21
Demlakian Strata & Remedial Pty Limited T/A Demlakian Consulting Engineers ABN 42 651 771 142 Level 2, 5 Ridge Street North Sydney 2060 P.O. Box 6553 North Sydney 2059 E-mail: [email protected] www.demlakian.com.au Telephone: (02) 9955 4485 Facsimile: (02) 9955 6122 30 May 2018 REF: 213025rpt20180530_DW_Water Management Report Australian Christian College C/- Lippmann Partnership Pty Ltd 570 Crown Street SURRY HILLS NSW 2010 RE: WATER MANAGEMENT REPORT FOR PROPOSED EXPANSION AUSTRALIAN CHRISTIAN COLLEGE – LOT 90 DP1224210 FARM ROAD RIVERSTONE 1.0 Introduction Demlakian Consulting Engineers have been commissioned to prepare stormwater and water management concept plans for the proposed development at the above site. These plans and this report have been formulated to address the requirements of Blacktown City Council Development Control Plans, in particular Part J, Water Sensitive Urban Design and Integrated Water Cycle Management (2015). This report should be read in conjunction with Demlakian Consulting Engineers Drawings 213025/ SW00 to SW011 (Revision N) which outlines the proposed storm water management system. Reference should also be made to the Architectural Drawings prepared by Lippmann Partnership, on which basis this report has been prepared. The Australian Christian College is currently located at Farm Road Riverstone (Lot 90 in DP1224210), and consist of a number of school buildings and demountables. A previous Development Application was submitted and approved for the construction of an additional school building on this property. (Determination No: 13-634 dated 27 th June 2013). Subsequently the school has purchased the above site, and this current submission is to locate a building similar to the above approval on the more recently purchased site. This site currently contains a domestic dwelling and several outbuildings. In addressing the water and storm water management issues, a similar approach has been taken to the previously approval, and similar design parameters have been adopted to those previously discussed and agreed with Council. 2.0 Proposed Development The works involve demolition of the existing site structures, filling of some existing farm dams, construction of a new three storey building with associated ground level pavements and

RE: WATER MANAGEMENT REPORT FOR PROPOSED EXPANSION

  • Upload
    others

  • View
    8

  • Download
    0

Embed Size (px)

Citation preview

Page 1: RE: WATER MANAGEMENT REPORT FOR PROPOSED EXPANSION

Demlakian Strata & Remedial Pty Limited

T/A Demlakian Consulting Engineers

ABN 42 651 771 142

Level 2, 5 Ridge Street

North Sydney 2060

P.O. Box 6553 North Sydney 2059

E-mail: [email protected]

www.demlakian.com.au

Telephone: (02) 9955 4485

Facsimile: (02) 9955 6122

30 May 2018 REF: 213025rpt20180530_DW_Water Management Report

Australian Christian College C/- Lippmann Partnership Pty Ltd 570 Crown Street SURRY HILLS NSW 2010

RE: WATER MANAGEMENT REPORT FOR PROPOSED EXPANSION AUSTRALIAN CHRISTIAN COLLEGE – LOT 90 DP1224210 FARM ROAD

RIVERSTONE

1.0 Introduction Demlakian Consulting Engineers have been commissioned to prepare stormwater and water management concept plans for the proposed development at the above site. These plans and this report have been formulated to address the requirements of Blacktown City Council Development Control Plans, in particular Part J, Water Sensitive Urban Design and Integrated Water Cycle Management (2015).

This report should be read in conjunction with Demlakian Consulting Engineers Drawings 213025/ SW00 to SW011 (Revision N) which outlines the proposed storm water management system. Reference should also be made to the Architectural Drawings prepared by Lippmann Partnership, on which basis this report has been prepared.

The Australian Christian College is currently located at Farm Road Riverstone (Lot 90 in DP1224210), and consist of a number of school buildings and demountables. A previous Development Application was submitted and approved for the construction of an additional school building on this property. (Determination No: 13-634 dated 27th June 2013). Subsequently the school has purchased the above site, and this current submission is to locate a building similar to the above approval on the more recently purchased site. This site currently contains a domestic dwelling and several outbuildings. In addressing the water and storm water management issues, a similar approach has been taken to the previously approval, and similar design parameters have been adopted to those previously discussed and agreed with Council.

2.0 Proposed Development The works involve demolition of the existing site structures, filling of some existing farm dams, construction of a new three storey building with associated ground level pavements and

Page 2: RE: WATER MANAGEMENT REPORT FOR PROPOSED EXPANSION

car parking. The works include the construction of link roadways, storm water drainage and other infrastructure. The proposed development will only affect the North portion of the Lot, as indicated in Figure 1. The affected part of the site has an area of 0.947 hectares (“Design Area”). Since the remainder of the site essentially remains in its existing state it has not been considered as part of the Design Area. The design area of the site generally consists of vegetation, with some small buildings and a dam. The development proposes the construction of a new three storey building, a carpark and a bus turning bay, as shown in the Drawings. All runoff from landscaped and paved areas will be directed through a series of pits containing enviropods to an onsite detention (OSD) tank located beneath the new roadway and through a proprietary water quality treatment device within the onsite detention tank. The new driveway/bus bay area proposed on the pre-existing school site was approved as part of the previous DA and as per previous conditions, runoff from this area will only be treated by an existing gross pollutant trap at the downstream property boundary. The roof area of the new building will drain to rainwater tanks and serve as reuse water. Overflow from the rainwater tanks will also be directed to the OSD tank. The site is also impacted by an upstream catchment located to the east. Since the proposed location of the new building impacts the current overland flow through the property, this flow will be intercepted and bypassed through the site in a piped drainage system. Approximately 60% of the design area is proposed to be impervious surfaces, such as roofs and pavements, with the remainder to remain as lawns and landscaping.

REF: 213025rpt20180723_DW_Water Management Report DEMLAKIAN CONSULTING ENGINEERS 30 May 2018 2 ©Copyright

Page 3: RE: WATER MANAGEMENT REPORT FOR PROPOSED EXPANSION

Figure 1: Site Map

REF: 213025rpt20180723_DW_Water Management Report DEMLAKIAN CONSULTING ENGINEERS 30 May 2018 3 ©Copyright

Page 4: RE: WATER MANAGEMENT REPORT FOR PROPOSED EXPANSION

Figure 2 – Upstream Catchment

3.0 Storm Water Management Strategy

The site is currently accessed from Farm Road and is surrounded by rural residential properties to the east and south and the existing school to the west. The site is relatively flat in nature with a minor slope running from East to West. Key issues for the site relate to water conservation, control of storm water flows and flooding impacts on adjoining properties, and water quality control. The site parameters and the proposed site layout lend themselves to an efficient control of the above factors. The attached storm water management drawings indicate the manner in which these objectives are achieved. A summary of key factors is outlined in the following sections of this report.

The following strategy has been adopted to manage the impacts from storm water. Upstream Overland Flow As noted above the site is impacted by an upstream catchment located to the east of Lot 8. Since the proposed location of the new building impacts the current overland flow through Lot 8, this flow will be intercepted and bypassed through the site in a piped drainage system. To ensure flows to not pond on the property to the east of the site the proposed driveway aisle and car parking will be constructed at a level at or below the existing boundary level. Flow will be allowed to enter the site at the existing low point and will be collected in a large grated entry pit. From this point the overland flow will be bypassed through the site to the existing 300x900 box culvert located at the front of the school property and thence to the existing headwall located in the north-western corner and discharging to the west of the current school site.

REF: 213025rpt20180723_DW_Water Management Report DEMLAKIAN CONSULTING ENGINEERS 30 May 2018 4 ©Copyright

Page 5: RE: WATER MANAGEMENT REPORT FOR PROPOSED EXPANSION

The proposed bypass pipeline will consist of twin 900 mm diameter pipes. Twin pipes have been adopted to allow for redundancy in the case of partial blockage. The large entry pit has been adopted to minimise the impact of partial blockage of the pit grating. The twin pipes will be provided under the driveway to a point in front of the existing school. At this location a surcharge pit will be provided with a connection to the existing 300 x 900 box culvert. In the event of full blockage of the 300x900 box culvert the flows in the system will have a downstream control of RL19.050 at which location the twin pipe system will surcharge and flow overland across the existing overland flow channel formed in the entry driveway to the existing school. This is in accordance with the design parameters approved by Council at the time of construction of the school based on a design provided by Healy Castle and Associates and approved by Council. The performance requirements of this system are as follows:

• As previously agreed with Council Engineers at the time of Determination No: 13-634 dated 27th June 2013, the catchment to the east of the site was determined as 5.66 hectares. Refer to Figure 2 for the catchment diagram.

• A time of concentration of 10 minutes was agreed for the flow, with a subsequent 100 year ARI rainfall intensity of 167 mm per hour.

• A runoff coefficient of 0.58 was agreed. • A design flow of 1.52 cubic metres per second was adopted. • Calculations are presented on the drawings demonstrating the hydraulic grade line in

the 1% AEP event allowing for full blockage of the 300x900 culvert, and 25% blockage in each of the 900 mm diameter pipes. As demonstrated the system flows adequately with an upstream ponding depth of 150 mm maximum which is anticipated to be less than the upstream flow depth.

Accordingly the proposed piped bypass system meets the requirements for diverting the upstream overland flows in the event of a 100 year ARI storm event. Drainage from Proposed Building and Pavements Stormwater runoff from the roof of the new structure will be drained to in-ground rainwater tanks located on the western side of the building. Collected roof water will then be re-used for toilet flushing and irrigation of landscaped areas thus achieving the water conservation objectives. In addition water tanks serve a valuable purpose in reducing pollutant loads in the storm water discharge from the site and also reduce the quantity of water discharged.

Ground surfaces will be directed to an on site detention tank that will be installed beneath the new section of roadway. Water quality objectives will be achieved by draining surface flows through pits containing enviropods and onto a proprietary water quality treatment device being installed within the on-site detention tank. This will treat the stormwater runoff before it leaves the site and allow it to achieve the water quality treatment objectives.

REF: 213025rpt20180723_DW_Water Management Report DEMLAKIAN CONSULTING ENGINEERS 30 May 2018 5 ©Copyright

Page 6: RE: WATER MANAGEMENT REPORT FOR PROPOSED EXPANSION

4.0 Water Conservation Measures A spreadsheet has been created to demonstrate that the frequency of overflow draining from the site post development does not exceed the frequency of overflow exiting the site prior to construction. A summary page is enclosed with this report.

The spreadsheet has been created using the daily rainfall data produced by the Bureau of Meteorology over a 20year period (1992-2012). To calculate the water overflowing from the design area into the neighbouring property to the west for the post construction site layout, the daily runoff from the paved and unpaved areas of the site has been calculated and added where applicable to the overflow volume from the rainwater tank. The spreadsheet calculates the volume of overflow on a day to day basis and on days where the volume of the water tank has been exceeded the runoff into the neighbouring property has been calculated. From this spreadsheet it was calculated that the site overflowed into the neighbouring property a total of 1812 days in 20 years in accordance with the developed conditions. Therefore overflow occurs 25.4% of the time and there is a total of 172,701 cubic metres of overflow over 20 years. For the pre-developed site, storm water from the same site area that has not infiltrated into the soil has flowed directly into the neighbouring property to the west. From this spreadsheet it was calculated that the site overflowed into the neighbouring property a total of 1791 days in 20 years. Therefore overflow occurs 14.2% of the time and there is a total of 152,155 cubic metres of overflow over 20years. Therefore there is an increase in overflow volume between pre and post development of 13%. Whilst water tanks provide for storage and water consumption, an onsite detention tank is required to reduce the peak site runoff in the post developed case. Refer to Section 5- Stormwater Quantity Modelling.

The daily water usage from the rainwater tank for flushing of toilets was calculated to be 2,700 L/day from the daily water usage rates supplied by The Government of South Australia in the document Water Smart: Rainwater Tanks for Toilet Flushing. Additionally, 1,500 L/day was allowed for drip irrigation based on the requirements for the landscaped areas on the property. Therefore the total daily water usage from the rainwater tank for the post-developed property is 4,200 L/day. Further, it is assumed that as there are no rainwater tanks on the pre-developed site the daily rainwater tank usage is zero in the pre developed case. In the post construction design of the site all of the roof area of the new structure is being drained to the rainwater tanks which are reusing the collected water to flush the toilets and provide drip irrigation to the surrounding landscaped areas. Using the assumptions previously stated that the site requires 2700L/day from the rainwater tank for irrigation purposes and 1500L/day for flushing of the toilets, the excel spreadsheet has calculated the amount of water entering and leaving the tank each day and summed the amount of days that there was not enough water for irrigation and toilet flushing purposes. In 20 years, the rainwater tank will be empty 1226 days which is equal to 16.8% of the time. Therefore in 20 years the rainwater tank is adequate for supplying the developments non potable demand for water 80% of the time.

Thus, the water conservation objective of for 80% of the sites non potable demand to be fulfilled using non potable sources, as per section 4.3 of the Blacktown Development Control Plan 2015 is achieved.

REF: 213025rpt20180723_DW_Water Management Report DEMLAKIAN CONSULTING ENGINEERS 30 May 2018 6 ©Copyright

Page 7: RE: WATER MANAGEMENT REPORT FOR PROPOSED EXPANSION

5.0 Storm Water Runoff Management The Development Consent Conditions (Determination No: 13-634, Condition 6.11.2.1) issued by Blacktown City Council in response to the previously approved DA submission, state that onsite detention of stormwater runoff from the site must be provided to achieve the following:

i. Nominated Discharge PSD: 147l/s/ha for 100%; 101l/s/ha for 90%; 562l/s/ha

for 80% ii. Nominated Storage SSR: 264 cu.m/ha for 100%; 301 cu.m/ha for 90%; 473

cu.m/ha for 80% As 100% of the developed area will drain to the on-site detention tank, the following permissible site discharge and site storage capacity have been calculated: - Site Area Draining to OSD= 0.947 ha (100% of the developed site area) - PSD = 147 l/s/ha (for 100% of the developed area being directed to the OSD tank) = 147 x 0.947 = 139 l/s - SSR = 264 cu.m/ha (for 100% of the developed area being directed to the OSD

tank) = 264 x 0.947 = 250 cu.m

REF: 213025rpt20180723_DW_Water Management Report DEMLAKIAN CONSULTING ENGINEERS 30 May 2018 7 ©Copyright

Page 8: RE: WATER MANAGEMENT REPORT FOR PROPOSED EXPANSION

6.0 Storm Water Quality Modelling Stormwater Quality: Urban development increases the pollution load entering local waterways. All developments in the Blacktown City Council are required to meet minimum treatment objectives in accordance with Table 2 of the Blacktown Development Control Plan 2015. The following stormwater quality load reduction controls are required:

i. 90% reduction in the post development mean annual load of Gross Pollutants (GP) ii. 85% reduction in the post development mean annual load of Total Suspended Solids

(TSS) iii. 65% reduction in the post development mean annual load of Total Phosphorus (TP) iv. 45% reduction in the post development mean annual load of Total Nitrogen (TN) v. 90% reduction in the post development mean annual load of Total Hydrocarbons

(TH)

These pollution load reductions have been modelled using Model for Urban Stormwater. Improvement Conceptualisation (MUSIC). The proposed development has been modelled MUSIC by Storm Water 360 on our behalf. (files available on request). - Figure 4 shows a schematic of the Music model. A summary of inputs and assumptions are outlined below.

Figure 4: Music Model Schematic As approved for the previous DA, the following has been adopted: - Roof to Rainwater Tank - Overflow from Rainwater Tank to Onsite Detention Tank - Landscaping to Onsite Detention Tank - Overland Flow from adjoining properties piped to Existing Headwall

REF: 213025rpt20180723_DW_Water Management Report DEMLAKIAN CONSULTING ENGINEERS 30 May 2018 8 ©Copyright

Page 9: RE: WATER MANAGEMENT REPORT FOR PROPOSED EXPANSION

7.0 Flood Emergency Response Plan The 1 in 100 year flood level in the area of the site has been calculated at 17.3m as obtained from a council letter dated 22nd February 2013 (File no: 120315/3). This is well beneath the lowest proposed floor level of the site. The proposed construction has a Floor Level RL= 19.8. Therefore, the development is not affected by the Flood Planning Levels within the area. As presented in Figure 5, the 1/100 year storm will only affect a small portion of the site located on the western boundary of the site. This storm event will impact the site at the approximate location of the car park but not approach the buildings. Therefore, during this storm event there should be no need to evacuate the school.

Figure 5: Flood Zoning Map The site is affected by the Probable Maximum Flood (PMF) level. This level as obtained from a council letter dated 22nd February 2013 (File no: 120315/3) is calculated as 26.4m in the area. This is 6.6m above the floor level of the proposed building. If evacuation from the site is required during an event of this nature, adequate warning times would be provided as a vast area surrounding the site will be affected. The areas highlighted in white in Figure 5 are not affected by the PMF. The following route should be taken by inhabitants of the school to access safe areas that are not affected by the PMF and to prevent crossing areas that are affected by the 1/100 year storm event:

- Exit the site from the Southern boundary and cross through the neighbouring properties to reach Robert Street.

- Travel South along Robert Street past the Walker Parade intersection. The area south of this intersection is not affected by the PMF.

Should road access be required the following route should be taken, however it should be noted that a small section of Farm Road subject to the 1/100 year flood will need to be crossed:

REF: 213025rpt20180723_DW_Water Management Report DEMLAKIAN CONSULTING ENGINEERS 30 May 2018 9 ©Copyright

Page 10: RE: WATER MANAGEMENT REPORT FOR PROPOSED EXPANSION

- Exit the site and travel East down Farm Road - Turn Right onto Cleveland Road - Turn Right onto Walker Street - Turn Left onto Robert Street. The area south of this intersection is not affected by

the PMF. Enclosed is a copy of the Emergency Flood Management Plan that the school will implement to ensure a safe flood emergency evacuation plan.

8.0 Conclusion The development of the site has been designed to ensure that there is minimal increase to the stormwater runoff flow rate from the site and will mitigate negative impacts on the surrounding properties both in routine and extreme events. The proposed drainage plan complies with the requirement of section 4.4 of the Blacktown Control Development 2015 which limits the post development flow of water from site to the predevelopment flow. The rainwater tanks proposed as part of the new construction will have a combined storage of 100,000L. The volume of these tanks ensures that the sites demand for non potable water is 80% satisfied by non potable sources. Therefore, the design satisfies section 4.3 Water Conservation of the Blacktown Development Control Plan 2015. The stormwater quality and treatment solution proposed has been designed to ensure that Blacktown City Council treatment targets and requirements are reasonably met. The design ensures that stormwater off the site as a result of the new construction will have limited effects on the downstream water quality. Yours Faithfully,

David Wilcox BE (Hons I) FIEAust CPEng NER RPEQ Director DEMLAKIAN CONSULTING ENGINEERS

Encl. Emergency Flood Management Plan

Water Balance Model Summary

REF: 213025rpt20180723_DW_Water Management Report DEMLAKIAN CONSULTING ENGINEERS 30 May 2018 10 ©Copyright

Page 11: RE: WATER MANAGEMENT REPORT FOR PROPOSED EXPANSION

AUSTRALIAN CHRISTIAN COLLEGE - Lot 90 DP1224210AUSTRALIAN CHRISTIAN COLLEGE - Lot 90 DP1224210PROPOSED NEW BUILDING & CARPARK EXTENSIONPROPOSED NEW BUILDING & CARPARK EXTENSIONSTORMWATER NOTESSTORMWATER NOTES

DATEDATE

DESIGNED:DESIGNED: DATE:DATE:

DRAWN:DRAWN: CHECKED:CHECKED:

DRAWING:DRAWING: REVISION:REVISION:

REV.NoREV.No

COPYRIGHT. DRAWINGS ISSUED UNDER LICENSE BY DEMLAKIAN CONSULTING ENGINEERSCOPYRIGHT. DRAWINGS ISSUED UNDER LICENSE BY DEMLAKIAN CONSULTING ENGINEERS

REVISIONREVISION BYBY

cccc

(02) 9955 6122(02) 9955 6122

www.demlakian.com.auwww.demlakian.com.au

P.O. Box 6553 North Sydney 2059P.O. Box 6553 North Sydney 2059

E-mail: [email protected]: [email protected]

Level 2, 5 Ridge StreetLevel 2, 5 Ridge Street

North Sydney NSW 2060North Sydney NSW 2060

(02) 9955 4485(02) 9955 4485

Facsimile:Facsimile:

Telephone:Telephone:

ORIGINAL: A1 DWGORIGINAL: A1 DWGIntelligent Thinking in EngineeringIntelligent Thinking in Engineering

CLIENT:CLIENT:

TITLE:TITLE:

PROJECT:PROJECT:

NOTE:NOTE:

This drawing must be read in conjunction withThis drawing must be read in conjunction with

ALL other drawings for this project includingALL other drawings for this project including

but not limited to all construction notes.but not limited to all construction notes.

