21
BASEMENT CONSTRUCTION AND UNDERPINNING METHOD STATEMENT Risner Design, The Bell Tower, 20 Great Peter Street, SW1P 2BU, London [email protected] PROJECT 14A FREEGROVE ROAD CONTRACTOR RISNER DESIGN SITE ADDRESS 14A FREEGROVE ROAD, N7 9JN, LONDON PROJECT START DATE FEBRUARY 2016 EXPECTED DURATION 7 MONTHS PROJECTED COMPLETION DATE SEPTEMBER 2016 NAME TITLE DATE Document Author Mark Risner MR 29.09.15 Authorised by: Daniel Risner MR 29.09.15 EMERGENCY CONTACT DETAILS Contact Mark Risner BA, MA Daniel Risner BA ARCH Ellis Bergman Position CDM Coordinator Project Manager Site Foreman Mobile 07415067718 07594992888 07767795999 Data Protection Statement The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in whole or in part for any purpose whatsoever without the prior written permission from Risner Design Partnership.

Risner Design, The Bell Tower, BASEMENT ... - Islington

  • Upload
    others

  • View
    6

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Risner Design, The Bell Tower, BASEMENT ... - Islington

BASEMENT CONSTRUCTION AND UNDERPINNINGMETHOD STATEMENT

Risner Design, The Bell Tower, 20 Great Peter Street, SW1P 2BU, London [email protected]

PROJECT 14A FREEGROVE ROADCONTRACTOR RISNER DESIGNSITE ADDRESS 14A FREEGROVE ROAD, N7 9JN, LONDONPROJECT START DATE FEBRUARY 2016EXPECTED DURATION 7 MONTHSPROJECTED COMPLETION DATE SEPTEMBER 2016

NAME TITLE DATE

Document Author Mark Risner MR 29.09.15

Authorised by: Daniel Risner MR 29.09.15

EMERGENCY CONTACT DETAILSContact Mark Risner BA, MA Daniel Risner BA ARCH Ellis BergmanPosition CDM Coordinator Project Manager Site ForemanMobile 07415067718 07594992888 07767795999

Data Protection StatementThe information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in whole or in part for any purpose whatsoever without the prior written permission from Risner Design Partnership.

Page 2: Risner Design, The Bell Tower, BASEMENT ... - Islington

BASEMENT CONSTRUCTION AND UNDERPINNINGMETHOD STATEMENT

Risner Design, The Bell Tower, 20 Great Peter Street, SW1P 2BU, London [email protected]

CONTENTS

1.0 Staff Information Sheet

2.0 General Precautions

3.0 Appendix A - Underpinning Temporary Works Sequence Drawings (includes Method Statement for underpinning works)

4.0 Appendix B - Underpinning Risk Assessment

Page 3: Risner Design, The Bell Tower, BASEMENT ... - Islington

BASEMENT CONSTRUCTION AND UNDERPINNINGMETHOD STATEMENT

Risner Design, The Bell Tower, 20 Great Peter Street, SW1P 2BU, London [email protected]

1. STAFF INFORMATION SHEET

The following method statement has been developed to provide a safe system of work and must be adhered to at all times, any significant deviation from this system must first be authorised by your manager or safety representative. Please read the entire sheet be-fore beginning the procedure, if you have any questions please contact your manager or safety representative.

The main hazards to your safety and health are:a) Contact with live services underground.b) Trench collapsec) Injury from incorrect Manual handling.d) Injury from slips trips and falls.e) Severe burns/Contact dermatitis from exposure to wet concrete and dust.f) Disease from standing/stagnant water.g) Injury from the incorrect actions of other contractors on site.h) Injury to members of the public during operations.i) Injury from machine hazards

Preventative Measures you must take:a) You must be “competent” to carry out the task.b) You must NOT carry out this task alonec) Barriers erected at entrances and around the work area if deemed necessary by the foreman or safety officer to protect tenants.d) You must not lift beyond your capabilities, get help if necessary.e) Visitors and other members of staff are prohibited from entry unless accompanied by competent person, all visitors to be issued with personal protective equipmentf) You must read and be familiar with the Safety Data Sheets for concrete which contains first aid, fire fighting, and accidental release measures.g) You must read and understand the information sheet on Leptospirosis

Personal Protective Equipment you must wear:a) Safety Glassesb) Dust maskc) Overallsd) Glovese) Safety boots

Environmental Protection Measures you must take:a) You must dispose of waste and spoil to the designated area or skip provided for waste.

