETI SSAP study was limited at 1-
2% and predominantly controlled by the high vertical permeability
and structure mapping. Dynamic storage efficiency in the ACT Acorn
CCS Project could be increased to a little over 2%, but none of the
techniques modelled has significant impact. This is due to the gravity
dominated flow within the Captain sandstone.
• The Acorn CO2 storage site is an open boundary storage site.
Upward plume migration, due to gravity effects, and lack of physical
boundaries on the north west side of the storage site make additional
storage capacity improvements quite challenging in the Acorn CO2
storage site.
• The fundamental challenge for improving CO2 storage efficiency in
the Acorn CO2 storage site is the significantly gravity dominated
displacement flow pattern that facilitates vertical migration of the CO2
plume.
Appraisal
• With nearly 100 wells drilled into the Captain Sandstone aquifer, it is
considered to be widely appraised. In addition, years of hydrocarbon
production indicates that there is connectivity throughout the fairway.
D07 Acorn CO2 Storage Site Development Plan Conclusions & Recommendations
ACT Acorn Consortium Page 129 of 151
• The key outstanding uncertainties are around the plume migration,
due to uncertainties in the top Captain structure map (discussed in
previous sections). This will not be resolved by appraisal drilling.
• Additional production and pressure data from operators would help
build a more thorough understanding of the regional connectivity.
Development
• Final Investment Decision needs to be in 2020 in order to achieve
the first injection date of 2023.
• The planning work indicates that approximately 2 years are required
to appraise and develop the store.
• A single subsea injection well is proposed for Phase 1 (200kT/yr),
with a dual completion (common in oil and gas operations) capable
of handling injection rates from 0.1MT/yr up to 2MT/yr as additional
CO2 sources come online. In the modelling, only the dual 3 ½’’ and
the 4 ½’’ tubing can achieve a target rate of 2MT/yr under initial
reservoir conditions. However, neither provide an option for the low
range of 0.1MT/yr.
• The dual completion has two injection tubulars run into the same
wellbore. One tubular might be considered for low injection rates, the
other for intermediate rates and both together for high injection rate.
A dual completion consisting of a 27/8“ tubing string and a 4½’’ tubing
string achieves the target injection range; however, this may require
a 103/4’’ casing.
• The existing 16” 170barg maximum operating pressure Atlantic
pipeline that runs from St Fergus to the Acorn Phase 1 injection area
can effectively handle all the envisaged CO2 supply scenarios. Flow
assurance is not a significant consideration for CO2 transportation
along the Atlantic pipeline if CO2 is dried sufficiently. The Atlantic
pipeline was installed in 2006 and ceased use in 2009 so has only
been used for a small amount of its 20-year design life.
• A £177 million capital investment is required to design, build, install
and commission the pipeline and wells for Phase 1. The operating
cost is £82 million over the 20-year project life, with an average of
£4 million per year.
Operations
• The maximum allowable reservoir pressure within the simulation
model has been constrained to 90% of the fracture pressure, which
is 283bara at the top of the perforations.
• The design assumption is 130bara arrival pressure of the CO2 supply
at the wellhead to enable injection through the life of the project. This
would require a discharge pressure of between 118bara and
142bara from the pump station at St Fergus for Phase 1 and for the
152MT (5MT/yr) cases.
8.2 Recommendations
Appraisal Programme (including Concept and FEED)
• Explore pipeline particulate debris risk.
• Explore Goldeneye pipeline as the back-up option to the Atlantic
pipeline if the Atlantic pipeline decommissioning plan progresses.
• Obtain well by well production and pressure data from the operators
of Blake, Atlantic, Cromarty and Goldeneye. Use this data to fully
calibrate the reservoir simulation model.
D07 Acorn CO2 Storage Site Development Plan Conclusions & Recommendations
ACT Acorn Consortium Page 130 of 151
• Obtain full abandonment records from operators and conduct a more
comprehensive study and risk assessment of the abandoned wells
in the planned storage complex.
• Detailed well design: explore the possibility of 10¾’’ casing for the
dual completion. Although the well design was based on 95/8’’ casing
for the purposes of this study, 10¾’’ casing may be required.
Investigate including stand-alone-screens to reduce chance of sand
failure in the reservoir.
• Further investigation of transient pressure variations in the wellbore.
If significant issues are identified, a combined deep-set shut-in valve
/ choke valve, could provide the solution to the variable rates (high
injection range) required for this development.
• Explore suitable mechanism to perform downhole shut-in function
which would mitigate transient effects. However, further work is
required in the pre-FEED to substantiate this approach, or to provide
alternate solutions.
