Upload
ganesh-wanjari
View
185
Download
0
Tags:
Embed Size (px)
Citation preview
1Upgrade of Sana'a WWTP14.03.2005
Upgrade of the Sana‘aUpgrade of the Sana‘aWastewater Treatment Plant Wastewater Treatment Plant
Presentation of the DesignPresentation of the Design
Implementation of the New Preliminary Implementation of the New Preliminary Wastewater and Sludge Treatment Wastewater and Sludge Treatment
FacilitiesFacilities
14.03.2005 Upgrade of Sana'a WWTP 2
TopicsTopics BackgroundBackground Goals of the ProjectGoals of the Project Design CriteriaDesign Criteria Objectives of the DesignObjectives of the Design The Final DesignThe Final Design Implementation / CostImplementation / Cost
14.03.2005 Upgrade of Sana'a WWTP 3
1994: Design of the new Sana‘a WWTP by Howard Humphreys, UK, 1994: Design of the new Sana‘a WWTP by Howard Humphreys, UK, as activated sludge process with simultaneous sludge stabilizationas activated sludge process with simultaneous sludge stabilization
1999: Turn-Key Implementation of the new Sana‘a WWTP (Financing 1999: Turn-Key Implementation of the new Sana‘a WWTP (Financing World Bank); Start of operation through Degremont, France (1 year)World Bank); Start of operation through Degremont, France (1 year)
2000: Takeover and responsible Operation through Sana’a Water 2000: Takeover and responsible Operation through Sana’a Water and Sanitation Local Corporation (SWSLC)and Sanitation Local Corporation (SWSLC)
Operational Problems right from the very beginning of operation:Operational Problems right from the very beginning of operation:
Overloading of WWTP due to high BODOverloading of WWTP due to high BOD55-concentration-concentration
High operation costs due to high energy consumption High operation costs due to high energy consumption Sludge not stabilized causing odor nuisance Sludge not stabilized causing odor nuisance Odorous nuisance along the inlet trunk main sewer Odorous nuisance along the inlet trunk main sewer Utilization of treated wastewater and sludge for irrigation / agriculture Utilization of treated wastewater and sludge for irrigation / agriculture had not been solved had not been solved
1 Background1 Background
14.03.2005 Upgrade of Sana'a WWTP 4
Remedying Measure: Execution of a Feasibility Study Remedying Measure: Execution of a Feasibility Study (August 2000(August 2000 until May 2001) until May 2001)
Decision for Implementation of Decision for Implementation of Sana‘a WWTP UpgradeSana‘a WWTP Upgrade (10/2002)(10/2002)
Preparation of Final Design + Tender Documents according to FIDIC Preparation of Final Design + Tender Documents according to FIDIC „Red„Red Book“ Book“ Consultant: CONSULAQUA Hamburg GmbH Consultant: CONSULAQUA Hamburg GmbH
1 Background1 Background
14.03.2005 Upgrade of Sana'a WWTP 5
Implementation of technical measures for upgrade ofImplementation of technical measures for upgrade of
Sana’aSana’a WWTP (design flow Q = 65,000 m³/d in 2020) WWTP (design flow Q = 65,000 m³/d in 2020)
Improvement of treatment efficiency + operational stability Improvement of treatment efficiency + operational stability
Reduction of external energy input Reduction of external energy input
Improvement of the quality of dried sludge to allow Improvement of the quality of dried sludge to allow
proper sludge marketing proper sludge marketing
Implementation of technical measures to reduce massive Implementation of technical measures to reduce massive
odor problems to a tolerable levelodor problems to a tolerable level
2 Goals of the Project2 Goals of the Project
14.03.2005 Upgrade of Sana'a WWTP 6
3 Design Criteria3 Design Criteria
Effluent RequirementsEffluent Requirements
BOD5 < 30 mg/l (inflow: BOD5 = 1,100 mg/l)
SS < 30 mg/l (inflow: SS = 1,200 mg/l) pathogen removal:
- Coliform Germs < 1,000/100 ml- Worm eggs < 1/Liter Avoidance of infections to those working on irrigated
fields and those consuming vegetables grown on fields
Existing wastewater treatment stage will be fully able to fulfil effluent requirements if sludge problem is solved
14.03.2005 Upgrade of Sana'a WWTP 7
Original Design
Existing Situation
Start of Operation
Design Horizon
Design Horizon / Target Year - 1995 2004 2008 2020
INFLOWDaily Wastewater Inflow m³/d 50.000 36.000 50.000 50.000
Peak factor (max flow/average flow) - 3,0 2,0 2,0 2,0 Safety factor - 1,0 1,0 1,0 1,3 Maximum Treatment Capacity m3/d 50.000 36.000 50.000 65.000
BOD5
BOD5-concentration mg/l 500 1.100 1.100 1.100
BOD5-load kg/d 25.000 39.600 55.000 71.500
