Seminar PPAP

Embed Size (px)

Citation preview

  • 8/8/2019 Seminar PPAP

    1/17

    1. INTRODUCTION

    The Production Part Approval Process (PPAP) is used in the automotive supplychain to establish confidence in component suppliers and their production processes, by

    demonstrating that:

    "....all customer engineering design record and specification requirements are properly

    understood by the supplier and that the process has the potential to produce product

    consistently meeting these requirements during an actual production run at the quoted

    production rate."

    PPAP is an important part of the product development process, allowing producers to

    evaluate the components and sub-systems which they receive from suppliers, and

    establishing confidence in the supplier's management systems. Although individual

    manufacturers have their own particular requirements.

    PPAP was the culmination of joint efforts by Chrysler, Ford and GM, working

    under the auspices of the Automotive Industry Action Group(AIAG) and the American

    Society for Quality Control (ASQC), to develop industry-wide standards that would

    apply to all their many suppliers. The first manual spelling out the multiple requirement

    of PPAP was published in 1993. PPAP is part of the auto industry's overall Advance

    Product Quality Planning initiative, step-by-step procedures designed to ensure

    production of an end-product that will satisfy consumers

    2. Who Uses Production Part Approval Process?

    The auto industry giants like Ford, Chrysler, GM and their vast network of

    suppliers (partners in AIAG, Auto Industry Action Group) strictly adhere to the PPAP.

    In their industry, a suppliers cannot ship components until the PPAP approval, or

    someone composes a written deviation to allow shipment prior to approval (much like

    A.I.S.S.M.S. COLLAGE OF ENGINEERING 2010-11 1

    http://www.ehow.com/culture-and-society/http://www.ehow.com/culture-and-society/
  • 8/8/2019 Seminar PPAP

    2/17

    our TD process). Several semiconductor companies such as Freescale are also reportedly

    using PPAP

    3. Purpose of Production Part Approval Process

    The purpose of the Production Part Approval Process (PPAP) is:

    To provide the evidence that all customer engineering design record and

    specification requirements are properly understood and fulfilled by the manufacturing

    organization.

    To demonstrate that the now established manufacturing process has the potential

    to produce product that consistently meets all requirements during an actual

    production run at the quoted production rate

    4. When Production Part Approval Process Submission Required?

    In general a PPAP is required anytime a new part or a change to an existing part

    or process is being planned. It is at the discretion of each Industries Division to determine

    when and if a PPAP submission will be required. As a supplier you should have the type

    of quality system that develops all of the requirements of a PPAP submission regardless

    of whether you have been asked to deliver a submission. In the event a PPAP submission

    is not requested, quality reserves the right to request any of these documents at any time

    during the life of the product. Quality reserves the right to request a PPAP submission for

    a variety of reasons including all of the following.

    New parts, process or suppliers:

    1. New part or product

    A.I.S.S.M.S. COLLAGE OF ENGINEERING 2010-11 2

  • 8/8/2019 Seminar PPAP

    3/17

    2. New supplier

    3. New process or technology

    Changes to existing product:

    1. Change to construction, material, or component

    2. New, additional or modified tools

    3. Upgrade or re-arrangement of existing tools

    4. Tooling, production, or equipment transferred to a different site

    5. Change of supplier or non-equivalent materials/services

    6. Product when tooling has been inactive for 12 months

    7. Product or process changes on the components of the product

    8. Change in test or inspection method

    9. Bulk material: New source of raw material

    10. Change in product appearance attributes

    11. Change in production process or method

    12. Change of sub-supplier or material source

    5. Critical Elements of the Process Approach

    Process owner exists

    Process is defined

    Process is documented

    Linkages of process established

    Process monitored, analyzed and improved

    Records maintained

    6. Approval of Production Part Approval Process

    The result of the PPAP process is a series of documents gathered in one specific

    location (a binder or electronically) called the "PPAP Package". The PPAP package is a

    series of documents which need a formal approval by the supplier and customer. The

    form that summarizes this package is called PSW (Part Submission Warrant). The

    A.I.S.S.M.S. COLLAGE OF ENGINEERING 2010-11 3

  • 8/8/2019 Seminar PPAP

    4/17

    approval of the PSW indicates that the supplier responsible person (usually the Quality

    Engineer) has reviewed this package and that the customer has not identified any issues

    that would prevent its approbation.

