44
QUANTITATIVE MODELLING OF OEE USE WITH SPREADSHEET FOR MACHINE CAPACITY PLANNING ONG YUNG CHIEH UNIVERSITI SAINS MALAYSIA 2014

quantitative modelling of oee use with spreadsheet for machine

  • Upload
    doliem

  • View
    224

  • Download
    0

Embed Size (px)

Citation preview

Page 1: quantitative modelling of oee use with spreadsheet for machine

QUANTITATIVE MODELLING OF OEE

USE WITH SPREADSHEET FOR

MACHINE CAPACITY PLANNING

ONG YUNG CHIEH

UNIVERSITI SAINS MALAYSIA

2014

Page 2: quantitative modelling of oee use with spreadsheet for machine

QUANTITATIVE MODELLING OF OEE

USE WITH SPREADSHEET FOR

MACHINE CAPACITY PLANNING

by

ONG YUNG CHIEH

Thesis submitted in fulfillment of the requirements

for the Degree of

Doctor of Philosophy

August 2014

Page 3: quantitative modelling of oee use with spreadsheet for machine

ii

ACKNOWLEDGEMENTS

I would like to express my sincere gratitude to my main supervisor Associate

Professor Dr. Shahrul Kamaruddin. Throughout the perplexing moments of Ph.D.

studies, he was always there dedicated much of his time to advise, discuss and

review this research work. His deep concern and invaluable guidance over the years

have been instrumental in making the timely completion of this thesis. Without him,

this thesis would have been impossible.

My utmost appreciations go to my parents, sisters and brother for their love,

unconditional support and encouragement that have help me accomplished so much.

To my wife and sons, I owe a great debt for their endurance, understanding, caring

and being with me throughout this research work, especially through the difficult

times.