Quality Control:a) Adhere strictly to the following procedure to ensure quality of serviceb) If in doubt contact your manager for clarification before proceeding.

Page 4: Risner Design, The Bell Tower, BASEMENT ... - Islington

2. GENERAL PRECAUTIONS

To be observed by all staff at all times, any deviation from these control procedures must be authorised by the site foreman or safety representative.

Staff and TrainingThe task will be carried out by staff from Risner Design Partnership and Ellis Bergman Build-ing, all staff are experienced and receive ongoing training. Apprentices are under con-stant supervision by senior members of staff.

PPEAll site workers will wear Safety boots Hi Visibility Vests, Hard Hats and protective cloth-ing at all times, other items of PPE such as eye protection, and gloves are available to be worn as and when necessary.

Preparation & InductionA risk assessment will be carried out for all tasks which will be discussed with members of staff and the sub contractors, any queries or concerns will be raised with the contract manager who will ensure it is dealt with. Staff and sub contractors will be inducted onto site by the principal contractor and will follow all site rules and safety procedures.

WelfareThe principal contractor is responsible for providing adequate washing, toilet, drying and refreshment facilities for staff and sub-contractors, staff and contractors are responsible for ensuring that such welfare facilities are maintained in a clean and wholesome man-ner.

First AidIt is the responsibility of all sub-contractors to ensure adequate first aid provision for its staff; Adequate means provision of suitable first aid equipment and the provision of an appoint-ed person as the minimum.

Site Access and EgressThe principal contractor is responsible for providing safe access and egress to the site, Risner Design staff will ensure safe access and egress is maintained for themselves and other contractors in the area they are working in, good standards of housekeeping will be maintained.

Material HandlingAll materials required for site will be unloaded to a designated unloading and storage area which will be away from the work area as far as is practicable. This area will be kept tidy to minimise trip hazards. Materials as and when required will be collected from the storage area to the work area. All staff will take care when handling materials.

BASEMENT CONSTRUCTION AND UNDERPINNING METHOD STATEMENT

Risner Design, The Bell Tower, 20 Great Peter Street, SW1P 2BU, London [email protected]

Page 5: Risner Design, The Bell Tower, BASEMENT ... - Islington

BASEMENT CONSTRUCTION AND UNDERPINNING METHOD STATEMENT

Risner Design, The Bell Tower, 20 Great Peter Street, SW1P 2BU, London [email protected]

Manual HandlingAll staff and contractors have been instructed on the potential dangers of manual han-dling, and have received manual handling training. Staff and contractors will not lift items of tools or equipment beyond their capabilities. Heavy or awkward items will be broken down into smaller units or dual lifted where this is not possible. It is the responsibility ofthe site foreman to identify and control potentially dangerous manual handling situations as they occur on site on a day to day basis.

Contractor/Visitor SafetyRisner Design will liaise with other contractor’s staff on a day to day basis and ensure they are aware of the risks present during the works. Staff and contractors will not leave any area of work in a dangerous condition or with risks to themselves, other contractors, ten-ants, or visitors, all tools and equipment will be cleared to secure storage at the comple-tion of each shift. Scaffold, ladders and any other access to height will be made inacces-sible.

Tools and Electrical EquipmentAll items of tools and equipment will be visually inspected on a regular basis defective or damaged equipment will be removed from service. Electrical tools will be 110V where possible, sub contractors will not be allowed to bring on to site any damaged or defective tools, the site foreman is responsible for ensuring all tools and equipment allowed on the site are fit for purpose

Working at heightAll employees and sub contractors have been made aware of the dangers and conse-quences of falling from height, all working at height will be properly planned, organised and supervised; only competent members of staff will be allowed to work at height and it is the responsibility of the site foreman to ensure conditions are safe before allowingany work at height to take place.