    The documentation on the PPAP package is closely related to the Advanced Product

    Quality Planning process (APQP) used during the design and development of new

    vehicles and component systems to reduce the risk of unexpected failure due to errors in

    design and manufacture. The PPAP manual is published by, Industries and specifies

    generic requirements for obtaining PPAP approvals. Additional customer specific

    requirements may be imposed by particular clients (vehicle manufacturers) and

    incorporated in the purchasing contracts. Suppliers are required to obtain PPAP approval

    from the vehicle manufacturers whenever a new or modified component is introduced to

    production, or the manufacturing process is changed. Obtaining approval requires the

    supplier to provide sample parts and documentary evidence showing that:

    1) The clients requirements have been understood

    2) The product supplied meets those requirements

    3) The process (including sub suppliers) is capable of producing conforming product

    4) The production control plan and quality management system will prevent non-

    conforming product reaching the client or compromising the safety and reliability of

    finished vehicles

    Production Part Approval Process (PPAP) may be required for all components and

    materials incorporated in the finished product, and may also be required if components

    are processed by external sub-contractors.

    7. Elements Of Production Part Approval Process

    PPAP specifies steps and standards for every phase of the planning and production

    process. PPAP documentation, which follows the product from inception to completion,contains at least 18 separate elements by the time production is completed. These

    include design records, engineering approvals (including approval of any changes made

    during the production phase), process-flow diagram, failure modes and effects analysis

    A.I.S.S.M.S. COLLAGE OF ENGINEERING 2010-11 4

    http://en.wikipedia.org/wiki/Advanced_Product_Quality_Planninghttp://en.wikipedia.org/wiki/Advanced_Product_Quality_Planninghttp://en.wikipedia.org/wiki/APQPhttp://en.wikipedia.org/wiki/Advanced_Product_Quality_Planninghttp://en.wikipedia.org/wiki/Advanced_Product_Quality_Planninghttp://en.wikipedia.org/wiki/APQP
  • 8/8/2019 Seminar PPAP

    5/17

    (in both design and process phases), measurement system analysis studies and all

    product test results.

    7.1. Design Records

    fig 1 Drawing Sheet

    A copy of the drawing. If the customer is design responsible this is a copy of

    customer drawing that is sent together with the Purchase Order (PO). If supplier is design

    responsible this is a released drawing in supplier's release system. Hard copies of the

    following items are to be submitted with the PPAP package: Engineering Drawings

    Process, Material and Engineering Specifications

    Design Records are required for all components and details e.g. where the part is a

    machined casting; the machining supplier is responsible to produce the design records for

    A.I.S.S.M.S. COLLAGE OF ENGINEERING 2010-11 5

  • 8/8/2019 Seminar PPAP

    6/17

    the casting, which includes the Suppliers approved Part Submission Warrants and all

    Design Records for all sub-supplier parts.

    Where the design record is in electronic format, the supplier shall still provide ahard

    copy of those documents.

    7.2. Authorized Engineering Change (Note) Documents

    It is possible that during product development a change is suggested in the

    product, part or tooling by R&D / Engineering but not yet incorporated in the drawing /

    standard. If such changes are incorporated in the part / product submitted for Production

    Part Approval, the authorized engineering change documents must also be submitted .