• Investigation of thermal fracturing and the effect of increasing
fracture pressure with increased pore pressure throughout the
injection process to define fracture limits,
• Evaluate the TGS-Nopec seismic volume over the Acorn CO2
storage site area. This dataset includes offset (angle) stacks that are
often useful in creating improved data quality in challenging areas.
• Undertake a modern rock physics study and seismic acquisition
modelling study to confirm whether the imaging at Top Captain can
be improved upon before a decision is taken to acquire new seismic.
This should also be revisited to check the performance of a new
survey in tracking plume migration. The final investment decision on
the project is not currently considered dependent on acquisition of a
new seismic survey.
• Further modelling work that can be fully calibrated to well by well
production and pressure data from the operators of Blake, Atlantic,
Cromarty and Goldeneye.
• Perform a full evaluation of a dual completion in GAP software.
Operational Planning
• Identify and quantify opportunities for cost and risk reduction across
the whole development, including operational efficiencies.
• Identify synergies with other offshore operations.
Development Planning
• Incorporate the regulatory licensing and permitting requirements into
the development schedule and plan.
• Work with the petroleum operators of nearby hydrocarbon fields and
the Regulator to ensure that the wells are abandoned using all best
practice to secure the CO2 integrity of the site.
• Work with the Regulator to ensure best practice in place for any
future exploration drilling near the CO2 storage site.
Future Study
This section highlights areas which require further study which could be useful
for broader industry research.
• A range of “worst case” modelling studies to consider known
uncertainties and knowledge gaps.
• Detailed modelling of CO2 flow along shallower secondary
containment (Palaeocene) formations.
D07 Acorn CO2 Storage Site Development Plan Conclusions & Recommendations
ACT Acorn Consortium Page 131 of 151
• Fault seal analysis to assess the likelihood of fault reactivation and
faults as leakage pathways.
• Numerical modelling of sensitivities around CO2 flow along an open
well to the overburden or surface and impact of any mitigation and
remediation strategies.
• Standardisation of calculating storage efficiency factors.
D07 Acorn CO2 Storage Site Development Plan References
ACT Acorn Consortium Page 132 of 151
9.0 References
(NIST), N. I. (2018, 3 8). NIST Chemistry WebBook. Retrieved from NIST:
http://webbook.nist.gov/chemistry/
AACE International. (2016). 18R-97 Recommended Practice Cost Estimation in
Process Industires. Association for Advancement of Cost Engineering
International.
Apache. (2017). SAGE Terminal, Access to Oil and Gas Infrastructure.
Retrieved from
http://www.apachecorp.com/Resources/Upload/file/UK/infrastructure_i
nformation/SAGE/SAGE_Terminal-access-to-infrastructure.pdf
Axis Well Technology. (2017). Preliminary Well Design and Modelling for the
Captain Subsea CO2 Injector.
BG Group. (2016). Atlantic & Cromarty Decommissioning Programmes
Environmental Impact Assessment.
BG Group. (2016). Atlantic & Cromarty Fields Decommissioning Programmes
Stakeholder Engagement Report.
BG Group. (2016). Atlantic and Cromarty Fields Draft Decommissioning
Programmes.
Colley, N. M. (1999). Blake Field Petrophysics Report. BG International.
Copestake, P., Sms, A. P., Crittenden, S., Hamar, G. P., Ineson, J. R., Rose, P.
T., & and Tringham, M. E. (2003). Lower Cretaceous. Evans, D;
Graham, C; Armour, A and Bathurst, P (eds.) The Millenium Atlas:
Petroleum Geology of the Central and Northern North Sea, pp. 191-211.
D3967-08, A. (2008). Standard test method for splitting tensile strength of intact
rock core specimens. ASTM International, 3. West Conshohocken, PA.
Du, K., Pai, S., Brown, J., Moore, R., & Simmons, M. (2000). Optimising the
development of Blake Field under tough economic and environmental
conditions. International Oil and Gas Conference and Exhibition in
China. Society of Petroleum Engineers.
Eclipse 300 Reference Manual. (2016).
(2008). Energy Act, Chapter 32. Retrieved from
http://www.legislation.gov.uk/ukpga/2008/32/pdfs/ukpga_20080032_e
n.pdf
Guariguata-Rojas, G., & Underhill, J. (2017, November). Implications of Early
Cenozoic Uplift and Fault Reactivation for Carbon Storage in the Moray
Firth Basin. Interpretation, 5(4), SS1-SS21.