213025213025

D.W.D.W.

RALRAL

FEB 2013FEB 2013

D.W.D.W.

AUSTRALIAN CHRISTIAN COLLEGEAUSTRALIAN CHRISTIAN COLLEGE

69 Farm Road RIVERSTONE69 Farm Road RIVERSTONE

Lot 90 DP1224210Lot 90 DP1224210

LIPPMANN PARTNERSHIPLIPPMANN PARTNERSHIP

AUSTRALIAN CHRISTIAN COLLEGEAUSTRALIAN CHRISTIAN COLLEGE

ARCHITECT:ARCHITECT:

T/A Demlakian Consulting EngineersT/A Demlakian Consulting Engineers

ABN 42 651 771 142ABN 42 651 771 142

Demlakian Strata & Remedial Pty LimitedDemlakian Strata & Remedial Pty Limited

FOR DEVELOPMENTFOR DEVELOPMENT

APPLICATION SUBMISSIONAPPLICATION SUBMISSION

STORMWATER NOTESSTORMWATER NOTES

& DRAWING SCHEDULE& DRAWING SCHEDULE

SW00SW00 NN

DRAWING SCHEDULEDRAWING SCHEDULESTORMWATER DRAWINGSSTORMWATER DRAWINGS

COVER UNDER ROADSCOVER UNDER ROADS

AND CAR PARKINGAND CAR PARKING

300mm ELSEWHERE300mm ELSEWHERE

TYPICAL PIPE LAYING DETAILTYPICAL PIPE LAYING DETAIL

PIPE BEDPIPE BED

GRAVELY SANDGRAVELY SAND

ORDINARY FILLORDINARY FILL

HAUNCH ZONEHAUNCH ZONE

GRAVELY SANDGRAVELY SAND

APPROVED SELECTAPPROVED SELECT

ORDINARY FILLORDINARY FILL

75

75

300

300

600

600

MIN.

MIN.

MIN.

MIN.

TYPICAL PIPE LAYINGTYPICAL PIPE LAYING

ADJACENT TO FOOTINGSADJACENT TO FOOTINGS

DEPTH TO BOTTOM

DEPTH TO BOTTOM

OF TRENCH (V

ARIES)

OF TRENCH (V

ARIES)

4

5

°

M

A

X

4

5

°

M

A

X

EXISTING SURFACEEXISTING SURFACE

FINISHED SURFACEFINISHED SURFACE

STORMWATER DRAINAGE NOTES:STORMWATER DRAINAGE NOTES:

GENERAL NOTES:GENERAL NOTES:

D1.D1. All levels are to Australian Height Datum (AHD), unless noted All levels are to Australian Height Datum (AHD), unless noted

otherwise.otherwise.

D2.D2. Dimensions shall not be scaled from drawings.Dimensions shall not be scaled from drawings.

D3.D3. The Contractor must verify all dimensions on site prior to The Contractor must verify all dimensions on site prior to

commencement of the works.commencement of the works.

D4.D4. These plans shall be read in conjunction with the approved These plans shall be read in conjunction with the approved

Architectural, Structural, Mechanical, Hydraulic, Electrical, LandscapeArchitectural, Structural, Mechanical, Hydraulic, Electrical, Landscape

& other Consultants drawings.& other Consultants drawings.

D5.D5. Where new work abuts existing, the Contractor shall ensure a smoothWhere new work abuts existing, the Contractor shall ensure a smooth

even profile free from abrupt changes.even profile free from abrupt changes.

D6.D6. The Contractor shall arrange for all survey setout & as-built to beThe Contractor shall arrange for all survey setout & as-built to be

performed by a Registered Surveyor.performed by a Registered Surveyor.

D7.D7. Invert levels are given at critical locations. The Contractor/DrainerInvert levels are given at critical locations. The Contractor/Drainer

shall determine levels on minor drainage lines and confirm design shall determine levels on minor drainage lines and confirm design

levels.levels.

D8.D8. Stormwater drains min. fall 1:100, unless noted otherwise.Stormwater drains min. fall 1:100, unless noted otherwise.

D9.D9. Advise Engineer for Inspection of all Stormwater works, pipes & pits,Advise Engineer for Inspection of all Stormwater works, pipes & pits,

prior to covering. Provide as-built survey upon completion.prior to covering. Provide as-built survey upon completion.

D10.D10. Construction of Drainage to conform with the requirements of the Construction of Drainage to conform with the requirements of the

relevant Authority or Council.relevant Authority or Council.

D11.D11. Connections to new & existing drainage shall be neatly trimmed & Connections to new & existing drainage shall be neatly trimmed &

cement rendered to a smooth finish.cement rendered to a smooth finish.

D12.D12. All work shall be in accordance with AS3500 'National Plumbing & All work shall be in accordance with AS3500 'National Plumbing &

Drainage Code', unless noted otherwise.Drainage Code', unless noted otherwise.

D13.D13. The Contractor shall expose the full drainage route and point of The Contractor shall expose the full drainage route and point of

discharge from the site and confirm levels prior to commencing discharge from the site and confirm levels prior to commencing

construction.construction.

EXISTING SERVICES:EXISTING SERVICES:

D14.D14. The Contractor shall excavate for, locate and co-ordinate with allThe Contractor shall excavate for, locate and co-ordinate with all

services within & beyond the property line prior to the commencementservices within & beyond the property line prior to the commencement

of the Works.of the Works.

D15.D15. Existing services which are to remain shall be adjusted as necessaryExisting services which are to remain shall be adjusted as necessary

to suit the new Works.to suit the new Works.

D16.D16. Existing services no longer required shall be capped off and removedExisting services no longer required shall be capped off and removed

out of sight to the relevant authorities requirements.out of sight to the relevant authorities requirements.

D17.D17. Care is to be taken when excavating near existing services. ObtainCare is to be taken when excavating near existing services. Obtain

services setout prior to works. Hand excavate as required to avoidservices setout prior to works. Hand excavate as required to avoid

damage to services.damage to services.

D18.D18. Construct temporary services as required.Construct temporary services as required.

DRAINAGE PIPES:DRAINAGE PIPES:

D19.D19. UPVC type pipes shall be used for pipes not greater than 300mm UPVC type pipes shall be used for pipes not greater than 300mm

diameter, unless noted otherwise. UPVC pipes shall have solvent diameter, unless noted otherwise. UPVC pipes shall have solvent

welded watertight joints.welded watertight joints.

D20.D20. Pipe diameter greater than 300mm shall be FRC type pipe Class '3',Pipe diameter greater than 300mm shall be FRC type pipe Class '3',

unless noted otherwise.unless noted otherwise.

D21.D21. Pipe laying, bedding & backfill to be in accordance with the Pipe laying, bedding & backfill to be in accordance with the

specification and the pipe manufacturer's requirements.specification and the pipe manufacturer's requirements.

D22.D22. Where UPVC drainage pipes pass under slabs, sewer grade pipes shallWhere UPVC drainage pipes pass under slabs, sewer grade pipes shall

be used.be used.

D23.D23. Contractor shall supply & install all proprietary fittings for Contractor shall supply & install all proprietary fittings for

connections & junctions.connections & junctions.

D24.D24. Additional subsoil drainage may be required where site conditions &Additional subsoil drainage may be required where site conditions &

groundwater dictate. Refer to Engineer for site inspection.groundwater dictate. Refer to Engineer for site inspection.

D25.D25. Pipes to be 100∅ unless noted otherwise.Pipes to be 100∅ unless noted otherwise.

D26.D26. Outlet pipes from pits shall have invert level at least 30mm lower thanOutlet pipes from pits shall have invert level at least 30mm lower than

the invert level of the lowest pipe entering the pit.the invert level of the lowest pipe entering the pit.

D27.D27. Inspection openings or stormwater pits shall be located where shownInspection openings or stormwater pits shall be located where shown

on the drawings and at the following locations:on the drawings and at the following locations:

a. Each point of connectiona. Each point of connection

b. Even spacing not more than 30m apart.b. Even spacing not more than 30m apart.

c. Each end of any inclined jump-up which exceeds 6m in length.c. Each end of any inclined jump-up which exceeds 6m in length.

d. Each connection to an existing stormwater drain.d. Each connection to an existing stormwater drain.

e. Any change of direction greater than 45°.e. Any change of direction greater than 45°.

D28.D28. Inspection openings shall be min 150∅ and shall be plugged or capped inInspection openings shall be min 150∅ and shall be plugged or capped in

accordance with AS3500.accordance with AS3500.

D29.D29. Planter boxes bases to be lined with 'Atlantis Drainage Cell' or Planter boxes bases to be lined with 'Atlantis Drainage Cell' or

approved equivalent wrapped in geotextile and draining to subsoil approved equivalent wrapped in geotextile and draining to subsoil

drainage pipes connected to the main stormwater system. Co-ordinatedrainage pipes connected to the main stormwater system. Co-ordinate

with requirements of Landscape Architect.with requirements of Landscape Architect.

D30.D30. Junctions in stormwater drains shall be made by means of a Junctions in stormwater drains shall be made by means of a

proprietary coupler or for pipes of at least 350∅ opening cut as proprietary coupler or for pipes of at least 350∅ opening cut as

detailed on the drawings.detailed on the drawings.

DRAINAGE PITS:DRAINAGE PITS:

D31.D31. All pits and arrestors shall be constructed to the relevant authoritiesAll pits and arrestors shall be constructed to the relevant authorities

requirements. Provide local falls to pits.requirements. Provide local falls to pits.

D32.D32. Minimum cover to all reinforcement in concrete to be 40mm.Minimum cover to all reinforcement in concrete to be 40mm.

D33.D33. Minimum Drainage pit size shall be as follows:Minimum Drainage pit size shall be as follows:

D34.D34. All pits to have galvanised hinged lockable gratings equivalent toAll pits to have galvanised hinged lockable gratings equivalent to

"Grate Drainage Products Pty Ltd" heelguard type."Grate Drainage Products Pty Ltd" heelguard type.

Use Class B in general areas and Class D in areas subject toUse Class B in general areas and Class D in areas subject to

vehicles.vehicles.

D35.D35. Drainage pit size may need to be increased over minimum to suit pipeDrainage pit size may need to be increased over minimum to suit pipe

size. Pit internal dimensions shall be of least 300mm greater than size. Pit internal dimensions shall be of least 300mm greater than

external diameter of corresponding pipe.external diameter of corresponding pipe.

D36.D36. Pits deeper than 1000mm are to be fitted with step irons at 300mmPits deeper than 1000mm are to be fitted with step irons at 300mm

centres. Contact Engineer for typical detail.centres. Contact Engineer for typical detail.

D37.D37. All exposed pit edges shall be rounded with 20mm radius or 20 x 20All exposed pit edges shall be rounded with 20mm radius or 20 x 20

chamfer.chamfer.

D38.D38. Walls of cast insitu pits shall be 200mm (min.) thick concrete, gradeWalls of cast insitu pits shall be 200mm (min.) thick concrete, grade

N32, unless noted otherwise.N32, unless noted otherwise.

D39.D39. Pits shall be reinforced with SL81 fabric, central in walls & base slabPits shall be reinforced with SL81 fabric, central in walls & base slab

U.N.O. Mesh to be lapped 400mm. Lap mesh at corners or use N12-200U.N.O. Mesh to be lapped 400mm. Lap mesh at corners or use N12-200

"L" bars lapping 400 each way."L" bars lapping 400 each way.

D40.D40. Approved precast pits may be used.Approved precast pits may be used.

D41.D41. Bases of drainage pits shall be grouted to prevent ponding of water,Bases of drainage pits shall be grouted to prevent ponding of water,

unless noted otherwise.unless noted otherwise.

EPEP

Denotes existing pipeDenotes existing pipe

K.I.K.I.

Denotes kerb entry & roadway pit system (900 x 600)Denotes kerb entry & roadway pit system (900 x 600)

Denotes grated stormwater pit.Denotes grated stormwater pit.

Denotes stormwater pit.Denotes stormwater pit.

I.L.139.50I.L.139.50 Denotes invert level.Denotes invert level.

Pipe grade as a percentage (min) Pipe grade as a percentage (min) 1:1001:100

Denotes subsoil drain.Denotes subsoil drain.

Denotes pipe diameter in mm.Denotes pipe diameter in mm.

100∅100∅

Denotes stormwater pipe.Denotes stormwater pipe.

G.L.139.50G.L.139.50 Denotes ground level.Denotes ground level.

R.L.139.50R.L.139.50 Denotes reduced level.Denotes reduced level.

Denotes downpipes.Denotes downpipes.

D.PD.P

Denotes downpipe with spreaderDenotes downpipe with spreader

LEGENDLEGEND

Denotes 100 wide x 100 min. depth grated drain typeDenotes 100 wide x 100 min. depth grated drain type

"ACO KS100" with Class A antislip stainless steel"ACO KS100" with Class A antislip stainless steel

heelguard grates U.N.O. Grated drains in areas subjectheelguard grates U.N.O. Grated drains in areas subject

to vehicle loads to be K100 and have Class D "ACO"to vehicle loads to be K100 and have Class D "ACO"

perforated steel grating.perforated steel grating.

1200 1200

900 900

Depth to InvertDepth to Invert

(mm)(mm)

12001200

900 900

600 600

600 600

DiameterDiameter

CircularCircular

900900

900900

600600

450450

LengthLength

RectangularRectangular

WidthWidth

900900

600600

600600

450450

10001000

10001000

900900

600600

Minimum Internal Dimensions (mm)Minimum Internal Dimensions (mm)

SW0SW0 STORMWATER NOTES & DRAWING SCHEDULESTORMWATER NOTES & DRAWING SCHEDULE

SW1SW1 STORMWATER SITE PLANSTORMWATER SITE PLAN

SW2SW2 STORMWATER MANAGEMENT PLAN SHEET 1STORMWATER MANAGEMENT PLAN SHEET 1

SW3SW3 STORMWATER MANAGEMENT PLAN SHEET 2STORMWATER MANAGEMENT PLAN SHEET 2

SW4SW4 STORMWATER DETAILS SHEET 1STORMWATER DETAILS SHEET 1

SW5SW5 STORMWATER DETAILS SHEET 2STORMWATER DETAILS SHEET 2

SW6SW6 SEDIMENT & EROSION CONTROL PLAN SHEET 1SEDIMENT & EROSION CONTROL PLAN SHEET 1

SW7SW7 SEDIMENT & EROSION CONTROL PLAN SHEET 2SEDIMENT & EROSION CONTROL PLAN SHEET 2

SW8SW8 SEDIMENT AND EROSION CONTROL DETAILSSEDIMENT AND EROSION CONTROL DETAILS

SW9SW9 STORMWATER LONGSECTION & HGLSTORMWATER LONGSECTION & HGL

SW10SW10 ENVIROPOD DETAILSENVIROPOD DETAILS

SAG INLET PIT PLANSAG INLET PIT PLAN

350350

INLET PIPEINLET PIPE

1A1A

DETAILDETAIL

--

MASS CONCRETEMASS CONCRETE

CHANNELLINGCHANNELLING

∅100 SUBSOIL DRAIN∅100 SUBSOIL DRAIN

REFER TO NOTE 3REFER TO NOTE 3

300

300

25

25

SL72 FABRICSL72 FABRIC

WITH 30mmWITH 30mm

COVERCOVER

350350

350350

1A1A

--

REFER TOREFER TO

NOTE D33NOTE D33

150150

1B1B

--

150150 350350

DETAILDETAIL

1B1B

--

SL72 FABRIC WITHSL72 FABRIC WITH

30mm COVER30mm COVER

300

300

SURFACE INLET PITSURFACE INLET PIT

COVER REFER TOCOVER REFER TO

NOTE 4NOTE 4

25

25

∅100 SUBSOIL∅100 SUBSOIL

DRAIN REFERDRAIN REFER

TO NOTE 3.TO NOTE 3.

INLET PIPEINLET PIPE

350

350

REFER TO

REFER TO

NOTE D33

NOTE D33

150

150

150

150

350

350

"T""T""T""T"

"T"

"T"

"H"

"H"

HINGEHINGE HINGEHINGE

REFER TOREFER TO

NOTE D33NOTE D33

"T""T""T""T"

REFER TOREFER TO

NOTE D33NOTE D33

SAG INLET PIT NOTES:SAG INLET PIT NOTES:

1.1. COMPRESSIVE STRENGTH COMPRESSIVE STRENGTH OF OF CONCRETECONCRETE TO BE TO BE A MINIMUM OF 20A MINIMUM OF 20MPaMPa AT AT

28 DAYS.28 DAYS.

2.2. TOP OF BENCHING TOP OF BENCHING SHALLSHALL BE 1/2 OF OUTLET PIPE BE 1/2 OF OUTLET PIPE D DIAMETER.IAMETER.

3.3. ∅∅100 SUBSOIL DRAINAGE PIPE 3m LONG100 SUBSOIL DRAINAGE PIPE 3m LONG WRAPPED IN FABRIC SOCK TOWRAPPED IN FABRIC SOCK TO

BE PROVIDED ATBE PROVIDED AT INVERT LEVEL EITHER SIDE OF INLET PIPES.INVERT LEVEL EITHER SIDE OF INLET PIPES.

4.4. ALL PITS TO HAVE GALVANISED HINGED LOCKABLE GRATINGSALL PITS TO HAVE GALVANISED HINGED LOCKABLE GRATINGS

EQUIVALENT TO "GRATE DRAINAGE PRODUCTS PTY LTD" HEELGUARDEQUIVALENT TO "GRATE DRAINAGE PRODUCTS PTY LTD" HEELGUARD

TYPE.TYPE.

USE CLASS B IN GENERAL AREAS AND CLASS D IN AREAS SUBJECT TOUSE CLASS B IN GENERAL AREAS AND CLASS D IN AREAS SUBJECT TO

VEHICLES.VEHICLES.

5.5. PROVIDE STEP IRONS WHERE PIT IS DEEPER THAN 1200.PROVIDE STEP IRONS WHERE PIT IS DEEPER THAN 1200.

GG 14.09.1514.09.15 FOR DA SUBMISSIONFOR DA SUBMISSION RALRAL

HH 23.04.1823.04.18 REVISED FOR DA SUBMISSIONREVISED FOR DA SUBMISSION RALRAL

MM 30.05.1830.05.18 REVISED FOR DA SUBMISSIONREVISED FOR DA SUBMISSION RALRAL

NN 23.07.1823.07.18 REVISED FOR DA SUBMISSIONREVISED FOR DA SUBMISSION RALRAL

Page 12: RE: WATER MANAGEMENT REPORT FOR PROPOSED EXPANSION

DP1DP1

DP1DP1

DP1DP1

DP1DP1

DP1DP1

DP1DP1

DP1DP1

DP1DP1

DP1DP1

DP1DP1

DP1DP1

DP1DP1

DP1DP1 DP1DP1

DP1DP1

DP1DP1

DP1DP1

DP1DP1

DP1DP1

DP1DP1

DP2DP2

DP2DP2

DP2DP2

EXISTING PLAYING FIELDEXISTING PLAYING FIELD

PROPOSED NEWPROPOSED NEW

CARPARKCARPARK

FA

RM

R

OA

DFA

RM

R

OA

D

PROPOSED NEWPROPOSED NEW

BUILDINGBUILDING

FOR DETAIL REFERFOR DETAIL REFER

TO DRAWINGTO DRAWING

213025/SW03213025/SW03

NEW ENTRYNEW ENTRY

TAPTAP

TOG 21.8TOG 21.8

TAPTAP

TAPTAP

TAPTAP

RIDGE 22.9RIDGE 22.9

T

O

G

2

2

.

4

T

O

G

2

2

.

4

R

I

D

G

E

2

6

.

0

R

I

D

G

E

2

6

.

0

RID

GE

RID

GE

PITPIT

PITPIT

22.3622.36

EAVEEAVE

T

O

G

2

2

.

4

T

O

G

2

2

.

4

R

O

O

F

2

3

.

0

R

O

O

F

2

3

.

0

V

E

R

A

N

D

A

H

R

L

1

9

.

8

1

V

E

R

A

N

D

A

H

R

L

1

9

.

