Project - Quarterly Progress Report
Promoter’s Name : MAYFLOWER ENTERPRISES PVT LTD., Project Name : MAYFLOWER ESTATE Project Registration No : TN/11/BUILDING/0111/2017 Quarter Ending : March Year 2020
A. Sales
Sl. No.
Description Cumulative No. of Units upto the
Quarter
Total Area
1. Plots/Flats Booked size wise (As
given in Carpet Area Statement
while registering)
AS ATTACHED
2. Parking Lots
3. UDS Registered in Sq.m.
B. Construction
Sl. No.
Description Block/Tower No. Status
1. Stage of construction of each Block/Tower, Floor wise
PROGRESS ATTACHED
2. Status of common Amenities for each Block/Tower, Item wise
Sl.No. Description Percentage
1. Percentage of Completion
i) Physical 3.20%
ii) Financial (Enter Anticipated Project Cost in Lakhs) 3.20%
C. Details of Clearances
1. Completion Certificate No. ------------------ (only CC No. in Text Format)
2. Compliance Report, if any (Kindly Specify) -------------- (in PDF Format)
3. Annual Audit Report of Special Account in Form 7 ------------ (in PDF Format)
D. Latest Photo with Date (Atleast from 2 angles) --------------- (in PDF Format)
Note: Mail the above particulars to “[email protected]“
APARTMENT WORK PROGRESS REPORT
31.03.2020
BAMBOO
Flooring tiles work 34/35 completed remaining 1 flat on going.
Balcony & Utility flooring tiles 23/35 completed remaining on
going.
Master & Common Toilet tiles work 33/35 completed remaining
2 flat on going.
Kitchen table top granite laying 32/35 completed remaining on
going.
Kitchen wall tile laying work 27/35 completed remaining on
going.
Balcony handrail & ODU grill fixing work completed.
Terrace floor press tile ,joint filling & skirting work completed.
Staircase No.1 & No.2 Step granite laying & skirting work
completed.
Corridor floor tile laying work 6/7 completed.
Door shutters ,Locks & fiitings fixing work on going.
Outer primer work ongoing.
Toilet false ceiling work on going.
UPVC Window frame & glass fixing work on going.
Passenger lift erectionwork on going.
Basement & Stilt floor grano flooring completed.
2nd coat putty work on going in 7th floor.
PINE
Corridor 1st coat putty work completed.
Inner 1st coat putty work completed.
Gooja fixing work completed.
Balcony handrail fixing work completed.
ODU Handrails fixing work completed.
All Door frames fixing work completed.
Terrace floor press tile ,joint filling & skirting work completed.
7th,6th & 5th floor plumbing waste & soil line core packing
completed.
SANDAL
2nd coat putty work 16/42 completed.
Tiles work 41/42 completed.
Staircase No.1 & 2 Handrail fixing work completed.
Outer primer work completed.
Outer emulsion 1st coat on going.
UPVC window fixing work on going.
Toilet false ceiling work on going.
Door shutter & fittings fixing work on going.
TEAK
Kitchen tabletop concrete completed except B Flats pending
Window Grill fixing work completed.
Gooja fixing work completed.
Outer Whitewash work 80% completed.
Outer primer work 80% completed.
Terrace floor press tile ,joint filling & skirting work completed
Communication & Fire Ducts Inner white wash work completed.
Staircase No.7 & No.8 Step granite laying & skirting work
completed.
Balcony Handrail Fixing work completed.
ODU handrail fixing work completed.
Tile laying work 7th ,3rd & 2nd floor 50% completed.
Passenger lift white wash completed.
All door frames fixing work completed.
WILLOW
Wiring & switches fixing work completed in all flats.
Sanitary wares fixing completed for all flats.
Colour primer 1st coat completed in all flats.
Toilet & Wash basin area false ceiling work completed.
Ground floor entrance area civil work on going.
Corridor colour primer completed in all floors.