IEAGHG. (2015). CCS Deployment in the Context of Regional Development in
Meeting Long-Term Climate Change Objectives.
IEAGHG. (2017). CO2 Pipeline Infrastructure. Retrieved from IEAGHG:
http://ieaghg.org/docs/General_Docs/Reports/2013-18.pdf
Jin, M., Mackay, E. J., Quinn, M., Hitchen, K., & Akhurst, M. (2012). Evaluation
of the CO2 Storage Capacity of the Captain Sandstone Formation. SPE
Europec/EAGE Annual Conference, 4-7 June. Copenhagen, Denmark:
Society of Petroleum Engineers.
D07 Acorn CO2 Storage Site Development Plan References
ACT Acorn Consortium Page 133 of 151
National Energy Technology Laboratory, US Department of Energy. (2012).
Best Practices for Monitoring, Verfication and Accounting of CO2 Stored
in Deep Geologic Formations.
Pale Blue Dot Energy & Axis Well Technology. (2016). Captain X Storage
Development Plan - Strategic UK CO2 Storage & Appraisal Project.
Energy Technologies Institute.
Pale Blue Dot Energy & Axis Well Technology. (2016). Progressing
Development of the UK’s Strategic Carbon Dioxide Storage Resource:
A summary of Results from the Strategic UK CO2 Storage Appraisal
Project. Energy Technologies Institute.
Pale Blue Dot Energy & Axis Well Technology. (2016). Strategic UK Storage
Appraisal Project. Energy Technologies Institute.
Pale Blue Dot Energy. (2016). D16 ACT Acorn Full Chain Development Plan
and Budget. ACT Acorn Consortium.
Pale Blue Dot Energy. (2017). ACT Acorn D02 CO2 Supply Profile. ACT Acorn
Consortium.
Pale Blue Dot Energy and University of Liverpool. (2018). ACT Acorn
Geomechanics. ACT Acorn Consortium.
Pale Blue Dot Energy; Axis Well Technology. (2015). D05: Due Diligence and
Portfolio Selection - Strategic UK CO2 Storage & Appraisal Project. The
Energy Technologies Institute.
PBDE and Axis WT. (2016). Captain X Storage Development Plan. Energy
Technologies Institute.
PGS. (2015). The PGS Mega surveys. Retrieved from
http://www.pgs.com/upload/31007/MegaSurvey%20(1366Kb).pdf
Pham, T. H., Maast, T. E., Hellevang, H., & Aagaard, P. (2011). Numerical
modeling including hysteresis properties for CO2 storage in Tubaen
formation, Snøhvit field, Barents Sea. Energy Procedia, 4, 3746–3753.
Pinnock, S., & Clitheroe, A. (2003). The Captain Field, Block 13/22a, UK North
Sea. Gluyas, JG & Hichens, HM (eds.) United Kingdom Oil and Gas
Fields, Commemorative Millenium Volume. Geological Society, London,
Memoir, 20, pp. 431-441.
Schlumberger. (2014). Eclipse 300 Reference Manual.
Schlumberger. (2018, 05 15). Fracture Gradient. Retrieved from Schlumberger
Oil Field Glossary:
http://www.glossary.oilfield.slb.com/Terms/f/fracture_gradient.aspx
ScottishPower CCS Consortium. (2010). Longannet FEED work, UK Carbon
Capture and Storage Demonstration Competition, FEED Close Out
Report, SP-SP 6.0 - RT015.
Shell. (2011). UK CCS Knowledge Transfer S7.19 SCAL Report. DECC.
Shell. (2015). Peterhead CCS Project Doc no PCCS-05-PTD-ZG-0580-00001
Date 19/03-2015.
Shell. (2015). Seismic Interpretation Report Doc no PCCS-05-PT-ZG-0580-
00002.
Shell. (2016). Peterhead CCS Project: Basic Design and Engineering Package
(K05). DECC 11.003 KKD Technical.
D07 Acorn CO2 Storage Site Development Plan References
ACT Acorn Consortium Page 134 of 151
Shell, The Crown Estate, Scottish Government, Scottish Enterprise and
Vattenfall. (2015). CO2Multistore: Optimising CO2 storage in geological
formations; a case study offshore Scotland.
The European Parliament And The Council Of The European Union. (2009).
Directive 2009/31/Ec Of The European Parliament And Of The Council
On The Geological Storage Of Carbon Dioxide. Official Journal of the
European Union, 114-135.
Tucker, O., & Tinios, L. (2017). Experience in Developing the Goldeneye
Storage Permit Application. Energy Procedia, 114, 7466-7479.