Page 4: quantitative modelling of oee use with spreadsheet for machine

iii

TABLE OF CONTENTS

Acknowledgement ii

Table of Contents iii

List of Tables viii

List of Figures x

List of Abbreviations xii

Abstrak xvi

Abstract xviii

CHAPTER 1 - INTRODUCTION

1.0 Background 1

1.1 PPC Overview 2

1.2 Shop Floor Basic Behaviour 6

1.2.1 Product Mix Demand Fluctuate 7

1.2.2 Manufacturing Hour Reduction 7

1.2.3 Machine Idling 9

1.2.4 Machine Variation 10

1.2.5 Process Cycle Time 10

1.2.6 Product Throughput Rate 11

1.2.7 Yield Loss 11

1.3 Important Shop Floor Quantitative Metrics 12

1.3.1 Machine Capacity Metrics 13

1.3.2 Machine Performance Metrics 14

1.4 Problem Statement 15

Page 5: quantitative modelling of oee use with spreadsheet for machine

iv

1.5 Research Objectives 18

1.6 Scope of the Study 19

1.7 Outline of the Thesis 20

CHAPTER 2 - LITERATURE REVIEW

2.0 Overview 22

2.1 PPC System Development and Evolution 23

2.2 Capacity Planning for PPC Improvement 29

2.2.1 Long Term Capacity Planning 30

2.2.2 Medium Term Capacity Planning 31

2.2.3 Short Term Capacity Planning 32

2.3 TPM and OEE for PPC Improvement 34

2.4 Capacity Planning Approaches 39

2.4.1 Static Capacity Model 41

2.4.2 Simulation-Based 41

2.4.3 Queuing-Model-Based 42

2.4.4 Linear Programming Based 43

2.4.5 Non-Linear Integer Programming Based 44

2.4.6 Stochastic Method 45

2.4.7 Mixed Integer Programming 46

2.5 Application of OEE 51

2.5.1 Adopted / Improved OEE Methodology 53

2.6 Literature Findings and Implications 64

2.7 Summary 69

Page 6: quantitative modelling of oee use with spreadsheet for machine

v

CHAPTER 3 – RESEARCH METHODOLOGY

3.0 Overview 70

3.1 Identify and Categorize Model Parameters, Model Variables

and Decision Variables 70

3.2 The Model Development Framework 72

3.3 Summary 79

CHAPTER 4 - MODEL DEVELOPMENT

4.0 Overview 80

4.1 Identify and Categorize Model Parameters 81

4.2 Formulation of Machine Capacity Module 85

4.2.1 First Stage: Design Capacity (CD) 85

4.2.2 Second Stage: Safety Capacity (CS) 87

4.2.3 Third Stage: Effective Capacity (CE) 87

4.2.4 Lower-Limit Capacity (CLL) and Upper-Limit Capacity (CUL) 88

4.3 Formulation of Machine Performance Module 91

4.3.1 First Phase:- Loading Time (Tι), Availability Losses (A)

and Total Operating Time (Tο) 91

4.3.2 Second Stage:- Net Operating Time (Tη) 92

4.3.3 Third Phase:- Valuable Operating Time (Tυ) 94

4.3.4 Final Phase:- Machine Performance Metric 95

4.4 Model Translation 98

4.5 Summary 102

Page 7: quantitative modelling of oee use with spreadsheet for machine

vi

CHAPTER 5 – MODEL VERIFICATION AND VALIDATION

5.0 Overview 103

5.1 The Case Study Company 103

5.2 Process Flow 104

5.3 Model Implementation 106

5.4 Qualitative Verification 106

5.5 Quantitative Verification 107

5.5.1 Machine Capacity Computation 107

5.5.2 Machine Performance Model Verification 117

5.6 Model Validation 125

5.6.1 Assessing Machine Capacity and Machine Performance 126

5.6.2 Analysing Machine Performance Losses 133

5.6.3 Maximizing Machine Capacity and Machine Performance 139

5.6.4 Model Validation for Product Mix Demand:-

Scenario 1 145

5.6.5 Model Validation for Total Numbers of Machine Allocation:-

Scenario 2 153

5.7 Summary 157

CHAPTER 6 - MODEL DISCUSSION AND ANALSYSIS

6.0 Overview 158

6.1 Principles of Modeling 158

6.2 Provide Insights 160

6.3 Performance Prediction 161

6.4 Justification 162

6.5 Control 163

Page 8: quantitative modelling of oee use with spreadsheet for machine

vii

6.6 Decision 165

6.7 Summary 166

CHAPTER 7 - CONCLUSIONS

7.0 Overview 167

7.1 Concluding Principles 167

7.2 Future Research Work 171

REFERENCES 172

APPENDICES

LIST OF PUBLICATIONS

Page 9: quantitative modelling of oee use with spreadsheet for machine

viii

LIST OF TABLES

Page

Table 2.1 Capacity Planning Task and Methodology 39

Table 2.2 Capacity Planning Literature Review 49

Table 2.2 Capacity Planning Literature Review (Continues) 50

Table 2.3 OEE Based Literature Review 54

Table 2.3 OEE Based Literature Review (Continues) 55

Table 2.3 OEE Based Literature Review (Continues) 56

Table 5.1 Machine Throughput Rate Input Parameters and

Computation Results 108

Table 5.2 Tbf Allocation 109

Table 5.3 TNW Inputs and Downtime Computation for

Injection Moulding Machine 109

Table 5.4 TSC of Injection Moulding Machine 110

Table 5.5 Tbd of Injection Moulding Machine 111

Table 5.6 Tpm of Injection Moulding Machine 112

Table 5.7 Plant Wide Tfo from WW 40 to WW 50 112

Table 5.8 Tmhr for Injection Moulding Machine 113

Table 5.9 CD of Injection Moulding Machine 114

Table 5.10 CS of Injection Moulding Machine 115

Table 5.11 CE of Injection Moulding Machine 116

Table 5.12 CLL and CUL of Injection Moulding Machine 117

Table 5.13 Downtime Losses Computation Results 118

Table 5.14 Total Operating Time (Tο) Computation Results 118

Table 5.15 Availability Rate (A) Computation Results 119

Table 5.16 Idling / Minor Stoppage Computation Results 119

Page 10: quantitative modelling of oee use with spreadsheet for machine

ix

Table 5.17 Reduced Speed Computation Results 120

Table 5.18 Speed Losses Computation Results 120

Table 5.19 Net Operating Time (Tη) Computation Results 121

Table 5.20 Performance Efficiency (P) Computation Results 121

Table 5.21 Data Input for Rework Rate and Reject Rate 122

Table 5.22 Quality Losses Computation Results 122

Table 5.23 Valuable Operating Time (Tυ) Computation Results 122

Table 5.24 Quality Rate (Q) Computation Results 123

Table 5.25 OEE Metric (Machine Performance) Computation Results 124

Table 5.26 Weekly Product Demand Plan for HE-212 126

Table 5.27 Machine Capacity Computation Results 128

Table 5.28 Machine Performance Computation Results 129

Table 5.29 OEE Component Time Losses Detail Breakdown 137

Table 5.30 Maximized Machine Capacity Computation Results 141

Table 5.31 Maximized Machine Performance Computation Results 142

Table 5.32 Product Mix Demand Plan 146

Table 5.33 Machine Capacity Computation Results 147

Table 5.34 Machine Performance Computation Results 148

Table 5.35 Product Mix Demand vs Manufacturing Process Capacity 149

Table 5.36 Required Machine Allocation / Work Week

Computation Results 155

Page 11: quantitative modelling of oee use with spreadsheet for machine

x

LIST OF FIGURES

Page

Figure 1.1 Hierarchical PPC Framework 5

Figure 2.1 PPC Development and Evolution 24

