12
1 REQUESTOR NAME: Joint Industry Electricity Steering Committee INFORMATION REQUEST ROUND NO: 2 TO: BRITISH COLUMBIA HYDRO & POWER AUTHORITY DATE: May 16, 2007 PROJECT NO: 3698455 APPLICATION NAME: BCH – F2007 [COSA/] Rate Design ________________________________________________________________________________________ 10.0 Reference: Exhibit B-1, Page 18-20; Page 13, Figure 1; Exhibit B-3, JIESC IR 1.3.1 Explanation: BC Hydro has used 12CP or an average of monthly peak demand. Additional information is required to evaluate the data used and trends in system demand. Request: 10.1 Provide the monthly coincident peak demands of each customer class, with and without losses, at the times of the domestic peak loads for the fiscal years 2001-2005 in the format used for fiscal year 2006 in the spreadsheet identified as JIESC_1_003_1 Attachment 1. 10.2 With respect to the data provided in response to JIESC IR 1.3.1 for F2006 and for F2001-F2005 provided in response to 10.1 above, please state whether the reported demands include any interruptible or curtailable loads that were not interrupted or curtailed. 10.3 If the demand data for F2001-F2006 include interruptible or curtailable loads, provide the monthly amounts of such loads for each customer class. 10.4 For F2001-F2006 provide the amounts (estimated as necessary) of interruptible or curtailable loads, by customer class, that were interrupted or curtailed at the time of each of the monthly peak demands. 11.0 Reference: Exhibit B-1, Page 21; Explanation: Additional information is required to understand the basis for demand allocations and use of the Transmission system. Request: 11.1 Provide a table of BC Hydro generation resources (owned and under contract) by generating unit (not in aggregate) with the in-service date and showing each resource’s dependable summer and winter capacity rating for the years F1999-F2006. Include all resources that were available at any time during these years. 11.2 Provide a tabulation of the planned maintenance schedules for all generating resources of BC Hydro for F1999-F2006 with the beginning and ending dates for all planned outages as scheduled at the beginning of each year. Identify extraordinary planned outages and the causes. 11.3 Provide a tabulation of the actual maintenance schedules for all generating resources of BC Hydro for F1999-F2006 with the beginning and ending dates for all outages. Identify extraordinary outages and the causes. C18-3

REQUESTOR NAME: INFORMATION REQUEST ROUND NO: … · 1 REQUESTOR NAME: Joint Industry Electricity Steering Committee INFORMATION REQUEST ROUND NO: 2 TO: BRITISH COLUMBIA HYDRO & POWER

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: REQUESTOR NAME: INFORMATION REQUEST ROUND NO: … · 1 REQUESTOR NAME: Joint Industry Electricity Steering Committee INFORMATION REQUEST ROUND NO: 2 TO: BRITISH COLUMBIA HYDRO & POWER

1

REQUESTOR NAME: Joint Industry Electricity Steering Committee INFORMATION REQUEST ROUND NO: 2 TO: BRITISH COLUMBIA HYDRO & POWER AUTHORITY DATE: May 16, 2007 PROJECT NO: 3698455 APPLICATION NAME: BCH – F2007 [COSA/] Rate Design

________________________________________________________________________________________

10.0 Reference: Exhibit B-1, Page 18-20; Page 13, Figure 1; Exhibit B-3, JIESC IR 1.3.1

Explanation: BC Hydro has used 12CP or an average of monthly peak demand. Additional information is required to evaluate the data used and trends in system demand.

Request:

10.1 Provide the monthly coincident peak demands of each customer class, with and without losses, at the times of the domestic peak loads for the fiscal years 2001-2005 in the format used for fiscal year 2006 in the spreadsheet identified as JIESC_1_003_1 Attachment 1.

10.2 With respect to the data provided in response to JIESC IR 1.3.1 for F2006 and for F2001-F2005 provided in response to 10.1 above, please state whether the reported demands include any interruptible or curtailable loads that were not interrupted or curtailed.