UK Government. (2017). Oil and gas: decommissioning of offshore installations
and pipelines. Retrieved from gov.uk: https://www.gov.uk/guidance/oil-
and-gas-decommissioning-of-offshore-installations-and-pipelines
Veritas, Det Norske. (2010). Recommended Practice DNV-RP-J202, Design
and Operation of CO2 Pipelines. Retrieved from
https://rules.dnvgl.com/docs/pdf/DNV/codes/docs/2010-04/RP-
J202.pdf
Zhang, J., & Yin, S. X. (2017). Fracture gradient prediction: an overview and an
improved method. Petroleum Science, 14(4), 720–730.
Zoback, M. D. (2007). Reservoir Geomechanics. Cambridge: Cambridge
University Press.
D07 Acorn CO2 Storage Site Development Plan Annexes
ACT Acorn Consortium Page 135 of 151
10.0 Annexes
10.1 Annex 1 – Data inventory
10.1.1 Seismic data summary
The seismic 3D dataset used for the evaluation of Captain Aquifer was the PGS
UK CNS Mega Survey:
• Survey: MC3D_NSEA (CNS)_MEGA (UK Sector)
o Final Merged Migration (53 Tiles)
The data was supplied as SEG-Y on a USB hard drive and has the following
survey datum and map projections:
Setting Value
Survey Datum ED50
Ellipsoid International 1924
Semi Major Axis 6378388
1/Flattening 297
Map Projection UTM 31N
Central Meridian 3 EAST
Scale Factor or Central Meridian 0.9996
Latitude of Origin 0.00N
False Northing 0
False Easting 500000
Table 10-1: SEG-Y survey datum and map projections
The following tiles of SEG-Y data were used for the Captain site selection and
evaluation:
File Name Format Tile Media IL Range
XL Range
OS0445_MC3D_
NSEA_MEGA_F
04_MAR2014
SEG-Y F04 27395002 15001-20000
120001-
124000
MC3D_NSEA_M
EGA_F05 SEG-Y F05 27395002
20001-25000
120001-
124000
Table 10-2: SEG-Y tiles for Captain Aquifer evaluation
Figure 10-1: PGS Mega Survey time slice showing the seismic data extent and tiles used in the Captain Aquifer evaluation
D07 Acorn CO2 Storage Site Development Plan Annexes
ACT Acorn Consortium Page 136 of 151
10.1.2 Well data summary
The table below shows a summary of the well log data for the Acorn CO2 storage
site, downloaded from CDA (table extracted from (PBDE and Axis WT, 2016)).
D07 Acorn CO2 Storage Site Development Plan Annexes
ACT Acorn Consortium Page 137 of 151
Well Date E/A/D DLIS or las?
GR Neutron Density DT/ Sonic
SP Comp Log
Geological Report/Final Well Report
Digital Checkshots
Deviation Data
Well Tops
Core Data over Captain
13/21b- 2 1990 E y n n y n n y n y y n
13/22b- 19 1993 A y n n y y y y n y y n
13/22b- 20 1993 E y n n y y y y n y y n
13/22b- 4 1990 E y n n y y n y n y y n
13/22c- 30 2006 E y y y n n y y n y y n
13/23- 1 1991 E y n y n n n y n y y n
13/23a- 4 1999 E y y y n n y y n y y n
13/23b- 5 2005 E DLIS y y n n y y y n y y y
13/23b- 6 2008 A LAS y n n n n y y n y y n
13/24- 1 1974 E y n y y n y y n n n n
13/24a- 4 1997 A y y y y y y y y y y y
13/24a- 5 1998 A y y y y y y y y y
13/24a- 6 1998 A y n y y n y y y y y y
13/24a-7 2000 D n n n n n y y n y y n
13/24a- 7Z 2000 D n n n n n y y n y y n
13/24A-8 2001 A n n n n n y y n y y n
13/24A-8Y 2001 A n n n n n y y n y y n
13/24a- 8Z 2001 A n n n n n y y n y y n
13/24b- 10 2010 D n n n n n y y n y y n
13/24b- 3 1997 E y n y n n y y n y y y
13/24b- 9 2003 D DLIS y n n n n y y n y y n
D07 Acorn CO2 Storage Site Development Plan Annexes
ACT Acorn Consortium Page 138 of 151
Well Date E/A/D DLIS or las?
