Upload
saurabh-garg
View
221
Download
0
Embed Size (px)
Citation preview
7/31/2019 Robin Report1
1/44
1
SUMMER TRAINING REPORT(11.06.2012-20.07.2012)
(LARSEN & TOUBRO CONSTRUCTIONS)
Construction of Air Traffic Control Tower (ATC) &
Associated Works
DCRUST, Murthal
SUBMITTED BY:-ROBIN KUKREJA
ROLL NO. :- 0909044
FINAL YEAR B.Tech (Civil Engineering)
7/31/2019 Robin Report1
2/44
2
ACKNOWLEDGEMENT
I would like to take this opportunity to thank Larsen & Toubro
Limited for giving me an opportunity to do my internship with them.
I express my sincere thanks and gratitude towards Mr.Rakesh Kumar
Singh (Project Manager) and Ms.Pooja Mishra (Assistant Planning
Manager) who guided me and provided valuable inputs and insights
throughout the internship.
I would also like to express my special gratitude and thanks toMr.ShushilKumar (Sr. Engineer) and other site engineers for giving me
such attention and time.
Mr. Ashim Gupta,for familiarizing me with the processes and details of
site work
My thanks and appreciation also goes to my colleagues for their special
co-operation and people who have willingly helped me out with their
abilities.
7/31/2019 Robin Report1
3/44
3
CONTENT
1. Introduction 42.Air traffic control tower model picture 63.Construction: ATC Tower 8-114.Construction: ACC and TBB 12-165.Earth work 17-196.Waterproofing 20-237.Reinforcement 23-27
a)Re baring8.Concreting 28-359. Injection grouting 36-39
10. Brick work 40-4311. Safety precaution 44
7/31/2019 Robin Report1
4/44
4
INTRODUCTION
During Summer vacations after completed3rd
year in Deenbandhu
Chotu Ram Engineering College, Murthal,Sonipat, I did six week
internship (from 11.06.2012 to 20.07.2012) wit LARSEN & TOUBRO
LIMITED (ECC DIVISION).
Project: ATC Tower & Associated Works at T3-DIAL, IGI Airport, New
Delhi
Project detail:- New Control Tower Construction consists of Air
Traffic Control Tower (ATC), Area Control Centre Building (ACC), Tower
Base Building (TBB) & Link Bridge
1.Client Delhi International Airport Ltd.2.Contractor L&T (ECC Division B&F BU)3.Architect HOK International, London4.Structural Consultant BuroHappold UK, Taylor Devices
India Pvt. Ltd.
5.Area Control Centre BUA 25,185 Sq.m. (approx.); B+4 Floor6.Tower Base Building BUA 9,375 Sq.m. (approx.); 4 Floor7.ATC Tower BUA 2154 Sq.m. (102 m Ht.)This tower is 3rd
highest ATC tower of the world & highest ATC tower of the
Asia. 26 Floors
To manage site requirements below mentioned area are covered:Steel
yard, Form work yard, Batching Plant & Basic Infrastructure Facilities.
7/31/2019 Robin Report1
5/44
5
The new Air Traffic Control Tower at Delhis Indra Gandhi International
Airport will be the countrys tallest ATC once constructed .It will stand
102m tall with 26 controller postion with a 360-degree view at the
visual control room and 12 ground controller positions at operationallevel. The tower will employ the Tuned Mass Damper (TMD) technology,
first of its kind in India, to reduce the building sway due to lateral forces
such as wind and earthquake forces.
The ATC tower has two associated building for control and functionthe
Area Control Centre (ACC) and the Tower Base Building (TBB).These
buildings are G+4 structures. These buildings will house the equipments
required for air traffic control.
The ATC Tower is scheduled for completion in a time period of 22
months and commissioned in October 2013. It will be fully functional by
2014. The associated works-ACC and TBB- are scheduled for completion
in 12 months and commissioned by 1st
Janaury 2013
7/31/2019 Robin Report1
6/44
6
AIR TRAFFIC CONTROL TOWER PROJECT
MODEL PICTURE
7/31/2019 Robin Report1
7/44
7
CONSTRUCTION
AREA TRAFFIC CONTROL TOWER(ATCC)
AREA CONTROL CENTRE(ACC)
TOWER BASE BUILDING(TBB)
7/31/2019 Robin Report1
8/44
8
AIR TRAFFIC CONTROL TOWER
The ATC Tower ,once constructed ,will be the tallest ATC in India with a
height of 102m. Also,it will be the 7th
tallest ATC Tower in the world.It
will consist of 26 floors and be made of Self Compacting Concrete (SCC)
of varying grades. The facing of the tower will be in Glass Reinforced
Concrete (GRC).