The foreman will carry out a risk assessment before carrying out work at height and put in place equipment and measures to prevent falls occurring.

Where he cannot eliminate the risk of a fall he will put in place measures and equipment to minimise the distance and consequences of a fall, should one occur.

All company access equipment will be inspected on a regular basis and any damaged equipment will be withdrawn from service immediately. Sub contractors will follow all safe working procedures

Portland cementPortland cement is a light gray powder that poses little immediate hazard. A single short term exposure to the dry powder is not likely to cause serious harm. However, exposure of sufficient duration to wet Portland cement can cause serious, potentially irreversible tissue (skin or eye) destruction in the form of chemical (caustic) burns. The same type of tissue

Page 6: Risner Design, The Bell Tower, BASEMENT ... - Islington

BASEMENT CONSTRUCTION AND UNDERPINNING METHOD STATEMENT

Risner Design, The Bell Tower, 20 Great Peter Street, SW1P 2BU, London [email protected]

destruction can occur if wet or moist areas of the body are exposed for sufficient duration to dry Portland cement.

All persons exposed to Portland cement must ensure that they have sufficient protection from the caustic effects of cement. Staff will wear impervious gloves overalls and wel-lington boots, eye protection must be used during mixing, working and laying of Portland cement and its products. Periodic occupational health checks should be made on those who are regularly exposed to this medium.

Page 7: Risner Design, The Bell Tower, BASEMENT ... - Islington

BASEMENT CONSTRUCTION AND UNDERPINNING METHOD STATEMENT

Risner Design, The Bell Tower, 20 Great Peter Street, SW1P 2BU, London [email protected]

Appendix A - Temporary Works Sequence Drawings (includes method statement for underpinning works)

The following temporary works sequence drawings include MSJ Design Limited (Structural Engineer).

Page 8: Risner Design, The Bell Tower, BASEMENT ... - Islington

1. The foundations underpinning is to be carried out in a sequential “hit-and-miss” fashion,

where individual underpinning/retaining wall bases are constructed in a scattered arrangement

around the perimeter of the specified walls, in accordance with the numbered sequence.2. The excavations of individual pins will be carried out by hand, to profile as shown.

3. The sequence of construction is indicated with the circled numbers shown on the individualunderpin base.

4. Note that the underpinning operation is to be carried out in a sequential operation observing

the time gaps between the steps as specified.5. The contractor will provide all necessary shoring, propping, shuttering etc to ensure that the

subject and adjoining properties are fully secured against any movement, slippage or similar,and also that the concrete is cast to the exact profile as indicated.

THIS DRAWING IS TO BE READ IN

CONJUNCTION WITH HUUKARCHITECTS LIMITED DRAWINGS,

MSJ DESIGN LIMITED DRAWINGS

AND HEALTH AND SAFETYDIRECTIVES

TEMPORARY HOARDINGS

NOTE: THE FOLLOWING SEQUENCE OF

WORKS STAGE DIAGRAMS INCLUDE MSJDESIGN LIMITED 'CONSTRUCTION OF

UNDERPINNING STRUCTURES' NOTES 1 TO 9

AS INDICATED ON MSJ DESIGN LIMITEDDRAWINGS: 23051/701-704

RISNER DESIGN

Page 9: Risner Design, The Bell Tower, BASEMENT ... - Islington

a. Excavate the individual underpin profile as shown on the typical underpin section.

b. As excavation progresses, apply shuttering ply to the back of the excavation, propped with a

raking accrow prop as necessary to hold the excavation.