GR Neutron Density DT/ Sonic
SP Comp Log
Geological Report/Final Well Report
Digital Checkshots
Deviation Data
Well Tops
Core Data over Captain
13/29b- 5 1995 E y n n n n y y n y y n
13/29b- 6 1999 A y y n y n y y n y y y
13/29b- 7 2001 E LAS n n n n n y y n y y n
13/29b- 8 2001 D y n n n n y y y y y n
13/29b- 9 2004 E DLIS n n n n n y n n y y n
13/30- 1 1981 E y y y y y y y n y y n
13/30- 2 1984 E n n n n n n y n y y n
13/30- 3 1986 E y y y y y n y n y y y
13/30a- 4 1998 E LAS y n y y y y y n y y y
13/30a- 6 2005 D DLIS n n n n n y y n y y n
13/30b- 5 1999 E n n n n n y y n y y n
13/30b- 7 2007 E y y n y n y y n y y n
14/26- 1 1979 E y y y y y n y n y n n
14/26- 2 1982 E y y y y y n y n y n n
14/26- 3 1983 E y y y y y n y n y n n
14/26a- 6 1997 E y y y y y y y n y y y
14/26a- 7 1999 A n n n n n n n n n n n
14/26a- 7A 1999 A y y y n n y y n y y y
14/26a- 8 2000 A DLIS y y n y y y y y y y y
14/26a- 9 2011 A n y y n n y y y y y n
14/26b- 5 1997 E y y y y y y y y y y n
D07 Acorn CO2 Storage Site Development Plan Annexes
ACT Acorn Consortium Page 139 of 151
Well Date E/A/D DLIS or las?
GR Neutron Density DT/ Sonic
SP Comp Log
Geological Report/Final Well Report
Digital Checkshots
Deviation Data
Well Tops
Core Data over Captain
14/27a- 1 1990 E y n y n y n y n y y n
14/27a- 2 2006 E n n n n n y y n y y n
14/28a- 3A 2000 E y n n n n y y y y y n
14/28b- 2 1997 E y y y y y y y y y y y
14/28b- 4 2006 E DLIS y y y y y y y n y y n
14/29a- 2 1980 E y y y y y y y y y y n
14/29a- 3 1996 E DLIS y n y y n y y n y y y
14/29a- 5 1999 E DLIS y y y y n y y n y y y
20/02b- 10 2010 E DLIS y y y n n y y n y y n
20/04b- 6 1997 E y y y y y y y n y y y
20/04b- 7 1999 E y n n n n y y y y y y
20/01-11 2009 A n y y n n y y y y y n
20/01-11Z 2009 A y n y n n y y y y y n
20/01-6 2006 D y y y n n y y n y y n
20/01-8 2009 E y y y n n y y n y y n
Table 10-3: Summary of well data used in the Captain Aquifer evaluation
D07 Acorn CO2 Storage Site Development Plan Annexes
ACT Acorn Consortium Page 140 of 151
10.1.3 Core data summary
The table below show a summary of the core data available over the Acorn CO2
storage site.
Field Well Core Depth (MD)
13/23b- 5 4240.3-4261.2
BLAKE 13/24a- 4 5295.1-5450.1
BLAKE 13/24a- 5 5207.2-5400.6
BLAKE 13/24a- 6 5177.4-5409.1
BLAKE 13/24b- 3 4990.0-5302.0
BLAKE 13/29b- 6 5203.85-5375.0
CROMARTY 13/30- 3 6577.0-6702.85
13/30a- 4 6364.2-6461.0
ATLANTIC 14/26a- 6 6467.1-6541.9
ATLANTIC 14/26a- 7A 6540.1-6577.8
SOLITAIRE 14/26a- 8 6428.9-6658.9
14/28b- 2 8248.0-8331.0
GOLDENEYE 14/29a- 3 9727.0-10188.9
GOLDENEYE 14/29a- 5 8473.1-8680.0
GOLDENEYE 20/04b- 6 8644.2-8777.9
GOLDENEYE 20/04b- 7 8639.2-8812.0
Table 10-4: List of core data used in the characterisation of the Acorn CO2 Storage Site
The core data used in the geomechanical rock strength analysis was carried out
on wells: 14/26-1; 14/26a-6; 14/26a-7, 7A; and 14/26a-8, near the proposed
primary CO2 injection site. The depth intervals chosen for sampling for each
respective well were chosen according to several parameters, including:
availability of core, depth, occurrence in the oil/water-leg; porosity; and general
lithological variation, as determined from hand specimen observations, gamma
ray and density wireline logs.
10.1.4 Data from operators
Limited pressure data from Operators in the area were provided as input to the
Acorn CO2 storage site work.