The construction sequence of the ATCTower are furnished below:
PILLING DETAILS
REINFORCEMENT CONCRETING
1.PILING DETAILS:
The type of foundation selected for the Air Traffic Control Tower on the
basis of Geotechnical Investigation Report was Bored Cast In-Situ
Friction Piles. The geotechnical report classified the soil as Sandy Silt
Soil with a CBR value of 9-13%
A)FONDATION DETAILS
The details of the foundation are:
PILES
Diameter of Pile :1500mm
Depth of Piles : 23.5m
No. of Concrete: M30(SCC)
PILE CAP
7/31/2019 Robin Report1
9/44
9
Area of Pile Cap :650.301 sqm
Height : 3m
Grade of Concrete :M40(SCC)
B) PROCEDURE FOR FOUNDATION WORKS
a)Procedure for Piling Works
The procedure for piling works is essentially a two component
procedure .It includes :
Pile Load Test
Piling WorkPILE LOAD TEST
The Pile Load Test was conduted as described below
7/31/2019 Robin Report1
10/44
10
TEST PROCEDURE as per IS 2911(Part-4)-1985
1.Preparation of Pile HeadThe top of pille head shall be exposed and top of concrete
chipped off upto the required test level .The top of the pile head
shall be finished smooth and level with non-shrink grout material.
Two bearing plates of suitable size and thickness 60mm shall be
placed one above the other on the of the pile for the jack to rest.
2.Kent Ledge ArrangementA Platform shall be made of steel joist with primary and
secondary girders . The Centre of Gravity (C.G) of this platform
should concide with the C.G of the pile head .Dead weights such
as concrete block or sand bags should be placed aove the
platform to obtain the necessary reaction.The reaction available
should be 25% more than the test load proposed.
3. Intial Load Tests on Test PilesThe intial pile is tested upto 3 times the design load or up to
failure whichever occurs earlier .The test is carried out by applyinga series of vertical downward incremental loads, each increment
being about 20% of the design load. At each load increment ,the
pile deflection shall be observed accurate to 0.02 mm at an
interval upto a time when the rate of settlement reduces to either
0.1 mm in first 60 minutes or 120 minutes ,whichever occurs first.
The final load shall be maintained for 24 hours and reading
recorded for 5,10,15,30,60,90,120 minutes and at every hour till24 hour completes.
7/31/2019 Robin Report1
11/44
11
ii) Procedure for Mass Concreting of the Pile cap of ATC Tower
Dimension of Pile Cap and Type of Concrete:
Area : 650.301
Height: 3m
Total Quantity of Concrete :1780 cum
Grade of Concrete:M40(SCC)
Placement Temprature:550mm(min)
Mock Up Test for Pile Cap:
A mock-up test was conducted in the laboratory prior to the actual
concrete placement at site.The mock-up was conducted to determine
the temperature changes in the mass concrete due to heat of hydration
process.
Scope: To find the temperature changes in the concrete due to heat of
hydration process.
Concrete: 3.0 cum fresh concrete of Grade 40(SCC) was cast in a cube
of dimensions 1.5m x 1.5m x 1.35m
Insulations:100mm thick Polyurethane foam insulation materials were
placed on the inner sides of the formwork.
Reinforcements: Reinforcements of diameter 10mm@100mm c/c
spacing were placed at top buttom and sides.
Placement of Thermocouples: The thermocouples are placed as shown
in the diagram:
7/31/2019 Robin Report1
12/44
12
AREA CONTROL CENTRE (ACC) & TOWER
BASE BUILDING(TBB)
Construction sequence in ACC and TBB
1 SUBSTRUCTURE:
a)EARTHWORK
Excavation Sand Filling PCC Water Proofing Screed(50mm)b)RAFT
Reinforcement Shuttering Concreting
2. SUPERSTRUCTURE:
a)VERTICAL: Retaining Walls,Columns,Shear Walls and Staircases
Reinforcement Shuttering Concreting
b)HORIZONTAL : Beams & Slabs
Reinforcement Shuttering Concreting
7/31/2019 Robin Report1
13/44
13
1.SUBSTRUCTURE
a)EATHWORK
Excavation:The excavation work commences after settingout of levels by the surveyor. The depth to be excavated
is determined by the design consideration . For example :
In the basement of the ACC building 6m of soil was
excavated for basement construction.