Figure 2.2 OEE Framework 36

Figure 2.3 The OEE Formulation and the Six Losses 38

Figure 2.4 OEP & X-factor Combinations and What They Indicate 59

Figure 3.1 Machine Capacity Computation Framework 73

Figure 3.2 Machine Performance Computation Framework 74

Figure 3.3 Model Validation Cycle 78

Figure 4.1 Machine Capacity Computation Module Template 90

Figure 4.2 Machine Performance Computation Module Template 97

Figure 4.3 Model Translation for Machine Capacity Computation 100

Figure 4.4 Model Translation for Machine Performance Computation 101

Figure 5.1 Manufacturing Process Flow 104

Figure 5.2 Comparisons between Product Demand and Machine Effective

Capacity 130

Figure 5.3 Machine OEE Metrics for Different Processes 132

Figure 5.4 Injection Moulding OEE Time Metrics 134

Figure 5.5 Tufting OEE Time Metrics 134

Figure 5.6 Polishing OEE Time Metrics 135

Figure 5.7 HF Sealing OEE Time Metrics 135

Figure 5.8 Comparison of Effective Capacity 143

Figure 5.9 Machine Performance Metric 144

Figure 5.10 Comparisons between Product Mix Demand and

Machine Effective Capacity 150

Page 12: quantitative modelling of oee use with spreadsheet for machine

xi

Figure 5.11 Machine OEE Metrics for Product Mix Demand 151

Page 13: quantitative modelling of oee use with spreadsheet for machine

xii

LIST OF ABBREVIATIONS

A Availability

CAPS Capacity Optimisation Planning System

CC Clearing & Cleaning

CD Design Capacity

CE Effective Capacity

CLL Lower-Limit Capacity

CM Constraints Management

CRP Capacity Requirements Planning

CS Safety Capacity

CSU Consumables Item Setup

CUL Upper-Limit Capacity

DOE Design of Experiment

EOQ Economic Order Quantity

ERP Enterprise Resource Planning

FO Facilities Outages

JF Jig & Fixture Setup

JIT Just-In-Time

L Lot Size

LMS Lean Manufacturing System

LSS Lean Six Sigma

MPS Master Production Schedule

MRP II Manufacturing Resource Planning

MRP Material Requirements Planning

Page 14: quantitative modelling of oee use with spreadsheet for machine

xiii

MTBA Mean Time between Assist

MTBF Mean Time between Failures

MTTA Mean Time to Assist

MTTR Mean Time to Repair

NW Not Work Schedule

OEE Overall Equipment Effectiveness

P Performance Efficiency

PDT Planned Downtime

PES Process Engineering Setup

PM Preventive Maintenance

PPC Production Planning and Control

Q Quality Rate

QES Quality Engineering Setup

RDS R&D setup

Rt Machine Throughput rate

SA Specification Adjustment

SCAPS Stochastic Capacity Optimisation System

SCM Supply Chain Management

SEMI Semiconductor Equipment and Materials International

SPC Statistical Process Control

Ta Available Time

Tasu Short Stoppage Time to do Minor Adjustment on the Machine

Tbf Buffer Time

Tbd Time Loss Due to Machine Breakdown / Failure

Tcc Stoppage Time to Do Cleaning & Clearing

Page 15: quantitative modelling of oee use with spreadsheet for machine

xiv

Tco Changeover Time

Tcsu Time to Top up Consumable Items / Parts

Tdt Downtime Losses

Tjf Time to Do Jig & Fixture Setup

Tlsu Lot Setup Time

Tmax Maximum Number of Manufacturing Hour

Tmhr Manufacturing Hour Reduction

Tmtbf Average Time between Machines Failed

Tmttr Time to Repair Machine

TNW Time Loss Due to the System Not Worked

TOC Theory of Constraints

Tp Processing Time

TP Trial Run Process

Tpes Process Engineering Activities Time

TPM Total Productive Maintenance

TPS Toyota Production System

Tqes Quality Engineering Activities Time

Tql Quality Losses

TQM Total Quality Management

Trds R&D Setup Activities Time

Tsa Specification Adjustment Time

TSC Set up and Changeover Time

Tsl Speed Losses

Ttp Trial Run Time

Twt Time to Replace Wear & Tear of Items / Parts

Page 16: quantitative modelling of oee use with spreadsheet for machine

xv

Tη Net Operating Time

Tι Loading Time

Tο Total Operating Time

Tυ Valuable Operating Time

UPDT Unplanned Downtime

UPH Units per Hour

WIP Work-in Process

WW Work Week

Page 17: quantitative modelling of oee use with spreadsheet for machine

xvi

PERMODELAN KUANTITATIF OEE DENGAN MENGGUNAKAN

‘SPREADSHEET’ UNTUK PERANCANGAN KAPASITI MESIN

ABSTRAK

Mengurus kelakuan asas lantai pegeluaran seperti permintaan pelbagai produk yang

tidak tetap, pengurangan masa pengeluaran, mesin melahu, variasi mesin dan

kehilangan penghasilan adalah asas perancangan dan kawalan pengeluaran yang

berkesan. . Kajian-kajian lepas dalam mengurus kelakuan asas lantai pegeluaran

memberi tumpuan kepada pengukuran produktiviti, celusan pengeluaran dan

penggunaan tidak dapat mengenalpasti masalah-masalah secara keseluruhan. Maka,

adalah amat penting untuk membina suatu model yang boleh mengintegrasikan

kerawakan kelakuan asas lantai pegeluaran dengan komponen OEE. Ia boleh

digunakan untuk pengiraan bagi tujuan memastikan kapasiti mesin yang optimal dan

memberi justifikasi terhadap prestasi mesin. Oleh itu, kajian ini akan

membentangkan permodelan kuantitatif OEE dengan menggunakan „spreadsheet‟

untuk perancangan kapasiti mesin. Model yang dibangunkan ini terdiri daripada dua

bahagian, iaitu modul pengiraan kapasiti mesin dan modul pengiraan prestasi mesin.

Faktor-faktor penting yang mempengaruhi kelakuan asas lantai pegeluaran akan

dikenalpasti, dikasifikasi dan difomulasi ke dalam bentuk parameter model.

Pengubah model and pengubah keputusan model pula dibentuk secara berperingkat

berdasarkan kaedah matematik. Kesemua persamaan matematik yang telah dibentuk

akan diterjemahkan ke dalam „spreadsheet‟ bagi tujuan kemasukan data dan

pengiraan hasil. Seksyen verifikasi model memastikan integrasi dinamik yang tepat

dan tanpa ralat antara persamaan-persamaan matematik dalam model itu. Manakala

Page 18: quantitative modelling of oee use with spreadsheet for machine

xvii

seksyen validasi model pula menunjukkan kemantapan model dalam mengesahkan

kes kajian industri. Model ini digunakan dalam (i) menilai kapasiti mesin dan

prestasi mesin bagi tiga jenis permintaan produk yang tercampur dan (ii) untuk

mengira jumlah mesin yang diperlukan bagi memperuntukkan kekangan proses

pembuatan. Keputusan kajian menunjukkan suatu kaedah bagi merancang

peruntukkan jumlah mesin dan bilangan minggu kerja pengeluaran yang diperlukan

untuk menghasilkan pelbagai permintaan campuran produk. Kekuatan model ini

ialah sebarang perubahan boleh dibuat untuk mensimulasi pelbagai scenario

pengeluaran tanpa risiko kos gangguan terhadap sistem pengeluaran yang sebenar.