8

1

PITPIT

PITPIT

SWITCH SWITCH

BOARDBOARD

DIS

AB

LED

DIS

AB

LED

CONCRETE DRAINCONCRETE DRAIN

1

0

0

m

m

1

0

0

m

m

2

2

5

m

m

2

2

5

m

m

2

2

5

m

m

2

2

5

m

m

225mm∅225mm∅

225mm∅225mm∅

PITPIT

225mm∅225mm∅

2

2

5

m

m

2

2

5

m

m

TOG 22.4TOG 22.4

RIDGE 23.85RIDGE 23.85

CEILING RL 21.47CEILING RL 21.47 CEILING RL 22.41CEILING RL 22.41

1

8

.

5

1

8

.

5

1

9

.

5

1

9

.

5

1

9

.

5

1

9

.

5

1

9

.

5

1

9

.

5

2

0

.

5

2

0

.

5

2

0

.

5

2

0

.

5

2

1

.

5

2

1

.

5

1

9

.

5

1

9

.

5

1

9

.

5

1

9

.

5

1

8

.

5

1

8

.

5

1

9

.

5

1

9

.

5

1

8

.

5

1

8

.

5

1

8

.

5

1

8

.

5

2

0

2

0

1

9

1

9

1

9

.

5

1

9

.

5

1818

17

.5

17

.5

1

8

.

5

1

8

.

5

1

8

1

8

1919

2

0

2

0

2

1

2

1

2

0

2

0

1

9

1

9

1

9

1

9 2

0

2

0

1

9

1

9

1

9

1

9

1

9

1

9

1

8

1

8

1

8

.

5

1

8

.

5

1

7

.

5

1

7

.

5

1818

1

7

1

7

1

9

.

5

1

9

.

5

1

9

1

9

2

0

2

0

1919

2

0

2

0

UPPER RIDGE 29.6UPPER RIDGE 29.6

TOG 27.46TOG 27.46

TOG 26.01TOG 26.01

TOG 27.32TOG 27.32

TOG 26.01TOG 26.01

TOG 22.4TOG 22.4

TO

G 21.7

TO

G 21.7

LOWER RIDGE 27.3LOWER RIDGE 27.3

2 x 450mm∅

2 x 450mm∅

2 x 450mm∅

2 x 450mm∅

100m

m∅

100m

m∅

23.9

23.9

375m

m∅

375m

m∅

375m

m∅

375m

m∅

300m

m∅

300m

m∅

300m

m∅

300m

m∅

100mm∅100mm∅

225∅225∅

1

8

.

5

1

8

.

5

1

9

1

9

TTTT

279°17'20"

279°17'20"

TTTT

(

2

1

.

5

)

(

2

1

.

5

)

(2

0

)

(2

0

)

(

2

1

)

(

2

1

)

(

2

1

)

(

2

1

)

TAPTAP

(

2

0

.

5

)

(

2

0

.

5

)

(

1

9

.

5

)

(

1

9

.

5

)

267.151267.151

80.065

80.065

(

2

2

)

(

2

2

)

(

2

1

.

5

)

(

2

1

.

5

)

267.151267.151

189°09'20"189°09'20"

(

2

0

)

(

2

0

)

(

2

0

.

5

)

(

2

0

.

5

)

(

2

1

.

5

)

(

2

1

.

5

)

(

2

0

)

(

2

0

)

(

2

1

)

(

2

1

)

(

2

2

)

(

2

2

)

A

W

N

I

N

G

2

0

.

2

2

A

W

N

I

N

G

2

0

.

2

2

T

O

G

2

2

.

9

0

T

O

G

2

2

.

9

0

R

O

O

F

2

3

.

3

0

R

O

O

F

2

3

.

3

0

(

2

0

.

5

)

(

2

0

.

5

)

(

2

1

.

5

)

(

2

1

.

5

)

(

2

0

)

(

2

0

)

(20)(20)

(

1

9

.

5

)

(

1

9

.

5

)

(

1

9

.

5

)

(

1

9

.

5

)

(

2

1

)

(

2

1

)

(

2

2

)

(

2

2

)

(

2

0

)

(

2

0

)

80.065

80.065

99°08'20"

99°08'20"

TAPTAP

TAPTAP

TOG 22.25TOG 22.25

189°09'20"189°09'20"

(

2

0

.

5

)

(

2

0

.

5

)

(

1

9

.

5

)

(

1

9

.

5

)

(

2

0

)

(

2

0

)

T

O

G

2

4

.

2

0

T

O

G

2

4

.

2

0

R

O

O

F

2

4

.

8

6

R

O

O

F

2

4

.

8

6

ROOF 23.18

ROOF 23.18

ROOF 23.27ROOF 23.27

TOG 22.67

TOG 22.67

FOR DETAIL REFERFOR DETAIL REFER

TO DRAWINGTO DRAWING

213025/SW02213025/SW02

DIRECTION OF UPHILLDIRECTION OF UPHILL

OVERLAND FLOWOVERLAND FLOW

PROPOSED NEWPROPOSED NEW

CARPARK /CARPARK /

DRIVEWAYDRIVEWAY

PROPOSED OVERLANDPROPOSED OVERLAND

FLOW BYPASS PIPESFLOW BYPASS PIPES

PROPOSED ON-SITEPROPOSED ON-SITE

DETENTION TANKDETENTION TANK

HATCHED AREA INDICATESHATCHED AREA INDICATES

EXTENT OF NEWEXTENT OF NEW

DRIVEWAY / DROP OFFDRIVEWAY / DROP OFF

AREA.AREA.

DIRECTION OFDIRECTION OF

OVERLAND FLOWOVERLAND FLOW

EXISTINGEXISTING

DRIVEWAY WITHDRIVEWAY WITH

DEPRESSION FORDEPRESSION FOR

OVERLAND FLOWOVERLAND FLOW

EXISTINGEXISTING

CARPARKCARPARK

NEW OULET FROM ON-SITENEW OULET FROM ON-SITE

DETENTION SYSTEM LOCATEDDETENTION SYSTEM LOCATED

ADJACENT TO EXISTING OUTLETADJACENT TO EXISTING OUTLET

∅225 OUTLET CONNECTED∅225 OUTLET CONNECTED

TO EXISTING GROSSTO EXISTING GROSS

POLLUTANT TRAPPOLLUTANT TRAP

PROPOSED IN-GROUNDPROPOSED IN-GROUND

WATER TANKSWATER TANKS

900 x 900900 x 900

INLET PIT 29INLET PIT 29

R.L. = 21.50R.L. = 21.50

I.L. = 20.70I.L. = 20.70

900 x 900900 x 900

INLET PIT 29INLET PIT 29

R.L. = 19.70R.L. = 19.70

I.L. = 18.90I.L. = 18.90

900 x 900900 x 900

INLET PIT 31INLET PIT 31

R.L. = 19.45R.L. = 19.45

I.L. = 18.20I.L. = 18.20

900 x 900900 x 900

INLET PIT 32INLET PIT 32

R.L. = 19.10R.L. = 19.10

I.L. = 17.85I.L. = 17.85

900 x 900900 x 900

INLET PIT 33INLET PIT 33

R.L. = 18.75R.L. = 18.75

I.L. = 17.50I.L. = 17.50

900 x 900900 x 900

INLET PIT 34INLET PIT 34

R.L. = 18.40R.L. = 18.40

I.L. = 17.14I.L. = 17.14

DATEDATE

DESIGNED:DESIGNED: DATE:DATE:

DRAWN:DRAWN: CHECKED:CHECKED:

DRAWING:DRAWING: REVISION:REVISION:

REV.NoREV.No

COPYRIGHT. DRAWINGS ISSUED UNDER LICENSE BY DEMLAKIAN CONSULTING ENGINEERSCOPYRIGHT. DRAWINGS ISSUED UNDER LICENSE BY DEMLAKIAN CONSULTING ENGINEERS

REVISIONREVISION BYBY

cccc

(02) 9955 6122(02) 9955 6122

www.demlakian.com.auwww.demlakian.com.au

P.O. Box 6553 North Sydney 2059P.O. Box 6553 North Sydney 2059

E-mail: [email protected]: [email protected]

Level 2, 5 Ridge StreetLevel 2, 5 Ridge Street

North Sydney NSW 2060North Sydney NSW 2060

(02) 9955 4485(02) 9955 4485

Facsimile:Facsimile:

Telephone:Telephone:

ORIGINAL: A1 DWGORIGINAL: A1 DWGIntelligent Thinking in EngineeringIntelligent Thinking in Engineering

CLIENT:CLIENT:

TITLE:TITLE:

PROJECT:PROJECT:

NOTE:NOTE:

This drawing must be read in conjunction withThis drawing must be read in conjunction with

ALL other drawings for this project includingALL other drawings for this project including

but not limited to all construction notes.but not limited to all construction notes.

213025213025

D.W.D.W.

RALRAL

FEB 2013FEB 2013

D.W.D.W.

AUSTRALIAN CHRISTIAN COLLEGEAUSTRALIAN CHRISTIAN COLLEGE

69 Farm Road RIVERSTONE69 Farm Road RIVERSTONE

Lot 90 DP1224210Lot 90 DP1224210

LIPPMANN PARTNERSHIPLIPPMANN PARTNERSHIP

AUSTRALIAN CHRISTIAN COLLEGEAUSTRALIAN CHRISTIAN COLLEGE

ARCHITECT:ARCHITECT:

T/A Demlakian Consulting EngineersT/A Demlakian Consulting Engineers

ABN 42 651 771 142ABN 42 651 771 142

Demlakian Strata & Remedial Pty LimitedDemlakian Strata & Remedial Pty Limited

FOR DEVELOPMENTFOR DEVELOPMENT

APPLICATION SUBMISSIONAPPLICATION SUBMISSION

STORMWATER SITE PLANSTORMWATER SITE PLAN

SW01SW01 PP

STORMWATER SITE PLANSTORMWATER SITE PLAN

SCALE 1:500SCALE 1:500EXISTING STORMWATER PIPEEXISTING STORMWATER PIPE

100∅100∅

EXISTING PIPE DIAMETER IN MMEXISTING PIPE DIAMETER IN MM

KK 23.04.1823.04.18 LAYOUT REVISEDLAYOUT REVISED RALRAL

MM 28.05.1828.05.18 LAYOUT REVISEDLAYOUT REVISED RALRAL

NN 06.06.1806.06.18 LAYOUT REVISEDLAYOUT REVISED RALRAL

PP 23.07.1823.07.18 REVISED FOR DA SUBMISSIONREVISED FOR DA SUBMISSION RALRAL

Page 13: RE: WATER MANAGEMENT REPORT FOR PROPOSED EXPANSION

3

0

0

3

0

0

3

0

0

3

0

0

3

7

5

3

7

5

∅225∅225

∅300∅300

HATCHED AREAHATCHED AREA

INDICATES NEWINDICATES NEW

DROP OFF AREADROP OFF AREA

EXISTING 100∅ PIPEEXISTING 100∅ PIPE

TO BE REMOVEDTO BE REMOVED

EXISTING OVERLANDEXISTING OVERLAND

FLOW PATH. REFER TOFLOW PATH. REFER TO

SECTION.SECTION.

11

SW4SW4

22

SW4SW4

33

S

W

4

S

W

4

HEADWALL 4 TO BE ROCLAHEADWALL 4 TO BE ROCLA

MULTI-CELL PIPE HEADWALLMULTI-CELL PIPE HEADWALL

HWC300JZ02 OR EQUIVALENTHWC300JZ02 OR EQUIVALENT

300 WIDE X 200 DEEP GRATED300 WIDE X 200 DEEP GRATED

DRAIN, DEPRESSED 50mm.DRAIN, DEPRESSED 50mm.

EXTEND 900x300 BOX CULVERTEXTEND 900x300 BOX CULVERT

BASE IL VARIES, IL 18.35 TO 18.01BASE IL VARIES, IL 18.35 TO 18.01

KERB &

GUTTER

KERB &

GUTTER

KERB &

GUTTER

KERB &

GUTTER

KERB &

GUTTER

KERB &

GUTTER

KERB ONLY

KERB ONLY

KERB ONLY

KERB ONLY

KERB ONLY

KERB ONLY

KERB ONLY

KERB ONLY

KERB &

GUTTER

KERB &

GUTTER

EXISTING OVERLANDEXISTING OVERLAND

FLOW PATHFLOW PATH

EXISTING 300x900EXISTING 300x900

CULVERTCULVERT

EX PIT 3EX PIT 3

R.L. = 18.80R.L. = 18.80

EX PIT 4EX PIT 4

R.L. = 18.65R.L. = 18.65

EX PIT 5EX PIT 5

R.L. = 18.00R.L. = 18.00

I.L. = 17.62I.L. = 17.62

EX PIT 6EX PIT 6

R.L. = 17.85R.L. = 17.85

I.L. = 17.47I.L. = 17.47

900 x 900900 x 900

INLET PIT 11INLET PIT 11

R.L. = 18.70R.L. = 18.70

I.L. = 17.70I.L. = 17.70

300∅ OUTLET PIPE300∅ OUTLET PIPE

I.L. = 17.20I.L. = 17.20

HEADWALL 2 HEADWALL 2

EXISTINGEXISTING

PUMPHOUSEPUMPHOUSE

EX PIT 7EX PIT 7

R.L. = 17.97R.L. = 17.97

EX GPT 8EX GPT 8

R.L. = 17.95R.L. = 17.95

I.L. = 17.06I.L. = 17.06

300 WIDE X 200 DEEP GRATED300 WIDE X 200 DEEP GRATED

DRAIN, DEPRESSED 50mm. AT

600 x 600600 x 600

PIT 12PIT 12

R.L. = 18.20R.L. = 18.20

I.L. = 17.42I.L. = 17.42

600 x 600600 x 600

PIT 13PIT 13

R.L. = 18.10R.L. = 18.10

I.L. = 17.30I.L. = 17.30

EXISTING BUILDINGEXISTING BUILDING

FFL = 19.88FFL = 19.88

EXISTING HEADWALLEXISTING HEADWALL

TO BE REMOVEDTO BE REMOVED

EXISTING HEADWALLEXISTING HEADWALL

3 TO BE RETAINED3 TO BE RETAINED

EX HEADWALL 1EX HEADWALL 1

I.L. = 17.64I.L. = 17.64

KERB ONLYKERB ONLY

1500 x 15001500 x 1500

INLET PIT 14INLET PIT 14

R.L. = 19.05R.L. = 19.05

I.L. = 18.05I.L. = 18.05

900 x 900900 x 900

INLET PIT 10INLET PIT 10

R.L. = 19.00R.L. = 19.00

I.L. = 18.175I.L. = 18.175

R

L

1

9

.

5

0

R

L

1

9

.

5

0

R

L

1

9

.

2

0

R

L

1

9

.

2

0

R

L

1

9

.

2

0

R

L

1

9

.

2

0

R

L

1

8

.

9

0

R

L

1

8

.

9

0

R

L

1

8

.

9

0

R

L

1

8

.

9

0

R

L

1

9

.

1

8

R

L

1

9

.

1

8

R

L

1

9

.

1

2

R

L

1

9

.

1

2

R

L

1

8

.

6

0

R

L

1

8

.

6

0

R

L

1

8

.

6

0

R

L

1

8

.

6

0

R

L

1

8

.

5

0

R

L

1

8

.

5

0

R

L

1

8

.

5

0

R

L

1

8

.

5

0

R

L

1

8

.

4

5

R

L

1

8

.

4

5

R

L

1

8

.

7

0

R

L

1

8

.

7

0

R

L

1

8

.

5

0

R

L

1

8

.

5

0

R

L

1

8

.

5

1

5

R

L

1

8

.

5

1

5

R

L

1

8

.

0

0

R

L

1

8

.

0

0

R

L

1

8

.

2

0

R

L

1

8

.

2

0

R

L

1

8

.

1

5

R

L

1

8

.

1

5

R

L

1

8

.

1

0

R

L

1

8

.

1

0

R

L

1

8

.

1

5

R

L

1

8

.

1

5

R

L

1

7

.

9

5

R

L

1

7

.

9

5

R

L

1

9

.

1

5

R

L

1

9

.

1

5

R

L

1

8

.

3

0

R

L

1

8

.

3

0

R

L

1

9

.

5

0

R

L

1

9

.

5

0

R

L

1

9

.

4

8

1% FALL1% FALL

1% FALL1% FALL

1% FALL1% FALL

1% FALL1% FALL

R

L

1

9

.

0

0

R

L

1

9

.

0

0

R

L

1

9

.

0

0

R

L

1

9

.

0

0

TAPTAP

TAPTAP

TAPTAP

PITPIT

PITPIT

PITPIT

PITPIT

SWITCH SWITCH

BOARDBOARD

DIS

AB

LED

DIS

AB

LED

CONCRETE DRAINCONCRETE DRAIN

1

0

0

m

m

1

0

0

m

m

2

2

5

m

m

2

2

5

m

m

2

2

5

m

m

2

2

5

m

m

225mm∅225mm∅

225mm∅225mm∅

PITPIT

225mm∅225mm∅

2

2

5

m

m

2

2

5

m

m

1

8

.

5

1

8

.

5

1

9

.

5

1

9

.

5

1

8

.

5

1

8

.

5

1

8

.

5

1

8

.

5

1

8

.

5

1

8

.

5

2

0

2

0

1

9

1

9

1

9

1

9

1

9

1

9

1

8

1

7

.

5

1

8

1

8

1

7

1

7

100mm∅

100mm∅

375mm∅

375mm∅

375mm∅

375mm∅

300mm∅

300mm∅

300mm∅

300mm∅

100mm∅100mm∅

225∅225∅

TT

TT

TT

TT

TAPTAP

(20)

(20)

TAPTAP

(

1

9

.

5

)

(

1

9

.

5

)

900 x 900900 x 900

INLET PIT 9INLET PIT 9

R.L. = 19.48R.L. = 19.48

I.L. = 18.40I.L. = 18.40

EXISTING HEADWALLEXISTING HEADWALL

TO BE REMOVEDTO BE REMOVED

EXISTING PIT TO BEEXISTING PIT TO BE

REMOVEDREMOVED

1500 x 15001500 x 1500

SURCHARGE PIT 15SURCHARGE PIT 15

R.L. = 19.18R.L. = 19.18

I.L. = 18.06I.L. = 18.06

CONTAINSCONTAINS

ENVIROPODENVIROPOD

900 x 900

2x900 DIA BYPASS2x900 DIA BYPASS

PIPESPIPES

SURCHARGE PITSURCHARGE PIT

OVERLAND FLOWOVERLAND FLOW

DATEDATE

DESIGNED:DESIGNED: DATE:DATE:

DRAWN:DRAWN: CHECKED:CHECKED:

DRAWING:DRAWING: REVISION:REVISION:

REV.NoREV.No

COPYRIGHT. DRAWINGS ISSUED UNDER LICENSE BY DEMLAKIAN CONSULTING ENGINEERSCOPYRIGHT. DRAWINGS ISSUED UNDER LICENSE BY DEMLAKIAN CONSULTING ENGINEERS

REVISIONREVISION BYBY

cccc

(02) 9955 6122(02) 9955 6122

www.demlakian.com.auwww.demlakian.com.au

P.O. Box 6553 North Sydney 2059P.O. Box 6553 North Sydney 2059

E-mail: [email protected]: [email protected]

Level 2, 5 Ridge StreetLevel 2, 5 Ridge Street

North Sydney NSW 2060North Sydney NSW 2060

(02) 9955 4485(02) 9955 4485

Facsimile:Facsimile:

Telephone:Telephone:

ORIGINAL: A1 DWGORIGINAL: A1 DWGIntelligent Thinking in EngineeringIntelligent Thinking in Engineering

CLIENT:CLIENT:

TITLE:TITLE:

PROJECT:PROJECT:

NOTE:NOTE:

This drawing must be read in conjunction withThis drawing must be read in conjunction with

ALL other drawings for this project includingALL other drawings for this project including

but not limited to all construction notes.but not limited to all construction notes.

213025213025

D.W.D.W.

RALRAL

FEB 2013FEB 2013

D.W.D.W.