Sand Filling:Sand Filling was done in expansion jointbetween the upper raft and basement raft of ACC and
TBB . The sand used for sand fillng is obtained from
suitable source and compacted to required density before
fillng .
PCC: After sand filling,a layer of Plain Cement Concrete(PCC) 1:6:12 is applied .The grade of this concrete is M10
Water Proofing: The Material used for water proofing isPolyurethane. It is a derivative of bituminous water
proofing and is applied on the retaining wall between the
basement raft and upper raft of ACC
Screed: A floor usually a cementitous material made froma 1:3 or 1:4:5 ratio of cement to sharp sand.It may be
apllied onto either a solid in-situ concrete ground floor
slab or onto a precast concrete floor unit. The screed may
be directly bonded to the base ,with a minimum thickness
of 40mm, laid bounded onto a suitable damp proofmembrane ,which is placed over the slab , with a
minimum thickness of 50mm
2.SUPERSTRUCTURE
7/31/2019 Robin Report1
14/44
14
A) VERTICAL
Columns Shear Wall
i) Columns: Reinforcement
Columns, the vertical members in RC building
contain two types of steel reinforcement, namely
a)Long straight bars placed vertically along the length.b)Closed loops of small diameter steel bars placed horizontally
at regular intervals along its full length
Design strategy of columns as per IS 456-2000 and IS 13920-
1993
(a)Closely spaced ties must be provided at the two ends of thecolumn over a length not less than larger dimension of the
column, one-sixth the column height or 450mm.
(b) Over the distance specified in item (a) above and below abeam-column junction, the vertical spacing of ties in columns
should not exceed D/4 for where D is the smallest dimension of
the column (e.g.: in rectangular column, D is the length of the
small side). This spacing need not be less than 75mm nor more
than 100mm. At other locations, ties are spaced as percalculations but not more than D/2.
(c)The length of tie beyond the 1350 bends must be at least 10 timesdiameter of steel bar used to make the closed tie;this extension
beyond the bend should not be less than 75mm.
7/31/2019 Robin Report1
15/44
15
Lapping of Vertical BarsIn the construction of RC buildings, due to limitation in available length
of bars and due to constraints in construction, there are numerousoccasions when columns bars have to be joined. A simple way of
achieving this is by overlapping the two bars over at least a minimum
specified length, called lap length. The lap length depends on type of
reinforcement and concrete. For ordinary situations, it is about 50
times bar diameter. Furthur, IS13920-1993 prescribes that the lap
length would be largest only in the middle half of column and not near
its top or bottom ends. Also, only half the vertical bars in column are to
be lapped at a time in any storey . Furthur, when laps are provided, tiesmust be provided along the length of the lap at spacing not more than
150mm.
ShutteringShuttering of the columns is checked with the help of plumb
bobs.The perpendicular distance between the plunb thread and
formwork surface is measured at the top and bottom to ensure
vertically of the column formwork
Concreting:Concrete of grade M40 SCC is used for the columns .The concrete is
placed using boom placers and then vibrated using vibrators of
diameter 40mm or 60mm as applicable.The shuttering of columns isremoved after a period of 24 hours after which the concrete is
cured till it attain its required strength.
7/31/2019 Robin Report1
16/44
16
ii)Shear Walls
Reinforced concrete (RC) building often have vertical plate-like RC wallsin addition to slabs ,beams and columns .these walls generally at
foundation level and are continous throughout the building height.
Therir thickness can be as low as 150mm,or as high as 400mm in high
rise buildings. Shear wall are provided along both length and width of
building shear walls are alike vertically oriented beams that carry
earthquake load downwards to foundation
REINFOCEMENT IN SHEAR WALLS
Stell reinforcing bars are to be provided in walls in regularly spaced
vertical and horizontal grids. The vertical and horizontal reinforcement
in the wall can be placed in one or two parallel layers called
curtains.horizntal reinforcement need to be anchored to the walls the
min. area of reinforcing steel to be provided is .0025 times the cross
sectional area, along each of the horizontal and vertical directions .This
vertical reinforcement should be distributed uniformly across the wall
cross section.