Page 19: quantitative modelling of oee use with spreadsheet for machine

xviii

QUANTITATIVE MODELLING OF OEE USE WITH SPREADSHEET FOR

MACHINE CAPACITY PLANNING

ABSTRACT

Managing shop floor basic behaviours such as product mix demand fluctuate,

manufacturing hour reduction, machine idling, machine variation, and yield loss are

fundamental for the effective production planning and control. Previous works in

managing shop floor behaviours focused on measuring productivity, throughput, and

utilization are insufficient for identifying the problem. Therefore, the concerns are to

develop model that can integrate stochastic characters of shop floor basic behaviours

with OEE components. It is used for calculation to ensure an optimal machine

capacity and machine performance justification. Therefore, this research will present

quantitative modelling of OEE use with spreadsheet for machine capacity planning.

The developed model consists of machine capacity computation module and

machine performance computation module. All influencing factors of shop floor

basic behaviour are being identified, categorized and formulated into model

parameters. Model variables and decision variables are built in incremental steps

based on the mathematical approaches. All mathematical equations derived are then

translated and resided into a common computation spreadsheet for data input and

output computation. Model verification section ensures dynamic integration between

numerous mathematical equations in the model is error free and accurate. Model

validation section demonstrates the robustness of the model in validating industrial

case study. The model is employed in (i) assessing machine capacity and machine

performance under three different types of product mix demand and (ii) to compute

Page 20: quantitative modelling of oee use with spreadsheet for machine

xix

total numbers units of machine needed to allocate to the constraint manufacturing

process. The study demonstrated a methodology to allocate or plan total number of

machine and number of work week needed in completing various product mix

demands. The strength of the model is that any changes made to simulate various

manufacturing scenarios are possible without the risk of costly disruptions to the real

manufacturing system.

Page 21: quantitative modelling of oee use with spreadsheet for machine

1

CHAPTER 1

INTRODUCTION

1.0 Background

Production system is fundamentally concern with managing production

resources to meet customer‟s demand. Gershwin (1994) described that a

production system consists of machines, people, computers, transportation

elements, storage buffers and other items that are used together for

manufacturing. Cells, work centers or work stations can be used

interchangeably and are subsets of production systems. Production system

involves the basic task of managing the processes which transform a set of

inputs (raw material, labour, energy, technology, capital and information) to

outputs (functionally desirable, reliable and quality products). Companies

must plan and control their production in such a way that the disruptions in

performance of their production systems are minimised in order to remain

competitive and able to adapt to today‟s fast changing business environment.

Slack et al. (2004) defined planning as formalisation of what is intended to

happen in the future. Rather it is a statement of intention. However, the

stochastic nature of the manufacturing environment does not guarantee that the

plan always followed as expected. It is frequently evidenced by supplier‟s late

delivery, price fluctuation of raw material, defective parts, machine

breakdown, workers absence and / or uncertainty in customer demand.

Page 22: quantitative modelling of oee use with spreadsheet for machine

2

Control is the process of coping with changes and makes the adjustment to

reset the plan and bring the operations back to its original objectives. The

examples are: sourcing for alternative supplier, repairing the machine,

swapping workers to cover absentees and etc.

Production Planning & Control (PPC) is concerned with planning and

controlling all aspects of manufacturing, including demand management,

detailed material planning, capacity planning, quality control, scheduling

machines and people, maintenance management, coordinating suppliers and

respond to key customers requirements. Many important decisions in

manufacturing organisations are made in regards of these activities. The

purpose of planning and control is to ensure all activities are well organized

and well integrated for highly effective and efficient production system.

1.1 PPC Overview

PPC change over time and differ greatly with regard to the length of time. In

managing the system, various decisions have to be made continuously, from a

simple choice, which job to be processed next on a certain machine, to the

serious consideration, whether to build a new factory or to shut down an

existing one. It is therefore essential to categorize the decision making process

into system-wide planning horizon. Different planning horizons will imply

different PPC scope, with plans becoming more specific and detailed as the

planning horizon becomes shorter. Virtually, every manufacturing

Page 23: quantitative modelling of oee use with spreadsheet for machine

3

organization in the world divided it into long term, medium term and short

term horizons.

In the long term, company establishes the overall company direction

concerning business activities that place demands on the manufacturing

capacity. Planning horizon can range from 2 to 5 years, with normal emphasis

in product options and volumes to produce in the future and in determining the

manufacturing capacity, human resource capabilities technology, and

geographical locations to meet the firm‟s future needs. Nahmias (2004)

predicted patterns of demand, costs of constructing and operating new

facilities, new technologies and competitors‟ strategies as an important

capacity strategy in this planning horizon. Financial targets and budgets will

be set to identify the costs and revenue targets which are intended to achieve.

The medium term encompasses activities focus on providing the exact

material and production capacity needed to meet customer needs. This means

detailed material planning for the right quantities of raw material, part and

components to arrive at the right time and place to support product production.

The manufacturing capacity requirement for typically a month to 1 year

planning horizon needs to be checked against the production plan in order to

ensure an achievable plan. Stephen et al. (2007) pointed on type of products,

quantity, delivery date and location preference are among basic information

that needs to be match with manufacturing capacity, workforce level,

inventory level, quota availability and other factors in order to fulfill the

demand within a specific time frame. Contingencies production plan will have

Page 24: quantitative modelling of oee use with spreadsheet for machine

4

been put in place to allow for slight deviations when it is not followed as

intended.

