63
MBB3173 Project Management Planning a Project (PART 2) Topic To Be Covered Planning Procedures Developing a Network Planning Diagram Project Evaluation and Review Technique Precedence Diagramming MBB3173 Project Management

Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

  • Upload
    ngoanh

  • View
    238

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

MBB3173

Project ManagementPlanning a Project (PART 2)

Topic To Be Covered

• Planning Procedures

• Developing a Network Planning Diagram

• Project Evaluation and Review Technique

• Precedence Diagramming

MBB3173 Project Management

Page 2: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Lecture Outline

• Project Planning

• Project Scheduling

• Project Control

• CPM/PERT

• Probabilistic Activity Times

• Microsoft Project

• Project Crashing and Time-Cost Trade-off

Page 3: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Project Management Process

• Project• unique, one-time operational activity or effort

9-3

Page 4: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Project Management Process

9-4

Page 5: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Project Management Process

9-5

Page 6: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Project Elements

• Objective

• Scope

• Contract requirements

• Schedules

• Resources

• Personnel

• Control

• Risk and problem analysis

9-6

Page 7: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Project Team and Project Manager

• Project team• made up of individuals from various areas and

departments within a company

• Matrix organization• a team structure with members from functional areas,

depending on skills required

• Project manager• most important member of project team

9-7

Page 8: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Scope Statement

• Scope statement• a document that provides an understanding, justification,

and expected result of a project

• Statement of work• written description of objectives of a project

9-8

Page 9: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Work Breakdown Structure

• Work breakdown structure (WBS)• Breaks a project into components, subcomponents,

activities, and tasks

9-9

Page 10: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

9-10

Work Breakdown Structure for Computer Order

Processing System Project

Page 11: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

A Partial WBS (Gozinto Chart) for an Annual Tribute Dinner Project

MBB3173 Project Management

Page 12: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

… another example

PROGRAM

TRAINING HARDWARE

ENGINEERING

SUBSYSTEM

MANUFACTURIN

G SUBSYSTEM

COMPONENT

TESTING

MODULE A MODULE B MODULE C MODULE D

LEVEL 1

LEVEL 2

LEVEL 3

LEVEL 4

MBB3173 Project Management

Page 13: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

… another example

MBB3173 Project Management

NEW CAR

DESIGN

BRAKE ENGINE

CHEMICHAL

MECHANICAL

LEVEL 1 - PROGRAM

LEVEL 2 - PROJECT

LEVEL 3 - TASK

STRUCTURE INTERIOR

ELECTRIICAL

CHASIS

DOOR

BONNET

GRILL

Page 14: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Responsibility Assignment Matrix

• Organizational Breakdown Structure (OBS)• a chart that shows which organizational units are

responsible for work items

• Responsibility Assignment Matrix (RAM)• shows who is responsible for work in a project

9-14

Page 15: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

9-15

Responsibility Assignment Matrix

Page 16: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Global and Diversity Issues in Project Management

• Global project teams are formed from different genders, cultures, ethnicities, etc.

• Diversity among team members can add an extra dimension to project planning

• Cultural research and communication are important elements in the planning process

9-16

Page 17: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Project Scheduling

• Steps• Define activities

• Sequence activities

• Estimate time

• Develop schedule

• Techniques• Gantt chart

• CPM/PERT

• Software• Microsoft Project

9-17

Page 18: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Gantt Chart

• Graph or bar chart

• Bars represent the time for each task

• Bars also indicate status of tasks

• Provides visual display of project schedule

• Slack• amount of time an activity can be delayed without

delaying the project

9-18

Page 19: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Example of Gantt Chart