7/31/2019 Robin Report1
17/44
17
EARTHWORK
INTRODUCTION: -Earth work is the works related to soil.Which consist
excavation, earthfilling.
EQUIPMENTS:-
1.Roller, Plate Compactor & hand rammer2.Dumper, trolley3.Auto level4.NDG (Nuclear Density Gauge)MATERIAL:-
1.Yamuna Sand2.Excavated SoilEXPECTED QUANTITY:-99,036 cu.m
EXCAVATION:-
Excavation in different area of the site
Excavation shall be taken to the width of lowest step of footing or the
pile caps (required level) and the sides shall be left in slope where the
nature of the soil allow it for safety purpose.
DEWATERING AND PROTECION:-Where water is met with in excavation due to stream flow,
seepage,springs,rain or other reasons. Take adequate measures such as
bailing,pumping,construction of diversion channels, drainage
channels,bunds,cofferdams and other necessary works to keep the
7/31/2019 Robin Report1
18/44
18
foundation trenches/ pits dry when so required and to keep the green
concrete against damage by erosion or sudden rise of water level.
No pumping shall be permitted during the placing of concrete or for any
period of atleast 24 hours thereafter.
PREPRATION OF FOUNDATION:-
The bottom of the foundation shall be leveled both longitudinally and
transversally or stepped. Before the footing is laid, the surface shall be
slightly watered and rammed.
If there is any slips or blows in the excavation, these shall be removed.
BACKFILLING:-
Backfilling is done with Yamuna sand.
7/31/2019 Robin Report1
19/44
19
EARTHFILLING
GENERAL: - Filling is done with excavated earth soil. It is free from
salts, organic matter, black cotton soil and combustible material. So it
can be easily used for filling at the site.
FILLING IN PLINTH:- Filling is done in layer of 25 cm, watered &
consolidated by ramming with iron rammers weighing 7 to 8 kg, and
having base 20 cm. dia. .
When the filling reaches the finished level, surface is kept flooded with
water for 24 hours, allowed to dry and then rammed and consolidate,
in order to avoid settlement at a large stage.
FILLING IN OUTDOOR POSITION AND FOR SITE DEVELOPMENT:-
Filling is done in layer of 30 cm and each layer is adequately watered.
When filling reaches the required level topmost layer is dressed to
proper section, grade and chamber and rolled by 8 to 10 tons.
Power roller and adequate watered to aid compaction.
7/31/2019 Robin Report1
20/44
20
WATERPROOFING
INTRODUCTION: -Waterproofing is done to prevent the dampness
which is caused by rising the water from earth by the capillary action.
MATERIAL:-
a.)Elastothane
PROCEDURE:-
1.Fillet or Gola on Sharp corners:-Fillet on sharp corner: laying &placing of fillet of polymeric mortar (75 mm * 75 mm) on sharp
corner of roof with vertical wall. Make polymeric cement slurry by
adding cement to SBR(1:1 ratio) and apply by brush inside the
groove. Add fresh polymeric mortar over the groove.
Polymeric cement: Sand mortar can be prepared by adding 5-10%
SBR on gauging water and cement: coarse sand mortar (1:3)
2.Surface cracks on walls: -Surface cracks more than 2 mm shall beopen & chiseled to V groove and repaired with polymeric mortar
and extra layer of Elastothane of 6 inch shall be placed over cracks as
a crack bridging layer.
3.Basement:-Surface preparation:-
7/31/2019 Robin Report1
21/44
21
Assure that PCC shall be smooth enough to receive primer
application.The concrete of basement must be sound enough and free
from moisture. If surface undulation is found then it shall be repaired
with polymeric cement sand mortar.
Clean properly the concrete surface and remove all dust, dirt, foreign
matters, loose particles or any deposits of contaminants, which could
affect the bond failure between the mother surface and waterproof
coating. Remove all sharp projections and make surface reasonably
smooth to receive Bituthane P a liquid applied, primer.
APPLICATION:-
Apply first coat of Elastothane over cleaned prime surface with
roller/ brush or appropriate spray application. All day work-joints,
where as the application extended more than a day use an overlap of
Elasthothane by 150 mm.
After 12-36 hours when first coat become touch dry then apply second
coat. A total composite thickness will be 1 to 1.2 mm thick and
coverage of 1 kg. to 1.20 kg per sq. m. depending upon the surface
condition. Allow the coating to cure for 24-36 hours.
