58
Project Management Project Management Chapter 9 Chapter 9 Copyright 2009 John Wiley & Sons, Inc. Copyright 2009 John Wiley & Sons, Inc. Beni Asllani Beni Asllani University of Tennessee at Chattanooga University of Tennessee at Chattanooga Operations Management - 6 th Edition Operations Management - 6 th Edition Roberta Russell & Bernard W. Taylor, III Roberta Russell & Bernard W. Taylor, III

Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Project ManagementProject Management

Chapter 9Chapter 9

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc.

Beni AsllaniBeni AsllaniUniversity of Tennessee at ChattanoogaUniversity of Tennessee at Chattanooga

Operations Management - 6th EditionOperations Management - 6th Edition

Roberta Russell & Bernard W. Taylor, IIIRoberta Russell & Bernard W. Taylor, III

Page 2: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Lecture OutlineLecture Outline

� Project Planning� Project Scheduling� Project Control

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--22

� Project Control� CPM/PERT� Probabilistic Activity Times� Microsoft Project� Project Crashing and Time-

Cost Trade-off

Page 3: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Project Management Process

� Project� unique, one-time operational activity or effort

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--33

Page 4: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Project Management Process Project Management Process (cont.)(cont.)

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--44

Page 5: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Project Management Process Project Management Process (cont.)(cont.)

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--55

Page 6: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Project ElementsProject Elements

�� ObjectiveObjective

�� ScopeScope

�� Contract requirementsContract requirements

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--66

�� Contract requirementsContract requirements

�� SchedulesSchedules

�� ResourcesResources

�� PersonnelPersonnel

�� ControlControl

�� Risk and problem analysisRisk and problem analysis

Page 7: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Project Team and Project Manager

�� Project teamProject team�� made up of individuals from various areas made up of individuals from various areas

and departments within a companyand departments within a company

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--77

and departments within a companyand departments within a company

�� Matrix organizationMatrix organization�� a team structure with members from a team structure with members from

functional areas, depending on skills functional areas, depending on skills requiredrequired

�� Project managerProject manager�� most important member of project teammost important member of project team

Page 8: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Scope Statement and Work Scope Statement and Work Breakdown StructureBreakdown Structure

�� Scope statementScope statement�� a document that provides an a document that provides an

understanding, justification, and expected understanding, justification, and expected

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--88

understanding, justification, and expected understanding, justification, and expected result of a projectresult of a project

�� Statement of workStatement of work�� written description of objectives of a written description of objectives of a

projectproject

�� Work breakdown structure (WBS)Work breakdown structure (WBS)�� breaks down a project into components, breaks down a project into components,

subcomponents, activities, and taskssubcomponents, activities, and tasks

Page 9: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--99

Work Breakdown Structure for Computer Order

Processing System Project

Work Breakdown Structure for Computer Order

Processing System Project

Page 10: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

�� Organizational Organizational Breakdown Breakdown Structure (OBS)Structure (OBS)�� a chart that a chart that

shows which shows which

Responsibility Assignment MatrixResponsibility Assignment Matrix

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--1010

shows which shows which organizational organizational units are units are responsible for responsible for work itemswork items

�� Responsibility Responsibility Assignment Assignment Matrix (RAM)Matrix (RAM)�� shows who is shows who is

responsible for responsible for work in a work in a projectproject

Page 11: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Global and Diversity Issues in Global and Diversity Issues in Project ManagementProject Management

�� In existing global business environment, In existing global business environment, project teams are formed from different project teams are formed from different genders, cultures, ethnicities, etc.genders, cultures, ethnicities, etc.

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--1111

�� In global projects diversity among team In global projects diversity among team members can add an extra dimension to members can add an extra dimension to project planningproject planning

�� Cultural research and communication are Cultural research and communication are important elements in planning processimportant elements in planning process

Page 12: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Project Scheduling

�� StepsSteps

�� Define activitiesDefine activities

Sequence Sequence

�� TechniquesTechniques

�� Gantt chartGantt chart

CPM/PERTCPM/PERT

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--1212

�� Sequence Sequence activitiesactivities

�� Estimate timeEstimate time

�� Develop scheduleDevelop schedule

�� CPM/PERTCPM/PERT

�� Microsoft ProjectMicrosoft Project

Page 13: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Gantt Chart

� Graph or bar chart with a bar for each project activity that shows passage of time