9-19

| | | | |

Activity

Design house and obtain financing

Lay foundation

Order and receive materials

Build house

Select paint

Select carpet

Finish work

0 2 4 6 8 10Month

Month1 3 5 7 9

Page 20: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Project Control

• Time management

• Cost management

• Performance management• Earned Value Analysis – standard procedure to

• numerically measure a project’s progress

• forecast its completion date and cost

• measure schedule and budget variation

9-20

Page 21: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Project Control

• Quality management

• Communication

• Enterprise project management

9-21

Page 22: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

CPM/PERT

• Critical Path Method (CPM)• DuPont & Remington-Rand

• Deterministic task times

• Activity-on-node network construction

• Project Evaluation and Review Technique (PERT)• US Navy and Booz, Allen & Hamilton

• Probabilistic task time estimates

• Activity-on-arrow network construction

9-22

Page 23: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Project Network

• Activity-on-node (AON)• nodes represent activities

• arrows show precedence relationships

• Activity-on-arrow (AOA)• arrows represent activities

• nodes are events for points in time

• Event• completion or beginning of

an activity in a project

9-23

1 32

Branch Node

Page 24: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

AOA Project Network for a House

9-24

3

2 0

1

3

1 1

11 2 4 6 7

3

5

Lay

foundation

Design house

and obtain

financing

Order and

receive

materials

Dummy

Finish

work

Select

carpet

Select

paint

Build

house

Page 25: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Concurrent Activities

• Dummy• two or more activities cannot share same start and end

nodes

9-25

2 3

Lay foundation

Order material

(a) Incorrect precedence

relationship

(b) Correct precedence

relationship

3

42

DummyLay

foundation

Order material

1

2 0

Page 26: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

AON Network for House Building Project

9-26

1

3

2

2

4

3

3

1

5

1

6

1

7

1Start

Design house

and obtain

financingOrder &receive

materials

Select

paint

Select

carpet

Lay

foundationBuild

house

Finish work

Activity Number

Activity Time

Page 27: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Critical Path

9-27

Critical path

Longest path through a

network

Minimum project

completion time

A: 1-2-4-7

3 + 2 + 3 + 1 = 9 months

B: 1-2-5-6-7

3 + 2 + 1 + 1 + 1 = 8 months

C: 1-3-4-7

3 + 1 + 3 + 1 = 8 months

D: 1-3-5-6-7

3 + 1 + 1 + 1 + 1 = 7 months

1

3

2

2

4

3

3

1

5

1

6

1

7

1Start

Page 28: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Activity Start Times

9-28

1

3

2

2

4

3

3

1

5

1

6

1

7

1Start

Start at 3 months Start at 6 months

Start at 5 months

Finish at 9 months

Finish

Page 29: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Node Configuration

9-29

1 0 3

3 0 3

Activity

duration

Activity

number

Earliest

start

Latest

start

Latest

finish

Earliest

finish

Page 30: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Activity Scheduling

• Earliest start time (ES)• earliest time an activity can start

• ES = maximum EF of immediate predecessors

• Forward pass• starts at beginning of CPM/PERT network to determine

earliest activity times

• Earliest finish time (EF)• earliest time an activity can finish

• earliest start time plus activity time

• EF= ES + t

9-30

Page 31: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Earliest Activity Start and Finish Times

9-31

1 0 3

1

2 3 5

2

3 3 4

1 5 5 6

1

4 5 8

3

6 6 7

1

7 8 9

1Start

Design house

and obtain

financing

Select paint

Lay foundation

Select carpet

Build house

Finish work

Order and

receive materials

Page 32: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Activity Scheduling

• Latest start time (LS)• Latest time an activity can start without delaying critical path

time

• LS= LF - t

• Latest finish time (LF)• latest time an activity can be completed without delaying

critical path time

• LF = minimum LS of immediate predecessors

• Backward pass• Determines latest activity times by starting at the end of

CPM/PERT network and working forward

9-32

Page 33: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Latest Activity Start and Finish Times