Short term activities as described by Vollman et al. (2005) mainly on

assessing demand in totally disaggregate basis. This involves detailed

scheduling of material, machine, labour and delivery lead time to meet

customer requirements. The shop floor system will properly schedule

customer orders into daily or weekly production plan. All important

manufacturing performance such as material consumption, labour utilisation,

machine utilisation, on time delivery and etc are systematically tracked,

measured and reported for day to day activities monitoring.

Thus, Hopp et al. (2008) mentioned the logical function of PPC consists of

strategy (long term), tactics (medium term) and control (short term) which

forms a hierarchical framework. Each planning horizon represents different

production function activities and decision problems in separate planning and

control module. Followed Vollman et al. (2005), Figure 1.0 relates the vertical

integration of these PPC modules in the production system.

Page 25: quantitative modelling of oee use with spreadsheet for machine

5

RESOURCE

PLANNING

AGGREGATE

PLANNING

DEMAND

MANAGEMENT

MARKETING

PLANNING

DETAILED

MATERIAL

PLANNING

MATERIAL & CAPACITY

PLANS

CAPACITY

REQUIREMENTS

PLANNING

SUPPLIER/VENDOR

SYSTEMS

SHOP FLOOR

CONTROL (SFC)

STRATEGY

(LONG TERM)

2 ~ 5 YEARS

TACTICS

(MEDIUM TERM)

1 MONTH ~ 1 YEARS

CONTROL

(SHORT TERM)

DAILY ~ WEEKLY

FINITE

LOADING

CAPACITY

SIMULATION

INPUT / OUTPUT

ANALYSIS

Figure 1.1 Hierarchical PPC Framework (Vollman et al., 2005)

As depicts in hierarchical PPC system, the output from each planning module

in long term and medium term are considered in short term control module.

Over the past decades, many principles and methods of planning and control

(e.g. MRP, MRP II, ERP, SCM and etc) and also wide range of PPC

improvement methodologies such as TQM, JIT or range of lean manufacturing

tools had been proposed, developed, evolved and widely implemented in

various industries. These developed principles and methods of planning and

control are presented in Section 2.2 of Chapter 2.

However, most of these approaches which is commonly supported by software

packages do not necessary worked all right in all manufacturing company.

Page 26: quantitative modelling of oee use with spreadsheet for machine

6

According to Hopp et al. (2008) a survey by the Standish Group in 1995,

showed that over 31 percent of all IT projects are cancelled before they get

completed and that almost 53 percent of the projects would cost 189 percent of

their original estimates. Moreover, only 16 percent of the software projects

were completed on time and on budget.

The following sections will describe inherent complexity of the shop floor

basic behaviour and discussed on the needs for quantitative metrics in PPC.

1.2 Shop Floor Basic Behaviour

The nature of shop floor activities is concerned with ensuring high-level

planning module in the long term and medium term that is consistent with

low-level control module in the short term PPC hierarchy. Shop floor is the

workplace consisting of the part of a factory housing the materials, machines

and man power directly involved in the productive work to produce parts or

final products. The essential task of the shop floor system is to manage and to

control the flow of material, the capacity of the machine and people, and to

respond to a given production plan over a planning horizon to meet customer‟s

demand.

The specific requirements to accomplish these tasks must take into account

inherent complexity of shop floor basic behaviour such as product mix

demand fluctuate, manufacturing hour reduction, machine idling, machine

variation, and yield loss that are fundamental for the effective PPC.

Page 27: quantitative modelling of oee use with spreadsheet for machine

7

1.2.1 Product Mix Demand Fluctuate

Based on actual shop floor requirements, there exist several different products

(or termed as product mix) using the same or similar machine. Given that the

demands vary not only over time but also by the product type, shop floor

loading plan has to periodically revise and subject to changes. Customers will

feedback a certain product mix ratio, e.g., the product mix ratio for three types

of products may be (A : B : C) = (1 : 2 : 3) and later revised to (A : B : C) = (3

: 1 : 2). It is obvious that demands are lumpy and time varying. Due to the

fluctuation of' product mix demand pattern, machine in shop floor are faced

with irregular utilization fluctuation between over and under-loading. Shop

floor‟s ability to response to the dynamic demand and product mix changes

has become a key competitive advantage in PPC.

1.2.2 Manufacturing Hour Reduction

The shop floor activities have an explicit reference of time. Manufacturing

hour of a production system is the total time allocated for manufacturing

activities on a daily, weekly or monthly basis. In a typical 7-day period, the

planning department programmed shop floor operated on 24-hour day basis as

weekly maximum manufacturing hours (Tmax).

Most shop floor operates on shift basis. In practice, there are some periods the

shop floor can not operate continuously at all time. Public holidays, un-

Page 28: quantitative modelling of oee use with spreadsheet for machine

8

worked shift, shutdown of any reasons such as weekend, plant maintenance,

stock take and etc. are all so called as Not Worked Time Loss (Tnw).

Downtime is unpredictable and can not be ignored in PPC. Time losses take

place when the production is interrupted by a temporarily malfunction. For

instance, short idle periods or minor stoppages between consecutive machines

runs, malfunctioning of conveyors, blockages of raw material in the nozzle, air

pressure adjustment, major machine breakdown or aborts and so on. Based on

a machine‟s history of interrupted breaks down, unplanned stoppage and

failure, they are considered as unscheduled downtime (Tusdt).