PUSH PULL PROPS

INDICITIVE (RAKING ASREQUIRED)

WALE

STEEL TRENCH SHEETS AND TRENCH PROPSAT MAXIMUM 900MM CENTRES

PROP ENDS BEARINGINTO EXCAVATION FACE

TO BE FITTED WITH

250MM X 350MM

SPREADERS.EXCAVATIONS TO BE

PLANKED AND

STRUTTEDTHROUGHOUT

Page 10: Risner Design, The Bell Tower, BASEMENT ... - Islington

c. After two to three pins review the situation with the Engineer or Party Wall Surveyor and if

excavations are holding on their own seek agreement that temporary shoring of the backs of

the excavations are not necessary.d. Level the bottom of footing and blind if necessary with 50-100mm lean mix concrete. Apply

reinforcing cage to the bottom of the pit and to the vertical face of the wall.e. Apply dowel bars to the sides of excavation for continuation into the adjoining bays

f. Apply dowel bars to the front of the excavation for continuation into basement slab.

SAFE SLOPE

ANGLES

PUSH PULL PROPS

INDICITIVE (RAKING ASREQUIRED)

WALE

STEEL TRENCH SHEETS AND TRENCH PROPSAT MAXIMUM 900MM CENTRES

Page 11: Risner Design, The Bell Tower, BASEMENT ... - Islington

g. Apply concrete to the bottom excavation, with 150mm upstand kicker into the vertical face.

Vibrate and compact as necessary.

Page 12: Risner Design, The Bell Tower, BASEMENT ... - Islington

h. 24 hours after the base pour, shutter the rest of the section up to underside of existing

foundation and apply concrete. Vibrate and compact as necessary.

*RETAIN TEMPORARY ACCROW (OR RMD OR MABEY) BETWEEN NEW WALLS AND SIDEOF EXCAVATION

Page 13: Risner Design, The Bell Tower, BASEMENT ... - Islington

i. 36 hours later, apply drypack between foundation and top of new concrete.

7. The concrete is to be Grade C35, with a maximum aggregate size of 20mm. GGBS or PFAcan be added to the concrete mix for enhancement of mixture resistance of concrete, to

Specialist Concrete Manufacturer’s detail specification.

8. The adjoining bays must not be excavated within less than 48 hours after drypacking themost recently constructed adjacent bay.

9. The contractor will provide all necessary shoring, propping, shuttering etc to ensure that thesubject and adjoining properties are fully secured against any movement, slippage or similar,

and also that the concrete is cast to the exact profile as indicated.*FULL WIDTH TEMPORARY RMD OR MABEY PROPPING INSTALLED ACROSS SITE UNTIL

THE BASE SLAB HAS CURED

FULL WIDTH TEMPORARY RMD OR MABEY

PROPPING INSTALLED ACROSS SITE UNTIL

THE BASE SLAB HAS CURED (MAXIMUMHEIGHT TO BE 1/3RD HEIGHT OF EXCAVATION

TO HELP REDUCE ANY ROTATIONAL SLIDING

AT THE BASE)

Page 14: Risner Design, The Bell Tower, BASEMENT ... - Islington

10. When all the underpins in one underpinning group are completed, the floor slabs inside

that area is to be constructed to detail shown; as follows;

11. Excavate central section of the relevant area of site, install reinforcement for the slab.

12. Apply concrete to the basement slab, compact and cure.

Page 15: Risner Design, The Bell Tower, BASEMENT ... - Islington

BASEMENT CONSTRUCTION AND UNDERPINNING METHOD STATEMENT

Risner Design, The Bell Tower, 20 Great Peter Street, SW1P 2BU, London [email protected]

Appendix B - Underpinning Risk Assessment

Page 16: Risner Design, The Bell Tower, BASEMENT ... - Islington

RISK ASSESSMENT

Risner Design, The Bell Tower, 20 Great Peter Street, SW1P 2BU, London [email protected]

RISK ASSESSMENT

9-10 Jew Street, Brighton, BN1 1UT

01273 711602 [email protected]

Task Description Underpinning Location 13 Guthrie St Date 20/04/15

Hazard / Consequences

Control Procedures Likelihood (a)

Severity (b)

Risk Ranking (= a x b)

Injury from live services underground; contact with live parts causing shock and burns (normal mains voltage, 230 volts AC, can kill)

Follow HSG 47 “Avoiding Danger from Underground Services”. Always assume cables will be present when digging in the street, pavement or near buildings. Use up-to-date service plans, cable avoidance tools and safe digging practice to avoid danger. Service plans should be available from regional electricity companies, local authorities, highways authorities, etc. Have the power switched off by the local electricity distributor. Consider all conductors live unless it is positively known they have been de-energised, isolated and earthed by the local electricity distributor. Workers must be deemed competent to carry out this task.