9-33

0 3

1 0 3

1

3 5

2 3 5

2

4 5

3 3 4

1

6 7

5 5 6

1

5 8

4 5 8

3

6 7

6 6 7

1

8 9

7 8 9

1Start

Design house

and obtain

financing

Select paint

Lay foundation

Select carpet

Build house

Finish work

Order and

receive materials

Page 34: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Activity Slack

9-34

* Critical Path

09988*7

178676

167565

08855*4

145343

05533*2

03300*1

Slack SEFLFESLSActivity

Page 35: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Probabilistic Time Estimates

• Beta distribution• probability distribution traditionally used in CPM/PERT

9-35

a = optimistic estimate

m = most likely time estimate

b = pessimistic time estimate

where

Mean (expected time): t =a + 4m + b

6

Variance: 2 =

2b - a

6

Page 36: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Examples of Beta Distributions

9-36

P(t

ime)

P(t

ime)

P(t

ime)

Time

a mt ba m t b

m = t

Time

Time

ba

Page 37: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Project with Probabilistic Time Estimates

9-37

Finish23,6,9

31,3,5

16,8,10

52,3,4

63,4,5

42,4,12

72,2,2

83,7,11

92,4,6

10

1,4,7

11

1,10,13

Equipment

installation

System

development

Position

recruiting

Equipment testing

and modification

Manual

testing

Job Training

Orientation

System

training

System

testing

Final

debugging

System

changeover

Start

Page 38: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Activity Time Estimates

9-38

1 6 8 10 8 0.44

2 3 6 9 6 1.00

3 1 3 5 3 0.44

4 2 4 12 5 2.78

5 2 3 4 3 0.11

6 3 4 5 4 0.11

7 2 2 2 2 0.00

8 3 7 11 7 1.78

9 2 4 6 4 0.44

10 1 4 7 4 1.00

11 1 10 13 9 4.00

TIME ESTIMATES (WKS) MEAN TIME VARIANCE

ACTIVITY a m b t б2

Page 39: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Activity Early, Late Times & Slack

9-39

ACTIVITY t б ES EF LS LF S

1 8 0.44 0 8 1 9 1

2 6 1.00 0 6 0 6 0

3 3 0.44 0 3 2 5 2

4 5 2.78 8 13 16 21 8

5 3 0.11 6 9 6 9 0

6 4 0.11 3 7 5 9 2

7 2 0.00 3 5 14 16 11

8 7 1.78 9 16 9 16 0

9 4 0.44 9 13 12 16 3

10 4 1.00 13 17 21 25 8

11 9 4.00 16 25 16 25 0

Page 40: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Earliest, Latest, and Slack

9-40

1 0 8

8 1 9

3 0 3

3 2 5

4 8 13

5 16 21

6 3 7

4 5 9

7 3 5

2 14 16

9 9 13

4 12 16

10 13 17

1 0 3

2 0 6

6 0 65 6 9

3 6 9

8 9 16

7 9 16

11 16 25

9 16 25

Critical Path 2-5-8-11

FinishStart

Page 41: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Total Project Variance

9-41

2 = б22 + б5

2 + б82 + б11

2

= 1.00 + 0.11 + 1.78 + 4.00

= 6.89 weeks

Page 42: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

CPM/PERT With OM Tools

9-42

Page 43: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Probabilistic Network Analysis

9-43

Determine probability that project is

completed within specified time

where

= tp = project mean time

= project standard deviation

x = proposed project time

Z = number of standard deviations that

x is from the mean

Z =x -

Page 44: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Normal Distribution of Project Time

9-44

= tp Timex

Z

Probability

Page 45: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Southern Textile

9-45

What is probability that project is completed within 30 weeks?

2 = 6.89 weeks

= 6.89

= 2.62 weeks

Z =

=

= 1.91

x -

30 - 25

2.62

From Table A.1, (appendix A) a Z score of 1.91 corresponds to a

probability of 0.4719. Thus P(30) = 0.4719 + 0.5000 = 0.9719

= 25 Time (weeks)x = 30

P(x 30 weeks)

Page 46: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Southern Textile

9-46

What is probability that project is completed within 22 weeks?