AUSTRALIAN CHRISTIAN COLLEGEAUSTRALIAN CHRISTIAN COLLEGE

69 Farm Road RIVERSTONE69 Farm Road RIVERSTONE

Lot 90 DP1224210Lot 90 DP1224210

LIPPMANN PARTNERSHIPLIPPMANN PARTNERSHIP

AUSTRALIAN CHRISTIAN COLLEGEAUSTRALIAN CHRISTIAN COLLEGE

ARCHITECT:ARCHITECT:

T/A Demlakian Consulting EngineersT/A Demlakian Consulting Engineers

ABN 42 651 771 142ABN 42 651 771 142

Demlakian Strata & Remedial Pty LimitedDemlakian Strata & Remedial Pty Limited

FOR DEVELOPMENTFOR DEVELOPMENT

APPLICATION SUBMISSIONAPPLICATION SUBMISSION

STORMWATER MANAGEMENT PLANSTORMWATER MANAGEMENT PLAN

SW02SW02 PP

STORMWATER MANAGEMENT PLANSTORMWATER MANAGEMENT PLAN

SCALE 1:200SCALE 1:200

EXISTING STORMWATER PIPEEXISTING STORMWATER PIPE

100∅100∅

EXISTING PIPE DIAMETER IN MMEXISTING PIPE DIAMETER IN MM

ALL PIPES TO BE ∅150 UPVC @ 1% FALL, TYPICAL U.N.O.ALL PIPES TO BE ∅150 UPVC @ 1% FALL, TYPICAL U.N.O.

INDICATES ITEMS ALREADY CONSTRUCTED ININDICATES ITEMS ALREADY CONSTRUCTED IN

ACCORDANCE WITH DRAWINGS BY HEALEY CASTLE &ACCORDANCE WITH DRAWINGS BY HEALEY CASTLE &

ASSOCIATES APPROVED BY COUNCIL (19.12.07)ASSOCIATES APPROVED BY COUNCIL (19.12.07)

FOR CONTINUATION OF PLAN SEE DRAWING 213025/SW03FOR CONTINUATION OF PLAN SEE DRAWING 213025/SW03

SHEET 1SHEET 1

PIT NUMBERPIT NUMBER PIT TYPEPIT TYPE PIT SIZEPIT SIZE INVERT LEVELINVERT LEVEL SURFACE LEVELSURFACE LEVEL

HEADWALL 1HEADWALL 1 EXISTINGEXISTING HEADWALLHEADWALL 17.6417.64 18.3018.30

INLET PIT 10INLET PIT 10 CONCRETECONCRETE 900x900900x900 18.17518.175 19.0019.00

PIT SCHEDULEPIT SCHEDULE

EX PIT 3EX PIT 3 CONCRETECONCRETE

EX PIT 4EX PIT 4 CONCRETECONCRETE

EX PIT 5EX PIT 5 CONCRETECONCRETE

EXISTINGEXISTING

EXISTINGEXISTING

EXISTINGEXISTING

-- 18.8018.80

-- 18.6518.65

17.6217.62 18.0018.00

PIT NUMBERPIT NUMBER PIT TYPEPIT TYPE PIT SIZEPIT SIZE INVERT LEVELINVERT LEVEL SURFACE LEVELSURFACE LEVEL

EX GPT 8EX GPT 8 GPTGPT EXISTINGEXISTING 17.0617.06 17.9517.95

INLET PIT 19INLET PIT 19 CONCRETECONCRETE 900x900900x900 -- 20.0520.05

PIT SCHEDULEPIT SCHEDULE

HEADWALL 2HEADWALL 2 CONCRETECONCRETE HEADWALLHEADWALL 17.2017.20 17.4017.40

EX PIT 6EX PIT 6 CONCRETECONCRETE EXISTINGEXISTING 17.4717.47 17.8517.85

EX PIT 7EX PIT 7 CONCRETECONCRETE EXISTINGEXISTING -- 17.9717.97

JUNCTION PIT 12JUNCTION PIT 12 CONCRETECONCRETE 900x900900x900 17.4217.42 18.2018.20

JUNCTION PIT 13JUNCTION PIT 13 CONCRETECONCRETE 900x900900x900 17.3017.30 18.1018.10

GRATED PIT 15GRATED PIT 15 CONCRETECONCRETE 1500x15001500x1500 18.0618.06 19.1819.18

SEALED PIT 17SEALED PIT 17 CONCRETECONCRETE 18.7118.71 20.3020.301500x15001500x1500

INLET PIT 14INLET PIT 14 CONCRETECONCRETE 18.0518.05 19.0519.05

INLET PIT 11INLET PIT 11 CONCRETECONCRETE 900x900900x900 17.7017.70 18.7018.70

1500x15001500x1500

INLET PIT 18INLET PIT 18 CONCRETECONCRETE 19.4019.40 20.4020.40900x900900x900

INLET PIT 9INLET PIT 9 CONCRETECONCRETE 900x900900x900 18.4018.40 19.4819.48

SEALED PIT 16SEALED PIT 16 CONCRETECONCRETE 18.5018.50 20.5720.571500x15001500x1500

INLET PIT 20INLET PIT 20 CONCRETECONCRETE 900x900900x900 -- 19.9719.97

INLET PIT 21INLET PIT 21 CONCRETECONCRETE 900x900900x900 -- 19.8819.88

INLET PIT 22INLET PIT 22 CONCRETECONCRETE 900x900900x900 -- 19.8019.80

INLET PIT 23INLET PIT 23 CONCRETECONCRETE 900x900900x900 -- 19.7019.70

INLET PIT 24INLET PIT 24 CONCRETECONCRETE 900x900900x900 -- 19.6019.60

INLET PIT 25INLET PIT 25 CONCRETECONCRETE 900x900900x900 -- 19.5019.50--

INLET PIT 26INLET PIT 26 CONCRETECONCRETE 600x600600x600 18.7018.70 19.5019.50

INLET PIT 27INLET PIT 27 CONCRETECONCRETE 600x600600x600 19.3519.35 20.2820.28

INLET PIT 28INLET PIT 28 CONCRETECONCRETE 600x600600x600 18.8018.80 19.6019.60

PIT NUMBERPIT NUMBER PIT TYPEPIT TYPE PIT SIZEPIT SIZE INVERT LEVELINVERT LEVEL SURFACE LEVELSURFACE LEVEL

PIT SCHEDULEPIT SCHEDULE

INLET PIT 29INLET PIT 29 CONCRETECONCRETE 900x900900x900 20.7020.70 21.5021.50

INLET PIT 30INLET PIT 30 CONCRETECONCRETE 900x900900x900 18.9018.90 19.7019.70

INLET PIT 31INLET PIT 31 CONCRETECONCRETE 900x900900x900 19.4519.4518.2018.20

INLET PIT 32INLET PIT 32 CONCRETECONCRETE 17.8517.85 19.1019.10

INLET PIT 33INLET PIT 33 CONCRETECONCRETE 17.5017.50 18.7518.75

INLET PIT 34INLET PIT 34 CONCRETECONCRETE 17.1417.14 18.4018.40

900x900900x900

900x900900x900

900x900900x900

INLET PIT 35INLET PIT 35 CONCRETECONCRETE -- 20.1320.13900x900900x900

INLET PIT 36INLET PIT 36 CONCRETECONCRETE -- 20.2020.20900x900900x900

INLET PIT 37INLET PIT 37 CONCRETECONCRETE -- 20.2720.27900x900900x900

INLET PIT 38INLET PIT 38 CONCRETECONCRETE 18.7018.70 20.6520.65900x900900x900

LL 30.04.1830.04.18 REVISED FOR DA SUBMISSIONREVISED FOR DA SUBMISSION RALRAL

MM 29.05.1829.05.18 LAYOUT REVISEDLAYOUT REVISED RALRAL

NN 06.06.1806.06.18 LAYOUT REVISEDLAYOUT REVISED RALRAL

PP 23.07.1823.07.18 REVISED FOR DA SUBMISSIONREVISED FOR DA SUBMISSION RALRAL

Page 14: RE: WATER MANAGEMENT REPORT FOR PROPOSED EXPANSION

DP1DP1

DP1DP1

DP1DP1

DP1DP1

DP1DP1

DP1DP1

DP1DP1

DP1DP1

∅225∅225

∅225∅225

∅225

∅225

∅225

∅225

∅300

∅300

∅300∅300

DP1DP1

DP1DP1

DP1DP1

DP1DP1

DP1DP1 DP1DP1

DP1DP1

DP1DP1

∅225∅225

DP1DP1

DP1DP1

DP1DP1

DP1DP1

∅225∅225

DP2DP2

DP2DP2

DP2DP2

∅225

∅225

∅225∅225

∅225

∅225

∅300

∅300

3

7

5

3

7

5

3

0

0

3

0

0

3

7

5

3

7

5

∅225∅225

∅300∅300

HATCHED AREAHATCHED AREA

INDICATES EXTENT OFINDICATES EXTENT OF

PROPOSED NEW BUILDINGPROPOSED NEW BUILDING

OV

ERLA

ND FLOW

OV

ERLA

ND FLOW

GRADE SURFACEGRADE SURFACE

AREAS TO DRAIN TOAREAS TO DRAIN TO

OVERLAND FLOW PATHOVERLAND FLOW PATH

HATCHED AREAHATCHED AREA

INDICATES NEWINDICATES NEW

DROP OFF AREADROP OFF AREA

4532

4532

KERB ONLY

KERB ONLY

KERB ONLY

KERB ONLY

5000x4000 GRATED INLET PIT5000x4000 GRATED INLET PIT

RL = 19.85 (APPROX)RL = 19.85 (APPROX)

IL = 18.85IL = 18.85

TWIN 900 DIA PIPESTWIN 900 DIA PIPES

900x900 HINGED900x900 HINGED

LOCKABLE CLASS DLOCKABLE CLASS D

GRATES (10 TOTAL)GRATES (10 TOTAL)

HATCHED AREA REPRESENTS 250 CUBIC METREHATCHED AREA REPRESENTS 250 CUBIC METRE

ONSITE DETENTION STORAGE TANK TO STRUCTURALONSITE DETENTION STORAGE TANK TO STRUCTURAL

ENGINEERS DETAIL BELOW CARPARK.ENGINEERS DETAIL BELOW CARPARK.

REFER TO DRAWING 213025/S05 FOR DETAILS.REFER TO DRAWING 213025/S05 FOR DETAILS.

RL = 20.30 - 19.50RL = 20.30 - 19.50

TWL = 19.43TWL = 19.43

IL = 18.30IL = 18.30

INLET GRATE 19INLET GRATE 19

R.L. = 20.05R.L. = 20.05

22E22E

FIRST FLUSHFIRST FLUSH

DIVERTORDIVERTOR

PROPOSED WATER TANKSPROPOSED WATER TANKS

PROVIDE 3 x 34,000 LITREPROVIDE 3 x 34,000 LITRE

INGROUND TANKS. REFERINGROUND TANKS. REFER

TO SCHEMATIC.TO SCHEMATIC.

300∅ OUTLET PIPE300∅ OUTLET PIPE

KERB ONLY

KERB ONLY

300 WIDE X 200 DEEP GRATED300 WIDE X 200 DEEP GRATED

DRAIN, DEPRESSED 50mm. ATDRAIN, DEPRESSED 50mm. AT

RL = 19.50RL = 19.50

1500 x 15001500 x 1500

SEALED PIT 17 SEALED PIT 17

R.L. = 20.30R.L. = 20.30

I.L. = 18.71I.L. = 18.71

1500 x 15001500 x 1500

SEALED PIT 16SEALED PIT 16

R.L. = 20.57R.L. = 20.57

I.L. = 18.50I.L. = 18.50

FFL = 20.750FFL = 20.750

KERB ONLY

KERB ONLY

KERB &

GUTTER

KERB &

GUTTER

KERB &

GUTTER

KERB &

GUTTER

KERB &

GUTTER

KERB &

GUTTER

KERB &

GUTTER

KERB &

GUTTER

KERBKERB

900 x 900900 x 900

INLET PIT 10INLET PIT 10

R.L. = 19.00R.L. = 19.00

I.L. = 18.175I.L. = 18.175

R

L

1

9

.

5

0

R

L

1

9

.

5

0

R

L

1

9

.

5

0

R

L

1

9

.

5

0

R

L

2

0

.

4

5

R

L

2

0

.

4

5

R

L

2

0

.

2

5

R

L

2

0

.

2

5

0.5%

FA

LL

0.5%

FA

LL

R

L

2

0

.

5

0

R

L

2

0

.

5

0

R

L

1

9

.

4

8

R

L

1

9

.

4

8

R

L

2

1

.

4

0

R

L

2

1

.

4

0

R

L

2

1

.

3

9

R

L

2

1

.

3

9

R

L

2

0

.

4

0

R

L

2

0

.

4

0

R

L

1

9

.

6

0

R

L

1

9

.

6

0

R

L

2

0

.

1

5

R

L

2

0

.

1

5

R

L

2

0

.

1

0

R

L

2

0

.

1

0

R

L

2

0

.

4

0

R

L

2

0

.

4

0

R

L

2

1

.

2

9

R

L

2

1

.

2

9

R

L

2

0

.

8

9

R

L

2

0

.

8

9

R

L

2

0

.4

9

R

L

2

0

.4

9

R

L

1

9

.

8

5

R

L

1

9

.

8

5

PRECAST BENDPRECAST BEND

TYP.TYP.

300 WIDE X 200 DEEP GRATED300 WIDE X 200 DEEP GRATED

DRAIN, DEPRESSED 50mm.DRAIN, DEPRESSED 50mm.

TAPTAP

TAPTAP

1

0

0

m

m

2

0

.

5

2

0

.

5

2

0

.

5

2

0

.

5

2

1

.

5

2

1

.

5

1

9

.

5

1

9

.

5

1

9

.

5

1

9

.

5

2

0

2

0

2

0

2

0

2

1

2

1

2

0

2

0

1

9

1

9

1

9

1

9

TT

TT

TT

TT

(

2

1

.

5

)

(

2

1

.

5

)

(

2

1

)

(

2

1

)

TAPTAP

267.151267.151

189°09'20"189°09'20"

(

2

0

)

(

2

0

)

(

2

0

.

5

)

(

2

0

.

5

)

(

2

1

.

5

)

(

2

1

.

5

)

(

2

0

)

(

2

0

)

(

2

1

)

(

2

1

)

(

2

2

)

(

2

2

)

(

2

0

.

5

)

(

2

0

.

5

)

(

2

1

.

5

)

(

2

1

.

5

)

(

2

0

)

(

2

0

)

(20)

(20)

(

1

9

.

5

)

(

1

9

.

5

)

(

1

9

.

5

)

(

1

9

.

5

)

(

2

1

)

(

2

1

)

(

2

2

)

(

2

2

)

(

2

0

)

(

2

0

)

80.065

80.065

99°08'20"

99°08'20"

TAPTAP

(

2

0

.

5

)

(

2

0

.

5

)

(

2

0

)

(

2

0

)

FIRST FLUSHFIRST FLUSH

DIVERTORDIVERTOR

R

L

2

0

.

6

0

R

L

2

0

.

6

0

R

L

2

0

.

6

0

R

L

2

0

.

6

0

FA

LL

FA

LL

FA

LL

FA

LL

900 x 900900 x 900

INLET PIT 18INLET PIT 18

R.L. = 20.40R.L. = 20.40

I.L. = 19.40I.L. = 19.40

EXTENT OF 150 HIGH BARRIER TOEXTENT OF 150 HIGH BARRIER TO

DIVERT OVERLAND FLOWDIVERT OVERLAND FLOW

EXTENT OF 150 HIGH BARRIER TOEXTENT OF 150 HIGH BARRIER TO

DIVERT OVERLAND FLOWDIVERT OVERLAND FLOW

KERBKERB

KERBKERB

KERBKERB

300 WIDE X 200 DEEP GRATED300 WIDE X 200 DEEP GRATED

DRAIN, DEPRESSED 50mm ATDRAIN, DEPRESSED 50mm AT

RL = 20.40RL = 20.40

300 WIDE X 200 DEEP GRATED300 WIDE X 200 DEEP GRATED

DRAIN, DEPRESSED 50mm ATDRAIN, DEPRESSED 50mm AT

RL = 20.10RL = 20.10

300 WIDE X 200 DEEP GRATED300 WIDE X 200 DEEP GRATED

DRAIN, DEPRESSED 50mm ATDRAIN, DEPRESSED 50mm AT

RL = 20.00RL = 20.00

R

L

2

0

.

5

0

R

L

2

0

.

5

0

FALLFALL

FALLFALL

O

V

E

R

L

A

N

D

O

V

E

R

L

A

N

D

F

L

O

W

F

L

O

W

FALLFALL

900 x 900900 x 900

INLET PIT 9INLET PIT 9

R.L. = 19.48R.L. = 19.48

I.L. = 18.40I.L. = 18.40

EARTH BARRIER TO DIRECTEARTH BARRIER TO DIRECT

SURFACE FLOW TO ON-SITESURFACE FLOW TO ON-SITE

DETENTION TANKDETENTION TANK

INLET GRATE 20INLET GRATE 20

R.L. = 19.97R.L. = 19.97

INLET GRATE 21INLET GRATE 21

R.L. = 19.88R.L. = 19.88

INLET GRATE 22INLET GRATE 22

R.L. = 19.80R.L. = 19.80

INLET GRATE 23INLET GRATE 23

R.L. = 19.70R.L. = 19.70

INLET GRATE 24INLET GRATE 24

R.L. = 19.60R.L. = 19.60

INLET GRATE 25INLET GRATE 25

R.L. = 19.50R.L. = 19.50

600 x 600600 x 600

INLET PIT 26INLET PIT 26

R.L. = 19.50R.L. = 19.50

I.L. = 18.70I.L. = 18.70

CONTAINSCONTAINS

ENVIROPODENVIROPOD

CONTAINSCONTAINS

ENVIROPODENVIROPOD

600 x 600600 x 600

INLET PIT 27INLET PIT 27

R.L. = 20.28R.L. = 20.28

I.L. = 19.35I.L. = 19.35

CONTAINSCONTAINS

ENVIROPODENVIROPOD

2x900 DIA BYPASS2x900 DIA BYPASS

PIPESPIPES

900 x 900900 x 900

INLET PIT 28INLET PIT 28

R.L. = 19.60R.L. = 19.60

I.L. = 18.80I.L. = 18.80

CONTAINSCONTAINS

ENVIROPODENVIROPOD

CONTAINSCONTAINS

ENVIROPODENVIROPOD

44

SW04SW04

INLET GRATE 35INLET GRATE 35

R.L. = 20.13R.L. = 20.13

INLET GRATE 36INLET GRATE 36

R.L. = 20.20R.L. = 20.20

INLET GRATE 37INLET GRATE 37

R.L. = 20.27R.L. = 20.27

900 x 900900 x 900

INLET PIT 38INLET PIT 38

R.L. = 20.65R.L. = 20.65

I.L. = 18.70I.L. = 18.70

DATEDATE

DESIGNED:DESIGNED: DATE:DATE:

DRAWN:DRAWN: CHECKED:CHECKED:

DRAWING:DRAWING: REVISION:REVISION:

REV.NoREV.No

COPYRIGHT. DRAWINGS ISSUED UNDER LICENSE BY DEMLAKIAN CONSULTING ENGINEERSCOPYRIGHT. DRAWINGS ISSUED UNDER LICENSE BY DEMLAKIAN CONSULTING ENGINEERS

REVISIONREVISION BYBY

cccc

(02) 9955 6122(02) 9955 6122

www.demlakian.com.auwww.demlakian.com.au

P.O. Box 6553 North Sydney 2059P.O. Box 6553 North Sydney 2059

E-mail: [email protected]: [email protected]

Level 2, 5 Ridge StreetLevel 2, 5 Ridge Street

North Sydney NSW 2060North Sydney NSW 2060

(02) 9955 4485(02) 9955 4485

Facsimile:Facsimile:

Telephone:Telephone:

ORIGINAL: A1 DWGORIGINAL: A1 DWGIntelligent Thinking in EngineeringIntelligent Thinking in Engineering

CLIENT:CLIENT:

TITLE:TITLE:

PROJECT:PROJECT:

NOTE:NOTE:

This drawing must be read in conjunction withThis drawing must be read in conjunction with

ALL other drawings for this project includingALL other drawings for this project including

but not limited to all construction notes.but not limited to all construction notes.

213025213025

D.W.D.W.

RALRAL

FEB 2013FEB 2013

D.W.D.W.

