Proposed EmKey Resources Pipeline — Color Version

Embed Size (px)

DESCRIPTION

Preliminary presentation labeled October 2012 on a 75-mile, 24-inch natural gas pipeline proposed to run north to Morrisville from Windsor, NY.Uploaded to illustrate a blog post here:http://nyshalegasnow.blogspot.com/2012/11/emkey-successor-to-part-of-norse.html

Citation preview

Page 1: Proposed EmKey Resources Pipeline — Color Version

OCTOBER 2012

Page 2: Proposed EmKey Resources Pipeline — Color Version

Outline• Preliminary Meeting to review EmKey’s potential pipeline project• Pipeline Utilization

– Transport natural gas from newly developed Shale exploration– Allow access to local municipalities and end users

• Route– Anticipated route from Morrisville to Windsor

• Estimated length of 75 mile– Plan to utilize ROW acquired from Norse– Incorporate route/approval previously received from PSC

• 16” steel pipeline Case 09-T-0499– Currently reviewing ROW

• Type of Pipeline– Currently Engineering for Utilization– Steel Pipeline

• Coated steel from 16” to 24”• Pressure rating of approximately 1400 psi

• Type of PSC Filing– Article 7 Filing– PSC to be lead agency

Page 3: Proposed EmKey Resources Pipeline — Color Version

Outline• List of necessary approving agencies

– PSC• Environmental and Safety

– Army Corps of Engineers• River crossings & wetlands

– NYS Office of Parks Recreation and Historic Preservation• Archeological studies

– Federal and NYSDEC Wetlands• Open and wooded wetland crossings

– NYSDOT• Road use and crossings

– County • Road use and crossings• Soil and water

– Townships• Road use and crossings

– NYS Agriculture and Markets• Active fields/crop land• Conservation districts

– NYSDEC Soil & Water• SWPPP• SPDES permitting

• Taps– Dominion, Tennessee and Millennium– End user taps as feasible

• Compression – Currently under evaluation

Page 4: Proposed EmKey Resources Pipeline — Color Version

Outline• Time Line

– Review existing ROW• Currently finalizing

– Notification to ROW land owners• End of month

– Flag and survey route• Possibly start end of month

– Select areas– Visual Inspection

• Possibly end of month– Prepare PSC application

• First or second quarter of 2013– Installation dependent on permitting and approval of SGEIS

• Additional Meetings– PSC will require additional public meetings as part of the application process– Town/County meeting as needed

• Comments and Questions