SPRAY APPLICATION: Only airless spray equipment shall be used, in
case of spray application.
REPAIR OF DAMAGE LAYER OF ELASTOTHANE:-
Minor damage to Elastothanebe repaired by removing loose
membrane; cleaning the surrounding area with aromatic hydrocarbonssolvent; overlapping by 150 mm; priming the area and finishing with
two coats of Elastothane.
Elastothane is easily applied and quickly applied manually at a rate of
40 sq. m. per man per day or upto 600 sq m per man per day by spray
7/31/2019 Robin Report1
22/44
22
application. Wipe all detail work with a cloth wet with Xylene/ Acetone
or Aromatic hydrocarbon solvent and allow drying.
The coating should be protected from damages by future operation and
other trade. Allow the coating to cure 36 hours and install protection
course after water pounding test.
Separation Layer: place 150 GSM Geotextile Mat/ 300 micron LDPE
sheet as separation layer over waterproofing coating before placing
Protection layer.
PROTECTION COURSE: - Place 50 mm thick protection screed
concrete.
7/31/2019 Robin Report1
23/44
23
REINFORCEMENT
REINFORCEMENT GRADE: - Fe 500
BENDING OF REINFORCEMENT:-
Bars should not be heat bending.
PLACING OF REINFORCEMENT:-
All reinforcement bars shall be accurately placed in exact position
shown on the drawings,
And shall be securely tied in position during placing of concrete by
annealed binding wire not less then 1 mm in size and conforming to
Is:280, and by using stay blocks or metal chairs, spacers, metal hangers,
supporting wires or other approved devices at sufficiently close
intervals.
Bars will not be allowed to sag between supports nor displaced during
concreting or any other operation over the work.
All devices used for positioning shall be of non-corrodible material.
Pieces of broken stone or brick and wooden block shall not be used.
Layers of bars shall be separated by spacer bars, precast mortar blocks
or other approved devices.
7/31/2019 Robin Report1
24/44
24
Chairs used to separate the two layers of slabs, walls etc. shall be
placed not more than 2 m clear in all four directions. The ratio of the
maximum horizontal length between the legs of the chair to the
diameter of bars used in preparing chairs shall not be more than100.
Spacing of cover blocks shall not exceed 1 m in any direction.
Reinforcement after being placed in position shall be maintained in a
clean condition until completely embedded in concrete.
To protect reinforcement from corrosion, concrete cover shall be
provided as indicated on the drawings.
In the case of columns & walls, vertical bars shall be kept in normal
position with timber templates having slots accurately cut in for bar
position. Such templates shall be removed after the concreting.
Dowels if provided for further lapping shall be coated with approved
quality bitumen paint over and above the anti corrosive treatment.
WELDING OF BARS:-
Welding of main bars shall not be permitted.
In special case Welding will be permitted by Client with Welding rod
7018.
Welding may be permitted for temporary works and areas where
welding will not affect the structure adversely.
7/31/2019 Robin Report1
25/44
25
REBARING
INTRODUCTION:-
Re-baring is done where the further reconstruction is
required due to revision of Drawings after
construction.
EQUIPMENTS:-
1.Drilling machiene2.Grouting gun3.Air pump
MATERIAL:-
1.Chemical RE 500(M/S HILTI)
7/31/2019 Robin Report1
26/44
26
7/31/2019 Robin Report1
27/44
27
7/31/2019 Robin Report1
28/44
28
CONCRETING
INTRODUCTION:-Concrete is prepared by mixing the following raw
materials in a right proportion:
1.Aggregates2. Coarse Sand or Dust3.Fly ash4.Water5.Cement6.Admixtures
Mixing of these raw materials dependson the grade of the concrete.
EQUIPMENT:-
a) For Production of Concrete:Concrete batching and mixing plant (fully automatic) with minimum
capacity of 15 cu.m. per hour.
b) For Concrete Transportation : depending upon actual
requirement
i) Concrete dumpers minimum 2 tones capacityii) Powered hoists minimum 0.5 tone capacityiii)Chutesiv)Buckets handled by cranesv) Transit truck mixervi)Concrete pumpvii)Concrete distributor booms
7/31/2019 Robin Report1
29/44
29
viii) Belt conveyorix)Cranes with skipsx) Tremies
c) For Compaction of concrete:
i) Internal vibrators size 25 mm to 70 mmii) Form vibrators minimum 500 wattsiii)Screed vibrators full width of carriageway
(up to two lanes)
SIZE OF COARSE AGGREGATE:-
The size (maximum nominal) of coarse aggregates for concrete to
be used in various components shall be given as Table 1700-7.