AUSTRALIAN CHRISTIAN COLLEGEAUSTRALIAN CHRISTIAN COLLEGE

69 Farm Road RIVERSTONE69 Farm Road RIVERSTONE

Lot 90 DP1224210Lot 90 DP1224210

LIPPMANN PARTNERSHIPLIPPMANN PARTNERSHIP

AUSTRALIAN CHRISTIAN COLLEGEAUSTRALIAN CHRISTIAN COLLEGE

ARCHITECT:ARCHITECT:

T/A Demlakian Consulting EngineersT/A Demlakian Consulting Engineers

ABN 42 651 771 142ABN 42 651 771 142

Demlakian Strata & Remedial Pty LimitedDemlakian Strata & Remedial Pty Limited

FOR DEVELOPMENTFOR DEVELOPMENT

APPLICATION SUBMISSIONAPPLICATION SUBMISSION

STORMWATER MANAGEMENT PLANSTORMWATER MANAGEMENT PLAN

SW03SW03 PP

STORMWATER MANAGEMENT PLANSTORMWATER MANAGEMENT PLAN

SCALE 1:200SCALE 1:200

EXISTING STORMWATER PIPEEXISTING STORMWATER PIPE

100∅100∅

EXISTING PIPE DIAMETER IN MMEXISTING PIPE DIAMETER IN MM

ALL PIPES TO BE ∅150 UPVC @ 1% FALL, TYPICAL U.N.O.ALL PIPES TO BE ∅150 UPVC @ 1% FALL, TYPICAL U.N.O.

ALL STORMWATER PITS TO CONTAIN ENVIROPODSALL STORMWATER PITS TO CONTAIN ENVIROPODS

INDICATES ITEMS ALREADY CONSTRUCTED ININDICATES ITEMS ALREADY CONSTRUCTED IN

ACCORDANCE WITH DRAWINGS BY HEALEY CASTLE &ACCORDANCE WITH DRAWINGS BY HEALEY CASTLE &

ASSOCIATES APPROVED BY COUNCIL (19.12.07)ASSOCIATES APPROVED BY COUNCIL (19.12.07)

FOR CONTINUATION OF PLAN SEE DRAWING 213025/SW02FOR CONTINUATION OF PLAN SEE DRAWING 213025/SW02

SHEET 2SHEET 2

LL 30.04.1830.04.18 REVISED FOR DA SUBMISSIONREVISED FOR DA SUBMISSION RALRAL

MM 29.05.1829.05.18 LAYOUT REVISEDLAYOUT REVISED RALRAL

NN 06.06.1806.06.18 LAYOUT REVISEDLAYOUT REVISED RALRAL

PP 23.07.1823.07.18 REVISED FOR DA SUBMISSIONREVISED FOR DA SUBMISSION RALRAL

Page 15: RE: WATER MANAGEMENT REPORT FOR PROPOSED EXPANSION

EXISTING PITEXISTING PIT

T.W.L. = 18.85T.W.L. = 18.85

600x600600x600

NEW PAVEMENTNEW PAVEMENT

NEW KERB & GUTTERNEW KERB & GUTTER

EXISTING PITEXISTING PIT

600x600600x600

EXISTING 900x300EXISTING 900x300

CULVERTCULVERT

SW2SW2

22

SECTIONSECTION

SCALE 1:20SCALE 1:20

T.W.L. = 18.85T.W.L. = 18.85

EXISTING 225∅ DRAINAGE PIPEEXISTING 225∅ DRAINAGE PIPE

FROM EXISTING PITFROM EXISTING PIT

50005000

186

186

MAX OVERLAND FLOW WATER LEVELMAX OVERLAND FLOW WATER LEVEL

SW2SW2

11

SECTIONSECTION

SCALE 1:20SCALE 1:20

18.5018.5018.5018.50

18.4018.40

18.4018.40

300300

EXISTING 900x300EXISTING 900x300

CULVERTCULVERT

EXISTING DRIVEWAYEXISTING DRIVEWAY

100 HIGH SPEED HUMP100 HIGH SPEED HUMP

TO CARPARK ENTRANCETO CARPARK ENTRANCE

AS BUILTAS BUILT

100

100

300300300300 300300

RECONSTRUCT DRIVEWAYRECONSTRUCT DRIVEWAY

NEW PAVINGNEW PAVING

SW2SW2

33

SECTIONSECTION

SCALE 1:20SCALE 1:20

NEW KERB & GUTTERNEW KERB & GUTTER

NEW BUS SHELTERNEW BUS SHELTER

PAVEMENTPAVEMENT

900 x 300 BOX900 x 300 BOX

CULVERTCULVERT

FA

LL

FA

LL

EXTEND EXISTINGEXTEND EXISTING

900 x 300 BOX900 x 300 BOX

CULVERT BELOWCULVERT BELOW

NEW PAVEMENTNEW PAVEMENT

RL 19.85RL 19.85

SW2SW2

44

SECTIONSECTION

SCALE 1:20SCALE 1:20

IL 18.85IL 18.85

4000 x 5000 GRATED INLET4000 x 5000 GRATED INLET

INTERMEDIATE SUPPORTINTERMEDIATE SUPPORT

BEAMSBEAMS

INTERMEDIATE SUPPORTINTERMEDIATE SUPPORT

BEAMSBEAMS1

:

2

0

F

A

L

L

1

:

2

0

F

A

L

L

1

:

2

0

F

A

L

L

1

:

2

0

F

A

L

L

5000 x 20005000 x 2000

2

x

9

0

0

2

x

9

0

0

1:200 FALL

1:200 FALL

STORMWATER DETAILSSTORMWATER DETAILS

SW4SW4 NN

DATEDATE

DESIGNED:DESIGNED: DATE:DATE:

DRAWN:DRAWN: CHECKED:CHECKED:

DRAWING:DRAWING: REVISION:REVISION:

REV.NoREV.No

COPYRIGHT. DRAWINGS ISSUED UNDER LICENSE BY DEMLAKIAN CONSULTING ENGINEERSCOPYRIGHT. DRAWINGS ISSUED UNDER LICENSE BY DEMLAKIAN CONSULTING ENGINEERS

REVISIONREVISION BYBY

cccc

(02) 9955 6122(02) 9955 6122

www.demlakian.com.auwww.demlakian.com.au

P.O. Box 6553 North Sydney 2059P.O. Box 6553 North Sydney 2059

E-mail: [email protected]: [email protected]

Level 2, 5 Ridge StreetLevel 2, 5 Ridge Street

North Sydney NSW 2060North Sydney NSW 2060

(02) 9955 4485(02) 9955 4485

Facsimile:Facsimile:

Telephone:Telephone:

ORIGINAL: A1 DWGORIGINAL: A1 DWGIntelligent Thinking in EngineeringIntelligent Thinking in Engineering

CLIENT:CLIENT:

TITLE:TITLE:

PROJECT:PROJECT:

NOTE:NOTE:

This drawing must be read in conjunction withThis drawing must be read in conjunction with

ALL other drawings for this project includingALL other drawings for this project including

but not limited to all construction notes.but not limited to all construction notes.

213025213025

D.W.D.W.

RALRAL

FEB 2013FEB 2013

D.W.D.W.

AUSTRALIAN CHRISTIAN COLLEGEAUSTRALIAN CHRISTIAN COLLEGE

69 Farm Road RIVERSTONE69 Farm Road RIVERSTONE

Lot 90 DP1224210Lot 90 DP1224210

LIPPMANN PARTNERSHIPLIPPMANN PARTNERSHIP

AUSTRALIAN CHRISTIAN COLLEGEAUSTRALIAN CHRISTIAN COLLEGE

ARCHITECT:ARCHITECT:

T/A Demlakian Consulting EngineersT/A Demlakian Consulting Engineers

ABN 42 651 771 142ABN 42 651 771 142

Demlakian Strata & Remedial Pty LimitedDemlakian Strata & Remedial Pty Limited

FOR DEVELOPMENTFOR DEVELOPMENT

APPLICATION SUBMISSIONAPPLICATION SUBMISSION

SHEET 1SHEET 1

HH 14.09.1514.09.15 FOR DA SUBMISSIONFOR DA SUBMISSION RALRAL

JJ 23.04.1823.04.18 REVISED FOR DA SUBMISSIONREVISED FOR DA SUBMISSION RALRAL

MM 30.05.1830.05.18 REVISED FOR DA SUBMISSIONREVISED FOR DA SUBMISSION RALRAL

NN 23.07.1823.07.18 REVISED FOR DA SUBMISSIONREVISED FOR DA SUBMISSION RALRAL

Page 16: RE: WATER MANAGEMENT REPORT FOR PROPOSED EXPANSION

TANK REFILLER CONTROL SWITCHTANK REFILLER CONTROL SWITCH

LOW WATER EMERGENCY CUT OFFLOW WATER EMERGENCY CUT OFF

HIGH PRESSUREHIGH PRESSURE

SUBMERSIBLE PUMPSUBMERSIBLE PUMP

STORMWATERSTORMWATER

LINELINE

IRRIGA

TION

IRRIGA

TION

150

150

MIN

MIN

SCALE 1:50SCALE 1:50

RAINWATER REUSE CYCLE RAINWATER REUSE CYCLE

OVERFLOW TOOVERFLOW TO

BIORETENTIONBIORETENTION

RAINWATER TANKRAINWATER TANK

WATER METERWATER METER

WITH BACK FLOWWITH BACK FLOW

PREVENTIONPREVENTION

REMOTE TANKREMOTE TANK

ACCESSACCESS

(FIRST FLUSH DEVICE)(FIRST FLUSH DEVICE)

GROUND LEVELGROUND LEVEL

DOWNPIPEDOWNPIPE

AIR GAPAIR GAP

GUTTER SCREENGUTTER SCREEN

(OPTIONAL)(OPTIONAL)

GUTTERGUTTER

TOILETS

TOILETS

FILTER

FILTER

SCALE 1:10SCALE 1:10

6mm S.S. PLATE6mm S.S. PLATE

WITH 4M10 S.S.WITH 4M10 S.S.

DYNABOLTSDYNABOLTS

∅260 ORIFICE WITH SHARP∅260 ORIFICE WITH SHARP

EDGES MACHINED TO 0.5mmEDGES MACHINED TO 0.5mm

ACCURACYACCURACY

ORIFICE PLATE DETAILORIFICE PLATE DETAIL

400

400

IL 18.43IL 18.43

400400

SCALE 1:10SCALE 1:10

FLEXIBLE SHEET PVCFLEXIBLE SHEET PVC

(NICHOLAS FLEX-FLAP OR(NICHOLAS FLEX-FLAP OR

APPROVED EQUIVALENT)APPROVED EQUIVALENT)

FLAP VALVEFLAP VALVE

MOUNTINGMOUNTING

BRACKETBRACKET

R

1

2

5

R

1

2

5

5

0

O

V

E

R

F

L

A

P

5

0

O

V

E

R

F

L

A

P

900x900 ACCESS900x900 ACCESS

COVERCOVER

900

900

18001800

57500

57500

58505850

1120011200

55505550 150150

20020037503750150150

4000

4000

150

150

900x900 COVER PLATE900x900 COVER PLATE

OVER TOP OFOVER TOP OF

CARTRIDGE BAYCARTRIDGE BAY

ENERGY DISSIPATORENERGY DISSIPATOR

150mm DEEP VOID FOR150mm DEEP VOID FOR

STORMFILTER FITOUTSTORMFILTER FITOUT

ALL INFLOW TOALL INFLOW TO

STORMFILTERSSTORMFILTERS

FLOW FROM STORMFILTERFLOW FROM STORMFILTER

UNDERDRAINS(S). TO GO TOUNDERDRAINS(S). TO GO TO

OUTLET PIT AND BYPASSOUTLET PIT AND BYPASS

ORIFICE PLATEORIFICE PLATE

150 DIA SW PIPES WITH NON-RETURN150 DIA SW PIPES WITH NON-RETURN

VALVES TO DRAIN DETENTION TANKVALVES TO DRAIN DETENTION TANK

DRY. SUPPLIED AND INSTALLED BYDRY. SUPPLIED AND INSTALLED BY

OTHERS. INVERT SET TO 150 ABOVEOTHERS. INVERT SET TO 150 ABOVE

INVERT LEVEL OF FALSE FLOORINVERT LEVEL OF FALSE FLOOR

FULL HEIGHT WALLFULL HEIGHT WALL

STORMFILTERSTORMFILTER

CHAMBERCHAMBER

STORMFILTER SLOTSTORMFILTER SLOT

/ WEIR OVERFLOW/ WEIR OVERFLOW

LOWER HEIGHT WALLLOWER HEIGHT WALL

TO CONVEY FLOWTO CONVEY FLOW

HIGH EARLY DISCHARGEHIGH EARLY DISCHARGE

CHAMBER WEIR AT RL = 19.10CHAMBER WEIR AT RL = 19.10

150 DIA SW PIPE WITH NON-RETURN150 DIA SW PIPE WITH NON-RETURN

VALVE TO DRAIN DETENTION TANKVALVE TO DRAIN DETENTION TANK

DRY AT INVERT LEVEL OF EXTENDEDDRY AT INVERT LEVEL OF EXTENDED

STORAGE. SUPPLIED AND INSTALLEDSTORAGE. SUPPLIED AND INSTALLED

BY OTHERSBY OTHERS

ORIFICE SIZE TO BE MANUALLYORIFICE SIZE TO BE MANUALLY

ADJUSTED AFTER DEDUCTINGADJUSTED AFTER DEDUCTING

STORMFILTER FLOW FROM PSD.STORMFILTER FLOW FROM PSD.

PROTECT ORIFICE WITH SCREEN.PROTECT ORIFICE WITH SCREEN.

OUTLET PIPE

OUTLET PIPE

EXTENDEDEXTENDED

DETENTIONDETENTION

STORAGESTORAGE

150150

AA

--

SCALE 1:50SCALE 1:50

EXTENDED DETENTION STORAGE TANKEXTENDED DETENTION STORAGE TANK

FULL HEIGHT WALLFULL HEIGHT WALL

R

L

1

8

.

8

7

R

L

1

8

.

8

7

R

L

1

8

.

8

7

R

L

1

8

.

8

7

R

L

1

8

.

3

0

R

L

1

8

.

3

0

R

L

1

8

.

3

0

R

L

1

8

.

3

0

150150

RL 19.50RL 19.50

900 SQUARE HINGED900 SQUARE HINGED

LOCKABLE CLASS 'D'LOCKABLE CLASS 'D'

GRATES TYP.GRATES TYP.

150150

RL 18.30RL 18.30

1

:1

0

0

M

IN

1

:1

0

0

M

IN

F

A

L

L

T

O

G

R

A

T

E

F

A

L

L

T

O

G

R

A

T

E

--

AA

SECTIONSECTION

SCALE 1:20SCALE 1:20

RL 19.50RL 19.50

1

:1

0

0

M

IN

1

:1

0

0

M

IN

F

A

L

L

T

O

G

R

A

T

E

F

A

L

L

T

O

G

R

A

T

E

TWL 19.43TWL 19.43

ENERGY DISSIPATORENERGY DISSIPATOR

BELOW PIPEBELOW PIPE

3550x2000x150 DEEP3550x2000x150 DEEP

VOID FOR STORMFILTERVOID FOR STORMFILTER

FITOUTFITOUT

INVERT O F SLOT TO MATCH STORMFILTERINVERT O F SLOT TO MATCH STORMFILTER

REQUIREMENTS, TYPICALLY 540mmREQUIREMENTS, TYPICALLY 540mm

(STANDARD) ABOVE FALSE FLOOR(STANDARD) ABOVE FALSE FLOOR

1

:1

0

0

M

IN

1

:1

0

0

M

IN

F

A

L

L

T

O

G

R

A

T

E

F

A

L

L

T

O

G

R

A

T

E

250250

300

300

200

200

600

600

900 SQUARE HINGED900 SQUARE HINGED

LOCKABLE CLASS 'D'LOCKABLE CLASS 'D'

GRATES TYP.GRATES TYP.

HIGH EARLYHIGH EARLY

DISCHARGE CHAMBERDISCHARGE CHAMBER

WEIR AT RL = 19.10WEIR AT RL = 19.10

OPENOPEN

SEALED HOOD TO CONTAINSEALED HOOD TO CONTAIN

FLOATABLES INCLUDING OILFLOATABLES INCLUDING OIL

80

80

IL = 18.50IL = 18.50

STORMWATER DETAILSSTORMWATER DETAILS

SW5SW5 NN

DATEDATE

DESIGNED:DESIGNED: DATE:DATE:

DRAWN:DRAWN: CHECKED:CHECKED:

DRAWING:DRAWING: REVISION:REVISION:

REV.NoREV.No

COPYRIGHT. DRAWINGS ISSUED UNDER LICENSE BY DEMLAKIAN CONSULTING ENGINEERSCOPYRIGHT. DRAWINGS ISSUED UNDER LICENSE BY DEMLAKIAN CONSULTING ENGINEERS

REVISIONREVISION BYBY

cccc

(02) 9955 6122(02) 9955 6122

www.demlakian.com.auwww.demlakian.com.au

P.O. Box 6553 North Sydney 2059P.O. Box 6553 North Sydney 2059

E-mail: [email protected]: [email protected]

Level 2, 5 Ridge StreetLevel 2, 5 Ridge Street

North Sydney NSW 2060North Sydney NSW 2060

(02) 9955 4485(02) 9955 4485

Facsimile:Facsimile:

Telephone:Telephone:

ORIGINAL: A1 DWGORIGINAL: A1 DWGIntelligent Thinking in EngineeringIntelligent Thinking in Engineering

CLIENT:CLIENT:

TITLE:TITLE:

PROJECT:PROJECT:

NOTE:NOTE:

This drawing must be read in conjunction withThis drawing must be read in conjunction with

ALL other drawings for this project includingALL other drawings for this project including

but not limited to all construction notes.but not limited to all construction notes.

213025213025

D.W.D.W.

RALRAL

FEB 2013FEB 2013

D.W.D.W.

AUSTRALIAN CHRISTIAN COLLEGEAUSTRALIAN CHRISTIAN COLLEGE

69 Farm Road RIVERSTONE69 Farm Road RIVERSTONE

Lot 90 DP1224210Lot 90 DP1224210

LIPPMANN PARTNERSHIPLIPPMANN PARTNERSHIP

AUSTRALIAN CHRISTIAN COLLEGEAUSTRALIAN CHRISTIAN COLLEGE

ARCHITECT:ARCHITECT:

T/A Demlakian Consulting EngineersT/A Demlakian Consulting Engineers

ABN 42 651 771 142ABN 42 651 771 142

Demlakian Strata & Remedial Pty LimitedDemlakian Strata & Remedial Pty Limited

FOR DEVELOPMENTFOR DEVELOPMENT

APPLICATION SUBMISSIONAPPLICATION SUBMISSION

SHEET 2SHEET 2

CONSTRUCTION NOTES - SITE STABILISATION ACCESSCONSTRUCTION NOTES - SITE STABILISATION ACCESS

STRIP TOPSOIL & LEVEL SITE.STRIP TOPSOIL & LEVEL SITE.

COMPACT SUBGRADE.COMPACT SUBGRADE.

COVER AREA WITH NEEDLE-PUNCHED GEOTEXTILE OR 30mmCOVER AREA WITH NEEDLE-PUNCHED GEOTEXTILE OR 30mm

AGGREGATE. MINIMUM LENGTH 15m OR TO BUILDINGAGGREGATE. MINIMUM LENGTH 15m OR TO BUILDING

ALIGNMENT. MINIMUM WIDTH 3m.ALIGNMENT. MINIMUM WIDTH 3m.

CONSTRUCT HUMP IMMEDIATELY WITHIN BOUNDARY TOCONSTRUCT HUMP IMMEDIATELY WITHIN BOUNDARY TO

DIVERT WATER TO A SEDIMENT FENCE OR SEDIMENT TRAP.DIVERT WATER TO A SEDIMENT FENCE OR SEDIMENT TRAP.

1.1.

2.2.

3.3.

4.4.

200 M

IN.

200 M

IN.

STABILISED SITE ACCESSSTABILISED SITE ACCESS

RUNOFF DIRECTED TORUNOFF DIRECTED TO

SEDIMENT TRAP / FENCESEDIMENT TRAP / FENCE

300 M

IN.

300 M

IN.

M

I

N

.

W

I

D

T

H

3

M

E

T

R

E

S

M

I

N

.

W

I

D

T

H

3

M

E

T

R

E

S

CONSTRUCTION SITECONSTRUCTION SITE

M

I

N

.

L

E

N

G

T

H

1

5

M

E

T

R

E

S

M

I

N

.

L

E

N

G

T

H

1

5

M

E

T

R

E

S

P

R

O

P

E

R

T

Y

B

O

U

N

D

A

R

Y

P

R

O

P

E

R

T

Y

B

O

U

N

D

A

R

Y

ALL EROSION & SEDIMENT CONTROL MEASURES SHALL BE MAINTAINED ASALL EROSION & SEDIMENT CONTROL MEASURES SHALL BE MAINTAINED AS

SHOWN ON THE DRAWINGS.SHOWN ON THE DRAWINGS.