    This document shows the detailed description of the change. Usually this

    document is called "Engineering Change Notice", but it may be covered by the customer

    PO or any other engineering authorization. PPAPs are NOT to be submitted if the design

    requirements have not been met

    7.3. Engineering Approval

    This approval is usually the Engineering trial with production parts performed at

    the customer plant. A "temporary deviation" usually is required to send parts to customer

    before PPAP. Customer may require other "Engineering Approvals". As an example

    included in this document.

    7.4. DFMEA (Design Failure Mode and Effect Analysis)

    A copy of the Design Failure Mode and Effect Analysis (DFMEA), reviewed and

    signed-off by supplier and customer. If customer is design responsible, usually customer

    may not share this document with the supplier. However, the list of all critical or high

    A.I.S.S.M.S. COLLAGE OF ENGINEERING 2010-11 6

    http://en.wikipedia.org/wiki/Failure_mode_and_effects_analysishttp://en.wikipedia.org/wiki/Failure_mode_and_effects_analysishttp://en.wikipedia.org/wiki/Failure_mode_and_effects_analysishttp://en.wikipedia.org/wiki/Failure_mode_and_effects_analysis
  • 8/8/2019 Seminar PPAP

    7/17

    impact product characteristics should be shared with the supplier, so they can be

    addressed on the PFMEA and Control Plan.

    7.5. Process Flow Diagram

    A copy of the Process Flow, indicating all steps and sequence in the fabrication

    process, including incoming components. The production process steps and the sequence

    should be clearly described, as appropriate. Process Flow Chart should project a pictorial

    representation of the entire manufacturing process.

    Typically it should start with incoming material inspection to packing and pre-

    dispatch inspection. All operations should be represented by appropriate symbols. Details

    of Product & Process Characteristics to be filled-up in the format along with its

    Characteristic Classification.

    Fig 2 Process flow diagram

    A.I.S.S.M.S. COLLAGE OF ENGINEERING 2010-11 7

    Rawgoods

    received

    Rawgood

    warehous

    Manufacturing Process

    Non

    confirming

    product flow

    Rework

    Scrap Inspection Testing

    Finishedgood

    warehousing

    To market

    http://en.wikipedia.org/wiki/Process_Flow_Diagramhttp://en.wikipedia.org/wiki/Process_Flow_Diagramhttp://en.wikipedia.org/wiki/Process_Flow_Diagram
  • 8/8/2019 Seminar PPAP

    8/17

    7.6. PFMEA (Process Failure Mode and Effect Analysis)

    A copy of the Process Failure Mode and Effect Analysis (PFMEA) reviewed and

    signed-off by supplier and customer. The PFMEA follows the Process Flow steps, and

    indicate "what could go wrong" during the fabrication and assembly of each component.

    Process Failure Mode & Effects Analysis (PFMEA) is carried out to analyse a

    process for potential failure mode and its effects. PFMEA should be carried out by a

    Cross-Functional Team approach. Actions on prioritized failure modes must be

    completed and the revised rating should be documented. The completed PFMEA

    document should be submitted along with the PSW. While preparing PFMEA, the focus

    should be on Process deficiencies, rather than on Design related deficiencies.

    7.7. Control Plan

    A copy of the Control Plan reviewed and signed-off by supplier and customer.

    The Control Plan follows the PFMEA steps, and provides more details on how the

    "potential issues" are checked in the incoming quality, assembly process or during

    inspections of finished products.

    7.8. Measurement System Analysis Studies (MSA)

    MSA usually contains the Gage R&R for the critical or high impact

    characteristics, and a confirmation that gauges used to measure these characteristics are

    calibrated. Measurement system Analysis studies such as Gage R&R, Bias, and Linearity

    & Stability shall be carried out for all equipments used for new or modified gages,

    measurement, and test equipments.