ComponentsMaximum Nominal size of coarse
Aggregate
(mm)i) RCC well curbii) RCC/PCCiii)Well cap or pile cap solid type
piers and abutments
iv)RCC work in girders, slabs,wearing coat, kerb, approach
slab hollow piers and
abutments, pier / abutmentcaps, piles
v) PSC workvi)Any other item.
20
40
40
20
20
As specified by Engineer
7/31/2019 Robin Report1
30/44
30
Maximum nominal size of aggregates shall also be restricted to
the smaller of the following values:
a)10 mm less than the minimum lateral clear distance betweenmain reinforcements
b)10 mm less than the minimum clear cover to thereinforcements.
The proportions of the various individual size of aggregates shall
be so adjusted that the grading produces densest mix and the grading
curve corresponds to the maximum nominal size adopted for the
concrete mix.
TEST FOR RAW MATERIALS:-
1.Aggregates
a)Sieve analysis of 20mm aggregateb)Sieve analysis of 10mm aggregatec) Impact test of 10mm aggregate
2. Test for the Sand
a)Sieve analysis of coarse sandb)Sieve analysis of Fine sandc)
Silt content
3.Cement
a)Sieve analysisb)Consistency test
7/31/2019 Robin Report1
31/44
31
c)Fineness of Cementd)Initial and Final Setting Time
For Concrete:-
1.SLUMP TEST2.COMPRESSIVE SRENGTH TEST
MIXING CONCRETE:-
Concrete shall be mixed either in a concrete mixer or in a batching
and mixing plant, as per these Specifications.
Hand mixing shall not be permitted.
Mixing shall be continued till materials are uniformly distributed
and a uniform color of the entire mass is obtained and eachindividual particle of the coarse aggregate shows
complete coating of mortar containing its proportionate amount
of cement.
In no case shall mixing be done for less than 2 minutes.
Mixers which have been out of use for more than 30 minutes shallbe thoroughly cleaned
before putting in a new batch.
Mixing plant shall be thoroughly cleaned before changing from
one type of cement to another.
7/31/2019 Robin Report1
32/44
32
TRANSPORTING, PLACING AND COMPACTION OF CONCRETE:-
The method of transporting and placing concrete shall be less
time taken.
Concrete shall be transported and placed as near as practicable
to its final position, sothat no contamination, segregation or loss
of its constituent materials takes place. \
Concrete shall not be freely dropped into place from a height
exceeding 1.5 meters.
All formwork and reinforcement contained in it shall be cleaned
and made free from standing water, dust, snow or ice
immediately before placing of concrete.
No concrete shall be placed in any part of the structure until the
approval of the Engineer has been obtained.
Except where otherwise agreed to by the Engineer, concrete shall
be deposited in
Horizontal layers to a compacted depth of not more than 450 mm
when internal Vibrators are used and not exceeding 300 mm in all
other cases.
7/31/2019 Robin Report1
33/44
33
Concrete when deposited shall have a temperature of not less
than 5 degrees Celsius, and not more than 40 degrees Celsius.
It shall be compacted in its final position within 30 minutes of its
discharge from the Mixer,
Concrete shall be thoroughly compacted by vibration or other
means during placing and worked around the reinforcement,
tendons or duct formers, embedded fixtures and into corners of
the formwork to produce a dense homogeneous void-free mass
having the required surface finish.
When vibrators are used, vibration shall be done continuously
during the placing of each batch of concrete until the expulsion of
air has practically ceased and in a manner that does not promote
segregation.
Over vibration shall be avoided to minimize the risk of forming a
weak surface layer.
Requirements of Consistency:-
The optimum consistency for various types of structures shall beas indicated in Table . The slump of concrete shall be checked as per
IS: 516.
7/31/2019 Robin Report1
34/44
34
TYPESLUMP (mm)
1 (a)Structures with exposed inclinedsurface requiring low slump concrete
to allow proper compaction.(b)Plain cement concrete.