EROSION & SEDIMENT CONTROL NOTESEROSION & SEDIMENT CONTROL NOTES

THE TEMPORARY SEDIMENT TRAP PIT SHALL BE CLEANED REGULARLY. INTHE TEMPORARY SEDIMENT TRAP PIT SHALL BE CLEANED REGULARLY. IN

THE EVENT THE GEOTEXTILE FILTER BECOMES CLOGGED DURINGTHE EVENT THE GEOTEXTILE FILTER BECOMES CLOGGED DURING

DEWATERING OF THE EXCAVATION, PUMPING SHALL BE STOPPED AND THEDEWATERING OF THE EXCAVATION, PUMPING SHALL BE STOPPED AND THE

FILTER CLEANED OR RENEWED.FILTER CLEANED OR RENEWED.

DUST SHALL BE CONTROLLED BY REGULAR MOISTENING OF EXCAVATEDDUST SHALL BE CONTROLLED BY REGULAR MOISTENING OF EXCAVATED

SERVICES AND STOCKPILES.SERVICES AND STOCKPILES.

THE TRUCK SHAKER SHALL BE REGULARLY CLEANED BY LIFTING,THE TRUCK SHAKER SHALL BE REGULARLY CLEANED BY LIFTING,

DISLODGING & REMOVING SPOIL.DISLODGING & REMOVING SPOIL.

4.4.

3.3.

1.1.

2.2.

RAINWATER RE-USE SYSTEM NOTES:RAINWATER RE-USE SYSTEM NOTES:

1.1. RAINWATER SUPPLY PLUMBING TO BE CONNECTEDRAINWATER SUPPLY PLUMBING TO BE CONNECTED

TO ALL TOILETS AND ALL TO ALL TOILETS AND ALL EXTERNAL GARDEN EXTERNAL GARDEN TAPS.TAPS.

2.2. TOWNWATER CONNECTION TO RAINWATER TANK TOTOWNWATER CONNECTION TO RAINWATER TANK TO

BE TO THE SATISFACTION OF SYDNEY WATER. THISBE TO THE SATISFACTION OF SYDNEY WATER. THIS

MAY REQUIRE PROVISION OF:MAY REQUIRE PROVISION OF:

a. PERMANENT AIR GAP.a. PERMANENT AIR GAP.

b. A BACKFLOW PREVENTION DEVICE.b. A BACKFLOW PREVENTION DEVICE.

c. NO DIRECT CONNECTION BETWEEN c. NO DIRECT CONNECTION BETWEEN

TOWN WATER SUPPLY AND THE TOWN WATER SUPPLY AND THE

RAIN WATER SUPPLY.RAIN WATER SUPPLY.

d. AN APPROVED STOP VALVE AND/OR d. AN APPROVED STOP VALVE AND/OR

PRESSURE LIMITING VALVE AT PRESSURE LIMITING VALVE AT

THE RAINWATER TANK.THE RAINWATER TANK.

3.3. PROVIDE AT LEAST ONE (1) EXTERNAL HOSE COCK ONPROVIDE AT LEAST ONE (1) EXTERNAL HOSE COCK ON

THE TOWN WATER SUPPLY FOR FIRE FIGHTING.THE TOWN WATER SUPPLY FOR FIRE FIGHTING.

4.4. PROVIDE APPROPRIATE FLOAT VALVES PROVIDE APPROPRIATE FLOAT VALVES AND/ORAND/OR

SOLENOID VALVES TO CONTROL TOWN WATERSOLENOID VALVES TO CONTROL TOWN WATER

SUPPLY INLET TO TANK IN ORDER TO ACHIEVESUPPLY INLET TO TANK IN ORDER TO ACHIEVE

TOP-UP TO 25% OF TOP-UP TO 25% OF RETENTION CAPACITY.RETENTION CAPACITY.

5.5. ALL PLUMBING WORKS ARE TO BE CARRIED OUT BYALL PLUMBING WORKS ARE TO BE CARRIED OUT BY

LICENSED PLUMBERS IN ACCORDANCE WITHLICENSED PLUMBERS IN ACCORDANCE WITH

AS3500.1 NATIONAL PLUMBING AND DRAINAGE CODE.AS3500.1 NATIONAL PLUMBING AND DRAINAGE CODE.

6.6. PRESSURE PUMP ELECTRICAL CONNECTION TO BEPRESSURE PUMP ELECTRICAL CONNECTION TO BE

CARRIED OUT BY LICENSED ELECTRICIAN.CARRIED OUT BY LICENSED ELECTRICIAN.

7.7. PIPE MATERIALS FOR RAINWATER SUPPLY PLUMBINGPIPE MATERIALS FOR RAINWATER SUPPLY PLUMBING

ARE TO BE APPROVED MATERIALS TO AS3500 PART 1ARE TO BE APPROVED MATERIALS TO AS3500 PART 1

SECTION 2 AND TO BE CLEARLY AND PERMANETLYSECTION 2 AND TO BE CLEARLY AND PERMANETLY

IDENTIFIED "RAINWATER". THIS MAY BE ACHIEVED FORIDENTIFIED "RAINWATER". THIS MAY BE ACHIEVED FOR

BELOW GROUND PIPES USING IDENTIFICATION TAPEBELOW GROUND PIPES USING IDENTIFICATION TAPE

(MADE IN ACCORDANCE WITH AS2648) AND FOR(MADE IN ACCORDANCE WITH AS2648) AND FOR

ABOVE GROUND PIPES BY USING ADHESIVEABOVE GROUND PIPES BY USING ADHESIVE

PIPEMARKERS (MADE IN ACCORDANCE WITH AS1345).PIPEMARKERS (MADE IN ACCORDANCE WITH AS1345).

8.8. EVERY RAINWATER SUPPLY OUTLET POINT AND THEEVERY RAINWATER SUPPLY OUTLET POINT AND THE

RAINWATER TANK ARE TO BE LABELLEDRAINWATER TANK ARE TO BE LABELLED

"RAINWATER" ON A METALLIC SIGN IN ACCORDANCE"RAINWATER" ON A METALLIC SIGN IN ACCORDANCE

WITH AS1319.WITH AS1319.

9.9. ALL INLETS AND OUTLETS TO THE RAINWATER TANKALL INLETS AND OUTLETS TO THE RAINWATER TANK

ARE TO HAVE SUITABLE MEASURES PROVIDED TOARE TO HAVE SUITABLE MEASURES PROVIDED TO

PREVENT MOSQUITO AND VERMIN ENTRY.PREVENT MOSQUITO AND VERMIN ENTRY.

10.10. ALL WORK SHALL BE IN ACCORDANCE WITH COUNCILALL WORK SHALL BE IN ACCORDANCE WITH COUNCIL

REQUIREMENTS.REQUIREMENTS.

d)d)

c)c)

f)f)

e)e)

3.3.

ENSURE REHABILITATED LANDS HAVE EFFECTIVELY REDUCED THEENSURE REHABILITATED LANDS HAVE EFFECTIVELY REDUCED THE

EROSION HAZARD AND TO INITIATE UPGRADING OR REPAIR ASEROSION HAZARD AND TO INITIATE UPGRADING OR REPAIR AS

APPROPRIATE;APPROPRIATE;

MAINTAIN EROSION AND SEDIMENT CONTROL MEASURES IN A FULLYMAINTAIN EROSION AND SEDIMENT CONTROL MEASURES IN A FULLY

FUNCTIONING CONDITION UNTIL ALL EARTHWORK ACTIVITIES AREFUNCTIONING CONDITION UNTIL ALL EARTHWORK ACTIVITIES ARE

COMPLETED AND THE SITE IS REHABILITATED; ANDCOMPLETED AND THE SITE IS REHABILITATED; AND

REMOVE TRAPPED SEDIMENT WHENEVER LESS THAN DESIGNREMOVE TRAPPED SEDIMENT WHENEVER LESS THAN DESIGN

CAPACITY REMAINS WITHIN THE STRUCTURE;CAPACITY REMAINS WITHIN THE STRUCTURE;

AS A PART OF THE STATUTORY "DILIGENCE AND CARE"AS A PART OF THE STATUTORY "DILIGENCE AND CARE"

RESPONSIBILITIES, THE SITE SUPERINTENDENT WILL KEEP A LOG BOOK,RESPONSIBILITIES, THE SITE SUPERINTENDENT WILL KEEP A LOG BOOK,

MAKING ENTRIES AT LEAST WEEKLY, IMMEDIATELY BEFORE FORECASTMAKING ENTRIES AT LEAST WEEKLY, IMMEDIATELY BEFORE FORECAST

RAIN AND AFTER RAINFALL. ENTRIES WILL INCLUDE:RAIN AND AFTER RAINFALL. ENTRIES WILL INCLUDE:

REMOVE TEMPORARY SOIL CONSERVATION STRUCTURES AS THE LASTREMOVE TEMPORARY SOIL CONSERVATION STRUCTURES AS THE LAST

ACTIVITY IN THE REHABILITATION PROGRAM.ACTIVITY IN THE REHABILITATION PROGRAM.

A.A.

2.2.

3.3.

1.1.

5.5.

4.4.

1.1.

6.6.

B.B.

CONSTRUCT EARTH BANKS & CUT-OFF DRAINS TO DIRECT OVERLANDCONSTRUCT EARTH BANKS & CUT-OFF DRAINS TO DIRECT OVERLAND

FLOW TO THE DESIGNATED OUTLET PIT.FLOW TO THE DESIGNATED OUTLET PIT.

INSTALL ALL BARRIER FENCING TO EXCLUDE ACCESS TO THEINSTALL ALL BARRIER FENCING TO EXCLUDE ACCESS TO THE

NOMINATED RESTRICTED AREAS.NOMINATED RESTRICTED AREAS.

CONSTRUCT STABILISED SITE ACCESSES.CONSTRUCT STABILISED SITE ACCESSES.

CONSTRUCT EARTH BANKS AND CUT-OFF DRAINS TO DIRECT OVERLANDCONSTRUCT EARTH BANKS AND CUT-OFF DRAINS TO DIRECT OVERLAND

FLOW BEYOND THE SITE.FLOW BEYOND THE SITE.

SITE INSPECTION MAINTENANCE CONDITIONSSITE INSPECTION MAINTENANCE CONDITIONS

UNDERTAKE WORKS ACCORDING TO THE ENGINEERING PLANS.UNDERTAKE WORKS ACCORDING TO THE ENGINEERING PLANS.

STRIP AND STOCKPILE TOPSOIL FROM THOSE LANDS TO BE EXPOSED TOSTRIP AND STOCKPILE TOPSOIL FROM THOSE LANDS TO BE EXPOSED TO

CONSTRUCTION ACTIVITIES.CONSTRUCTION ACTIVITIES.

b)b)

c)c)

d)d)

a)a)

e)e)

THE CONDITION OF ANY SOIL AND WATER MANAGEMENT WORKS;THE CONDITION OF ANY SOIL AND WATER MANAGEMENT WORKS;

THE NEED FOR DUST PREVENTION STRATEGIES; ANDTHE NEED FOR DUST PREVENTION STRATEGIES; AND

ANY REMEDIAL WORKS TO BE UNDERTAKEN.ANY REMEDIAL WORKS TO BE UNDERTAKEN.

THE CONDITION OF VEGETATION AND ANY NEED TO IRRIGATE;THE CONDITION OF VEGETATION AND ANY NEED TO IRRIGATE;

THE BOOK WILL BE KEPT ON-SITE AND MADE AVAILABLE TO ANYTHE BOOK WILL BE KEPT ON-SITE AND MADE AVAILABLE TO ANY

AUTHORISED PERSON ON REQUEST. IT WILL BE GIVEN TO THE PROJECTAUTHORISED PERSON ON REQUEST. IT WILL BE GIVEN TO THE PROJECT

MANAGER AT THE CONCLUSION OF WORKS.MANAGER AT THE CONCLUSION OF WORKS.

THE VOLUME AND INTENSITY OF ANY RAINFALL EVENTS;THE VOLUME AND INTENSITY OF ANY RAINFALL EVENTS;

a)a)

2.2.

b)b)

ENSURE THAT DRAINS OPERATE PROPERLY AND TO EFFECT ANYENSURE THAT DRAINS OPERATE PROPERLY AND TO EFFECT ANY

NECESSARY REPAIRS;NECESSARY REPAIRS;

REMOVE SPILLED SAND OR OTHER MATERIALS FROM HAZARD AREAS,REMOVE SPILLED SAND OR OTHER MATERIALS FROM HAZARD AREAS,

INCLUDING LANDS CLOSER THAN FIVE METRES FROM AREAS OFINCLUDING LANDS CLOSER THAN FIVE METRES FROM AREAS OF

LIKELY CONCENTRATED OR HIGH VELOCITY FLOWS ESPECIALLYLIKELY CONCENTRATED OR HIGH VELOCITY FLOWS ESPECIALLY

WATERWAYS AND PAVED AREAS;WATERWAYS AND PAVED AREAS;

THE SITE SUPERINTENDENT WILL INSPECT THE SITE AT LEAST WEEKLYTHE SITE SUPERINTENDENT WILL INSPECT THE SITE AT LEAST WEEKLY

AND WILL:AND WILL:

WASTE BINS WILL BE EMPTIED AS NECESSARY. DISPOSAL OF WASTEWASTE BINS WILL BE EMPTIED AS NECESSARY. DISPOSAL OF WASTE

WILL BE IN A MANNER APPROVED BY THE SITE SUPERINTENDENT.WILL BE IN A MANNER APPROVED BY THE SITE SUPERINTENDENT.

CONSTRUCTION SEQUENCECONSTRUCTION SEQUENCE

SOIL & WATER MANAGEMENT PLAN NOTESSOIL & WATER MANAGEMENT PLAN NOTES

GG 23.04.1823.04.18 TANK LAYOUT REVISEDTANK LAYOUT REVISED RALRAL

HH 30.04.1830.04.18 TANK LAYOUT REVISEDTANK LAYOUT REVISED RALRAL

MM 30.05.1830.05.18 TANK LAYOUT REVISEDTANK LAYOUT REVISED RALRAL

NN 23.07.1823.07.18 REVISED FOR DA SUBMISSIONREVISED FOR DA SUBMISSION RALRAL

Page 17: RE: WATER MANAGEMENT REPORT FOR PROPOSED EXPANSION

SEDIMENT AND EROSIONSEDIMENT AND EROSION

CONTROL FENCECONTROL FENCE

TRUCK SHAKER. WASHTRUCK SHAKER. WASH

DOWN TRUCKS PRIOR TODOWN TRUCKS PRIOR TO

LEAVING SITE. REFER TOLEAVING SITE. REFER TO

DETAIL.DETAIL.

APPROXIMATE LOCATION OFAPPROXIMATE LOCATION OF

MATERIAL STOCKPILE. EXACTMATERIAL STOCKPILE. EXACT

LOCATION TO BE CONFIRMED BYLOCATION TO BE CONFIRMED BY

CONTRACTOR. REFER TO DETAILS.CONTRACTOR. REFER TO DETAILS.

TAPTAP

9°09'20"

8

0

.

0

6

5

8

0

.

0

6

5

9

9

°

0

8

'

2

0

"

9

9

°

0

8

'

2

0

"

TAPTAP

TAPTAP

PITPIT

PITPIT

PITPIT

PITPIT

SWITCH SWITCH

BOARDBOARD

DIS

AB

LED

DIS

AB

LED

CONCRETE DRAINCONCRETE DRAIN

1

0

0

m

m

1

0

0

m

m

2

2

5

m

m

2

2

5

m

m

2

2

5

m

m

2

2

5

m

m

225mm∅225mm∅

225mm∅225mm∅

PITPIT

225mm∅225mm∅

2

2

5

m

m

2

2

5

m

m

2

0

.

5

2

0

.

5

1

8

.

5

1

8

.

5

1

9

.

5

1

9

.

5

1

8

.

5

1

8

.

5

1

8

.

5

1

8

.

5

2

0

2

0

1

9

1

9

1

9

1

9

1

9

1

9

1

8

1

8

1

7

.

5

1

7

.

5

1

8

1

8

1

7

1

7

1

9

.

5

1

9

.

5

100mm∅

100mm∅

375mm∅

375mm∅

375mm∅

375mm∅

300mm∅

300mm∅

300mm∅

300mm∅

100mm∅100mm∅

225∅225∅

TT

TT

TT

TT

TAPTAP

(

2

0

)

(20)

(20)

TAPTAP

(

1

9

.

5

)

(

1

9

.

5

)

//

//

//

//

//

//

//

//

//

//

//

//

//

//

//

//

//

//

//

//

//

//

//

/

///////////////////////////////////////////////////////////////////////////////

SEDIMENT AND EROSIONSEDIMENT AND EROSION

CONTROL FENCECONTROL FENCE

//

//

//

/

//

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

SEDIMENT AND EROSIONSEDIMENT AND EROSION

CONTROL FENCECONTROL FENCE

//////////////////////////////////////////////

/

/

/

/

SEDIMENT AND EROSIONSEDIMENT AND EROSION

CONTROL PLAN SHEET 1CONTROL PLAN SHEET 1

SW6SW6 PP

SEDIMENT & EROSION CONTROL PLAN - PART 1 SEDIMENT & EROSION CONTROL PLAN - PART 1

INDICATES EARTH BANK CUT OFF DRAININDICATES EARTH BANK CUT OFF DRAIN

INDICATES ROCK CHECK DAMINDICATES ROCK CHECK DAM

INDICATES SEDIMENT FENCEINDICATES SEDIMENT FENCE

INDICATES WIND EROSION FENCEINDICATES WIND EROSION FENCE

INDICATES HAY BALE WALLINDICATES HAY BALE WALL

INDICATES TYPICAL DISTURBED CONSTRUCTION ZONEINDICATES TYPICAL DISTURBED CONSTRUCTION ZONE

//

SCALE 1:200SCALE 1:200

W

DUST SHALL BE CONTROLLED BY REGULAR MOISTENING OF EXCAVATEDDUST SHALL BE CONTROLLED BY REGULAR MOISTENING OF EXCAVATED

SERVICES AND STOCKPILES.SERVICES AND STOCKPILES.

EROSION & SEDIMENT CONTROL NOTESEROSION & SEDIMENT CONTROL NOTES

ALL EROSION & SEDIMENT CONTROL MEASURES SHALL BE MAINTAINED ASALL EROSION & SEDIMENT CONTROL MEASURES SHALL BE MAINTAINED AS

SHOWN ON THE DRAWINGS.SHOWN ON THE DRAWINGS.

1.1.

2.2.

DATEDATE

DESIGNED:DESIGNED: DATE:DATE:

DRAWN:DRAWN: CHECKED:CHECKED:

DRAWING:DRAWING: REVISION:REVISION:

REV.NoREV.No

COPYRIGHT. DRAWINGS ISSUED UNDER LICENSE BY DEMLAKIAN CONSULTING ENGINEERSCOPYRIGHT. DRAWINGS ISSUED UNDER LICENSE BY DEMLAKIAN CONSULTING ENGINEERS

REVISIONREVISION BYBY

cccc

(02) 9955 6122(02) 9955 6122

www.demlakian.com.auwww.demlakian.com.au

P.O. Box 6553 North Sydney 2059P.O. Box 6553 North Sydney 2059

E-mail: [email protected]: [email protected]

Level 2, 5 Ridge StreetLevel 2, 5 Ridge Street

North Sydney NSW 2060North Sydney NSW 2060

(02) 9955 4485(02) 9955 4485

Facsimile:Facsimile:

Telephone:Telephone:

ORIGINAL: A1 DWGORIGINAL: A1 DWGIntelligent Thinking in EngineeringIntelligent Thinking in Engineering

CLIENT:CLIENT:

TITLE:TITLE:

PROJECT:PROJECT:

NOTE:NOTE:

This drawing must be read in conjunction withThis drawing must be read in conjunction with

ALL other drawings for this project includingALL other drawings for this project including

but not limited to all construction notes.but not limited to all construction notes.

213025213025

D.W.D.W.

RALRAL

FEB 2013FEB 2013

D.W.D.W.