Another downtime related to machine is scheduled preventive maintenance,

e.g. routine inspections, servicing, maintenance or calibration on the machine

and keeping facilities in good repair to prevent failure. It is a weekly, bi-

weekly, monthly, quarterly, semi annually, yearly and bi-annually plan that

scheduled by maintenance department. As this time loss is planned and

scheduled; it is termed as scheduled downtime (Tsdt).

Machine generally can perform same process function for different product.

Changing from running one product to another in any machine involved

product changeover time loss, waiting for raw material or specification

changeover time loss, that can be sum up to denote by (Tco).

Setup time losses is normally followed after changeover to perform jig/fixture

setup, cleaning & clearing job, specification adjustment, trial processing or

Page 29: quantitative modelling of oee use with spreadsheet for machine

9

consumables item setup. These setup time losses (Tsu) may also occur during

changing shift.

Quality failure investigation by quality engineering department, new product

qualification by process engineering, R&D test and other various

manufacturing and engineering time losses are categorised under engineering

time loss (Tel).

Therefore, the time available for productive working can be significant below

the maximum time available even in a well managed operation. The actual

machine operating time remains, after such time losses are accounted for, is

the most important aspects in optimizing PPC.

1.2.3 Machine Idling

Machine may idle due to its machine operator break‟s time (meal break or tea

break), shift briefing, meeting or simply absenteeism. Machine also frequently

interrupted by small outages to do some minor adjustment or assist. A

production line with poor line balancing may also cause machine idle waiting

for WIP from previous process or workstation. All these are machine idling

time losses (Tid).

Page 30: quantitative modelling of oee use with spreadsheet for machine

10

1.2.4 Machine Variation

Each station may consist of several machines or equipment that either similar

or different by manufacturer‟s brand, version or model. However, they

perform essentially identical function. Each machine has different

manufacturing characteristics; machine speed may vary in different instances

of the same processing operation, perhaps because of differences in operator

handling and system constants (for example, machine setting parameters) that

need to be checked periodically for consistency. These kinds of variations may

result in speed losses (Tsl).

1.2.5 Process Cycle Time

In shop floor, there is no standard route that all products undertake the

different workstation. Each product can have its own routing through a unique

sequence of workstations or processes. Cycle time in individual workstation is

made up of move time (time for parts being moved from previous station),

queue time (time for parts spend waiting for processing at the station), setup

time (time for parts waiting for setup the station) and process time (time for

parts actually being process at the station). For batch processes, to be more

detailed, the cycle time components should include wait-to-batch time (parts

waiting to form a batch), wait-in-batch time (average time for parts spends in a

batch waiting its turn to be processed) and wait-to-match time (occur at

assembly station where parts are waiting for other components to be

Page 31: quantitative modelling of oee use with spreadsheet for machine

11

assembled). Process time and all other cycle time components for the

manufacture of products are unique and specific to each product type.

1.2.6 Product Throughput Rate

A production line is one in which each workstation can pass work in process

(WIP) on when its processing is complete. The WIP includes the items at first

process through last process including the one item being processed or held at

each process. However, it does not include any raw material held in front of

first process as materials are assumed to be always available at any time. A

process flow analysis can be used for seeing the sequence of process steps

from inputs to outputs in between each workstation. Throughput time is the

actual elapsed time for the parts to go through the start and end points of the

process routing. The average output (number of units products processed or

number of lot processed) of a production process over the throughput time is

called throughput rate. Since many different products are produced and each

with different processes routing, throughput time and throughput rate for

different products is product specific.

1.2.7 Yield Loss

Yield loss is another shop floor basic behaviour that further complicates the

PPC problem. It is used to indicate the proportion of defective production

output to the total production output. WIP or products are rejected or scrapped

at various workstations along product‟s specific process routing. Different

Page 32: quantitative modelling of oee use with spreadsheet for machine

12

process yield loss for different types of products will definitely affect the

output quantities of production line and inevitable trouble the production

planners and practitioners. Thus, to achieve the desired output, a production

system must release extra loading into the production line to compensate for

yield loss.

The above shop floor basic behaviour may give the impression that PPC is

closely associated to variability and randomness that exists in all production

system and can have enormous impact on its performance. Therefore, a set of

quantitative metrics that can assess, measure and report on how good or bad

the production system, is fundamental for performance measures.

1.3 Important Shop Floor Quantitative Metrics

According to Melnyk and Christensen (2000) quantitative metric is defined as

verifiable measures that should be consistent and stated in meaningful terms.

Anyone should be able to calculate the measures and get the same results if

they are given the same information with similar calculating procedure.

To capture and measure on the variability and randomness of the shop floor

basic behavior. The quantitative metric can generally divided into two basic

categories as follow:

i. Machine capacity

ii. Machine performance

Page 33: quantitative modelling of oee use with spreadsheet for machine

13

1.3.1 Machine Capacity Metrics

The primary goal of the machine capacity metrics is to minimize the

discrepancy by matching the shop floor machine capacity to the demand for its

products over time. Generally, management is dependent upon the

manufacturing organization to faithfully report all time losses in order to

correctly determine machine capacity. The machine capacity metrics is the

most important aspects in PPC.

Machine capacity which its technical designer had in mind without

considering a variety of time restriction that can limit its operation is the

machine design capacity (CD). It gives maximum theoretical output of a

machine that has been assigned for a process within weekly maximum

manufacturing hours (Tmax).