25
25
2 RCC structures with widely spaced
reinforcements; e.g. solid columns,
piers, abutments, footings, well steining
40 50
3 RCC structures with fair degree of
congestion of reinforcement; e.g. pier
and abutment caps, box culverts well
curb, well cap, walls with thickness
greater than 300 mm.
50 75
4 RCC and PSC structures with highly
congested reinforcements e.g. deck slab
girders, box girders, walls with thickness
less than 300 mm
75 125
5 Underwater concreting through tremie
e.g. bottom plug, cast-in-situ piling
100 200
7/31/2019 Robin Report1
35/44
35
1. Grade of concrete in ACC: Structure concrete M10 to M402.Grade of concrete in TBB: Structure concrete M10 to M403.Grade of concrete in ATC: Self Compacting Concrete
a)SCC M30 in Pileb)SCC M40 in Pile Cap & Above Level 9c)SCC M60 up toLevel 9
LEVELING COURSE:-It is a lean concrete mix which is placed in
position conforming line and level shown in the drawing and
compacted by approved means and cured adequately.
7/31/2019 Robin Report1
36/44
36
INJECTION GROUTINTG
INRODUCTION: -Injection grouting is done to joint the layer of greenconcrete to the old hardened concrete.
EQUIPMENTS:
Pressure Pump Pressure Gauge Drilling/Chisel Machine Mixing Drum Pipe NRV (Non Returning Valve) Ultrasonic Pulse Velocity(UPV) Rebound Hammer Carborandum stone
MATERIALS:-
Low viscous epoxy (Conbextra EP 10) Epoxy Repair Mortar(Nitocrete) Non Shrink Cementations Grout(GP2) Nitobond/Latex
ROOT CAUSE ANALYSIS:
It is observed that during concreting of particular column due topressure of concrete minor gap has been created at corner of two
vertical shutter.
7/31/2019 Robin Report1
37/44
37
Slurry Loss has been occurred due to improper Packing of thegaps in shuttering Material.
Inadequate tamping of the shuttering during the concreting.PROCEDURE:
The Entire Repair Procedure shall been done in 3 Stages i.eSurface PreparationEpoxy Grouting in the Honey Comb LocationNon-Shrink Cementations Grouting Surface Preparation:
a) Mark the honey combed area to be Rectified.b)Saw cut the edges with a minimum of 10mm with concrete saw
cutter.
c)Remove all loose concrete from the column until hard concretesurface with proper bonding is obtained.
d)Cleaning of all loose laitance, loose concrete up to the desireddepth by
Mechanical or manual means to have dust free surface to
have good bond
between the existing concrete and with the high strength
repair mortar.
e)Clean the Surface by water jetting.Epoxy Grouting in the Honey Comb Location
i)Drilling shall be made to a depth of 100-300mm. Just beforefixing NRV (Non Returnable Valve) packer on the cavity
7/31/2019 Robin Report1
38/44
38
portion it shall be cleaned with the air pressure to get clean
and dry surface.
ii)Fixing of NRV packer of size 13mm for 100-300mm deep drilledholes
@ 200mm c /c in staggered manner shall be done withproper tightening to have proper packing of rubber gaskets.
iii)Injection of Low Viscous Epoxy (Conbextra EP10) in the NRVPackers with a pressure of 3-5kg/sqcm.
iv)The Injection Grouting shall last till backward pressure isobserved on further applying the pressure in the injection
grouting
v)After the injection Grouting operations are over, the nozzlesshall be removed & the area is filled with Epoxy Repair mortar.
Non-Shrink Cementations Grouting :i) The Concrete chipped surface to be grouted & filled with Epoxy
Repair Mortar.
ii)The area shall be cleaned with water / air jet to remove anyloose particles
or dust.
iii)As Recommended Latex/Nitobond shall be applied on the old &new surface either by brush or by spraying for proper bonding
with the newly laid concrete.
iv)Proper shuttering arrangement shall be taken before pouringthe Non-Shrink Cementations Grouting.
v)The Non-Shrink cementations Grout is Poured From one side &corner with proper head to fill the area & all the air voids.
vi)Allow the system to get water cured for 3 Daysvii) After the Completion of the Entire Process the Grouting
surface shall be finished with Carborandum stone
7/31/2019 Robin Report1
39/44
39
TESTING
After completion of repair procedure, the column shall be tested byUPV and Rebound Hammer. The overall process of NDT tests (UPV
and Rebound Hammer test) results shall be satisfactory ofrepaired column structure.