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--1313

time

� Provides visual display of project schedule

� Slack� amount of time an activity can be delayed

without delaying the project

Page 14: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

| | | | |

Activity

Design house and obtain financing

Lay foundation

Order and receive materials

00 22 44 66 88 1010MonthMonth

Example of Gantt ChartExample of Gantt Chart

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--1414

receive materials

Build house

Select paint

Select carpet

Finish work

MonthMonth11 33 55 77 99

Page 15: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Project ControlProject Control

�� Time managementTime management�� Cost managementCost management�� Quality managementQuality management�� Performance managementPerformance management

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--1515

�� Performance managementPerformance management�� Earned Value AnalysisEarned Value Analysis

�� a standard procedure for numerically measuring a a standard procedure for numerically measuring a project’s progress, forecasting its completion date project’s progress, forecasting its completion date and cost and measuring schedule and budget and cost and measuring schedule and budget variationvariation

�� CommunicationCommunication�� Enterprise project managementEnterprise project management

Page 16: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

CPM/PERTCPM/PERT

�� Critical Path Method (CPM)Critical Path Method (CPM)�� DuPont & RemingtonDuPont & Remington--Rand (1956)Rand (1956)

�� Deterministic task timesDeterministic task times

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--1616

�� Deterministic task timesDeterministic task times

�� ActivityActivity--onon--node network constructionnode network construction

�� Project Evaluation and Review Technique Project Evaluation and Review Technique (PERT)(PERT)�� US Navy, Booz, Allen & HamiltonUS Navy, Booz, Allen & Hamilton

�� Multiple task time estimates; probabilisticMultiple task time estimates; probabilistic

�� ActivityActivity--onon--arrow network constructionarrow network construction

Page 17: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Project NetworkProject Network

� Activity-on-node (AON)� nodes represent

activities, and arrows show precedence relationships

NodeNode

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--1717

� Activity-on-arrow (AOA)� arrows represent

activities and nodes are events for points in time

� Event� completion or beginning

of an activity in a project

� Dummy� two or more activities

cannot share same start and end nodes

1 32

BranchBranch

Page 18: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

AOA Project Network for AOA Project Network for a Housea House

22 00

3Lay Lay foundationfoundation

DummyDummy

Finish Finish Build Build

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--1818

33

22 00

11

33

11 11

111 2 4 6 7

5

Design house Design house and obtain and obtain financingfinancing

Order and Order and receive receive materialsmaterials

Finish Finish workwork

Select Select carpetcarpet

Select Select paintpaint

Build Build househouse

Page 19: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Concurrent ActivitiesConcurrent Activities

2 3

Lay foundationLay foundation3

DummyDummyLay Lay foundationfoundation

22 00

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--1919

Order materialOrder material

(a)(a) Incorrect precedence Incorrect precedence relationshiprelationship

(b)(b) Correct precedence Correct precedence relationshiprelationship

42Order materialOrder material

11

Page 20: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

AON Network for House Building Project

22

43

7

Lay foundations Build house

Finish work

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--2020

13

31 5

1

61

71Start

Design house and obtain financing

Order and receive materials Select paint

Select carpet

Page 21: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

13

22

43

3 6

71Start

Critical Path

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--2121

31 5

1

61

�� Critical pathCritical path�� Longest path Longest path

through a networkthrough a network

�� Minimum project Minimum project completion timecompletion time

A:A: 11--22--44--773 + 2 + 3 + 1 = 9 months 3 + 2 + 3 + 1 = 9 months

B:B: 11--22--55--66--773 + 2 + 1 + 1 + 1 = 8 months3 + 2 + 1 + 1 + 1 = 8 months

C:C: 11--33--44--773 + 1 + 3 + 1 = 8 months3 + 1 + 3 + 1 = 8 months

D:D: 11--33--55--66--773 + 1 + 1 + 1 + 1 = 7 months3 + 1 + 1 + 1 + 1 = 7 months

Page 22: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Activity Start Times

22

43

7

Start at 5 months

Finish at 9 months

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--2222

13

31 5

1

61

71Start

Start at 3 monthsStart at 6 months

Finish

Page 23: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Node ConfigurationNode Configuration

Activity number Earliest start

Earliest finish

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--2323

1 0 3

3 0 3

Activity duration Latest start

Latest finish

Page 24: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Activity SchedulingActivity Scheduling

� Earliest start time (ES)� earliest time an activity can start

� ES = maximum EF of immediate predecessors

� Forward pass

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--2424

� Forward pass� starts at beginning of CPM/PERT network to

determine earliest activity times

� Earliest finish time (EF)� earliest time an activity can finish

� earliest start time plus activity time

� EF= ES + t

Page 25: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Earliest Activity Start and Earliest Activity Start and Finish TimesFinish Times

1 0 3

2 3 5

24 5 8

3

Start

Lay foundationsBuild house

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--2525

1 0 3

1

3 3 4

1 5 5 6

1

6 6 7

1

7 8 9

1

Design house and obtain financing

Select pain

Select carpet

Finish work

Order and receive materials

Page 26: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Activity Scheduling (cont.)Activity Scheduling (cont.)