In actual, many organizations would not operate their machines at the shop

floor continuously all the time. There are many factors as mentioned earlier to

explain such unavoidable manufacturing time loss. Therefore, machines are

normally run at a rate less than maximum capacity. The actual capacity which

remains after such losses are accounted for is called Effective Capacity (CE).

Fluctuations in equipment availability, operator availability, WIP availability

and/or unplanned situations (power failure, water supply cut off, fire and even

included any other natural disaster that may occur) must be taken into

consideration as it will play a significant effect in causing manufacturing hour

Page 34: quantitative modelling of oee use with spreadsheet for machine

14

loss, which in turn contributes to down time. Safety Capacity (Cs) express in a

form of percentage (%), set aside total units of products produced per single

unit machine that can accommodate protection against interruption to the

normal operation of the shop floor.

1.3.2 Machine Performance Metrics

Every machine in the shop floor deal with various downtime, operational

losses, performance loss and quality problems, which unable it to reach the

maximum theoretical design performance. Based on Overall Equipment

Effectiveness (OEE) proposed by Nakajima (1988), machine performance

relative to its maximum capability can be measured through Aeff, Peff and Qeff

as explained below:

where,

i. Aeff is the availability efficiency that captures:

Planned downtime includes days of work off, state holidays, time for

overhaul, time for cleaning the workplace, but even development and

testing, in some cases, can be considered as a loss;

Operational loss includes time for setting up machines, time for

changes in production, waiting time for material delivery, and time

wasted with bottlenecks or by operator's mistakes, as well as

breakdowns;

Page 35: quantitative modelling of oee use with spreadsheet for machine

15

ii. Peff is the performance efficiency that captures productivity loss due to

wrong machine settings, slowing down the production cycle or causing

failures, reduced speed, idling and minor stoppages.

iii. Qeff is the quality efficiency that captures loss due to material defects

and product rejects, production imperfections, reworks, and repairs

decrease efficiency and production effectiveness.

Shop floor basic behaviour and quantitative metrics problems are now the

focus of this PPC research. The following problem statement is presented as

the underlying of the model development study.

1.4 Problem Statement

Global competitive conditions, new technology development, higher customer

expectations, increasing supplier capabilities and so on push for continuing

improvement of the PPC system. Shop floor system implemented must be able

to react quickly and have the flexibility to adapt to the variability and

randomness events encountered.

Depending on the size of the companies, shop floor may have only a few units

of machine or hundred units of machine that performed different functions

according to the routing of its unit processes. Most machines are running

twenty-four hours to supply enough products for the global market demands.

Poor computation yielded over capacity commitment which results in failures

Page 36: quantitative modelling of oee use with spreadsheet for machine

16

to keep promised delivery dates, or that is under capacity and result in

excessive lead times. For small companies involving only small number units

of machines, machine capacity planning is not a complicated task. Therefore,

it was not considered in this research.

Many organizations unknowingly invest in more capital to compensate for

poor performance machine. Some invest money to supplement capacity that

already have but do not exploit. For example, invest in a new machine to

increase the capacity while the existing is operating at only 30% of its

potential.

In practice, machine capacity and machine performance are not constant over

time and greatly related to variability and randomness of shop floor basic

behaviour that could change at shift level, daily level or work week level.

Together with the high-continuity requirements of its production line, both

have become an important PPC issue. Traditional metrics for measuring

productivity, throughput, and utilization are insufficient for identifying the

problems and underlying improvements for PPC. As such, production system

should have a well defined quantitative metric to use as standardized measure

for computing machine capacity and judging on the machine performances.

PPC depends on basic rules and principles. From modelling view point, some

commercial software are just too simple or too idealistic and do not include in

realistic variability and randomness faced in the shop floor. There has not been

much effort in deriving widely accepted rules for machine capacity

Page 37: quantitative modelling of oee use with spreadsheet for machine

17

computation and machine performance measurement in shop floor design and

control. This research reduces the complexity of shop floor in a production

system to a manageable level by restricting the attention to modelling shop

floor basic behaviour and quantitative metrics for PPC using a spreadsheet.

The ideal model construction enables input recording of different shop floor

behaviors, which can occur within areas of a shop floor. The effective model

would have quantitative metrics based on mathematical approach and resides

in a spreadsheet for data input and output computation. A significant criterion

of the model is that, it can also provide what-if scenarios to help users to

generate solution for any practical case study scenarios and requirements. It

compares the actual input and output to the planned input and output that

routes through production system. The model helps to find hidden production

capacity for even better utilization of production machine through machine

capacity computation and monitoring. It also provides reason for investments

into new machines if machine performance is justified to be cannot further

improve.

Making changes to the models of the shop floor system instead of the actual

system allows fast acquisition of the knowledge and avoids the risk of costly

disruptions to the real system. It builds a description to understand the

important factors in the real system and finds a good solution to the problem.

Page 38: quantitative modelling of oee use with spreadsheet for machine

18

1.5 Research Objectives

This research has several objectives, includes:

1 To provide insights - better understanding of the shop floor behavior and

quantitative metrics associated with it.

2 To allow performance prediction - examining machine capacity and

machine performance to meet product mix demand over a planning

horizon.

3 To perform justification - as diagnostic tools to find underlying cause of

the PPC problems exist in the production system based on quantitative

metric, the real causes can be identified then.

4 To allow control - aiding the selection of the control policies for the shop

floor system.

5 To make decision - finding the best machine capacity and machine

performance.

Page 39: quantitative modelling of oee use with spreadsheet for machine

19

1.6 Scope of the Study

In this research, machine capacity and machine performance problem for PPC

will be addressed. The scope is across medium term (tactics) and short term

(control) machine capacity and machine performance decisions in PPC

horizon.