D07 Acorn CO2 Storage Site Development Plan Annexes
ACT Acorn Consortium Page 141 of 151
10.2 Annex 2: Risk Register
Attached separately.
D07 Acorn CO2 Storage Site Development Plan Annexes
ACT Acorn Consortium Page 142 of 151
10.3 Annex 3: Leakage Workshop Spider Diagrams
The leakage scenarios investigated during the leakage workshop are shown in
Figure 10-2 with the categories and grades of consequences highlighted in
Table 10-5.
Figure 10-2: The 11 leakage scenarios considered as relevant for the area investigated
Impact Low Medium High
Storage Security
CO2 migrates inside the storage complex or does not reach shallower formations.
CO2 reaches the shallow overburden.
CO2 reaches to the seabed.
Social Acceptance
Not present in the public discussion and no coverage in the media. Covered in the scientific community.
Present in the local news; policy and industry are aware
Nation-wide coverage, headline news and broad debate in the public
Environment Minor damage, no threat to the environment.
Local damage, certain threat to flora and fauna and, if any, minor restitution required.
Widespread damage with major risk for the environment; major restitution required.
Hydrocarbon Industry
Negligible impact, strategy plans of hydrocarbon industry do not need adjustment.
Small to medium adjustments may be required.
Major change of industry operations, including long delays and significant costs.
Costs Negligible costs < £10 million > £10 million
Table 10-5: Summary of categories and grades of consequences
D07 Acorn CO2 Storage Site Development Plan Annexes
ACT Acorn Consortium Page 143 of 151
10.3.1 Leakage Scenario 1
10.3.1.1 Scenario Description
CO2 migrating through overlying primary seal, the Rodby and the Carrick Shale,
into secondary reservoir, one of the Palaeocene sandstone formations.
10.3.1.2 Consequence Analysis
Figure 10-3: Spider diagram showing the impact of consequences
Impact on storage security – Low
CO2 is still within the storage complex.
Impact on social acceptance – Med
CO2 leaking into shallower formations will be of concern to the public. Although
the severity of the leakage event is expected to be low, CO2 leaving the storage
complex may compromise faith in carbon capture and storage (CCS) operations.
Impact on environment – Low
The CO2 is still deep in the subsurface, no impact on the environment expected.
Costs – Med
Some remediation strategies expected if fault reactivation or CO2 migrating
through the caprock occurs. The CO2 storage operation will require either a new
storage development plan (SDP) or operations to cease entirely.
Impact on hydrocarbon industry – Low
There are no significant hydrocarbon accumulations present in the shallower
strata above the injection site.
10.3.2 Leakage Scenario 2
10.3.2.1 Scenario Description
CO2 enters abandoned well and leaks to seabed. This is generally seen as one
of the more serious risks to CO2 storage operations and involves complicated
and expensive remediation procedures.
D07 Acorn CO2 Storage Site Development Plan Annexes
ACT Acorn Consortium Page 144 of 151
10.3.2.2 Consequence Analysis
Figure 10-4: Spider diagram showing the impact of consequences
Impact on storage security – High
CO2 leaks to the seabed, which is a worst-case scenario.
Impact on social acceptance – High
CO2 leaking to the seabed will be alarming for the public as well as regulators
and policy makers. This will have nationwide, probably global, effect on the
public perception of CO2 storage.
Impact on environment – Med
Although the volume of leaking CO2 is relatively small, local damage to the
seafloor near the well is likely.
Costs – High
The remediation of an abandoned well is costly.
Impact on hydrocarbon industry – Low
No impact expected.
10.3.3 Leakage Scenario 3
10.3.3.1 Scenario Description
CO2 enters a modern well or leaks along pathways opened due to drilling or the
operation process of the modern well, most likely during the drilling process or
during/after completion problems, and then leaks vertically to seafloor. A modern
well is defined as a well drilled for this CO2 storage project (injection well,
monitoring well, pressure relief well, etc) or any well that is drilled through a CO2
storage site (e.g. for future petroleum activity).
10.3.3.2 Consequence Analysis
Figure 10-5: Spider diagram showing the impact of consequences
Impact on storage security – High
CO2 leaks to the seabed, which is a worst-case scenario.
D07 Acorn CO2 Storage Site Development Plan Annexes
ACT Acorn Consortium Page 145 of 151
Impact on social acceptance – High
CO2 leaking to the seabed will be alarming for the public as well as regulators
and policy makers. This will have, probably global, effect on the public
perception of CO2 storage.
Impact on environment – Med
Although the volume of leaking CO2 is relatively small, local damage to the
seafloor near the well is likely.