Communication,plumbing & fire duct inner 1st colour primer
completed.
Communication wiring for flats from EB room ongoing.
Staircase handrail fixing work completed.
VILLAS WORK PROGRESS
31.06.2020
VILLA-04
Ground floor Brick Work on going.
First floor roof slab concrete completed.
Head room column completed.
Head room roof slab reinforcement on going.
VILLA-06
Over all plastering completed.
Elevation work completed.
Putty work on progress.
Outer white wash completed.
VILLA-07
Compound wall and Gate fixing completed.
VILLA-08
Finishing Work on Going.
VILLA-09
Tile flooring completed.
Finishing work on progress.
VILLA-10
Compound wall plastering on progress.
Finishing work on progress.
VILLA-11
Compound wall block work completed.
Civil work completed.
Finishing work to be start.
VILLA-12
Civil work completed.
Finishing to be start.
Compound wall block work completed.
VILLA-13
Civil work completed.
Finishing to be start.
Compound wall block work completed.
VILLA-14
Civil work completed.
Finishing to be start.
Compound wall block work completed.
VILLA-15
Client alteration work on progress.
Electrical work on going.
Compound wall pile concrete completed.
VILLA-16
Client alteration work on progress.
Electrical work on going.
Compound wall pile concrete completed.
VILLA-17
Plastering work completed.
VILLA-18
Elevation work on going.
Plastering completed.
Window grill fixing on going.
Plumbing work on going.
VILLA-19
Plastering completed.
Taper slab tile completed.
Elevation work on going.
VILLA-20
Plastering completed.
Taper slab tile completed.
Elevation work on going.
VILLA-21
First floor plastering completed.
Ground floor plastering on going.
VILLA-22
Ground floor and First floor brick work on going.
VILLA-23
Plastering completed.
Grill fixing completed.
Terrace press tile completed.
Elevation on progress.
VILLA-24
Basement brickwork completed.
Basement filling on going.
VILLA-26
Basement Filling completed.
Basement consolidation on progress.
VILLA-27
Ground floor roof slab concrete completed.
First floor column reinforcement on progress.
VILLA-28
Over all brick work completed.
Electrical work on progress.
VILLA-29
Plastering completed.
Terrace press tile completed.
Grill work completed.
Taper slab shuttering and reinforcement completed.
VILLA-30
Ground floor roof slab concrete completed.
First floor column and staircase completed.
First floor roof slab shuttering reinforcement on progress.
VILLA-31
Plinth beam concrete completed.
Basement column on progress.
VILLA-32
Brick work completed.
Electrical work on going.
VILLA-33
Lintel level brick work completed on ground floor and first floor.
Parapet wall and headroom wall completed.
Lintel shuttering work on going.
VILLA-34
Plastering completed.
Grill work completed.
Terrace press tile completed.
Plumbing work on going.
VILLA-35
Plastering completed.
Terrace press tile on going.
Grill fixing completed.
VILLA-36
Outer plastering completed.
Brick work completed.
Ground floor and First floor inner wall plastering on going.