7/31/2019 Robin Report1
40/44
40
BRICKWORKMATERIAL:
1.Fly ash brick (size 230*115*75)2.
Mortar
a)Cementb)Waterc)Fine aggregate (sand)TOOLS FOR BRICK WORK:-
a.)Auto levelb.)Wooden/aluminum straight edge 3 m longc.) 3 m steel taped.) d.) Right angle m. longe.) Line and pin springf.) Plumb
g.) Storey rods
BRICK:-
a.Bricks shall be sound, hard, well burnt, uniform in size,shape&color,homogenous in texture giving a metallic ringing sound,
free from flaws,cracks,holes,lumps or grit & arises should be square,
straight and sharply defined.
b.They shall not break when struck against each other and droppedflat from a height of 1 m to the ground.
c. Maximum absorption shall not be more than 15% of its dry wt. onimmersion in water for 24 hours.
d.Min. crushing strength shall be 35 kg/sq cm.CEMENT:-Cement used shall be ordinary Portland cement conforming
to IS and shall be of grade 53 or 43.
7/31/2019 Robin Report1
41/44
41
WATER:-water used for masonry shall be clean and free from injurious
amount of deterious materials.
SAND:- Natural sand deposited by stream or glacial agencies as a result
of disintegration of rock is the best form of fine aggregate.
The fine aggregate shall conform to following standards.
(i) For plain and reinforced concrete IS 383 specificationfor coarse and fine
Aggregates from natural source for concrete
(ii) Mortar and grout IS 2116 Specification forsand for masonry
Mortars
Sea sand should not be used.
Sand shall be hard, durable, clean and free from adherent coatings and
organic matter and shall not contain any appreciable amount of clay
Sand should not contain any harmful impurities such as iron, pyrites,
coal particles, lignite, alkali and organic impurities in such form or
quantities as to affect the strength or durability of concrete or mortar.
MORTAR:-
Mortar shall be prepared by mixing fine graded aggregate with
cement in the proportion 1:4 for 115 mm width& 1:6 for 230 mm
width & above.
7/31/2019 Robin Report1
42/44
42
Cement and sand added to mixer shall be thoroughly mixed and
water shall be added to it gradually. After addition of water the
mixer shall run for a min. of 3 minutes.
The mortar mixed shall be consumed within 30 minutes of its
mixing.
METAL REINFORCEMENT:-
Metal reinforcement used in brick masonry shall conform to the
following IS specification.
IS 226 Specification for steel standard quality
IS 412 Specification for expanded metal steel sheet for general
purpose
IS 432 Specification for mild steel and medium tensile steel bars
IS 1566 Specification for steel fabric or hard drawn steel wire
WORKMANSHIP:-
Bricks used for masonry in cement mortar shall be soaked by
immersing in water or by hosing of water at least one hour prior
to start of actual lying.
Brick shall be laid in English bond unless otherwise specified. Half
or broken bricks shall be used only for the purpose of bond and at
no other place.
Work shall be true to horizontal lines and perfect plumb. Vertical
joint shall be truly vertical and those in alternate courses shall be
in the same vertical line. Joints of each course shall be within thelimit of 6 mm to 10 mm depending upon the size of brick.
Total ht. of 9 cm brick with 5 courses and 5 mortar joints shall be
50 cm.
7/31/2019 Robin Report1
43/44
43
In no case joint thickness shall not increase 50 cm.
Joint should be filled to full depth and checked each time.
Required datum level must be established throughout the floor
and only then work should start.
It is equally important to take into account level of window sills,
lintels etc.
PROTECTION & CURING: - green work should be protected from rains
by suitable covering.
Masonry in cement mortar shall be kept constantly moist on all the
faces for the min. period of 10 days.
The top of the masonry shall be left flooded with water at close of the
day.
7/31/2019 Robin Report1
44/44
SAFETY PRECAUTIONS:-
1.Avoid direct contact of the material with skin, eye & body.2.Wear proper safety helmets, goggles, shoes during application.3.Suitable lights for the application work during night shift should
be provided in and around the work area.
4.The area where injection grouting operations are to beundertaken must be cordoned off, and clearly signposted to
establish a restricted area.
5.All personnel to be fully attired in the required Safety gear.