� Latest start time (LS)� Latest time an activity can start without delaying

critical path time

� LS= LF - t

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--2626

� LS= LF - t

� Latest finish time (LF)� latest time an activity can be completed without

delaying critical path time

� LF = minimum LS of immediate predecessors

� Backward pass� Determines latest activity times by starting at the

end of CPM/PERT network and working forward

Page 27: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Latest Activity Start and Latest Activity Start and Finish TimesFinish Times

1 0 3

2 3 5

2 3 54 5 8

3 5 8

7 8 9

Start

Lay foundationsBuild house

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--2727

1 0 3

1 0 3

3 3 4

1 4 5 5 5 6

1 6 7

6 6 7

1 7 8

7 8 9

1 8 9

Design house and obtain financing

Select pain

Select carpet

Finish work

Order and receive materials

Page 28: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

00005555555533333333*2*2*2*2

00003333333300000000*1*1*1*1

Slack SSlack SEFEFLFLFESESLSLSActivityActivity

Activity SlackActivity Slack

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--2828

* Critical Path* Critical Path

00009999999988888888*7*7*7*7

111177778888666677776666

111166667777555566665555

00008888888855555555*4*4*4*4

111144445555333344443333

00005555555533333333*2*2*2*2

Page 29: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Probabilistic Time Estimates

� Beta distribution� a probability distribution traditionally used in

CPM/PERT

Mean (expected time):Mean (expected time): tt ==aa + 4+ 4mm + + bb

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--2929

aa = optimistic estimate= optimistic estimate

mm = most likely time estimate= most likely time estimate

bb = pessimistic time estimate= pessimistic time estimate

wherewhere

Mean (expected time):Mean (expected time): tt ==aa + 4+ 4mm + + bb

66

Variance:Variance: σσ 22 ==bb -- aa

66

22

Page 30: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Examples of Beta DistributionsExamples of Beta Distributions

PP(time)

(time)

PP(time)

(time)

aa mmtt bbaa mm tt bb

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--3030

PP(time)

(time)

TimeTime

m m = = tt

TimeTime

TimeTime

bbaa

Page 31: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Project Network with Probabilistic Time Estimates: Example

Start Finish2

16,8,10

42,4,12

83,7,11

10

1,4,7

Equipment

installation

System

development

Equipment testing

and modification

Manual

System

training

Final

debugging

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--3131

Start Finish23,6,9

31,3,5

52,3,4

63,4,5

72,2,2

3,7,11

92,4,6

1,4,7

11

1,10,13Position

recruiting

Manual

testing

Job Training

Orientation

System

testing

System

changeover

Page 32: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Activity Time EstimatesActivity Time Estimates

1 1 66 88 1010 88 0.440.4422 33 66 99 66 1.001.00

TIME ESTIMATES (WKS)TIME ESTIMATES (WKS) MEAN TIMEMEAN TIME VARIANCEVARIANCE

ACTIVITYACTIVITY aa mm bb tt бб22

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--3232

22 33 66 99 66 1.001.0033 11 33 55 33 0.440.4444 22 44 1212 55 2.782.7855 22 33 44 33 0.110.1166 33 44 55 44 0.110.1177 22 22 22 22 0.000.0088 33 77 1111 77 1.781.7899 22 44 66 44 0.440.441010 11 44 77 44 1.001.001111 11 1010 1313 99 4.004.00

Page 33: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Activity Early, Late Times, Activity Early, Late Times, and Slackand Slack

ACTIVITYACTIVITY tt бб22 ESES EFEF LSLS LFLF SS

11 88 0.440.44 00 88 11 99 1122 66 1.001.00 00 66 00 66 0033 33 0.440.44 00 33 22 55 224 4 55 2.782.78 88 1313 1616 2121 88

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--3333

4 4 55 2.782.78 88 1313 1616 2121 885 5 33 0.110.11 66 99 66 99 0066 44 0.110.11 33 77 55 99 2277 22 0.000.00 33 55 1414 1616 111188 77 1.781.78 99 1616 99 1616 0099 44 0.440.44 99 1313 1212 1616 331010 44 1.001.00 1313 1717 2121 2525 881111 99 4.004.00 1616 2525 1616 2525 00