10.3 If the demand data for F2001-F2006 include interruptible or curtailable loads, provide the monthly amounts of such loads for each customer class.

10.4 For F2001-F2006 provide the amounts (estimated as necessary) of interruptible or curtailable loads, by customer class, that were interrupted or curtailed at the time of each of the monthly peak demands.

11.0 Reference: Exhibit B-1, Page 21;

Explanation: Additional information is required to understand the basis for demand allocations and use of the Transmission system.

Request:

11.1 Provide a table of BC Hydro generation resources (owned and under contract) by generating unit (not in aggregate) with the in-service date and showing each resource’s dependable summer and winter capacity rating for the years F1999-F2006. Include all resources that were available at any time during these years.

11.2 Provide a tabulation of the planned maintenance schedules for all generating resources of BC Hydro for F1999-F2006 with the beginning and ending dates for all planned outages as scheduled at the beginning of each year. Identify extraordinary planned outages and the causes.

11.3 Provide a tabulation of the actual maintenance schedules for all generating resources of BC Hydro for F1999-F2006 with the beginning and ending dates for all outages. Identify extraordinary outages and the causes.

C18-3

bharvey
BCH 2007 Rate Design
Page 2: REQUESTOR NAME: INFORMATION REQUEST ROUND NO: … · 1 REQUESTOR NAME: Joint Industry Electricity Steering Committee INFORMATION REQUEST ROUND NO: 2 TO: BRITISH COLUMBIA HYDRO & POWER

2

12.0 Reference: Exhibit B-3-1, JIESC IR 1.4.3;

Explanation: BC Hydro has provided information by NAIC codes. The IR specified electro-chemicals and it appears that electro-chemicals have been grouped with other chemicals.

Request:

12.1 Confirm that the data for chemicals includes customers other than electro-chemicals.

12.2 If the chemicals customer data includes customers other than electro-chemicals, provide the data for the three electro-chemical producers (four facilities).

13.0 Reference: Exhibit B-3, BCUC IR 1.3.2, BCUC IR 1.7.3, JIESC IR 1.1.2, JIESC IR 1.1.9, JIESC IR 1.1.10, JIESC IR 1.1.12; Exhibit B-1, Page 35-40;

Explanation: In the response to BCUC IR 1.3.2, BC Hydro states that the elimination of declining blocks and discounts is necessary to removing the misalignment between these existing rate structures and the message of energy conservation.

In response to BCUC IR 1.7.3, BC Hydro states that from a cost of service perspective, adding a sub group is the same as adding a rate class. Adding a rate class does not necessarily enhance the ability to match costs and revenues for a specific group. Adding a rate class would only increase the ability to match costs and revenues for a specific group if:

1. The load profile for the new group is known;

2. The load profile or interconnection requirements for the new group are materially different than the load profile or interconnection requirements of the existing rate class, resulting in a materially different cost to serve; and

3. Customers who would be in the new group can be readily identified with minimal debate.

For simplicity and to provide price signals that are not contrary to the promotion of energy efficiency and conservation, BC Hydro is proposing to flatten the demand and energy charges for the General Service >35 kW rate.

The graph of accounts by demand level provided in response to JIESC IR 1.1.10 appears to suggest that customers are not homogenous and that higher demand customers are materially different than the average and mean of the customers within the SG>35 kW rate class as provided in response to JIESC IR 1.1.9.

Request:

13.1 Does BC Hydro agree that one of the purposes of declining block rate structures was to limit the number of rate classes by designing rates that would apply across a broad range of customer demand and energy levels?

13.2 Does BC Hydro agree that declining block rates would take into account the lower unit costs of serving customers with higher demand and energy use within a rate class?

13.3 Does BC Hydro agree that the graph of the distribution of GS>35 kW indicates that there are a limited number of customers outside of a normal bell curve distribution of demands within the

Page 3: REQUESTOR NAME: INFORMATION REQUEST ROUND NO: … · 1 REQUESTOR NAME: Joint Industry Electricity Steering Committee INFORMATION REQUEST ROUND NO: 2 TO: BRITISH COLUMBIA HYDRO & POWER

3

GS>35 kW rate class?