Costs – High
The remediation of a failed drilling campaign, including leakage to surface, is
costly. The well may be lost.
Impact on hydrocarbon industry – High (*)
*Only when drilled through CO2 storage site for deeper targets; but negligible
otherwise.
10.3.4 Leakage Scenario 4
10.3.4.1 Scenario Description
CO2 enters abandoned well and leaks into the secondary reservoir, a
Palaeocene sandstone.
10.3.4.2 Consequence Analysis
Figure 10-6: Spider diagram showing the impact of consequences
Impact on storage security – Low
CO2 leaks within the storage complex into shallower formations.
Impact on social acceptance – Medium
CO2 leaking into shallower formations will be of concern for the public as well as
regulators and policy makers. This will be heavily discussed in the industry and
research community.
Impact on environment – Low
No impact on the environment expected.
Costs – High
The remediation of a leaky abandoned well is extremely costly.
Impact on hydrocarbon industry – Low
D07 Acorn CO2 Storage Site Development Plan Annexes
ACT Acorn Consortium Page 146 of 151
No impact on the environment expected.
10.3.5 Leakage Scenario 5
10.3.5.1 Scenario Description
CO2 enters a modern well, most likely during the drilling process or during/after
completion problems, and then leaks into Palaeocene sandstone formations. A
modern well is defined as a well drilled for this CO2 storage project (injection
well, monitoring well, pressure relief well, etc.) or that is drilled through a CO2
storage site (e.g. for future petroleum activity).
10.3.5.2 Consequence Analysis
Figure 10-7: Spider diagram showing the impact of consequences
Impact on storage security – Low
CO2 leaks out of the storage complex into shallower formations.
Impact on social acceptance – Medium
CO2 leaking into shallower formations will be of concern for the public as well as
regulators and policy makers. This will be heavily discussed in the industry and
research community.
Impact on environment – Low
No impact expected.
Costs – High
The remediation of a failed drilling campaign, including leakage, is extremely
costly. The well will probably be lost. Additionally, the remediation procedure for
this leakage scenario will be technically extremely challenging.
Impact on hydrocarbon industry – High (*)
*Only when drilled through CO2 storage site for deeper targets; but negligible
otherwise.
10.3.6 Leakage Scenario 6
10.3.6.1 Scenario Description
CO2 migrates along the primary reservoir formation, the Captain Sandstone, out
of the storage complex in a north-westerly direction. Migration towards the
deeper south-east is excluded because CO2 is not expected to migrate
significantly down-dip.
D07 Acorn CO2 Storage Site Development Plan Annexes
ACT Acorn Consortium Page 147 of 151
10.3.6.2 Consequence Analysis
Figure 10-8: Spider diagram showing the impact of consequences
Impact on storage security – Low
CO2 is outside the storage complex but has not leaked into shallower strata.
Impact on social acceptance – Low
2-5% of CO2 migrating to the west of the Blake field but still inside the Captain
Sandstone will be of little concern.
Impact on environment – Low
Whether the CO2 is within the storage complex or outside makes no difference
for the environment as long it is still in the Captain Sandstone deep under the
seabed.
Costs – High
CO2 injection will be stopped if lateral leakage occurs during the injection
process; some remediation actions, such as back production, might be required
to reduce leakage. A new measuring, monitoring and verification (MMV) strategy
will be introduced.
Impact on hydrocarbon industry – Low
If CO2 escapes laterally, it may flow into currently unknown hydrocarbon fields.
Although it may result in the heavy oil produced to become less viscous (CO2-
EOR), the net CO2 emission impact will need to be considered for the
exploration, the development, the production and the decommissioning of these
fields.
10.3.7 Leakage Scenario 7
10.3.7.1 Scenario Description
CO2 leaks into depleted, underlying Jurassic formations under production via
leakage pathways, such as wells.
D07 Acorn CO2 Storage Site Development Plan Annexes
ACT Acorn Consortium Page 148 of 151
10.3.7.2 Consequence Analysis
Figure 10-9: Spider diagram showing the impact of consequences
Impact on storage security – Low
CO2 leaks out of the storage complex but into deeper strata.
Impact on social acceptance – Low
Less than 2% of CO2 migrating to a deeper horizon will be of little concern to the
public.
Impact on environment – Low
Whether the CO2 is within the storage complex or outside makes no difference
for the environment as long it is still deep under the seabed.
Costs – Low
CO2 injection will be reduced or stopped if downward migration occurs during
the injection process; some remediation actions, such as back production, might
be required to reduce leakage.