AUSTRALIAN CHRISTIAN COLLEGEAUSTRALIAN CHRISTIAN COLLEGE

69 Farm Road RIVERSTONE69 Farm Road RIVERSTONE

Lot 90 DP1224210Lot 90 DP1224210

LIPPMANN PARTNERSHIPLIPPMANN PARTNERSHIP

AUSTRALIAN CHRISTIAN COLLEGEAUSTRALIAN CHRISTIAN COLLEGE

ARCHITECT:ARCHITECT:

T/A Demlakian Consulting EngineersT/A Demlakian Consulting Engineers

ABN 42 651 771 142ABN 42 651 771 142

Demlakian Strata & Remedial Pty LimitedDemlakian Strata & Remedial Pty Limited

FOR DEVELOPMENTFOR DEVELOPMENT

APPLICATION SUBMISSIONAPPLICATION SUBMISSION

FOR CONTINUATION OF PLAN REFER TO DRAWING 213025/SW07FOR CONTINUATION OF PLAN REFER TO DRAWING 213025/SW07

KK 23.04.1823.04.18 REVISED FOR DA SUBMISSIONREVISED FOR DA SUBMISSION RALRAL

MM 29.05.1829.05.18 LAYOUT REVISEDLAYOUT REVISED RALRAL

NN 06.06.1806.06.18 LAYOUT REVISEDLAYOUT REVISED RALRAL

PP 23.07.1823.07.18 REVISED FOR DA SUBMISSIONREVISED FOR DA SUBMISSION RALRAL

Page 18: RE: WATER MANAGEMENT REPORT FOR PROPOSED EXPANSION

TAPTAP

TAPTAP

1

0

0

m

m

2

0

.

5

2

0

.

5

2

0

.

5

2

0

.

5

2

1

.

5

2

1

.

5

1

9

.

5

1

9

.

5

1

9

.

5

1

9

.

5

2

0

2

0

2

1

2

1

2

0

2

0

1

9

1

9

1

9

1

9

2

0

2

0

TT

TT

TT

TT

(

2

1

.

5

)

(

2

1

.

5

)

(

2

1

)

(

2

1

)

TAPTAP

267.151

189°09'20"

(

2

0

)

(

2

0

)

(

2

0

.

5

)

(

2

0

.

5

)

(

2

1

.

5

)

(

2

1

.

5

)

(

2

0

)

(

2

0

)

(

2

1

)

(

2

1

)

(

2

2

)

(

2

2

)

(

2

0

.

5

)

(

2

0

.

5

)

(

2

1

.

5

)

(

2

1

.

5

)

(

2

0

)

(

2

0

)

(20)

(20)

(

1

9

.

5

)

(

1

9

.

5

)

(

1

9

.

5

)

(

1

9

.

5

)

(

2

1

)

(

2

1

)

(

2

2

)

(

2

2

)

(

2

0

)

(

2

0

)

80.065

80.065

99°08'20"

99°08'20"

TAPTAP

(

2

0

.

5

)

(

2

0

.

5

)

(

2

0

)

(

2

0

)

//

//

//

//

//

//

//

//

//

//

//

//

//

//

//

//

//

//

//

//

//

//

/

/

APPROXIMATE LOCATION OFAPPROXIMATE LOCATION OF

MATERIAL STOCKPILE. EXACTMATERIAL STOCKPILE. EXACT

LOCATION TO BE CONFIRMED BYLOCATION TO BE CONFIRMED BY

CONTRACTOR. REFER TO DETAILS.CONTRACTOR. REFER TO DETAILS.

//////////////////////////////////////////////

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

SEDIMENT AND EROSIONSEDIMENT AND EROSION

CONTROL PLAN SHEET 2CONTROL PLAN SHEET 2

SW7SW7 PP

SEDIMENT & EROSION CONTROL PLAN - PART 2 SEDIMENT & EROSION CONTROL PLAN - PART 2

INDICATES EARTH BANK CUT OFF DRAININDICATES EARTH BANK CUT OFF DRAIN

INDICATES ROCK CHECK DAMINDICATES ROCK CHECK DAM

INDICATES SEDIMENT FENCEINDICATES SEDIMENT FENCE

INDICATES WIND EROSION FENCEINDICATES WIND EROSION FENCE

INDICATES HAY BALE WALLINDICATES HAY BALE WALL

INDICATES TYPICAL DISTURBED CONSTRUCTION ZONEINDICATES TYPICAL DISTURBED CONSTRUCTION ZONE

//

SCALE 1:200SCALE 1:200

W

DUST SHALL BE CONTROLLED BY REGULAR MOISTENING OF EXCAVATEDDUST SHALL BE CONTROLLED BY REGULAR MOISTENING OF EXCAVATED

SERVICES AND STOCKPILES.SERVICES AND STOCKPILES.

EROSION & SEDIMENT CONTROL NOTESEROSION & SEDIMENT CONTROL NOTES

ALL EROSION & SEDIMENT CONTROL MEASURES SHALL BE MAINTAINED ASALL EROSION & SEDIMENT CONTROL MEASURES SHALL BE MAINTAINED AS

SHOWN ON THE DRAWINGS.SHOWN ON THE DRAWINGS.

1.1.

2.2.

DATEDATE

DESIGNED:DESIGNED: DATE:DATE:

DRAWN:DRAWN: CHECKED:CHECKED:

DRAWING:DRAWING: REVISION:REVISION:

REV.NoREV.No

COPYRIGHT. DRAWINGS ISSUED UNDER LICENSE BY DEMLAKIAN CONSULTING ENGINEERSCOPYRIGHT. DRAWINGS ISSUED UNDER LICENSE BY DEMLAKIAN CONSULTING ENGINEERS

REVISIONREVISION BYBY

cccc

(02) 9955 6122(02) 9955 6122

www.demlakian.com.auwww.demlakian.com.au

P.O. Box 6553 North Sydney 2059P.O. Box 6553 North Sydney 2059

E-mail: [email protected]: [email protected]

Level 2, 5 Ridge StreetLevel 2, 5 Ridge Street

North Sydney NSW 2060North Sydney NSW 2060

(02) 9955 4485(02) 9955 4485

Facsimile:Facsimile:

Telephone:Telephone:

ORIGINAL: A1 DWGORIGINAL: A1 DWGIntelligent Thinking in EngineeringIntelligent Thinking in Engineering

CLIENT:CLIENT:

TITLE:TITLE:

PROJECT:PROJECT:

NOTE:NOTE:

This drawing must be read in conjunction withThis drawing must be read in conjunction with

ALL other drawings for this project includingALL other drawings for this project including

but not limited to all construction notes.but not limited to all construction notes.

213025213025

D.W.D.W.

RALRAL

FEB 2013FEB 2013

D.W.D.W.

AUSTRALIAN CHRISTIAN COLLEGEAUSTRALIAN CHRISTIAN COLLEGE

69 Farm Road RIVERSTONE69 Farm Road RIVERSTONE

Lot 90 DP1224210Lot 90 DP1224210

LIPPMANN PARTNERSHIPLIPPMANN PARTNERSHIP

AUSTRALIAN CHRISTIAN COLLEGEAUSTRALIAN CHRISTIAN COLLEGE

ARCHITECT:ARCHITECT:

T/A Demlakian Consulting EngineersT/A Demlakian Consulting Engineers

ABN 42 651 771 142ABN 42 651 771 142

Demlakian Strata & Remedial Pty LimitedDemlakian Strata & Remedial Pty Limited

FOR DEVELOPMENTFOR DEVELOPMENT

APPLICATION SUBMISSIONAPPLICATION SUBMISSION

FOR CONTINUATION OF PLAN REFER TO DRAWING 213025/SW06FOR CONTINUATION OF PLAN REFER TO DRAWING 213025/SW06

KK 23.04.1823.04.18 REVISED FOR DA SUBMISSIONREVISED FOR DA SUBMISSION RALRAL

MM 29.05.1829.05.18 LAYOUT REVISEDLAYOUT REVISED RALRAL

NN 06.06.1806.06.18 LAYOUT REVISEDLAYOUT REVISED RALRAL

PP 23.07.1823.07.18 REVISED FOR DA SUBMISSIONREVISED FOR DA SUBMISSION RALRAL

Page 19: RE: WATER MANAGEMENT REPORT FOR PROPOSED EXPANSION

CONSTRUCT SEDIMENT FENCE AS CLOSE AS POSSIBLE TOCONSTRUCT SEDIMENT FENCE AS CLOSE AS POSSIBLE TO

PARALLEL TO THE CONTOURS OF THE SITE.PARALLEL TO THE CONTOURS OF THE SITE.

DRIVE 1.5m LONG STAR PICKETS INTO GROUND, 3m APART.DRIVE 1.5m LONG STAR PICKETS INTO GROUND, 3m APART.

DIG A 150mm DEEP TRENCH ALONG THE UPSLOPE LINE OFDIG A 150mm DEEP TRENCH ALONG THE UPSLOPE LINE OF

THE FENCE FOR THE BOTTOM OF THE FEBRIC TO BETHE FENCE FOR THE BOTTOM OF THE FEBRIC TO BE

ENTRENCHED.ENTRENCHED.

BACKFILL TRENCH OVER BASE OF FABRIC.BACKFILL TRENCH OVER BASE OF FABRIC.

FIX SELF-SUPPORTING GEOTEXTILE TO UPSLOPE SIDE OFFIX SELF-SUPPORTING GEOTEXTILE TO UPSLOPE SIDE OF

POSTS WITH WIRE TIES OR AS RECOMMENDED BYPOSTS WITH WIRE TIES OR AS RECOMMENDED BY

GEOTEXTILE MANUFACTURER.GEOTEXTILE MANUFACTURER.

JOIN SECTIONS OF FABRIC AT A SUPPORT POST WITH AJOIN SECTIONS OF FABRIC AT A SUPPORT POST WITH A

150mm OVERLAP.150mm OVERLAP.

ON SOIL, 150mmx100mm TRENCH WITHON SOIL, 150mmx100mm TRENCH WITH

COMPACTED BACKFILL AND ON ROCK,COMPACTED BACKFILL AND ON ROCK,

SET INTO SURFACE CONCRETESET INTO SURFACE CONCRETE

6.6.

2.2.

3.3.

4.4.

5.5.

--

11

SECTIONSECTION

SCALE 1:20SCALE 1:20

1.5m STAR PICKETS1.5m STAR PICKETS

AT MAX. 3m CENTRESAT MAX. 3m CENTRES

SELF SUPPORTING GEOSELF SUPPORTING GEO

TEXTILETEXTILE

D

I

R

E

C

T

I

O

N

O

F

F

L

O

W

D

I

R

E

C

T

I

O

N

O

F

F

L

O

W

11

--

1.1.

STANDARD SEDIMENT FENCESTANDARD SEDIMENT FENCE

SEDIMENT FENCE CONSTRUCTION NOTESSEDIMENT FENCE CONSTRUCTION NOTES

SCALE 1:20SCALE 1:20

DISTURBED AREADISTURBED AREA

UNDISTURBED AREAUNDISTURBED AREA

SELF-SUPPORTINGSELF-SUPPORTING

GEOTEXTILEGEOTEXTILE

1.5m STAR PICKETS1.5m STAR PICKETS

AT MAX. 3m CENTRESAT MAX. 3m CENTRES

INSTALL FENCE TO HEIGHT AND LOCATION AS SPECIFIED ONINSTALL FENCE TO HEIGHT AND LOCATION AS SPECIFIED ON

SEDIMENT &EROSION CONTROL PLAN.SEDIMENT &EROSION CONTROL PLAN.

CUT A CHANNEL 200mm DEEP ALONG FENCE LINE.CUT A CHANNEL 200mm DEEP ALONG FENCE LINE.

PLACE A WIRE AND LIGHT RESISTANT, OPEN-WEAVEPLACE A WIRE AND LIGHT RESISTANT, OPEN-WEAVE

POLYMER MESH WITH 40% POROSITY ON PREVAILING WINDPOLYMER MESH WITH 40% POROSITY ON PREVAILING WIND

SIDE OF FENCE.SIDE OF FENCE.

FASTEN MESH TO ALL WIRES USING RING FASTENERS ATFASTEN MESH TO ALL WIRES USING RING FASTENERS AT

100mm-150mm INTERVALS ON TOP AND 300mm INTERVALS100mm-150mm INTERVALS ON TOP AND 300mm INTERVALS

ON OTHER WIRES.ON OTHER WIRES.

USE ONE Ø75-Ø100mm TREATED ROUND POST EVERY 20USE ONE Ø75-Ø100mm TREATED ROUND POST EVERY 20

METRES.METRES.

STAR PICKETS TO BE FITTED WITH SAFETY CAPS.STAR PICKETS TO BE FITTED WITH SAFETY CAPS.

3.3.

4.4.

5.5.

6.6.

WIND EROSION FENCE CONSTRUCTION NOTESWIND EROSION FENCE CONSTRUCTION NOTES

500m

m500m

m

MIN.

MIN.

TREATED Ø75-Ø100TREATED Ø75-Ø100

ROUND TIMBER POSTSROUND TIMBER POSTS

AT MAX. 4m CENTRESAT MAX. 4m CENTRES

2.2.

1.1.

LOWEST WIRE AND MESH BURIEDLOWEST WIRE AND MESH BURIED

200mm BELOW SOIL SURFACE200mm BELOW SOIL SURFACE

SOIL SURFACESOIL SURFACE

WIRE STAPLEDWIRE STAPLED

TO TIMBER POSTSTO TIMBER POSTS

4x 3.15mm PLAIN WIRES4x 3.15mm PLAIN WIRES

THREADED THROUGH STANDARDTHREADED THROUGH STANDARD

HOLES IN STAR PICKETSHOLES IN STAR PICKETS

SCALE 1:20SCALE 1:20

600m

m600m

m

MIN.

MIN.

WIND EROSION FENCEWIND EROSION FENCE

STAR PICKET ATSTAR PICKET AT

MAX 4m CENTRESMAX 4m CENTRES

TREATED Ø75-Ø100TREATED Ø75-Ø100

ROUND TIMBER POSTSROUND TIMBER POSTS

OPEN-WEAVE MESHOPEN-WEAVE MESH

WITH 40% POROSITYWITH 40% POROSITY

STAR PICKET ATSTAR PICKET AT

MAX 2m CENTRESMAX 2m CENTRES

SECTIONSECTION

SCALE 1:20SCALE 1:20

GRAVEL-FILLED WIREGRAVEL-FILLED WIRE

MESH OR GEOTEXTILEMESH OR GEOTEXTILE

'SAUSAGE''SAUSAGE'

TIMBER SPACER TO SUITTIMBER SPACER TO SUIT

11

--

SEDIMENT TRAP SOCK ARRANGMENTSEDIMENT TRAP SOCK ARRANGMENT

KERB LINEKERB LINE

GRAVEL-FILLED WIREGRAVEL-FILLED WIRE

MESH OR GEOTEXTILEMESH OR GEOTEXTILE

'SAUSAGE''SAUSAGE'

KERB-SIDE INLETKERB-SIDE INLET

GRATED DRAIN INLETGRATED DRAIN INLET

11

--

SCALE 1:50SCALE 1:50

TIMBER SPACERTIMBER SPACER

TO SUITTO SUIT

SCALE 1:10SCALE 1:10

TYPICAL TRUCK SHAKERTYPICAL TRUCK SHAKER

NOTE:NOTE:

EQUIVALENT PROPRIETARY SYSTEMS MAY BEEQUIVALENT PROPRIETARY SYSTEMS MAY BE

USED AS AN ALTERNATIVEUSED AS AN ALTERNATIVE

150 x 75 x 6 RHS AT150 x 75 x 6 RHS AT

2000 CTS.2000 CTS.

100 x 100 x 6 ANGLES,100 x 100 x 6 ANGLES,

TYPICALTYPICAL

CONSTRUCTION NOTES - SITE STABILISATION ACCESSCONSTRUCTION NOTES - SITE STABILISATION ACCESS

STRIP TOPSOIL & LEVEL SITE.STRIP TOPSOIL & LEVEL SITE.

COMPACT SUBGRADE.COMPACT SUBGRADE.

COVER AREA WITH NEEDLE-PUNCHED GEOTEXTILE OR 30mmCOVER AREA WITH NEEDLE-PUNCHED GEOTEXTILE OR 30mm

AGGREGATE. MINIMUM LENGTH 15m OR TO BUILDINGAGGREGATE. MINIMUM LENGTH 15m OR TO BUILDING

ALIGNMENT. MINIMUM WIDTH 3m.ALIGNMENT. MINIMUM WIDTH 3m.

CONSTRUCT HUMP IMMEDIATELY WITHIN BOUNDARY TOCONSTRUCT HUMP IMMEDIATELY WITHIN BOUNDARY TO

DIVERT WATER TO A SEDIMENT FENCE OR SEDIMENT TRAP.DIVERT WATER TO A SEDIMENT FENCE OR SEDIMENT TRAP.

1.1.

2.2.

3.3.

4.4.

200 M

IN.

200 M

IN.

STABILISED SITE ACCESSSTABILISED SITE ACCESS

RUNOFF DIRECTED TORUNOFF DIRECTED TO

SEDIMENT TRAP / FENCESEDIMENT TRAP / FENCE

300 M

IN.

300 M

IN.

M

I

N

.

W

I

D

T

H

3

M

E

T

R

E

S

M

I

N

.

W

I

D

T

H

3

M

E

T

R

E

S

CONSTRUCTION SITECONSTRUCTION SITE

M

I

N

.

L

E

N

G

T

H

1

5

M

E

T

R

E

S

M

I

N

.

L

E

N

G

T

H

1

5

M

E

T

R

E

S

P

R

O

P

E

R

T

Y

B

O

U

N

D

A

R

Y

P

R

O

P

E

R

T

Y

B

O

U

N

D

A

R

Y

d)d)

c)c)

f)f)

e)e)

3.3.

ENSURE REHABILITATED LANDS HAVE EFFECTIVELY REDUCED THEENSURE REHABILITATED LANDS HAVE EFFECTIVELY REDUCED THE

EROSION HAZARD AND TO INITIATE UPGRADING OR REPAIR ASEROSION HAZARD AND TO INITIATE UPGRADING OR REPAIR AS

APPROPRIATE;APPROPRIATE;

MAINTAIN EROSION AND SEDIMENT CONTROL MEASURES IN A FULLYMAINTAIN EROSION AND SEDIMENT CONTROL MEASURES IN A FULLY

FUNCTIONING CONDITION UNTIL ALL EARTHWORK ACTIVITIES AREFUNCTIONING CONDITION UNTIL ALL EARTHWORK ACTIVITIES ARE

COMPLETED AND THE SITE IS REHABILITATED; ANDCOMPLETED AND THE SITE IS REHABILITATED; AND

REMOVE TRAPPED SEDIMENT WHENEVER LESS THAN DESIGNREMOVE TRAPPED SEDIMENT WHENEVER LESS THAN DESIGN

CAPACITY REMAINS WITHIN THE STRUCTURE;CAPACITY REMAINS WITHIN THE STRUCTURE;

AS A PART OF THE STATUTORY "DILIGENCE AND CARE"AS A PART OF THE STATUTORY "DILIGENCE AND CARE"

RESPONSIBILITIES, THE SITE SUPERINTENDENT WILL KEEP A LOG BOOK,RESPONSIBILITIES, THE SITE SUPERINTENDENT WILL KEEP A LOG BOOK,

MAKING ENTRIES AT LEAST WEEKLY, IMMEDIATELY BEFORE FORECASTMAKING ENTRIES AT LEAST WEEKLY, IMMEDIATELY BEFORE FORECAST

RAIN AND AFTER RAINFALL. ENTRIES WILL INCLUDE:RAIN AND AFTER RAINFALL. ENTRIES WILL INCLUDE:

REMOVE TEMPORARY SOIL CONSERVATION STRUCTURES AS THE LASTREMOVE TEMPORARY SOIL CONSERVATION STRUCTURES AS THE LAST

ACTIVITY IN THE REHABILITATION PROGRAM.ACTIVITY IN THE REHABILITATION PROGRAM.

A.A.

2.2.

3.3.

1.1.

5.5.

4.4.

1.1.

6.6.

B.B.

CONSTRUCT EARTH BANKS & CUT-OFF DRAINS TO DIRECT OVERLANDCONSTRUCT EARTH BANKS & CUT-OFF DRAINS TO DIRECT OVERLAND

FLOW TO THE DESIGNATED OUTLET PIT.FLOW TO THE DESIGNATED OUTLET PIT.

INSTALL ALL BARRIER FENCING TO EXCLUDE ACCESS TO THEINSTALL ALL BARRIER FENCING TO EXCLUDE ACCESS TO THE

NOMINATED RESTRICTED AREAS.NOMINATED RESTRICTED AREAS.

CONSTRUCT STABILISED SITE ACCESSES.CONSTRUCT STABILISED SITE ACCESSES.

CONSTRUCT EARTH BANKS AND CUT-OFF DRAINS TO DIRECT OVERLANDCONSTRUCT EARTH BANKS AND CUT-OFF DRAINS TO DIRECT OVERLAND

FLOW BEYOND THE SITE.FLOW BEYOND THE SITE.