13.3.1 Do the customers meet the criteria for a separate rate class as set out by BC Hydro in response to BCUC IR 1.7.3? If not, why not?

13.4 Provide the rates and bill impacts (JIESC IR 1.1.2) assuming a separate GS rates (LGS) for the specified customer groups and revenue neutrality for the new rate classes:

13.4.1 Separate rate classes for customers with demands between 200 kW and 1,000 kW (LGS1) and customers with demands above 1,000 kW (LGS2).

13.4.2 Separate rate classes for customers with demands between 200 kW and 3,000 kW (LGS1) and customers with demands above 3,000 kW (LGS2).

13.5 Provide the rates and bill impacts (JIESC IR 1.1.2) assuming a separate GS rates (LGS) for the specified customer groups and revenue neutrality for the new rate classes with all GS>35 kW customers with demand >3,000 kW moved to a rate based on Schedule 1823(1823-B) with a rate rider designed to recover the revenue difference between GS>35 kW and Schedule 1823:

13.5.1 Separate rate class for customers with demands between 200 kW and 3,000 kW (LGS1).

13.5.2 Separate rate class for customers with demands between 300 kW and 3,000 kW (LGS1).

13.5.3 Confirm that a rate for customers billed under a form of Schedule 1823 would meet the BC Hydro objectives of simplicity, fairness and price signals to promote energy efficiency and conservation.

14.0 Reference: Exhibit B-3, JIESC IR 1.3.7; Attachment: CRI Workshop Presentation (.ppt)

Explanation: A portion of a CRI presentation providing load graphs that formed the basis of the JIESC IR has been attached for reference. From the data and graphs provided in the response, it is difficult to confirm that the data and graphs are the same as those provided in the attachment.

Request:

14.1 Confirm that the data and graphs are in the attachment and the IR response are the same.

14.2 If the data and graphs in the attachment and the IR response are not the same, indicate which information is correct and provide the supporting data and resulting graphs in the same format and quality as the attachment.

15.0 Reference: Exhibit B-3, JIESC IR 1.7.2;

Explanation: BC Hydro declined to respond to the information request.

Request:

15.1 Confirm that if transmission and generation demand and energy allocation methodologies are fixed, the effect of other generally accepted cost allocations on revenue-cost ratios would be expected to fall within a range of +/-5%.

Page 4: REQUESTOR NAME: INFORMATION REQUEST ROUND NO: … · 1 REQUESTOR NAME: Joint Industry Electricity Steering Committee INFORMATION REQUEST ROUND NO: 2 TO: BRITISH COLUMBIA HYDRO & POWER

Conservation Research Initiative Residential Time of

Use Program

Working Group Meeting #2

March 21, 2007

Page 5: REQUESTOR NAME: INFORMATION REQUEST ROUND NO: … · 1 REQUESTOR NAME: Joint Industry Electricity Steering Committee INFORMATION REQUEST ROUND NO: 2 TO: BRITISH COLUMBIA HYDRO & POWER

2

Our Challenges - Winter PeakRecord Peak Day Load Shape

Domestic System November 2006

7,000

7,500

8,000

8,500

9,000

9,500

10,000

10,500

11,000

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Hour Ending

MW

Nov 29th 2006 Peak Day

November Domestic Peak: 10,113 MWNovember 29, 2006at Hour Ending 18

Note: Peak Day Load Shape not adjusted for Voluntary and Involuntary Outages

Page 6: REQUESTOR NAME: INFORMATION REQUEST ROUND NO: … · 1 REQUESTOR NAME: Joint Industry Electricity Steering Committee INFORMATION REQUEST ROUND NO: 2 TO: BRITISH COLUMBIA HYDRO & POWER