Impact on hydrocarbon industry – Medium
If CO2 escapes downwards, it may flow into known hydrocarbon fields. If it
contaminates a producing field, it could lead to corrosion in the production
infrastructure.
10.3.8 Leakage Scenario 8
10.3.8.1 Scenario Description
As per 1, 4 and 5 but additionally, CO2 leaks along secondary reservoirs
(Palaeocene sandstones) out of the storage complex.
10.3.8.2 Consequence Analysis
Figure 10-10: Spider diagram showing the impact of consequences
Impact on storage security – Low
D07 Acorn CO2 Storage Site Development Plan Annexes
ACT Acorn Consortium Page 149 of 151
CO2 leaks laterally out of the storage complex.
Impact on social acceptance – Medium
CO2 leaking into shallower formations out of the storage complex will be of
concern for the public as well as regulators and policy makers. This will be
heavily discussed in the industry and research community.
Impact on environment – Low
Whether the CO2 is within the storage complex or outside makes no difference
for the environment as long it is still deep under the seabed.
Costs – High
In addition to the costs of dealing with the CO2 leaking into the Palaeocene
sandstone, further costs might be required to deal with Scenario 8.
Impact on hydrocarbon industry – Low
If CO2 escapes laterally, it may flow into currently unknown hydrocarbon fields.
Although it may result in the heavy oil produced to become less viscous (CO2-
EOR), the net CO2 emission impact will need to be considered for the
exploration, development, production and decommissioning of these fields.
However, no such fields are known to date.
10.3.9 Leakage Scenario 9
10.3.9.1 Scenario Description
As per 1, 4 and 5 but, additionally, CO2 leaks across the secondary seal, the
Lista Shale, into the overburden.
10.3.9.2 Consequence Analysis
Figure 10-11: Spider diagram showing the impact of consequences
Impact on storage security – Medium
CO2 leaks out of the storage complex into the shallower overburden formations.
Impact on social acceptance – Medium
CO2 leaking into shallower formations out of the storage complex will be of
concern for the public as well as regulators and policy makers. This will be
heavily discussed in the industry and research community.
Impact on environment – Low
No impact expected.
Costs – Medium
The costs are similar to Scenario 1.
Impact on hydrocarbon industry – Low
D07 Acorn CO2 Storage Site Development Plan Annexes
ACT Acorn Consortium Page 150 of 151
No impact expected.
10.3.10 Leakage Scenario 10
10.3.10.1 Scenario Description
As per 6 and 8 but, additionally, CO2 reaches the seafloor either via a fault
crosscutting the primary and secondary reservoir or by migrating all the way
along the primary and secondary reservoirs until they reach the seafloor.
10.3.10.2 Consequence Analysis
Figure 10-12: Spider diagram showing the impact of consequences
Impact on storage security – High
CO2 leaks to the seabed, which is a worst-case scenario.
Impact on social acceptance – High
CO2 leaking to the seabed will be alarming for the public as well as regulators
and policy makers. This will have nationwide effect on the public perception of
CO2 storage.
Impact on environment – Med
Although the volume of leaking CO2 is relatively small, local damage to the
seafloor can occur where CO2 leaks out.
Costs – High
In addition to the costs of dealing with the CO2 leaking into the Palaeocene
sandstone, further costs for widespread remediation will be required because
CO2 leaks to the surface. The new European Union Allowance (EUA) will be
required.
Impact on hydrocarbon industry – Low
No impact expected.
10.3.11 Leakage Scenario 11
10.3.11.1 Scenario Description
As per 9 but, additionally, CO2 leaks through the overburden to the seafloor.
D07 Acorn CO2 Storage Site Development Plan Annexes
ACT Acorn Consortium Page 151 of 151
10.3.11.2 Consequence Analysis
Figure 10-13: Spider diagram showing the impact of consequences
Impact on storage security – High
CO2 leaks to the seabed, which is a worst-case scenario.
Impact on social acceptance – High
CO2 leaking to the seabed will be alarming for the public as well as regulators
and policy makers. This will have nationwide effect on the public perception of
CO2 storage.
Impact on environment – Medium
Although the volume of leaking CO2 is relatively small, local damage to the
seafloor can occur where CO2 leaks out.
Costs – High
In addition to the costs of dealing with the CO2 leaking into the Palaeocene
sandstone and into the overburden, additional costs for widespread remediation
will be required because CO2 leaks to the surface. The new European Union
Allowance (EUA) will be required.
Impact on hydrocarbon industry – Low
No impact expected.