SITE INSPECTION MAINTENANCE CONDITIONSSITE INSPECTION MAINTENANCE CONDITIONS

UNDERTAKE WORKS ACCORDING TO THE ENGINEERING PLANS.UNDERTAKE WORKS ACCORDING TO THE ENGINEERING PLANS.

STRIP AND STOCKPILE TOPSOIL FROM THOSE LANDS TO BE EXPOSED TOSTRIP AND STOCKPILE TOPSOIL FROM THOSE LANDS TO BE EXPOSED TO

CONSTRUCTION ACTIVITIES.CONSTRUCTION ACTIVITIES.

b)b)

c)c)

d)d)

a)a)

e)e)

THE CONDITION OF ANY SOIL AND WATER MANAGEMENT WORKS;THE CONDITION OF ANY SOIL AND WATER MANAGEMENT WORKS;

THE NEED FOR DUST PREVENTION STRATEGIES; ANDTHE NEED FOR DUST PREVENTION STRATEGIES; AND

ANY REMEDIAL WORKS TO BE UNDERTAKEN.ANY REMEDIAL WORKS TO BE UNDERTAKEN.

THE CONDITION OF VEGETATION AND ANY NEED TO IRRIGATE;THE CONDITION OF VEGETATION AND ANY NEED TO IRRIGATE;

THE BOOK WILL BE KEPT ON-SITE AND MADE AVAILABLE TO ANYTHE BOOK WILL BE KEPT ON-SITE AND MADE AVAILABLE TO ANY

AUTHORISED PERSON ON REQUEST. IT WILL BE GIVEN TO THE PROJECTAUTHORISED PERSON ON REQUEST. IT WILL BE GIVEN TO THE PROJECT

MANAGER AT THE CONCLUSION OF WORKS.MANAGER AT THE CONCLUSION OF WORKS.

THE VOLUME AND INTENSITY OF ANY RAINFALL EVENTS;THE VOLUME AND INTENSITY OF ANY RAINFALL EVENTS;

a)a)

2.2.

b)b)

ENSURE THAT DRAINS OPERATE PROPERLY AND TO EFFECT ANYENSURE THAT DRAINS OPERATE PROPERLY AND TO EFFECT ANY

NECESSARY REPAIRS;NECESSARY REPAIRS;

REMOVE SPILLED SAND OR OTHER MATERIALS FROM HAZARD AREAS,REMOVE SPILLED SAND OR OTHER MATERIALS FROM HAZARD AREAS,

INCLUDING LANDS CLOSER THAN FIVE METRES FROM AREAS OFINCLUDING LANDS CLOSER THAN FIVE METRES FROM AREAS OF

LIKELY CONCENTRATED OR HIGH VELOCITY FLOWS ESPECIALLYLIKELY CONCENTRATED OR HIGH VELOCITY FLOWS ESPECIALLY

WATERWAYS AND PAVED AREAS;WATERWAYS AND PAVED AREAS;

THE SITE SUPERINTENDENT WILL INSPECT THE SITE AT LEAST WEEKLYTHE SITE SUPERINTENDENT WILL INSPECT THE SITE AT LEAST WEEKLY

AND WILL:AND WILL:

WASTE BINS WILL BE EMPTIED AS NECESSARY. DISPOSAL OF WASTEWASTE BINS WILL BE EMPTIED AS NECESSARY. DISPOSAL OF WASTE

WILL BE IN A MANNER APPROVED BY THE SITE SUPERINTENDENT.WILL BE IN A MANNER APPROVED BY THE SITE SUPERINTENDENT.

CONSTRUCTION SEQUENCECONSTRUCTION SEQUENCE

SOIL & WATER MANAGEMENT PLAN NOTESSOIL & WATER MANAGEMENT PLAN NOTES

ALL EROSION & SEDIMENT CONTROL MEASURES SHALL BE MAINTAINED ASALL EROSION & SEDIMENT CONTROL MEASURES SHALL BE MAINTAINED AS

SHOWN ON THE DRAWINGS.SHOWN ON THE DRAWINGS.

EROSION & SEDIMENT CONTROL NOTESEROSION & SEDIMENT CONTROL NOTES

THE TEMPORARY SEDIMENT TRAP PIT SHALL BE CLEANED REGULARLY. INTHE TEMPORARY SEDIMENT TRAP PIT SHALL BE CLEANED REGULARLY. IN

THE EVENT THE GEOTEXTILE FILTER BECOMES CLOGGED DURINGTHE EVENT THE GEOTEXTILE FILTER BECOMES CLOGGED DURING

DEWATERING OF THE EXCAVATION, PUMPING SHALL BE STOPPED AND THEDEWATERING OF THE EXCAVATION, PUMPING SHALL BE STOPPED AND THE

FILTER CLEANED OR RENEWED.FILTER CLEANED OR RENEWED.

DUST SHALL BE CONTROLLED BY REGULAR MOISTENING OF EXCAVATEDDUST SHALL BE CONTROLLED BY REGULAR MOISTENING OF EXCAVATED

SERVICES AND STOCKPILES.SERVICES AND STOCKPILES.

THE TRUCK SHAKER SHALL BE REGULARLY CLEANED BY LIFTING, DISLODGING &THE TRUCK SHAKER SHALL BE REGULARLY CLEANED BY LIFTING, DISLODGING &

REMOVING SPOIL.REMOVING SPOIL.

4.4.

3.3.

1.1.

2.2.

SEDIMENT AND EROSIONSEDIMENT AND EROSION

CONTROL DETAILSCONTROL DETAILS

SW8SW8 NN

DATEDATE

DESIGNED:DESIGNED: DATE:DATE:

DRAWN:DRAWN: CHECKED:CHECKED:

DRAWING:DRAWING: REVISION:REVISION:

REV.NoREV.No

COPYRIGHT. DRAWINGS ISSUED UNDER LICENSE BY DEMLAKIAN CONSULTING ENGINEERSCOPYRIGHT. DRAWINGS ISSUED UNDER LICENSE BY DEMLAKIAN CONSULTING ENGINEERS

REVISIONREVISION BYBY

cccc

(02) 9955 6122(02) 9955 6122

www.demlakian.com.auwww.demlakian.com.au

P.O. Box 6553 North Sydney 2059P.O. Box 6553 North Sydney 2059

E-mail: [email protected]: [email protected]

Level 2, 5 Ridge StreetLevel 2, 5 Ridge Street

North Sydney NSW 2060North Sydney NSW 2060

(02) 9955 4485(02) 9955 4485

Facsimile:Facsimile:

Telephone:Telephone:

ORIGINAL: A1 DWGORIGINAL: A1 DWGIntelligent Thinking in EngineeringIntelligent Thinking in Engineering

CLIENT:CLIENT:

TITLE:TITLE:

PROJECT:PROJECT:

NOTE:NOTE:

This drawing must be read in conjunction withThis drawing must be read in conjunction with

ALL other drawings for this project includingALL other drawings for this project including

but not limited to all construction notes.but not limited to all construction notes.

213025213025

D.W.D.W.

RALRAL

FEB 2013FEB 2013

D.W.D.W.

AUSTRALIAN CHRISTIAN COLLEGEAUSTRALIAN CHRISTIAN COLLEGE

69 Farm Road RIVERSTONE69 Farm Road RIVERSTONE

Lot 90 DP1224210Lot 90 DP1224210

LIPPMANN PARTNERSHIPLIPPMANN PARTNERSHIP

AUSTRALIAN CHRISTIAN COLLEGEAUSTRALIAN CHRISTIAN COLLEGE

ARCHITECT:ARCHITECT:

T/A Demlakian Consulting EngineersT/A Demlakian Consulting Engineers

ABN 42 651 771 142ABN 42 651 771 142

Demlakian Strata & Remedial Pty LimitedDemlakian Strata & Remedial Pty Limited

FOR DEVELOPMENTFOR DEVELOPMENT

APPLICATION SUBMISSIONAPPLICATION SUBMISSION

FF 14.09.1514.09.15 FOR DA SUBMISSIONFOR DA SUBMISSION RALRAL

GG 23.04.1823.04.18 REVISED FOR DA SUBMISSIONREVISED FOR DA SUBMISSION RALRAL

MM 30.05.1830.05.18 REVISED FOR DA SUBMISSIONREVISED FOR DA SUBMISSION RALRAL

NN 23.07.1823.07.18 REVISED FOR DA SUBMISSIONREVISED FOR DA SUBMISSION RALRAL

Page 20: RE: WATER MANAGEMENT REPORT FOR PROPOSED EXPANSION

00 11 BEND 4BEND 4 BEND 3BEND 3 22 33 BEND 2BEND 2 BEND 1BEND 1 44 55

O

V

E

R

L

A

N

D

F

L

O

W

O

V

E

R

L

A

N

D

F

L

O

W

5000x4000 GRATED INLET PIT5000x4000 GRATED INLET PIT

RL = 19.85 (APPROX)RL = 19.85 (APPROX)

IL = 18.850IL = 18.850

PROPOSED TWINPROPOSED TWIN

900∅ PIPES900∅ PIPES

PROPOSED SURFACEPROPOSED SURFACE

LEVELLEVEL

H.G.L.H.G.L.

EXISTING HEADWALL 3EXISTING HEADWALL 3

TO BE RETAINEDTO BE RETAINED

BO

UN

DA

RY

BO

UN

DA

RY

EXISTING 900x300EXISTING 900x300

BOX CULVERTBOX CULVERT

EXISTING HEADWALLEXISTING HEADWALL

TO BE REMOVEDTO BE REMOVED

0.000

0.000

29.563

29.563

29.56329.563

18.031

18.031

18.476

18.476

18.031

18.031

18.626

18.626

17.640

17.640

17.936

17.936

0.660

0.660

1.214

1.214

1:100.01:100.0

EX 900x300 BOX CULVERTEX 900x300 BOX CULVERT

5.475.47

15251525

CHAINAGECHAINAGE

EXISTING SURFACEEXISTING SURFACE

FINISHED SURFACEFINISHED SURFACE

INVERT LEVELINVERT LEVEL

DEPTH TO INVERTDEPTH TO INVERT

HGL 100 YEAR ARIHGL 100 YEAR ARI

DATUM RL 12.6DATUM RL 12.6

SLOPE/GRADESLOPE/GRADE

PIPE DETAILSPIPE DETAILS

VELOCITY (m/s)VELOCITY (m/s)

100 YEAR ARI FLOW (l/sec)100 YEAR ARI FLOW (l/sec)

30.561

30.561

0.9980.998

18.026

18.026

18.657

18.657

17.950

17.950

17.955

17.955

1.200

1.200

0.702

0.702

1:200.01:200.0

900x300 BOX CULVERT900x300 BOX CULVERT

5.475.47

15251525

50.224

50.224

19.66319.663

18.700

18.700

19.165

19.165

18.053

18.053

1.111

1.111

1:200.01:200.0

900x300 BOX CULVERT900x300 BOX CULVERT

5.475.47

15251525

51.974

51.974

1.7501.750

18.742

18.742

19.183

19.183

18.062

18.062

1.112

1.112

0.988

0.988

19.050

19.050

1:200.01:200.0

900x300 BOX CULVERT900x300 BOX CULVERT

5.475.47

15251525

0.000

0.000

82.587

82.587

82.58782.587

20.625

20.625

20.572

20.572

18.087

18.087

18.500

18.500

0.963

0.963

2.072

2.072

19.154

19.154

19.495

19.495

1:200.01:200.0

900Ø x 2900Ø x 2

2.102.10

15251525

84.337

84.337

1.7501.750

20.729

20.729

20.609

20.609

18.525

18.525

18.534

18.534

2.047

2.047

2.075

2.075

19.502

19.502

1:2001:200

900Ø x 2900Ø x 2

2.342.34

15251525

117.784

117.784

33.44833.448

21.406

21.406

20.300

20.300

18.701

18.701

1.599

1.599

19.545

19.545

19.625

19.625

1:2001:200

900Ø x 2900Ø x 2

2.102.10

15251525

119.534

119.534

1.7501.750

21.380

21.380

20.300

20.300

18.710

18.710

1.590

1.590

19.668

19.668

19.674

19.674

1:2001:200

900Ø x 2900Ø x 2

2.122.12

15251525

143.234

143.234

23.70023.700

20.111

20.111

19.850

19.850

18.735

18.735

18.850

18.850

1.565

1.565

0.950

0.950

19.755

19.755

1:2001:200

900Ø x 2900Ø x 2

2.382.38

15251525

25% BLOCKAGE EACH PIPE25% BLOCKAGE EACH PIPE

O

V

E

R

F

L

O

W

A

T

R

L

1

9

.0

5

O

V

E

R

F

L

O

W

A

T

R

L

1

9

.0

5

50005000

20.100

20.100

STORMWATER LONGSECTION & HGLSTORMWATER LONGSECTION & HGL

SW9SW9 NN

DATEDATE

DESIGNED:DESIGNED: DATE:DATE:

DRAWN:DRAWN: CHECKED:CHECKED:

DRAWING:DRAWING: REVISION:REVISION:

REV.NoREV.No

COPYRIGHT. DRAWINGS ISSUED UNDER LICENSE BY DEMLAKIAN CONSULTING ENGINEERSCOPYRIGHT. DRAWINGS ISSUED UNDER LICENSE BY DEMLAKIAN CONSULTING ENGINEERS

REVISIONREVISION BYBY

cccc

(02) 9955 6122(02) 9955 6122

www.demlakian.com.auwww.demlakian.com.au

P.O. Box 6553 North Sydney 2059P.O. Box 6553 North Sydney 2059

E-mail: [email protected]: [email protected]

Level 2, 5 Ridge StreetLevel 2, 5 Ridge Street

North Sydney NSW 2060North Sydney NSW 2060

(02) 9955 4485(02) 9955 4485

Facsimile:Facsimile:

Telephone:Telephone:

ORIGINAL: A1 DWGORIGINAL: A1 DWGIntelligent Thinking in EngineeringIntelligent Thinking in Engineering

CLIENT:CLIENT:

TITLE:TITLE:

PROJECT:PROJECT:

NOTE:NOTE:

This drawing must be read in conjunction withThis drawing must be read in conjunction with

ALL other drawings for this project includingALL other drawings for this project including

but not limited to all construction notes.but not limited to all construction notes.

213025213025

D.W.D.W.

RALRAL

FEB 2013FEB 2013

D.W.D.W.

AUSTRALIAN CHRISTIAN COLLEGEAUSTRALIAN CHRISTIAN COLLEGE

69 Farm Road RIVERSTONE69 Farm Road RIVERSTONE

Lot 90 DP1224210Lot 90 DP1224210

LIPPMANN PARTNERSHIPLIPPMANN PARTNERSHIP

AUSTRALIAN CHRISTIAN COLLEGEAUSTRALIAN CHRISTIAN COLLEGE

ARCHITECT:ARCHITECT:

T/A Demlakian Consulting EngineersT/A Demlakian Consulting Engineers

ABN 42 651 771 142ABN 42 651 771 142

Demlakian Strata & Remedial Pty LimitedDemlakian Strata & Remedial Pty Limited

FOR DEVELOPMENTFOR DEVELOPMENT

APPLICATION SUBMISSIONAPPLICATION SUBMISSION

STORMWATER LONGITUDINAL SECTIONSTORMWATER LONGITUDINAL SECTION

00 50m50m1010 2020 3030 4040

DO NOT SCALE OFF DRAWINGDO NOT SCALE OFF DRAWING

(Scale bar provided for drawing representation only)(Scale bar provided for drawing representation only)

SCALE 1:100 VERTICALSCALE 1:100 VERTICAL

00 664422 88 10m10m

SCALE 1:500 HORIZONTALSCALE 1:500 HORIZONTAL

BB 14.09.1514.09.15 FOR DA SUBMISSIONFOR DA SUBMISSION RALRAL

CC 23.04.1823.04.18 REVISED FOR DA SUBMISSIONREVISED FOR DA SUBMISSION RALRAL

MM 30.05.1830.05.18 REVISED FOR DA SUBMISSIONREVISED FOR DA SUBMISSION RALRAL

NN 23.07.1823.07.18 REVISED FOR DA SUBMISSIONREVISED FOR DA SUBMISSION RALRAL

Page 21: RE: WATER MANAGEMENT REPORT FOR PROPOSED EXPANSION

DATE:DATE: SCALE:SCALE: CHK:CHK:DRN:DRN:FILE NAME:FILE NAME:13.02.1513.02.15 N.T.S.N.T.S. DP_EPOD_1ADP_EPOD_1A W.J.W.J. H.T.H.T.

DRAWINGDRAWINGBLACKTOWNBLACKTOWNDOWNPIPE TO ENVIROPODDOWNPIPE TO ENVIROPOD

CONFIGURATIONCONFIGURATIONWITH ENVIROPOD FILTERWITH ENVIROPOD FILTER

11AAStormwater360Stormwater360

DROP PIPE ENVIROPOD CONFIGURATIONDROP PIPE ENVIROPOD CONFIGURATIONSECTIONSECTION

ACCESSACCESS

GRATE & FRAMEGRATE & FRAME

ENVIROPOD FILTERENVIROPOD FILTER

FINISHED SURFACEFINISHED SURFACE

LEVELLEVEL

MIN

500

MIN

500

STANDARD ENVIROPOD CONFIGURATIONSTANDARD ENVIROPOD CONFIGURATIONSECTIONSECTION

OUTLET PIPEOUTLET PIPE

ACCESSACCESS

GRATE & FRAMEGRATE & FRAME

ENVIROPOD FILTERENVIROPOD FILTER

FINISHED SURFACEFINISHED SURFACE

LEVELLEVEL

MIN

550

MIN

550

INLET PIPEINLET PIPE

OUTLET PIPEOUTLET PIPEINLET PIPEINLET PIPE

ENVIROPOD DETAILSENVIROPOD DETAILS

SW10SW10 NN

DATEDATE

DESIGNED:DESIGNED: DATE:DATE:

DRAWN:DRAWN: CHECKED:CHECKED:

DRAWING:DRAWING: REVISION:REVISION:

REV.NoREV.No

COPYRIGHT. DRAWINGS ISSUED UNDER LICENSE BY DEMLAKIAN CONSULTING ENGINEERSCOPYRIGHT. DRAWINGS ISSUED UNDER LICENSE BY DEMLAKIAN CONSULTING ENGINEERS

REVISIONREVISION BYBY

cccc

(02) 9955 6122(02) 9955 6122

www.demlakian.com.auwww.demlakian.com.au

P.O. Box 6553 North Sydney 2059P.O. Box 6553 North Sydney 2059

E-mail: [email protected]: [email protected]

Level 2, 5 Ridge StreetLevel 2, 5 Ridge Street

North Sydney NSW 2060North Sydney NSW 2060

(02) 9955 4485(02) 9955 4485

Facsimile:Facsimile:

Telephone:Telephone:

ORIGINAL: A1 DWGORIGINAL: A1 DWGIntelligent Thinking in EngineeringIntelligent Thinking in Engineering

CLIENT:CLIENT:

TITLE:TITLE:

PROJECT:PROJECT:

NOTE:NOTE:

This drawing must be read in conjunction withThis drawing must be read in conjunction with

ALL other drawings for this project includingALL other drawings for this project including

but not limited to all construction notes.but not limited to all construction notes.

213025213025

D.W.D.W.

RALRAL

FEB 2013FEB 2013

D.W.D.W.

AUSTRALIAN CHRISTIAN COLLEGEAUSTRALIAN CHRISTIAN COLLEGE

69 Farm Road RIVERSTONE69 Farm Road RIVERSTONE

Lot 90 DP1224210Lot 90 DP1224210

LIPPMANN PARTNERSHIPLIPPMANN PARTNERSHIP

AUSTRALIAN CHRISTIAN COLLEGEAUSTRALIAN CHRISTIAN COLLEGE

ARCHITECT:ARCHITECT:

T/A Demlakian Consulting EngineersT/A Demlakian Consulting Engineers

ABN 42 651 771 142ABN 42 651 771 142

Demlakian Strata & Remedial Pty LimitedDemlakian Strata & Remedial Pty Limited

FOR DEVELOPMENTFOR DEVELOPMENT

APPLICATION SUBMISSIONAPPLICATION SUBMISSION

AA 14.09.1514.09.15 FOR DA SUBMISSIONFOR DA SUBMISSION RALRAL

BB 23.04.1823.04.18 REVISED FOR DA SUBMISSIONREVISED FOR DA SUBMISSION RALRAL

MM 30.05.1830.05.18 REVISED FOR DA SUBMISSIONREVISED FOR DA SUBMISSION RALRAL

NN 23.07.1823.07.18 REVISED FOR DA SUBMISSIONREVISED FOR DA SUBMISSION RALRAL