The research will present a shop floor basic behaviour and quantitative metric

model for manufacturing industry, particularly a high mixed low volume

production system which can provide a high degree of product flexibility.

Machines that perform the same function are classified into many workstations

in process oriented layout to satisfy different processing requirements.

In most operation of this kind, volumes of products produced are directly

dependent on the customer demand. It is assumed that the demand is given or

is based on deterministic demand forecast. Batch processes are used to

produce products based on customer order and specifications. Each batch

produces a fixed amount of product and consumes a fixed amount of the

limited resources as explained by Graves (1999).

This research presents the development of a process-oriented layouts machine

capacity computation and machine performance measurement model using

spreadsheet modeling technique. The model can assist in address a wide range

PPC issues and specific decision problems.

Page 40: quantitative modelling of oee use with spreadsheet for machine

20

1.7 Outline of the Thesis

The thesis is divided into seven chapters. They are organized as below:

Chapter 1 introduces the general scope of production planning & control

(PPC), specific problem of interest and importance to the research community,

and addresses the problem statement and associated research objectives.

Chapter 2 presents the literature reviews on previous research work of PPC

and quantitative metric measurement in general. It discusses the different

perspectives to fill the existing gap between theory and practice related to

machine capacity and machine performance for PPC.

Chapter 3 presents the methodology for quantitative modeling OEE using

spreadsheet for machine capacity planning. It entails identify and categorize

shop floor basic behavior, model development framework, verification and

validation approach for the model developed.

Chapter 4 presents the model development of quantitative metrics based on

shop floor basic behaviour. The formulation of a set of mathematical equations

used for development of the spreadsheet model will be derived.

Chapter 5 provides verification and validation of the PPC model developed.

The detail results are discussed to demonstrate the flexibility for execution and

proliferation in a wide range of applications through practical case study.

Page 41: quantitative modelling of oee use with spreadsheet for machine

21

Chapter 6 discusses and compares the results in relation to objectives of the

research. It highlights the evidence obtained from the verification and

validation findings and outlined extended knowledge of the research area in

comparison to what is already known.

Chapter 7 presents a summary and conclusions drawn from this research work

in terms of moving towards a disciplinary approach to PPC. This chapter ends

with the future research work recommendation.

Page 42: quantitative modelling of oee use with spreadsheet for machine

22

CHAPTER 2

LITERATURE REVIEW

2.0 Overview

This chapter reviews the previous and current literature studies related to the

PPC system, specifically capacity planning and overall equipment

effectiveness (OEE). It begins with discussion on PPC in general to provide a

broad review of some existing research on ways to managed uncertainty in

production system. It is intended to classify the literatures based on the trend

and development.

Literature related to challenges and issues in capacity planning are discussed

and model approaches are reviewed. The basic OEE theory is reviewed and

various OEE based research work implemented in the manufacturing industry

are presented to gain an understanding of the current state of the researches.

Implications of the review will be addressed to identify areas of machine

capacity planning and overall equipment effectiveness (OEE) that have not

been fully addressed. Summary is made to justify on the background of this

research.

Page 43: quantitative modelling of oee use with spreadsheet for machine

23

2.1 PPC System Development and Evolution

In a broad sense, production planning and control (PPC) is concerned with

ensuring operation processes run effectively and efficiently to satisfy customer

demand. Complexity of the production system, a varying set of customer‟s

requirements and operation resources require managing the ongoing planning

and control activities such as scheduling, coordination and organization.

In this era of company globalization, manufacturing business is facing

immense market requirements that change over time. Therefore, it is critical

for manufacturing management to make decision with future plan in mind.

One very best way is to consistently review the literature of PPC development

and evolution to understand the trend of formality and detail.

PPC development and evolution since the beginning of the 1930‟s to date has

been summarized in Figure 2.1 as follow:

Page 44: quantitative modelling of oee use with spreadsheet for machine

24

1930's 1970's 1980's

1950's 1990's

1951

1980's

1956

1960's

1961 Sampling

Ishikawa's Quality

Circles

Material

Requirements

Planning (MRP)

Juran's Handbook

of Quality Control

Total Quality Control

Manufacturing

Resources Planning

(MRP II)

Enterprise Resource

Planning (ERP)

Y2K Bug

Disaster

ERP software

transformed into

Supply Chain

Management

(SCM)

Pre

sent (d

evel

opm

ent an

d e

volu

tion

continues

.....)

Lean Six Sigma

(LSS)

Theory of

Constraints (TOC)

Constraints

Management (CM)

Deming Award

Japan Total Productive

Maintenance (TPM)

Japanese

(Shewhart's Book

on SPC)

Statistical Concept

Lean Manufacturing

System (LMS)

Just-in-time (JIT)

Total Quality

Management

(TQM)

Qual

ity R

evolu

tion

Statistical Process

Control (SPC)

Design of

Experiment (DOE)

Human Factors and

Material Flow

Control

Six Sigma (6σ)

Methodology

Figure 2.1 PPC Development and Evolution

PPC has been heavily concerned by manufacturers; according to Gilbert et al.

(1983) some of the common techniques used were the two-bin system,

economic order quantity (EOQ), and reorder point.

Back to 1930s, Shewhart (1931) introduced the concept of statistical methods

into quality control. Feigenbaum (1956) published the term total quality

control for good quality management. The quality trend of PPC movement

widely accepted from 1950s to 1980s under the influence of Deming (1960)

and Juran (1964). External quality concerned to customer satisfaction; and

internal quality of output from each unit process have both received focus and

attention to improve the production system.