1 P. Julien S. Ikeda River Engineering and Stream Restoration Pierre Y. Julien Hong Kong - December 2004 River Engineering and Stream Restoration I - Stream Restoration Objectives Brief overview of River Engineering and Stream Restoration with focus on : 1. River Equilibrium; 2. River Dynamics; 3. River Engineering; 4. Stream Restoration.

River Engineering and Stream Restoration River Engineering and

  • Upload
    others

  • View
    7

  • Download
    0

Embed Size (px)

Citation preview

Page 1: River Engineering and Stream Restoration River Engineering and

1

P. Julien S. Ikeda

River Engineering and Stream Restoration

Pierre Y. Julien

Hong Kong - December 2004

River Engineering and Stream Restoration

I - Stream Restoration

Objectives

Brief overview of River Engineering and Stream Restoration with focus on :

1. River Equilibrium; 2. River Dynamics;3. River Engineering;4. Stream Restoration.

Page 2: River Engineering and Stream Restoration River Engineering and

2

Objectives

Part Ia – Equilibrium and Bank Protection

1. Concept of Equilibrium, environmental river mechanics and bank protection

2. Provide Three basic laws for Stream Restoration

#1 There is no cookbook approach to stream restoration projects.

Three Laws of Stream Restoration

Concept of Equilibrium

Page 3: River Engineering and Stream Restoration River Engineering and

3

#1 There is no cookbook approach to stream restoration projects.

#2 Solutions normally require equilibriumconditions between sediment regime and stream ecology.

Three Laws of Stream Restoration

Page 4: River Engineering and Stream Restoration River Engineering and

4

Page 5: River Engineering and Stream Restoration River Engineering and

5

Figure 3.3 Typical Meandering River

Page 6: River Engineering and Stream Restoration River Engineering and

6

• The system is dynamic

• A stable river is one in which, over a period of years, slope is delicately adjusted to provide just the velocity required to transport the available water & sediment supplied from the drainage basin.

(… after Mackin, 1948)

Page 7: River Engineering and Stream Restoration River Engineering and

7

Page 8: River Engineering and Stream Restoration River Engineering and

8

2. Bank Protection

Page 9: River Engineering and Stream Restoration River Engineering and

9

Page 10: River Engineering and Stream Restoration River Engineering and

10

Figure 7.6 Launched Windrow Rock

Figure 7.10 Longitudinal Stone Fill Toe Protection Placed Adjacent to Bank WithTiebacks

Page 11: River Engineering and Stream Restoration River Engineering and

11

Figure 7.3 Schematic Diagram of Windrow Revetment

Figure 7 5 Placement of Windrow Rock in Excavated Trench on Top Bank

Page 12: River Engineering and Stream Restoration River Engineering and

12

Figure 8.2 Typical Impermeable Dikes

Page 13: River Engineering and Stream Restoration River Engineering and

13

Page 14: River Engineering and Stream Restoration River Engineering and

14

Page 15: River Engineering and Stream Restoration River Engineering and

15

#1 There is no cookbook approach to stream restoration projects.

#2 Solutions normally require equilibrium conditions between sediment regime and stream ecology.

#3 Solutions need to be effective, environmentally acceptable and economical.

Three Laws of Stream Restoration

Erosion and River Mechanics Textbooks

NEW!!www.cup.org

Page 16: River Engineering and Stream Restoration River Engineering and

16

Objectives

Part Ib – River Dynamics and Response

1. Deforestation impact on rivers 2. The concept of time scales3. Headcutting and degradation

Peligre Dam in Haiti (deforestation)

Peligre Dam (sedimentation)

Page 17: River Engineering and Stream Restoration River Engineering and

17

Peligre Dam (reduced life expectancy)

#1 Deforestation may impact river equilibrium for a very long time.

River Dynamics

Time Scale

• Geological ~ 1,000,000 years

• Engineering ~ 100 years

• Aquatic life ~ 1 year

Page 18: River Engineering and Stream Restoration River Engineering and

18

1935 1972 1992

Hydraulic geometry of the Rio Grande

Restoration•returning a resource to some former condition.

Rehabilitation•maximize the potential beneficial uses of a resource to some reasonable and practical level.

Restoration vs Rehabilitation

Page 19: River Engineering and Stream Restoration River Engineering and

19

MEI

Jetty System (near Bernardo), USACE 1963

Jetty fields and vegetation of the Rio Grande

Bernardo Gage

Debris Deposition

Page 20: River Engineering and Stream Restoration River Engineering and

20

Debris Deposition

#1 Deforestation may impact river equilibrium for a very long time.

#2 Stream restoration/rehabilitation may be effective only after a long period of time

River Dynamics

Bank Caving

Page 21: River Engineering and Stream Restoration River Engineering and

21

Bank Caving

Bank Caving

Page 22: River Engineering and Stream Restoration River Engineering and

22

Headcutting

Headcutting

65

70

75

80

85

90

0 5000 10000 15000 20000 25000

Meters Upstream of Highway 8

Yalo

bush

a R

iver

Tha

lweg

Ele

vatio

n (m

)

Page 23: River Engineering and Stream Restoration River Engineering and

23

Vertical Degradation

Headcutting

Vertical Degradation

Page 24: River Engineering and Stream Restoration River Engineering and

24

Page 25: River Engineering and Stream Restoration River Engineering and

25

Page 26: River Engineering and Stream Restoration River Engineering and

26

Page 27: River Engineering and Stream Restoration River Engineering and

27

#1 Deforestation may impact river equilibrium for a very long time.