Page 34: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Start Finish

1 0 8

8 1 9

4 8 13

5 16 2110 13 17

1 0 3

2 0 68 9 16

7 9 16

Critical Path

Earliest, Latest, and SlackEarliest, Latest, and Slack

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--3434

3 0 3

3 2 5

6 3 7

4 5 9

7 3 5

2 14 16

9 9 13

4 12 16

6 0 65 6 9

3 6 9

7 9 16

11 16 25

9 16 25

Page 35: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

σ2 = б 2 + б 2 + б 2 + б 2

Total project variance

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--3535

σ2 = б22 + б

52 + б

82 + б

112

σ = 1.00 + 0.11 + 1.78 + 4.00

= 6.89 weeks

Page 36: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--3636

Page 37: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Probabilistic Network AnalysisProbabilistic Network Analysis

Determine probability that project is Determine probability that project is

completed within specified timecompleted within specified time

ZZ ==xx -- µµσσ

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--3737

wherewhere

µµ == ttpp = project mean time= project mean time

σσ == project standard deviationproject standard deviation

x x == proposed project timeproposed project time

ZZ == number of standard deviations number of standard deviations xx

is from meanis from mean

ZZ ==σσ

Page 38: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Normal Distribution ofNormal Distribution ofProject TimeProject Time

ProbabilityProbability

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--3838

µµ = = ttpp TimeTimexx

Page 39: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Southern Textile ExampleSouthern Textile Example

What is the probability that the project is completed What is the probability that the project is completed

within 30 weeks?within 30 weeks?

σσ 22 = 6.89 weeks= 6.89 weeks ZZ ==xx -- µµσσ

PP((xx ≤≤ 30 weeks)30 weeks)

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--3939

σσ 22 = 6.89 weeks= 6.89 weeks

σσ = 6.89= 6.89

σσ = 2.62 weeks= 2.62 weeks

ZZ ==

==

= 1.91= 1.91

σσ

30 30 -- 25252.622.62

From Table A.1, (appendix A) a From Table A.1, (appendix A) a ZZ score of 1.91 corresponds to a score of 1.91 corresponds to a

probability of 0.4719. Thus probability of 0.4719. Thus PP(30) = 0.4719 + 0.5000 = 0.9719(30) = 0.4719 + 0.5000 = 0.9719

µµ = 25= 25 Time (weeks)Time (weeks)xx = 30= 30

Page 40: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Southern Textile ExampleSouthern Textile Example

PP((xx ≤≤ 22 weeks)22 weeks)

What is the probability that the project is completed What is the probability that the project is completed

within 22 weeks?within 22 weeks?

σσ 22 = 6.89 weeks= 6.89 weeks

σσ = 6.89= 6.89

ZZ ==

==

xx -- µµ

σσ

22 22 -- 2525

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--4040

µµ = 25= 25 Time Time

(weeks)(weeks)

xx = 22= 22

σσ = 6.89= 6.89

σσ = 2.62 weeks= 2.62 weeks

==

= = --1.141.14

22 22 -- 2525

2.622.62

From Table A.1 (appendix A) a From Table A.1 (appendix A) a ZZ score of score of --1.14 corresponds to a 1.14 corresponds to a

probability of 0.3729. Thus probability of 0.3729. Thus PP(22) = 0.5000 (22) = 0.5000 -- 0.3729 = 0.12710.3729 = 0.1271

Page 41: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Microsoft ProjectMicrosoft Project

�� Popular software package for project Popular software package for project management and CPM/PERT analysismanagement and CPM/PERT analysis

�� Relatively easy to useRelatively easy to use

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--4141

�� Relatively easy to useRelatively easy to use

Page 42: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Microsoft Project (cont.)Microsoft Project (cont.)

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--4242

Page 43: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Microsoft Project (cont.)Microsoft Project (cont.)

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--4343

Page 44: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Microsoft Project (cont.)Microsoft Project (cont.)

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--4444

Page 45: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Microsoft Project (cont.)Microsoft Project (cont.)

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--4545

Page 46: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Microsoft Project (cont.)Microsoft Project (cont.)

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--4646

Page 47: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Microsoft Project (cont.)Microsoft Project (cont.)

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--4747

Page 48: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

PERT Analysis withPERT Analysis withMicrosoft ProjectMicrosoft Project

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--4848

Page 49: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

PERT Analysis withPERT Analysis withMicrosoft Project (cont.)Microsoft Project (cont.)