3

Our Challenges - Winter PeakTotal Domestic System Monthly Peak

06/07

5,000

6,000

7,000

8,000

9,000

10,000

11,000

April

May

June Ju

ly

August

Septem

ber

October

Novembe

r

Decembe

r

Janu

ary

Februa

ry

M onth

MW

Page 7: REQUESTOR NAME: INFORMATION REQUEST ROUND NO: … · 1 REQUESTOR NAME: Joint Industry Electricity Steering Committee INFORMATION REQUEST ROUND NO: 2 TO: BRITISH COLUMBIA HYDRO & POWER

4

Our Challenges - Load Duration

Load Duration of the BC Hydro System

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

1 8,760

Hour in the Year

Perc

ent o

f pea

k lo

ad

Page 8: REQUESTOR NAME: INFORMATION REQUEST ROUND NO: … · 1 REQUESTOR NAME: Joint Industry Electricity Steering Committee INFORMATION REQUEST ROUND NO: 2 TO: BRITISH COLUMBIA HYDRO & POWER

5

Why Consider Residential? Typical Peak Week - by Rate Class

Comparison of Total Rate Class LoadsTypical Peak Week Jan 1 - Jan 7, 2005

1,000

1,500

2,000

2,500

3,000

3,500

1 5 9 13 17 21 1 5 9 13 17 21 1 5 9 13 17 21 1 5 9 13 17 21 1 5 9 13 17 21 1 5 9 13 17 21 1 5 9 13 17 21

Hour Ending

MW

Residential General Transmission

Page 9: REQUESTOR NAME: INFORMATION REQUEST ROUND NO: … · 1 REQUESTOR NAME: Joint Industry Electricity Steering Committee INFORMATION REQUEST ROUND NO: 2 TO: BRITISH COLUMBIA HYDRO & POWER

6

Why Consider Residential? Typical VI Peak Week - by Rate Class

Comparison of Vancouver Island Rate Class LoadsTypical Peak Week Jan 1 - Jan 7 2005

200

300

400

500

600

700

800

900

1,000

1,100

1 5 9 13 17 21 1 5 9 13 17 21 1 5 9 13 17 21 1 5 9 13 17 21 1 5 9 13 17 21 1 5 9 13 17 21 1 5 9 13 17 21Hour Ending

MW

Residential General Transmission

Page 10: REQUESTOR NAME: INFORMATION REQUEST ROUND NO: … · 1 REQUESTOR NAME: Joint Industry Electricity Steering Committee INFORMATION REQUEST ROUND NO: 2 TO: BRITISH COLUMBIA HYDRO & POWER

7

Peak MonthsTotal Domestic System Monthly Peak

06/07

5,000

6,000

7,000

8,000

9,000

10,000

11,000

April

May

June Ju

ly

August

Septem

ber

October

Novembe

r

Decembe

r

Janu

ary

Februa

ry

M onth

MW

Page 11: REQUESTOR NAME: INFORMATION REQUEST ROUND NO: … · 1 REQUESTOR NAME: Joint Industry Electricity Steering Committee INFORMATION REQUEST ROUND NO: 2 TO: BRITISH COLUMBIA HYDRO & POWER

8

Peak Days

Comparison of Total Rate Class LoadsTypical Peak Week Jan 1 - Jan 7, 2005

1,000

1,500

2,000

2,500

3,000

3,500

1 5 9 13 17 21 1 5 9 13 17 21 1 5 9 13 17 21 1 5 9 13 17 21 1 5 9 13 17 21 1 5 9 13 17 21 1 5 9 13 17 21

Hour Ending

MW

Residential General Transmission

Page 12: REQUESTOR NAME: INFORMATION REQUEST ROUND NO: … · 1 REQUESTOR NAME: Joint Industry Electricity Steering Committee INFORMATION REQUEST ROUND NO: 2 TO: BRITISH COLUMBIA HYDRO & POWER

9

Peak HoursRecord Peak Day Load Shape

Domestic System November 2006

7,000

7,500

8,000

8,500

9,000

9,500

10,000

10,500

11,000

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Hour Ending

MW

Nov 29th 2006 Peak Day

November Domestic Peak: 10,113 MWNovember 29, 2006at Hour Ending 18

Note: Peak Day Load Shape not adjusted for Voluntary and Involuntary Outages