2 = 6.89 weeks

= 6.89

= 2.62 weeks

Z =

=

= -1.14

x -

22 - 25

2.62

From Table A.1, (appendix A) a Z score of 1.14 corresponds to a

probability of 0.3729. Thus P(22) = 0.5000 - 0.3729 = 0.1271

= 25 Time (weeks)x = 22

P(x 22 weeks)

= 0.1271

0.3729

Page 47: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Microsoft Project

• Popular software package for project management and CPM/PERT analysis

• Relatively easy to use

9-47

Page 48: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Microsoft Project

9-48

Click on “Tasks”

First step;

Start Date

Page 49: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Microsoft Project

9-49

Precedence

relationships

Click on “Format” then ”Timescale”

to scale Gantt chart.

Gantt chart;

click on “View”

to activateCreate precedence

relationships;

click on predecessor

activity, then

holding “Ctrl” Key,

click on successor

activity.

Page 50: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Microsoft Project

9-50

Click on “View” then

Network Diagram

Critical path

in red

Page 51: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Microsoft Project – Zoom View

9-51

Page 52: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Microsoft Project – Task Information

9-52

Enter % completion

Page 53: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Microsoft Project – Degree of Completion

9-53

Activities 1, 2 and 3

100% complete

Black bars show

degree of completion

Page 54: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

PERT Analysis with Microsoft Project

9-54

Click on PERT Entry

Sheet to enter 3

time estimates

Click on PERT

calculator to compute

activity duration

Page 55: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

PERT Analysis with Microsoft Project

9-55

Page 56: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

PERT Analysis with Microsoft Project

9-56

Page 57: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Project Crashing

• Crashing• reducing project time by expending additional

resources

• Crash time• an amount of time an activity is reduced

• Crash cost• cost of reducing activity time

• Goal• reduce project duration at minimum cost

9-57

Page 58: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Project Network – Building a House

9-58

112

2

8

412

3

4

5

4

6

4

7

4

Page 59: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Normal Time and Costvs. Crash Time and Cost

9-59

$7,000 –

$6,000 –

$5,000 –

$4,000 –

$3,000 –

$2,000 –

$1,000 –

– | | | | | | |

0 2 4 6 8 10 12 14 Weeks

Normal activity

Normal time

Normal cost

Crash time

Crashed activity

Crash cost

Slope = crash cost per week

Page 60: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Project Crashing

9-60

TOTAL

NORMAL CRASH ALLOWABLE CRASH

TIME TIME NORMAL CRASH CRASH TIME COST PER

ACTIVITY (WEEKS) (WEEKS) COST COST (WEEKS) WEEK

1 12 7 $3,000 $5,000 5 $400

2 8 5 2,000 3,500 3 500

3 4 3 4,000 7,000 1 3,000

4 12 9 50,000 71,000 3 7,000

5 4 1 500 1,100 3 200

6 4 1 500 1,100 3 200

7 4 3 15,000 22,000 1 7,000

$75,000 $110,700

Page 61: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Project Duration:

36 weeks1

12

2

8

3

4 5

4

6

4

7

4

$400

$500

$3000

$7000

$200

$200

$700012

4 FROM …

1

7

2

8

3

4 5

4

6

4

7

4

$400

$500

$3000

$7000

$200

$200

$700012

4

Project Duration:

31 weeks

Additional Cost:

$2000

TO…

Page 62: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Time-Cost Relationship

• Crashing costs increase as project duration

decreases

• Indirect costs increase as project duration

increases

• Reduce project length as long as crashing costs

are less than indirect costs

Page 63: Project Management - ahmadbo.com€¦ · •CPM/PERT •Probabilistic Activity Times ... Gantt Chart •Graph or bar chart •Bars represent the time for each task •Bars also indicate

Time-Cost TradeoffC

ost

($)

Project duration

Crashing Time

Minimum cost = optimal project timeTotal project cost

Indirect cost

Direct cost