FLOOR 1st 2nd 3rd 4th 5th 6th 7th
FLAT
TYPEFLOOR FLOOR FLOOR FLOOR FLOOR FLOOR FLOOR
WEST 1251 A SOLD
NORTH 1129 B SOLD SOLD SOLD SOLD
EAST 1184 C
EAST 1485 D SOLD
SOUTH 1322 E
NORTH 691 A SOLD SOLD SOLD
EAST 623 B SOLD
EAST 579 C SOLD
WEST 630 D
WEST 636 E
NORTH 745 F SOLD SOLD SOLD SOLD SOLD
NORTH 683 G SOLD SOLD SOLD SOLD
WEST 1251 A
NORTH 1326 B SOLD
NORTH 1247 C SOLD SOLD SOLD SOLD SOLD SOLD SOLD
EAST 1188 D SOLD SOLD SOLD
EAST 1485 E SOLD SOLD SOLD SOLD SOLD SOLD
SOUTH 1327 F
NORTH 1513 A SOLD SOLD SOLD SOLD SOLD
SOUTH 1626 B SOLD SOLD SOLD SOLD SOLD
SOUTH 1251 C
WEST 1467 D SOLD
NORTH 1298 E SOLD
EAST 1543 A SOLD SOLD SOLD SOLD SOLD SOLD SOLD
SOUTH 1527 B SOLD SOLD SOLD SOLD SOLD SOLD SOLD
SOUTH 1508 C SOLD SOLD SOLD SOLD
NORTH 1364 D SOLD SOLD SOLD SOLD
MAYFLOWER ESTATES - APARTMENT BOOKING & ALLOTMENT DETAILS MAR 2020
BLO
CK
NA
MES
FACING SBA
WIL
LOW
3 &
2+
S
BH
K
SA
ND
AL
2 B
HK
TEA
K
3 &
2 B
HK
BA
MB
OO
2 B
HK
PIN
E
1 B
HK
VILLAS ALLOTMENT & BOOKING DETAILS Mar-20
Villa No.Villa
TypeFacing
Bed
Rooms
Carpet
Area
Plinth
AreaSBA
Land
Area UDS
Addl UDS
with
drive
way and
common
areas
UDS with
Drive
way
BOOKING STATUS
1 1 East 3 1853 2567 2705 1929 774 2703
2 1 East 3 1853 2567 2705 1958 786 2744
3 1 East 3 1853 2567 2705 1958 786 2744 SOLD
4 1 East 3 1853 2567 2705 1958 786 2744
5 1 East 3 1853 2567 2705 2240 899 3139 SOLD
6 1 East 3 1853 2567 2705 2301 924 3225 SOLD
7 2 East 3 1983 2857 3010 2391 960 3351 SOLD
8 2 East 3 1983 2857 3010 2400 963 3363
9 2 East 3 1983 2857 3010 2413 969 3382 SOLD
10 2 East 3 1983 2857 3010 2413 969 3382 SOLD
11 2 East 3 1983 2857 3010 2415 969 3384 SOLD
12 2 East 3 1983 2857 3010 2419 971 3390
13 2 East 3 1983 2857 3010 2444 981 3425 SOLD
14 2 East 3 1983 2857 3010 2430 975 3405 SOLD
15 2 East 3 1983 2857 3010 2415 969 3384 SOLD
16 2 East 3 1983 2857 3010 2405 965 3370
17 3 East 3 2006 2771 2920 2386 958 3344
18 3 East 3 2006 2771 2920 2841 1140 3981 SOLD
19 4 South 3 1716 2450 2581 1904 764 2668
20 4 South 3 1716 2450 2581 1904 764 2668
21 4 South 3 1716 2450 2581 1912 768 2680
22 4 South 3 1716 2450 2581 1903 764 2667 SOLD
23 4 South 3 1716 2450 2581 1903 764 2667 SOLD
24 4 South 3 1716 2450 2581 1903 764 2667
25 4 South 3 1716 2450 2581 1903 764 2667
26 4 South 3 1716 2450 2581 1903 764 2667
27 4 South 3 1716 2450 2581 1904 764 2668
28 4 South 3 1716 2450 2581 2369 951 3320 SOLD
29 7 North 4 2652 3539 3729 3822 1534 5356 SOLD
30 6 North 4 2958 4050 4267 2855 1146 4001 SOLD
31 6 North 4 2958 4050 4267 2855 1146 4001 SOLD
32 6 North 4 2958 4050 4267 2855 1146 4001 SOLD
33 6 North 4 2958 4050 4267 2855 1146 4001 SOLD
34 5 North 4 2097 2792 2942 2222 892 3114 SOLD
35 5 North 4 2097 2792 2942 2189 879 3068 SOLD
36 5 North 4 2097 2792 2942 2559 1027 3586 SOLD