    A.I.S.S.M.S. COLLAGE OF ENGINEERING 2010-11 8

    http://en.wikipedia.org/wiki/PFMEAhttp://en.wikipedia.org/wiki/Measurement_Systems_Analysishttp://en.wikipedia.org/wiki/ANOVA_Gage_R%26Rhttp://en.wikipedia.org/wiki/PFMEAhttp://en.wikipedia.org/wiki/Measurement_Systems_Analysishttp://en.wikipedia.org/wiki/ANOVA_Gage_R%26R
  • 8/8/2019 Seminar PPAP

    9/17

    Gauge Capability study should be performed for all new gauges procured & their

    capability indices reviewed before use. PU /Area must carryout Accuracy, Bias and

    Linearity studies for all used and new equipment, new or modified gages, measuring

    tools and test equipment.

    In addition, Gauge Repeatability & Reproducibility (GRR) studies should be

    carried out for equipments that are used for measuring critical and significant

    characteristics. It is recommended to conduct stability studies of these equipments and

    monitor there on. For attribute characteristics such as finish, feel, dent, rundown etc.,

    attribute MSA is to be carried out as per MQS guideline. MSA Attribute study to be

    conducted on attribute defects & not on attribute measuring equipment.

    7.9. Dimensional Results

    fig. 3 Dimensional tolerances example

    A list of every dimension noted on the ballooned drawing. This list shows the

    product characteristic, specification, the measurement results and the assessment showing

    A.I.S.S.M.S. COLLAGE OF ENGINEERING 2010-11 9

  • 8/8/2019 Seminar PPAP

    10/17

    if this dimension is "ok" or "not ok". Usually a minimum of 6 pieces is reported per

    product/process combination.

    7.10. Records of Material / Performance Tests

    A summary of every test performed on the part. This summary is usually on a

    form of DVP&R (Design Verification Plan and Report), which lists each individual test,

    when it was performed, the specification, results and the assessment pass/fail. If there is

    an Engineering Specification, usually it is noted on the print. The DVP&R shall be

    reviewed and signed off by both customer and supplier engineering groups. The quality

    engineer will look for a customer signature on this document.

    In addition, this section lists all material certifications (steel, plastics, plating, etc), as

    specified on the print. The material certification shall show compliance to the specific

    call on the print.

    7.11. Initial Process Studies

    Usually this section shows all Statistical Process Control charts affecting the most

    critical characteristics. The intent is to demonstrate that critical processes have stable

    variability and that is running near the intended nominal value.

    The purpose of conducting initial process capability study is to determine if the

    production process is capable / potential to produce products that meet internal / external

    customer requirements and result in customer satisfaction. For all Significant and Critical

    characteristics, (SCs & CCs) the concerned should be stable and under statistical control

    with Preliminary Process Capability Index (Ppk) above 1.67 in Production Trial Run and

    on-going process capability index (Cpk) greater than 1.33 in regular production.

    A.I.S.S.M.S. COLLAGE OF ENGINEERING 2010-11 10

    http://en.wikipedia.org/wiki/Statistical_process_controlhttp://en.wikipedia.org/wiki/Statistical_process_control
  • 8/8/2019 Seminar PPAP

    11/17

    The purpose of process capability study is to determine whether the production

    process has the potential to produce products that will meet the customer requirements

    and result in customer satisfaction. The Ppk study should be based on 100 (minimum 50)

    consecutively produced parts when process is in statistically stable condition where only

    Common Causes of variation are present. The performance index (Ppk) should be above

    1.67.It is essential to conduct Normality study to determine whether the process data are

    normally distributed. This is evident by calculating Skewness & Kurtosis. Skewness is

    the measure of Symmetry of the distribution & Kurtosis the measure of peakness of the

    distribution.

    Tests for Normality include Anderson Darling test, Ryan Joiner test,

    Kolmogorov Smirnov test. MQS recommends the use of Minitab software for

    conducting these tests. The skewness & Kurtosis should be within acceptable limits to

    proceed further for Process capability calculations.

    7.12. Qualified Laboratory

    The supplier shall have Inspection and Testing for PPAP (as well as regular production)

    performed by a qualified laboratory as defined by customer

    requirements.