1 5 5

Hazard / Consequences

Control Procedures Likelihood (a)

Severity (b)

Risk Ranking (= a x b)

Excavation collapse

No machines allowed near excavation All trenches to be braced timber (or metal trench sheets) shuttering, and sandbagged. Barriers to be put around all excavations Foreman to carry out regular inspections on excavations. Access via short timber ladder Banksmen to be placed when work anyone is working in the trench. Evacuation hoist to be provided. Emergency procedures for collapse to be made and in place. Surveillance of trench walls, support systems and excavations should be carried out by a competent person frequently and recorded.

1 5 5

14A Freegrove Rd 29/09/15

Page 17: Risner Design, The Bell Tower, BASEMENT ... - Islington

RISK ASSESSMENT

Risner Design, The Bell Tower, 20 Great Peter Street, SW1P 2BU, London [email protected]

RISK ASSESSMENT

9-10 Jew Street, Brighton, BN1 1UT

01273 711602 [email protected]

Task Description Underpinning Location 13 Guthrie St Date 20/04/15

Hazard / Consequences

Control Procedures Likelihood (a)

Severity (b)

Risk Ranking (= a x b)

Inclement weather

All staff have been informed of the greater risk of injury when working in inclement weather, all frost and snow will be cleared from access equipment and roofs if work in these conditions cannot be avoided. Staff to be issued with appropriate PPE including waterproofs, warm jumpers, coats hats and gloves as appropriate to conditions. The site foreman is responsible for suspending work if weather conditions make the task unsafe. Ensure safety of electrical equipment in wet weather as unsuitable equipment can easily become live and make its surroundings live. Take account of weather conditions, wear appropriate clothing and take warm drinks in cold weather, cover up or apply sun block to prevent sunburn.

2 3 6

Hazard / Consequences

Control Procedures Likelihood (a)

Severity (b)

Risk Ranking (= a x b)

Injury from slips trips and falls

All staff will keep the working area tidy and remove trip hazards as and when they occur. All staff will wear suitable footwear at all times.

1 3 3

14A Freegrove Rd 29/09/15

Page 18: Risner Design, The Bell Tower, BASEMENT ... - Islington

RISK ASSESSMENT

Risner Design, The Bell Tower, 20 Great Peter Street, SW1P 2BU, London [email protected]

RISK ASSESSMENT 9-10 Jew Street,

Brighton, BN1 1UT 01273 711602

[email protected]

Task Description Underpinning Location 13 Guthrie St Date 20/04/15

Hazard / Consequences

Control Procedures Likelihood (a)

Severity (b)

Risk Ranking (= a x b)

Injury from incorrect manual handling

Staff trained in correct lifting methods Lifting equipment provided where loads are heavy including sack / wheel barrows or chain hoists or rope hoists where appropriate Dual lifting to be used on awkward lifts

1 3 3

Hazard / Consequences

Control Procedures Likelihood (a)

Severity (b)

Risk Ranking (= a x b)

Illness from exposure from Asbestos

Asbestos is highly dangerous. Any asbestos-containing materials on site should have been identified before work starts.

If you come across any hidden or dusty materials which you suspect may contain asbestos, stop work and get advice. A specialist survey will then be carried out to determine the extent and nature of the asbestos risk to your staff.

It is strictly forbidden to work near items suspected of containing asbestos

1 5 5

Hazard / Consequences

Control Procedures Likelihood (a)

Severity (b)

Risk Ranking (= a x b)

Injury to other construction workers and members of the public during operations.