#2 Stream restoration/rehabilitation may be effective only after a long period of time

#3 Looking downstream may prevent headcutting and severe degradation problems

River Dynamics

ASCE Journal of Hydraulic Engineering

Page 28: River Engineering and Stream Restoration River Engineering and

28

Erosion and River Mechanics Textbooks

NEW!!www.cup.org

Objectives

Part Ic – Guidelines and Case Study

1. Guidelines for Stream Restoration Projects2. Case-study on the Rio Grande

Page 29: River Engineering and Stream Restoration River Engineering and

29

Stream Restoration Guidelines

1. OBJECTIVES - Clearly define the engineering and ecological objectives. Restoration vs rehabilitation.

2. PAST, PRESENT and FUTURE – Consider present conditions in the perspective of past events and examine future changes.

• Protect Levee• Create a Functioning Floodplain• Improve Wildlife Habitat

Rio Grande Restoration– Santa Ana

Project Goals

Bed material size

-1.6

-1.4

-1.2

-1.0

-0.8

-0.6

-0.4

-0.2

0.0

0.2

0.4

2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

CO-line Number

Chan

ge in

Mea

n Be

d El

evat

ion

(m)

Reach 1 Reach 2 Reach 3 Reach 4

Change in Mean Bed Elevation

Active channel width Sinuosity

1.00

1.05

1.10

1.15

1.20

1.25

Reach 1 Reach 2 Reach 3 Reach 4

Sinu

osity

1918193519491962197219851992

0

50

100

150

200

250

300

350

Reach 1 Reach 2 Reach 3 Reach 4

Reac

h Av

erag

ed A

ctiv

e Ch

anne

l Wid

th (

m)

1918193519491962197219851992

0.1

1

10

100

Reach 1 Reach 2 Reach 3 Reach 4

Med

ian

bed

mat

eria

l siz

e, d

50 (

mm

) 1918193519491962197219851992Gravel

Sand

Hydraulic geometry of the Rio Grande

Page 30: River Engineering and Stream Restoration River Engineering and

30

Stream Restoration Guidelines3. UPPER WATERSHED – Look at the

geology, deforestation, land use changes, urbanization, climate and extreme events. Examine water and sediment supply, flood frequency curves, sediment mass curves sediment concentrations, water quality, etc.

4. DOWNSTREAM REACH – Look at possible changes in the downstream reach that may affect current conditions – like reservoirs, base level changes, headcutting, etc.

Hydraulic geometry of the Rio Grande

Stream Restoration Guidelines

5. CHANNEL GEOMETRY – Determine equilibrium downstream hydraulic geometry in terms of width, depth, velocity, slope, discharge and morphology.

6. AQUATIC HABITAT– determine appropriate aquatic habitat conditions including low and high flow periods, pools, riffles, spawning grounds, shade, aeration, migration, etc.

Page 31: River Engineering and Stream Restoration River Engineering and

31

Santa Ana Reach - Mid 80’s

Santa Ana Reach – Mid 90’s

Rio Grande Restoration– Floodplain restoration

• Sandy/silty substrate• Shallow water h < 0.4 m• Water velocities

0.1 m/s < V < 0.5 m/s

• Bimodal sand/gravel bed• Deep water h ~ 1.20 m• Water velocities 1.4 m/s

Restoration• Create wider channels

Rio Grande Restoration– Endangered Species

Stream Restoration Guidelines

7. EXAMINE ALTERNATIVES – Identify several different stream rehabilitation schemes that would suit the engineering and environmental needs.

8. DESIGN SELECTION – examine the various alternatives and select the best possible alternative and proceed with the design. Solution must be effective, environmentally sound and economical.

Page 32: River Engineering and Stream Restoration River Engineering and

32

Gradient Restoration Facility• Raise Riverbed with GRF

River Realignment

• Construct Bio-engineering Bankline

Page 33: River Engineering and Stream Restoration River Engineering and

33

Floodplain Maintenance• Lower Terraces with Heavy Equipment

Floodplain Restoration

• Excavated Sediment Placed near Pilot Channel

Habitat Improvement

• Sediment Storage Upstream from GRF• Low Velocity Overbank Flows• Planting and Natural Reseeding of Native Vegetation

Page 34: River Engineering and Stream Restoration River Engineering and

34

Pilot Channel – Pre-Watering

Stream Restoration Guidelines

9. CONSTRUCTION – Carefully plan the construction and consider the possible impact of possible extreme events during the construction period.

10. MONITORING – Things may not work as planned. A post-construction analysis and monitoring should be carried out until the objectives have been met.

Opening Pilot Channel

Page 35: River Engineering and Stream Restoration River Engineering and

35

River Realignment• Divert River into Pilot Channel

Pilot Channel Widening

Spring Runoff - 2001

Page 36: River Engineering and Stream Restoration River Engineering and

36

Post-Runoff Assessment

• More Gravel than Anticipated• Mean Bed Elevation 2 ft Higher than Anticipated• Pilot Channel 50-100 ft Narrower than Desired

Effects on Bio-engineering

• Most Willows in Fabric Encapsulated Soil (FES) Completely Submerged

• Sections of Bio-engineering Covered in Sediment

Rio Grande Conclusions

• Thoroughly study river mechanics and apply finding to the design process.

• Understand the evolution of the project and consider intermediate conditions.

• Be Flexible…Apply adaptive management techniques.

Page 37: River Engineering and Stream Restoration River Engineering and

37

Stream Restoration Guidelines1. Clearly define the OBJECTIVES2. PAST, Present and FUTURE3. Look at the UPPER WATERSHED4. Look DOWNSTREAM for degradation5. EQUILIBRIUM Hydraulic Geometry6. Appropriate AQUATIC HABITAT7. Examine various design ALTERNATIVES8. DESIGN must be Effective, Environmentally sound

and Economical 9. Plan CONSTRUCTION for the unexpected10. Post-construction MONITORING