Specific BOD5-pollution load g/cap*d 55 55 55 55 Pollution load (Population Equivalents) PE 454.545 720.000 1.000.000 1.300.000
SUSPENDED SOLIDS SS-concentration mg/l 750 1.070 1.070 1.070 SS-load kg/d 37.500 38.520 53.500 69.550 Specific SS-pollution load g/cap*d 82,5 53,5 53,5 53,5
Design Criteria UnitBOD-Elim. / Sim. Aerobic Stab. BOD5-Elim. / Anaerobic Digestion
Wastewater Characteristics / Target YearsWastewater Characteristics / Target Years
3 Design Criteria3 Design Criteria
14.03.2005 Upgrade of Sana'a WWTP 8
4 Objectives of the Design4 Objectives of the Design
High safety of operation High safety of operation (( redundant systems, hydraulic redundant systems, hydraulic crosswise connections) crosswise connections)
O & M-requirementsO & M-requirements ( ( easy handling & maintenance of easy handling & maintenance of treatment facilities)treatment facilities)
Staff requirements Staff requirements (( number and skills of staff number and skills of staff degree degree and complexity of automation)and complexity of automation)
Local availability of material, equipment and Local availability of material, equipment and consumablesconsumables
Minimization of investment costsMinimization of investment costs Essential savings in operation costsEssential savings in operation costs Minimization of environmental impactsMinimization of environmental impacts (odor, noises) (odor, noises) Future extension possibilitiesFuture extension possibilities ( ( modular structure of modular structure of
plant layout, extension areas)plant layout, extension areas)
14.03.2005 Upgrade of Sana'a WWTP 9
5 The Final Design5 The Final Design
Technical Measures to be implemented Technical Measures to be implemented under the Sana’a WWTP Upgrade Projectunder the Sana’a WWTP Upgrade Project New Inlet Pumping Station with pre-applied Coarse New Inlet Pumping Station with pre-applied Coarse
ScreensScreens
Fine ScreensFine Screens
Primary Settling Tanks / New Distribution Chamber Primary Settling Tanks / New Distribution Chamber
Retention BasinRetention Basin
Primary Sludge ThickenersPrimary Sludge Thickeners
Anaerobic Digesters (incl. Auxiliary Building)Anaerobic Digesters (incl. Auxiliary Building)
Stabilized Sludge Thickeners Stabilized Sludge Thickeners
Co-Generation Plant + Co-Generation Plant + Boiler StationBoiler Station
Gasholders with gasflareGasholders with gasflare
Adaptation of Electrical Power Supply and Distribution Adaptation of Electrical Power Supply and Distribution
Additional 44 Sludge Drying Beds Additional 44 Sludge Drying Beds
Odor Control Measures Odor Control Measures
WWTPUpgrade
SludgeTreatment
OdorControl
14.03.2005 Upgrade of Sana'a WWTP 10
The new The new plant layout plant layout in complete in complete overviewoverview
Arrangement of New Plant Arrangement of New Plant Layout (newLayout (newstructures in RED color)structures in RED color)++ 4 4 clearlyclearly defined operational areas: defined operational areas: IPS/Mechanical Wastewater IPS/Mechanical Wastewater TreatmentTreatment Biological Wastewater Treatment Biological Wastewater Treatment Sludge Treatment Sludge Treatment Gas Utilization Gas Utilization+ + Connection of new with existing Connection of new with existing facilitiesfacilities is easy is easy continuation of operation continuation of operation duringduring construction construction++ Future Extension of Plant is very easy Future Extension of Plant is very easy++ O & M requirements can be kept at O & M requirements can be kept at acceptable standards acceptable standards
14.03.2005 Upgrade of Sana'a WWTP 11
The new The new layout layout in detailin detail
Mechanical Wastewater Mechanical Wastewater TreatmentTreatmentNew: Coarse / Fine Screens, Inlet New: Coarse / Fine Screens, Inlet PS, Aerated Grit Chambers, PS, Aerated Grit Chambers, Primary Settling Tanks and Primary Settling Tanks and Magnetic Flow MeterMagnetic Flow Meter+ Logical and modular arrangement of + Logical and modular arrangement of Screens,Screens, Grit Chambers and Primary Settling Grit Chambers and Primary Settling TanksTanks allowing easy extension in quantity allowing easy extension in quantity
+ + Separate Coarse and Fine Screens resultSeparate Coarse and Fine Screens result in higher efficiency, easier unloading of in higher efficiency, easier unloading of screenings, and better O & M conditions screenings, and better O & M conditions
+ New aerated grit chambers provide high + New aerated grit chambers provide high gritgrit removal efficiency (protection of new removal efficiency (protection of new digesters)digesters)