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--4949

Page 50: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

PERT Analysis withPERT Analysis withMicrosoft Project (cont.)Microsoft Project (cont.)

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--5050

Page 51: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Project Crashing

� Crashing� reducing project time by expending additional

resources

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--5151

� Crash time� an amount of time an activity is reduced

� Crash cost� cost of reducing activity time

�� GoalGoal� reduce project duration at minimum cost

Page 52: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

28

412

Project Network for Buildinga House

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--5252

112

8

34 5

4

64

74

Page 53: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Normal Time and CostNormal Time and Costvs. Crash Time and Costvs. Crash Time and Cost

$7,000 –

$6,000 –

$5,000 – Crashed activity

Crash cost

Slope = crash cost per week

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--5353

$4,000 –

$3,000 –

$2,000 –

$1,000 –

– | | | | | | |0 2 4 6 8 10 12 14 Weeks

Normal activity

Normal time

Normal cost

Crash time

Slope = crash cost per week

Page 54: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Project Crashing: ExampleProject Crashing: Example

TOTALTOTALNORMALNORMAL CRASHCRASH ALLOWABLEALLOWABLE CRASHCRASHTIMETIME TIMETIME NORMALNORMAL CRASHCRASH CRASH TIMECRASH TIME COST PERCOST PER

ACTIVITYACTIVITY (WEEKS)(WEEKS) (WEEKS)(WEEKS) COSTCOST COSTCOST (WEEKS)(WEEKS) WEEKWEEK

11 1212 77 $3,000$3,000 $5,000$5,000 55 $400$400

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--5454

11 1212 77 $3,000$3,000 $5,000$5,000 55 $400$400

22 88 55 2,0002,000 3,5003,500 33 500500

33 44 33 4,0004,000 7,0007,000 11 3,0003,000

44 1212 99 50,00050,000 71,00071,000 33 7,0007,000

55 44 11 500500 1,1001,100 33 200200

66 44 11 500500 1,1001,100 33 200200

77 44 33 15,00015,000 22,00022,000 11 7,0007,000

$75,000$75,000 $110,700$110,700

Page 55: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

1

12

2

8

3

4 5

4

6

4

7

4

$400

$500

$3000

$7000

$200

$200

$70012

4Project Duration:

36 weeks

FROM …

$500 $7000

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--5555

1

7

2

8

3

4 5

4

6

4

7

4

$400

$500

$3000

$7000

$200

$200

$70012

4

Project Duration:31 weeks

Additional Cost:$2000

TO…

Page 56: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

�� Crashing costs increase as project Crashing costs increase as project

duration decreasesduration decreases

�� Indirect costs increase as project Indirect costs increase as project

TimeTime--Cost RelationshipCost Relationship

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--5656

�� Indirect costs increase as project Indirect costs increase as project

duration increasesduration increases

�� Reduce project length as long as Reduce project length as long as

crashing costs are less than indirect crashing costs are less than indirect

costscosts

Page 57: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

TimeTime--Cost TradeoffCost TradeoffCost ($)

Cost ($)

Minimum cost = optimal project timeMinimum cost = optimal project timeTotal project costTotal project cost

Indirect costIndirect cost

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--5757

Cost ($)

Cost ($)

Project durationProject duration

CrashingCrashing TimeTime

Direct costDirect cost

Page 58: Project Management - Seoul National University · 2018. 1. 30. · Lecture Outline Project Planning Project Scheduling Project Control ... CPM/PERT Critical Path Method (CPM) DuPont

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc.

All rights reserved. Reproduction or translation of this work beyond that All rights reserved. Reproduction or translation of this work beyond that

permitted in section 117 of the 1976 United States Copyright Act without permitted in section 117 of the 1976 United States Copyright Act without

express permission of the copyright owner is unlawful. Request for further express permission of the copyright owner is unlawful. Request for further

Copyright 2009 John Wiley & Sons, Inc.Copyright 2009 John Wiley & Sons, Inc. 99--5858

express permission of the copyright owner is unlawful. Request for further express permission of the copyright owner is unlawful. Request for further

information should be addressed to the Permission Department, John Wiley & information should be addressed to the Permission Department, John Wiley &

Sons, Inc. The purchaser may make backSons, Inc. The purchaser may make back--up copies for his/her own use only and up copies for his/her own use only and

not for distribution or resale. The Publisher assumes no responsibility for not for distribution or resale. The Publisher assumes no responsibility for

errors, omissions, or damages caused by the use of these programs or from the errors, omissions, or damages caused by the use of these programs or from the

use of the information herein. use of the information herein.