    The suppliers qualified laboratory (internal or external) shall have a laboratory

    scope and documentation showing that the laboratory is qualified for the type of

    measurements or tests being conducted.

    Supplier shall submit test results on the laboratory letterhead or the normal

    laboratory report format when an outside laboratory is used. The following

    information must be included on the report:

    Name of the laboratory that performed the tests.

    The date(s) of the tests.

    The standard(s) used to run the tests shall be identified.

    A.I.S.S.M.S. COLLAGE OF ENGINEERING 2010-11 11

  • 8/8/2019 Seminar PPAP

    12/17

    7.13. Appearance Approval Report

    A copy of the AAI (Appearance Approval Inspection) form signed by the

    customer. Applicable for components affecting appearance only. Appearance Approval

    Report applies for parts with colour, grain, surface finish and texture requirements that

    are visible to the customer. It is recommended to take a photograph of the item,

    preferably by a digital camera with good resolution and submit the photographs along

    with the PPAP submissions.

    7.14. Sample Production Parts

    Fig 4 can ban tag

    A sample from the same lot of initial production runs. The PPAP package usuallyshows a picture of the sample and where it is kept (customer or supplier).Unless

    otherwise specified by the using plant approval activity, the supplier shall submit 3

    samples with the PPAP. If production parts will be produced from more than one cavity,

    mold, tool, die, pattern, or production process, e.g. line or cell, then the supplier shall

    A.I.S.S.M.S. COLLAGE OF ENGINEERING 2010-11 12

  • 8/8/2019 Seminar PPAP

    13/17

    submit one sample for each position of a multiple cavity die, mold, tool or pattern, or

    production process. Such samples shall be

    appropriately identified.

    7.15. Master Sample

    A sample signed off by customer and supplier, that usually is used to train

    operators on subjective inspections such as visual or for noise. If production parts will be

    produced from more than one cavity, mold, tool, die, pattern, or production process, e.g.

    line or cell, then the supplier shall retain one sample for each position of a multiple cavity

    die, mold, tool or pattern, or production process.

    7.16. Checking Aids

    When there are special tools for checking parts, this section shows a picture of the

    tool and calibration records, including dimensional report of the tool. Checking aid list

    includes all fixtures, gauges, models and templates specific to the product for which

    PPAP is carried out. The same should be submitted along with PSW. If requested by the

    approval authority, checking aids are to be reviewed for a specific component or

    assembly.

    PU / Area should certify that all aspects of the checking aids are in agreement

    with part dimensional requirements. PU / Area must have drawings for all checking aids,

    other than the standard instruments. The PU / Area shall document all released

    engineering design changes that have been incorporated in the checking aids at the time

    of submission. Generic checking aid list, if available is to be referenced in PSW format.

    A.I.S.S.M.S. COLLAGE OF ENGINEERING 2010-11 13

  • 8/8/2019 Seminar PPAP

    14/17

    7.17. Customer Specific Requirements

    Each customer may have specific requirements to be included on the PPAP

    package. It is a good practice to ask the customer for PPAP expectations before even

    quoting for a job.

    7.18. Part Submission Warrant (PSW)

    This is the form that summarizes the whole PPAP package. This form shows the reason

    for submission (design change, annual revalidation, etc) and the level of documents

    submitted to the customer. There is a section that asks for "results meeting all drawing

    and specification requirements: yes/no" refers to the whole package. If there is any

    deviations the supplier should note on the warrant or inform that PPAP cannot be

    submission.

    The purpose of thePart Submission Warrant(PSW) is to document

    thesubmission and the approval or rejection of purchased parts prior to production.

    7.18. A Submission Levels

    Submission levels define which elements are required to be submitted. The levels

    are used for different reasons and applications. The level to be submitted is determined

    by Industry, and unless otherwise noted, always defaults to Level 3 which is a full PAP

    submission. There are five submission levels listed below, and each is typically applied to

    the specific areas listed.