++ The logical spatial arrangement of the The logical spatial arrangement of the mechanical treatment facilities allows for mechanical treatment facilities allows for improved hydraulic conditions improved hydraulic conditions
+ Construction of the new mechanical + Construction of the new mechanical treatmenttreatment facilities can be carried out in one take facilities can be carried out in one take withoutwithout interfering plant operation interfering plant operation
+ Emergency overflow can be further used+ Emergency overflow can be further used
- - The new arrangement requires The new arrangement requires construction ofconstruction of a new Inlet Pumping Station and a new Inlet Pumping Station and extension ofextension of the main incoming sewer the main incoming sewer
14.03.2005 Upgrade of Sana'a WWTP 12
The new The new layout layout in detailin detail
Biological Wastewater Biological Wastewater TreatmentTreatmentConversion of Simultaneous Conversion of Simultaneous Sludge Stabilization to Sludge Stabilization to Activated Sludge Process Activated Sludge Process (Carbon removal only)(Carbon removal only)+ All tanks and connecting pipes can be + All tanks and connecting pipes can be
further used further used+ Existing Inlet Pumping Station can be + Existing Inlet Pumping Station can be usedused as Return Sludge Pumping Station as Return Sludge Pumping Station+ Mixing of pre-treated wastewater and+ Mixing of pre-treated wastewater and return sludge and the following return sludge and the following distributiondistribution on to 8 treatment lines can be on to 8 treatment lines can be facilitated by facilitated by construction of only one additional construction of only one additional structure structure
14.03.2005 Upgrade of Sana'a WWTP 13
The new The new layout layout in detailin detail
Sludge Treatment3 new Digesters @ 10.000 m3, Gravity Thickeners for Primary Sludge & Digested Sludge (4 in total), 2 Gas Holders, Co-Generation Plant, Boiler Station+ Implementation of third Digester considerably improves operational and process safety+ Expensive Polymers will not be needed anymore+ Due to new spatial arrangement all sludge thickeners can be fed by gravity+ Short distances between digester and thickeners allow for reduced pumping cost+ Gas Utilization facilities are very close together+ Gas Utilization allows for considerable reduction of specific energy supply from external sources (approx. 65 %)
14.03.2005 Upgrade of Sana'a WWTP 14
The new The new Digesters Digesters (Profile)(Profile)
14.03.2005 Upgrade of Sana'a WWTP 15
The new The new layout layout in detailin detail
Odor Control3 Biological Filters close to the new Screen Building, Return Sludge Pump Station, and PS Thickeners+ Easy to operate and maintain+ Low running cost+ High Efficiency
14.03.2005 Upgrade of Sana'a WWTP 16
5 The Final Design5 The Final Design
Power Supply ConceptPower Supply Concept
Introduction of 4 gas generator sets, each rated @ Introduction of 4 gas generator sets, each rated @ 626 kW626 kW Balance of Total Power Requirement for future Balance of Total Power Requirement for future Sana‘a WWTPSana‘a WWTP
Maximum Power Reduction is 25%Maximum Power Reduction is 25% Considering the extended capacity (increase of treatment Considering the extended capacity (increase of treatment capacitycapacity from 450,000 PE up to 1,000,000 PE,) the specific power from 450,000 PE up to 1,000,000 PE,) the specific power consumptionconsumption of Sana‘a WWTP can be reduced by approx. 67% of Sana‘a WWTP can be reduced by approx. 67%
14.03.2005 Upgrade of Sana'a WWTP 17
Implementation (planned)Implementation (planned)
09/2005:09/2005: Award of Contract Award of Contract 10/2007:10/2007: Commencement of Operation under Responsibility of the Commencement of Operation under Responsibility of the Contractor + Start of Staff Training (1 Year) Contractor + Start of Staff Training (1 Year) 10/2008: 10/2008: Takeover through SWSLCTakeover through SWSLC
Investment Cost (estimated)Investment Cost (estimated)
Civil WorksCivil Works:: 18.2 Mil. USD (incl. Sludge Drying 18.2 Mil. USD (incl. Sludge Drying Beds) Beds) Mechanical Works: Mechanical Works: 5.8 Mil. USD 5.8 Mil. USD Electrical Works: Electrical Works: 2.6 Mil. USD2.6 Mil. USD Incontingencies: Incontingencies: 1.6 Mil. USD 1.6 Mil. USD Engineering: Engineering: 1.8 Mil. USD 1.8 Mil. USD GRAND TOTALGRAND TOTAL 30.0 Mil. USD30.0 Mil. USD
6 Implementation & Cost6 Implementation & Cost
14.03.2005 Upgrade of Sana'a WWTP 18
ThanThankYoukYou