It is vitally important that potentially hazardous areas are signposted, barricaded and, where appropriate, covered to avoid possible injury to workers and members of the public. Anyone who may be affected by the works to be informed of site work, especially tenants and other contractors. Site to be secured to prevent un-authorised access. Foreman is to ensure no one access site without permit, or permission. Staff will cordon off work area and ensure tenants do not enter area of danger. Hand tools and power tools will not be left unattended. The site will be made safe at the end of

1 4 4

14A Freegrove Rd 29/09/15

Page 19: Risner Design, The Bell Tower, BASEMENT ... - Islington

RISK ASSESSMENT

Risner Design, The Bell Tower, 20 Great Peter Street, SW1P 2BU, London [email protected]

RISK ASSESSMENT 9-10 Jew Street,

Brighton, BN1 1UT 01273 711602

[email protected]

Task Description Underpinning Location 13 Guthrie St Date 20/04/15

each shift. Staff will follow the method statement devised for this task.

Hazard / Consequences

Control Procedures Likelihood (a)

Severity (b)

Risk Ranking (= a x b)

Injury from power tool hazards and machine hazards

All power tools and machinery must comply with Provision and Use of Work Equipment Regulations 1992. All employees and contractors must have received instruction in the safe use and operation of the equipment they are proposing to use. Eye protection must be worn at all times when there is a risk of flying parts, dust or fragments. All power tools and machinery must be regularly inspected and maintained in good condition.

2 3 6

Hazard / Consequences

Control Procedures Likelihood (a)

Severity (b)

Risk Ranking (= a x b)

Machine and vehicle movement on site

Only fully trained / license holders to use vehicles / machinery on site. Spotters to be used for reversing, vehicles fitted with audible warnings when in operation on site Vehicle movement to be planned and co-ordinated at all times All site workers to wear Hi Vis clothing. Warning whistles issued to allow audible danger warnings All vehicles and machinery to be maintained in correct manner and any required maintenance work to be carried out. Ensure vehicles are not moving in designated working areas, have a separate area for deliveries.

1 5 5

14A Freegrove Rd 29/09/15

Page 20: Risner Design, The Bell Tower, BASEMENT ... - Islington

RISK ASSESSMENT

9-10 Jew Street, Brighton, BN1 1UT

01273 711602 [email protected]

Task Description Underpinning Location 13 Guthrie St Date 20/04/15

Hazard / Consequences

Control Procedures Likelihood (a)

Severity (b)

Risk Ranking (= a x b)

Contact with wet concrete and dust causing severe burns, dermatitis etc

Follow HSE guidance from form INDG323 and ensure all employees are aware of this guidance and all appropriate measures are taken to reduce contact and provide appropriate washing facilities and PPE. Regular monitoring to spot early signs of contact dermatitis.

1 1 2

Hazard / Consequences

Control Procedures Likelihood (a)

Severity (b)

Risk Ranking (= a x b)

Disease from standing/stagnant water can cause Leptospirosis (weils Disease)

Staff will be given information on Leptospirosis and instructed to minimise contact with dirty water, good hygiene procedures will be followed to prevent transmission from hands to mouth etc

2 2 4

Likelihood Severity Priority

1 Highly Unlikely 1 Trivial 1 Urgent action – (Risk no 15 – 25)

2 Unlikely 2 Minor Injury 2 High Priority – (Risk no 10 – 12)

3 Possible 3 Over 3 day Injury 3 Medium Priority – (Risk no 5 – 9)

4 Probable 4 Major Injury 4 Low Priority – Risk no (2 – 4)

5 Certain 5 Incapacity or Death 5 Very Low Priority– No Action required (Risk no 1)

RISK ASSESSMENT

Risner Design, The Bell Tower, 20 Great Peter Street, SW1P 2BU, London [email protected]

14A Freegrove Rd 29/09/15

Page 21: Risner Design, The Bell Tower, BASEMENT ... - Islington