    Level 1 - Warrant only and Appearance Approval Report as requested

    A.I.S.S.M.S. COLLAGE OF ENGINEERING 2010-11 14

  • 8/8/2019 Seminar PPAP

    15/17

    submitted to the customer. Applied to: Non-critical parts, non critical raw/bulk

    material or catalog/ commodity parts for electrical applications and re-certification of

    existing parts previously approved. Also used for self-certification.

    Level 2 - Warrant with product samples and limited supporting data

    submitted to the customer. Applied to: Critical Bulk products such as

    Plastic/Paint/Chemicals, critical fasteners, simple material changes, simple revision level

    only changes or simple print updates not affecting form-fit-function. This level can also

    be applied to low and medium risk

    parts within a product family.

    Level 3 - Warrant with product samples and complete supporting data

    submitted to customer. Default Cooper Industries Submission

    Level Applied to: New parts on programs, changes affecting. Form-fit-function,

    reliability, or performance. All products resourced to new suppliers, serial production

    parts, and existing high risk parts undergoing a part number change.

    Level 4 - Warrant and other requirements as defined by the customer. This level is

    reserved for special applications only. Applied to: This level can only be applied with

    prior approval from the designated divisional quality PPAP representative.

    Level 5 - Warrant with product samples and complete supporting data reviewed at

    the suppliers manufacturing location. Applied to: On site review as requested by each

    Division.

    8. Benefits of Production Part Approval Process

    Many benefits exist for both customers and suppliers by adopting PPAP such as:

    1. Clearly planned, justified, validated, documented, and communicated (including

    training) key manufacturing process functions.

    2. Clearly communicated design requirements and design gaps.

    A.I.S.S.M.S. COLLAGE OF ENGINEERING 2010-11 15

  • 8/8/2019 Seminar PPAP

    16/17

    3. Improved quality over product life cycle.

    4. Inclusion of customer consent in the change process for better visibility (and

    Copy Exact requirements where implemented).

    5. Quick resolution of new problems due to documented product history

    6. Improved customer/supplier relationships

    7. Optimized business output and profits

    8. Developing a packet of documents used to assure that all reasonable risks have

    been addressed.

    A.I.S.S.M.S. COLLAGE OF ENGINEERING 2010-11 16

  • 8/8/2019 Seminar PPAP

    17/17

    REFERENCES

    : Reference to a book:

    [1] Serope Kalpakjian, Stephen R. Schmid, and Chih-Wah Kok , Manufacturing

    Processes for Engineering Materials Vol. I. 2nd edition, New York: Wiley Publications,

    1999.

    [2] Dominic Reeve, Andrew Chadwick, and Christopher Fleming, Coastal

    Engineering: Processes, Theory and Design Practice Johnson Publication, 1988.

    : Reference to a website

    [3] http://www.asqsandiego.net

    [4] http://www.anixter.com

    A I S S M S COLLAGE OF ENGINEERING 2010-11 17

    http://www.amazon.co.uk/Coastal-Engineering-Processes-Theory-Practice/dp/0415583535/ref=sr_1_2?s=books&ie=UTF8&qid=1294647243&sr=1-2http://www.amazon.co.uk/Coastal-Engineering-Processes-Theory-Practice/dp/0415583535/ref=sr_1_2?s=books&ie=UTF8&qid=1294647243&sr=1-2http://www.asqsandiego.net/http://www.anixter.com/http://www.amazon.co.uk/Coastal-Engineering-Processes-Theory-Practice/dp/0415583535/ref=sr_1_2?s=books&ie=UTF8&qid=1294647243&sr=1-2http://www.amazon.co.uk/Coastal-Engineering-Processes-Theory-Practice/dp/0415583535/ref=sr_1_2?s=books&ie=UTF8&qid=1294647243&sr=1-2http://www.asqsandiego.net/http://www.anixter.com/